CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION
|
|
- Emmeline White
- 6 years ago
- Views:
Transcription
1 PHASE 1: PRE-CONSTRUCTION Schematics Phase Based upon program requirements and design parameters, D&J will establish conceptual budget and preliminary schedule for the project, which will highlight specific needs and critical milestones during the schematics phase. After review of the conceptual budget by the project team, all major building systems will be analyzed to determine the most efficient and cost effective systems. Throughout the Schematics and Design Phase, D&J will continually update the project budget and provide value engineering alternatives to control costs and schedule. Conceptual Estimating D&J will survey building parameters, construction site logistics and major components to produce a realistic preliminary budget. Conceptual Systems Analysis Most construction projects can reasonably employ any of several major building systems. To help the Owner and the Architect choose among them, D&J s value engineering services will fully evaluate these major building systems and provide pricing information for each suitable alternative. Master Schedule After consulting with the Owner and the architect, D&J will submit a Preliminary Master Schedule, which will indicate work items of critical timing for design, construction and occupancy along with the key dates for major decisions by the project team. This Master Schedule will include projections for such procedures as design work, obtaining government permits, and the ordering of long lead items, if any. All team members are advised of their individual responsibilities to keep the project on time. Design Phase 80% potential cost savings are prior to start of construction. One of D&J s unique strength lies in our exceptional strong capability to provide comprehensive pre-construction services. The depth of this experience provides strength in project planning, cost estimating, and value engineering allowing the Owner to realize exceptional value in your completed program. Technical Services Total in-house technical resources. Conceptual estimating expertise. Value engineering specialist who focus on in-depth understanding of construction requirements. Comprehensive computer database of current construction facility costs. Full disclosure of all estimate documentation.
2 PHASE 1: PRE-CONSTRUCTION Our estimating staff will rely on both in-house historical data and their detailed knowledge of the market. This knowledge is also heavily relied on for package bids which conform to the skills and competitive bidding size of the local subcontractors. In addition, current estimating programs such as Expedition and others are also used to help develop and support the cost models. Project Budget As drawings and specifications are developed, we will refine and update the preliminary budget. Using all our pricing, current data resources and anything unique to the project, D&J will consolidate all data to provide a realistic construction budget. Budget Estimates D&J will assemble all known facts regarding the building program, current bidding climate, site conditions and historical costs. Considerable dialogue with the A/E disciplines will help define program concepts and quality levels for each system. Value Engineering D&J will provide systems analysis on all major building components for the project. Each building system is analyzed against the building parameters as defined for each project and recommendations are made for possible alternate schemes. Value Engineering is not synonymous with Cost Cutting, but a systematic procedure to evaluate design alternatives by functions, analyze cost/ value relationships Construction Planning D&J saves critical time anticipating construction planning early in the Design Phase of the project. Details concerning the project s work items, building systems and work schedule activities are addressed during the Design Phase. The availability of this information gives the field construction management team the earliest opportunity to implement orders for work item details and long-lead delivery purchases. Permits and Approvals D&J, if requested, will assist the Owner in obtaining approvals from local authorities as well as building permits and special permits other than those required to be obtained by the various trade contractors. We will also verify payment of application fees and assessments.
3 PHASE 1: PRE-CONSTRUCTION Construction Administration D&J is proud of its long standing reputation for satisfying clients. Throughout every stage of the Construction Phase, automated engineering systems monitoring assures us the capability of carrying out the requirements of the Schematics and Design Phases on time and within budget. Project Coordination Once work begins, the Owner, the architect, D&J and subcontractors will meet regularly to discuss job procedures, costs, and schedules. For the duration of the project, D&J will continue to coordinate these items to ensure quality construction and full value for costs. Project Supervision The superintendent is responsible for on-site management of day-to-day construction activities. Each project will have a superintendent assigned to monitor work of trade subcontractors for compliance to safety standards, labor relations, schedule, daily manpower needs, equipment cost and quality requirements. Onsite organization and lines of authority are established in order to ensure timely decisions pertaining to cost and schedule. Project Meetings D&J will schedule and conduct construction progress meetings to discuss matters relating to procedures, progress and scheduling. We will prepare and promptly distribute minutes of such meetings to all appropriate parties. Professional Consultant Services As required, D&J will make recommendations for retaining the services of consultants and will coordinate the services of any such consultants. Schedule Review The project Critical Path Method schedule will be updated and reissued to reflect project progress. Consideration and adjustments, as required, will be made to include activity sequences and durations, allocations of labor and materials, processing of shop drawings, product data, sample and delivery of products requiring long-lead time procurement. The CPM schedule will be further updated and regularly reissued to indicate current conditions and revisions required by actual experience. D&J will utilize Primavera SureTrak 3.0 Project Manager to maintain the CPM schedule throughout the duration of the project.
4 PHASE 2: CONSTRUCTION QUALITY ASSURANCE Through a program of stringent procedures implemented during the construction project, Dunlop & Johnston, Inc. has successfully raised the quality of our construction projects well above the industry standard and strives to continue this high level of commitment to quality. The main procedures implemented are: open communication during the design phase; shop drawing review; material confirmation; placement testing; and quality follow through. During the construction design phase constant communication and review with the architect and subcontractors helps set the quality and performance expectations to be achieved. Diligent review of shop drawings and submittals by all parties is a critical step to verify the materials to be used meet or exceed the needs of the project. Upon approval the onsite superintendent will verify all materials brought on site are in accordance with the approved submittals. During placements of the materials quality testing from outside sources are used for items such as concrete, steel, masonry, site work to assure proper handling and placing methods are utilized. Along with outside testing agencies all D&J employees are geared to keep a watchful eye out for any quality issues that may arise and address them immediately. If an issue with quality arises the matter is documented and corrected to meet the standards set by D&J. These issues are internally reviewed in order to gain an understanding where the process failed in order to correct the system and avoid future issues. Through this review process D&J has been able to reduce the quality related issues on projects as well as improve a projects overall time duration by avoiding quality related pitfalls. After Safety, Quality Assurance is the most important role every D&J Employee is responsible for each and every day. The company is geared around the quality of our work and ultimately the owner s satisfaction in the product delivered.
5 PHASE 2: CONSTRUCTION Reports and Records D&J will keep accurate and detailed written records of the project s progress during all stages of construction: submit written progress reports to the Owner including progress photographs, manpower analysis, schedule updates, financial status and critical items. D&J will maintain a detailed daily log of all events occurring on the job site or related to progress of the project.. Job Site Records, Contracts, Drawings and Manuals D&J will maintain at the job site, available to the Owner, current record of all contracts: including shop drawings, commercial and technical standards and specifications, and other related documents and revisions which arise out of the contract or the construction work. At the completion of the project, all record drawings, operating and maintenance manuals will be delivered to the Owner. Certification of Substantial and Final Completion As the work of each of the trade contractors approaches completion, D&J will prepare a list of incomplete items and a schedule for their completion. We will monitor progress and prepare for final inspection and issuance of the Certificate of Final Completion by the Architects. D&J will secure and transfer to the Owner required guarantees, affidavits, releases, bonds and waivers. We will also deliver all keys, manuals, record drawings and attic stock to the Owner. Primavera Contract Manager Primavera Contract Manager is the latest version of a leading contract management and project administration tool that D&J uses to ensure that the construction schedule that we have planned is executed successfully, on-time and on-budget. Primavera Contract Manager gives our project managers and job superintendents the peace of mind that all project information from contracts, changes, drawings, submittals, meeting minutes and correspondence is linked to critical issues and presented to the Owner on demand.
6 PHASE 3: POST CONSTRUCTION Post Construction Services are important after the completion of any project. Training programs, asbuilt drawings, certifications, safety programs/issues are offered and in most cases, mandatory at the end of and acceptance of the project. The Project Manager and the Project Superintendent or other D&J team members will identify the appropriate post construction services and be responsible for implementing or reviewing them at the completion of the project with the owner and representatives. Training & Occupancy Immediately prior to occupancy, D & J will certify the performance and testing of building systems to verify that they are operating in accordance with required criteria. Subsequently, a through training session will be scheduled for the any representative the Owner deems necessary. This meeting will serve to orient the Owner s staff with the building s systems. Proper maintenance and care of certain equipment will be discussed in detail. At this time, all closeout and record documents will be delivered to the Owner. These items, including but not limited to Certificates of Inspection and Occupancy, Operation and Maintenance Manuals, etc., will be combined in an easy-to-use format. To facilitate a smooth and effortless transition to the new facilities, D&J will offer all assistance necessary to the Owner. Warranty Period D&J will continue to monitor the project for a period of one year following occupancy in order to assist the Owner with any warranty questions and procedures. Additionally we will facilitate the performance of all warranty work to provide minimal disruption of the operations of the Owner.
Owner s Representative SCOPE OF SERVICES
Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,
More informationThis document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering
The Austin Company offers multiple approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers
More informationStep 1 Preliminary Design and Engineering
The Austin Company offers a variety of approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers
More informationREQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components
REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro
More informationATTACHMENT D SCOPE OF SERVICES
ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.
More informationChapter 4 State Requirements for Educational Facilities Section 4.1
providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,
More informationEXHIBIT 6 Preconstruction Work
EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements
More informationConstruction Documents Education Program
PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal
More informationWOHLSEN CONSTRUCTION COMPANY
WOHLSEN CONSTRUCTION COMPANY JOB DESCRIPTION Job Title: Special Projects Estimator & Project Manager Job Reports To: SPG Manager Exempt or Non-Exempt: Exempt Job Summary: In addition to other duties as
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 GENERAL 1.01 SECTION INCLUDES A. Preliminary schedule. SECTION 01 32 00 SECTION 01 32 00 B. Construction progress schedule, with network analysis diagrams and reports. C. Daily construction reports.
More informationCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More information1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES
TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING
More informationDeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT
DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE
More informationVILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information
VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationWhat You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President
What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives
More informationINVITATION FOR BID (IFB):
DATE: May 8, 2018 ADDENDUM NO. 1 INVITATION FOR BID (IFB): B180022132 RPD Furnish & Install Ballistic Glass Lobby Counters IFB #B180022132 WAS ISSUED: Wednesday April 25, 2018 RECEIPT DATE: May 23, 2018
More informationCONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS
CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS I. INTRODUCTION The East Rutherford School District is planning to hold a referendum on December 12, 2017 that incorporates facility
More informationCONSTRUCTION MANAGEMENT CORE COMPETENCIES
CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...
More informationREQUEST FOR PROPOSAL FOR. CONSTRUCTION MANAGER and DESIGN TEAM FOR. Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER and DESIGN TEAM FOR Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH December 2010 I. GENERAL The Urban Redevelopment Authority of
More informationProject # 570-CSI-001. Expand Mental Health Center, Building 27 SCOPE OF WORK
DEPARTMENT OF VETERANS AFFAIRS VA Central California Healthcare System Project # 570-CSI-001 Expand Mental Health Center, Building 27 SCOPE OF WORK 1. GENERAL DESCRIPTION The awarded contractor shall provide
More informationPLANNING AND EVALUATION PRELIMINARY DESIGN
PLANNING AND EVALUATION Project Initiation Discuss and refine client requirements Project brief, Schedule, Budget Confirm client's space needs and program Establish scope of work Obtain client-supplied
More informationExhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction
- State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN
More informationC. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.
SECTION 01400 QUALITY CONTROL SERVICES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification
More informationLevel 3 NVQ Diploma in Construction Contracting Operations
Level 3 NVQ Diploma in Construction Contracting Operations Qualification Specification ProQual 2016 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 12
More informationAudio Sessions. Session 5 MEETINGS. Construction Contract Administration Education Program
Audio Sessions Session 5 MEETINGS Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org This presentation
More informationSECTION QUALITY CONTROL
SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.
More informationG , Request for Proposal Land Survey
G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994
More informationDRAFT. Request for Proposal for Construction Manager at Risk Services ASHRAE. New Headquarters Building. Peachtree Corners, GA
DRAFT Request for Proposal for Construction Manager at Risk Services ASHRAE New Headquarters Building Peachtree Corners, GA 1. INTRODUCTION AND PROJECT DESCRIPTION A. Introduction On behalf of ASHRAE,
More informationEast Central College
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationSECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN
SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation
More informationEducation Construction & Management Development Advisory Services
Statement of Qualifications Project Development Education Construction & Management Development Advisory Services Site Selection Project Planning Design & Development Project Management Construction Oversight
More informationEx AC. Examination for Architects in Canada Examen des architectes du Canada
Ex AC Examination for Architects in Canada Examen des architectes du Canada General and Specific Objectives Theme 1 general objective specific objectives rogramming 1.1 Understand the process for the preparation
More informationPROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems
More informationREQUEST FOR QUALIFICATIONS (RFQ-18084) CONSTRUCTION MANAGEMENT AT RISK (CMAR) SERVICES STATEMENT OF QUALIFICATIONS (SOQ)
REQUEST FOR QUALIFICATIONS (RFQ-18084) CONSTRUCTION MANAGEMENT AT RISK (CMAR) SERVICES STATEMENT OF QUALIFICATIONS (SOQ) Project: Ludden Library Renovation & Expansion By Laramie County Community College
More informationQUALITY INTEGRATED ENGINEERING SERVICES to the energy sector
QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector COMPANY PROFILE offers a complete service including Project Management, Engineering, Procurement, Construction Management, Training and related
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
More informationQuality Management in Construction Projects 8. Dr. Nabil El Sawalhi
Quality Management in Construction Projects 8 Dr. Nabil El Sawalhi 1 Quality in Construction Projects Construction projects are constantly increasing in technological complexity. Electromechanical services
More informationREQUEST FOR QUALIFICATIONS AND PROPOSAL FOR OWNER S REPRESENTATIVE March 21, 2014
REQUEST FOR QUALIFICATIONS AND PROPOSAL FOR OWNER S REPRESENTATIVE March 21, 2014 Cortex Innovation Community requests qualifications from qualified firms and a fee proposal from such firms for the services
More informationTOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR
February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for
More informationFacilities Services 2017 Project Close-Out Process
Facilities Services 2017 Project Close-Out Process December 11, 2017 Linda J. Lindsey, CPA, CGAP, Senior Director Alva Johnson, Internal Auditor Table of Contents Page Number EXECUTIVE SUMMARY 1 BACKGROUND
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationThe construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.
L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationREQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services
REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request
More informationChapter 6, Construction
Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference
More informationDRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL
1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and
More informationQUALITY REQUIREMENTS
SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationDIVISION 1- GENERAL REQUIREMENTS
DIVISION 1- GENERAL REQUIREMENTS This division contains the following elements: 1.1 General 1.2 Summary of Work 1.3 Administration 1.4 Quality 1.5 Temporary Facilities 1.6 Products 1.7 Execution 1.8 Closeout
More informationChapter 1, Introduction
Chapter 1, Introduction CHAPTER CONTENTS 1.1 THE DESIGNERS MANUAL A. Purpose B. Contents 1.2 THE DIVISION OF FACILITIES PLANNING 1.3 THE UNIVERSITY AS OWNER A. The Owner B. Owner Agency 1.4 CAPITAL IMPROVEMENTS
More informationB. OPR and BoD documentation may be included by reference for information only.
SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationScope of Work Bid Package C-4 - West Polished Concrete
Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationAPPENDIX D CONSTRUCTION PHASE CRITERIA
A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance
More informationRichard B. Fisher Middle School Building The William Penn Charter School Philadelphia, PA
Dan Packer Construction Management Richard B. Fisher Middle School October 16, 2002 Project Delivery Evaluation Dr. Michael Horman EXECUTIVE SUMMARY This assignment allowed me to understand the way that
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationScience Technology Engineering and Mathematics (STEM) Initiative
DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationCONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal
More informationSECTION PAYMENT PROCEDURES
SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply
More informationForsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101
Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS
More informationMulti-Institutional Academic Health Science & Research Center Evansville, IN
SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationCHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,
More informationA62 PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationFlorida Cleanroom Systems
Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL
TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II El Paso, Texas EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL for the BUILDING CONCRETE GLASS AND GLAZING FIRE SPRINKLER MECHANICAL
More informationSUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY
SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS Professional Construction Management Services Harrisburg International Airport Rehabilitate Runway 13-31 Susquehanna Area Regional
More informationBULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE
200-4010 Regent Street Burnaby BC V5C 6N2 Canada Telephone: (604) 430-8035 Toll Free Canada-wide: 1-888-430-8035 Facsimile: (604) 430-8085 BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL
More informationBuilding Enclosure Pre-construction Meeting
Building Enclosure Pre-construction Meeting Melissa Payne, BECxP, CxA+BE, CDT Miller Engineering, P.C. Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute of
More informationCONSTRUCTION STANDARD DOCUMENT
CONSTRUCTION STANDARD DOCUMENT OVERALL CONSTRUCTION SCHEDULE REQUIREMENTS The Overall Schedule shall be prepared by the Contractor based on information from all subcontractors engaged on this project.
More informationARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES
- Architect/Engineer s Scope of Services (Multiple-Prime Project) State of Ohio Professional Services Agreements for Public Facility Construction 1.1 General ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES
More informationAdvantage. Proximity & Price. General Services Administration Federal Acquisition Service Authorized Federal Supply Schedule Price List
Proximity & Price Advantage On-line access to contract ordering information, terms and conditions, up-to-date pricing, and the option to create an electronic delivery order are available through GSA Advantage!,
More informationProject Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 12 PROJECT RECORDS MANAGEMENT
Project Procedure PROJECT RECORDS MANAGEMENT 09/21/2012 PAGE 1 OF 12 1.0 PURPOSE The purpose of this procedure is to establish the methods and responsibilities for identifying, collecting, indexing, storing,
More informationProcurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202
Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 June 28, 2017 ADDENDUM NUMBER: TWO (2) TITLE: Riverview Water Main Extension Phase
More informationSECTION SUPPLEMENTARY GENERAL CONDITIONS
SECTION 00800 SUPPLEMENTARY GENERAL CONDITIONS PART 1 - GENERAL 1.1 SCOPE OF WORK In general, the Work consists of application of a fluid applied membrane, installation of new tapered insulation, installation
More informationTownship of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement
Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director
More informationA62 UT PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationGENERAL AND SPECIFIC OBJECTIVES
GENERAL AND SPECIFIC OBJECTIVES 2018 LICENSING AUTHORITIES WHICH RECOGNIZE THE EXAC ARE: Alberta Association of Architects [ AAA ] Architectural Institute of British Columbia [ AIBC ] Architect s Association
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More informationOwner's Representative Scope Matrix - D/B Rev 10/28/2013
Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope
More informationLEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA
Project No. 4484/A4L-379/964840 LEVEL I PREQUALIFICATION DOCUMENTS for OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North
More informationScope of Work Bid Package C-8 - West Overhead Doors
Scope of Work Bid Package C-8 - West Overhead Doors CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationNew York City Transit (NYCT) DATE: July 19, 2018 CONSTRUCTION/ARCHITECTURAL & ENGINEERING CONTRACT SOLICITATION NOTICE/PROJECT OVERVIEW MTA-NYCT IS NOW ADVERTISING FOR THE FOLLOWING: SSE #: 0000226381
More informationSaint Luke s Episcopal Church 73 South Fullerton Avenue Montclair, NJ 07042
Saint Luke s Episcopal Church 73 South Fullerton Avenue Montclair, NJ 07042 REQUEST FOR PROPOSALS (RFP) 2016-3.0 (Architectural Design & Construction) RFP OPENS: RFP CLOSES: Introduction St. Luke s is
More informationRWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109
RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationEducational Use Only S A M P L E S A M P L E
CONSENSUSDOCS 240 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER This document was developed through a collaborative effort of entities representing a wide cross-section of the construction
More informationREQUEST FOR PROPOSAL. Design-Build Services for Intensive Care Unit and Patient Tower Expansion St. Charles Medical Center - Bend.
REQUEST FOR PROPOSAL Design-Build Services for Intensive Care Unit and Patient Tower Expansion St. Charles Medical Center - Bend For St. Charles Health System Issued: May 9, 2016 Proposal Due: June 9,
More information150/ G Versus 150/ H Contractor Quality Control Program
AC 150/5370-10G AC 150/5370-10H 1 Part 1 of General Provisions Part 2 of General Construction Items 2 Section 100 Item C-100 3 Quality Control Program (CQCP) 4 100-01 General. When the specification requires
More informationProject Execution Plan
Gulf Integrated Group Project Execution Plan P. O. Box: 19002, Doha Qatar Tel: +974-4582289/90/91 Fax: +974-4687886 COMMITTED TO QUALITY SECTION 1 1.0 INTRODUCTION Gulf Integrated Group (GIG) is pleased
More informationCommissioning Guidelines for the Arkansas Energy Performance Contracting Program
Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Version 1.1 March 2014 Arkansas Economic Development Commission Energy Office 900 West Capitol Avenue Little Rock, Arkansas
More informationRISE Certified Solar Roofing Professional (CSRP) Job Task Analysis August 2011 RISE CERTIFIED SOLAR ROOFING PROFESSIONAL (CSRP) JOB TASK ANALYSIS
RISE CERTIFIED SOLAR ROOFING PROFESSIONAL (CSRP) JOB TASK ANALYSIS Primary Objective: Given a proposed roof-mounted photovoltaic (PV) system design, a solar roofing professional will apply essential knowledge,
More information