OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

Size: px
Start display at page:

Download "OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING"

Transcription

1 PART I GENERAL 1.01 SECTION INCLUDES A. Commissioning objectives. B. Roles and responsibilities. C. Test Equipment. D. Systems to be commissioned. E. Construction Checklist requirements. SECTION F. Functional Performance Testing requirements. G. Training requirements RELATED REQUIREMENTS A. The following sections contain commissioning-related activities and requirements: 1. Section Submittals 2. Section Project Record Documents 3. Section Contract Closeout 4. Section Operating and Maintenance Manual 5. Specific Product, Equipment, and Assembly Technical Sections PROGRAM OBJECTIVES A. Work completed under this contract will be commissioned as part of Owner's overall project commissioning program. General Contractor shall be responsible to perform testing and commissioning activities. B. Commissioning is intended to achieve the following specific objectives: 1. Verify and document that systems, equipment and components are installed according to the Contract Documents and manufacturer's recommendations, and have received adequate pre-functional checkout. 2. Verify and document the functional performance of systems, equipment and components. 3. Verify continuity between systems, equipment and components. 4. Verify that operation and maintenance documentation is complete and accurate. 5. Verify that Owner's personnel have received the required training. C. The commissioning process is not a substitute for the General Contractor's quality control procedures, and does not diminish or subtract from the General Contractor's responsibility to provide a finished and fully functioning product in accordance with the Contract Documents ROLES AND RESPONSIBILITIES A. AGENT (CxA) 1. Owner will retain Commissioning Agent(s) (CxA) unless noted otherwise within the Contract Documents. 2. CxA shall develop and coordinate execution of a quality assurance plan for systems, equipment and components to be commissioned, shall observe and document performance, and shall determine whether systems, equipment and components are functioning in accordance with Contract Documents. 3. CxA will schedule and conduct a commissioning kickoff meeting. The CxA will prepare and distribute meeting minutes. 4. CxA shall track all deficiencies on CxA s Issues Log. 5. CxA shall review submittals for the purposes of preparing Construction Checklists and Functional Performance Testing procedures. 6. CxA shall review Contractor s documentation submittals for completeness

2 7. CxA shall create Construction Checklists and prepare Functional Performance Testing procedures after the shop drawings have been submitted and reviewed. 8. CxA shall visit site periodically to observe progress of Work to determine if commissioning activities are proceeding in accordance with Contract Documents. 9. CxA shall witness commissioning-related testing. 10. CxA shall facilitate and conduct Owner on-site classroom training and hands-on demonstration sessions with facility operating and maintenance personnel. B. CONTRACTOR S COORDINATOR (CCxC) 1. Contractor shall designate a person with authority to direct work, separate from superintendent or project manager, as the CCxC. The proposed CCxC shall have documented experience managing verification, startup, and closeout of similar systems, equipment and components. Owner s Representative shall have final approval of the proposed CCxC. 2. CCxC is responsible for planning, scheduling, coordinating, conducting and verifying all commissioning activities required by the Contract Documents, ensuring that all systems, equipment and components are complete and functioning. 3. CCxC shall conduct regular commissioning coordination meetings with Design Professional, Owner s Representative, Commissioning Agent, and all Subcontractors of commissioned systems, equipment and components. The purpose of these meetings will be to coordinate schedule, work activities, and deficiency resolution. These meetings shall be independent from the regularly scheduled construction progress meetings. The CCxC will prepare and distribute meeting minutes. 4. CCxC shall review CxA Issues Log and coordinate resolution of all deficiencies, issues, or areas of concern recorded. 5. CCxC shall communicate and coordinate with Owner s Representative and CxA to schedule and execute the commissioning process, including Construction Checklists, Functional Performance Testing, and other activities described in the Contract Documents. 6. CCxC shall visit the site as required by Owner s Representative to observe progress of Work and to determine if commissioning activities are proceeding in accordance with Contract Documents. CCxC shall keep Owner s Representative and CxA informed of progress of the work and commissioning activities. 7. CCxC shall coordinate the scheduling and execution of Owner on-site classroom training and hands-on demonstration sessions. C. GENERAL CONTRACTOR'S RESPONSIBILITIES 1. The cost of all commissioning activities shall be included as part of the General Contractor's bid. General Contractor shall provide all labor, supervision, materials, tools, equipment, and other services, as necessary, to complete commissioning activities in accordance with the Contract Documents. 2. General Contractor shall ensure that all system, equipment and component warranty requirements are followed throughout startup, commissioning, and training process. 3. General Contractor shall coordinate, manage and ensure completion of all commissioning documentation. 4. General Contractor shall invite Owner s Representative, Owner s Operations Personnel and CxA to all equipment startup as optional attendees. The purpose of this invitation is to familiarize personnel with equipment and systems prior to training and turnover. 5. With input from the CxA, General Contractor shall integrate commissioning activities into its master construction schedule. Each system, equipment and component shall be identified separately on General Contractor s schedule. At a minimum, schedule shall identify the following activities and milestones: a. Permanent utilities connected - by individual utility type b. IT interface completed c. End of dust producing activities d. Construction checklists complete by individual system e. Equipment startups completed by individual piece of equipment f. Functional performance testing completed - by individual system. g. Owner training and hands-on demonstration sessions. 6. General Contractor shall correct equipment and system deficiencies

3 PART 2 PRODUCTS TEST EQUIPMENT PART 3 EXECUTION A. General Contractor shall provide all test equipment required for installation, verification, startup, and checkout of systems, equipment and components. B. Specialty equipment, tools and instruments necessary to conduct testing (e.g., available only from the manufacturer for a specific piece of equipment) shall be included in the General Contractor's bid and shall be turned over to Owner at the end of project. C. All test equipment shall be of sufficient quality and accuracy to test and/or measure system performance within the specified tolerances. If not otherwise noted, the following minimum requirements apply: 1. Temperature sensors and digital thermometers shall have an accuracy of 0.5 F and a resolution of plus or minus 0.1 F. 2. Pressure sensors shall have an accuracy of +/- 2.0% of the value range being measured (not full range of meter). D. All test equipment shall be calibrated according to the manufacturer's recommendations or within the past year whichever is more stringent. Calibration tags shall be affixed to test equipment or certificates available upon request SYSTEMS TO BE COMMISSIONED A. PROCESS SYSTEMS 1. Major Equipment: a. Absorption chillers 2 New b. Cooling Towers 1 New 2. Chilled Water System, including chilled water distribution pumps, associated controls and metering: a. Conduct 100% check of central equipment, controls, and interlocks. 3. Condenser Water System, including condenser water pumps, condenser water side stream separator, associated controls and metering: a. Conduct 100% check of central equipment. 4. Refrigerant and solutions pump: a. Conduct 100% check of central equipment. 5. Hot Water System, including hot water secondary pump, associated controls and metering: a. Conduct 100% check of central equipment, controls, and interlocks. 6. Utility Metering and Reporting Systems a. Conduct 100% check of reporting points. 7. Full integration with existing systems. B. MECHANICAL SYSTEMS 1. Makeup Air Handling Unit (MAU-02) - Relocated: a. Conduct 100% check of central equipment, controls, and interlocks. 2. Full integration with existing systems. C. ELECTRICAL SYSTEMS 1. Utility Metering and Reporting Systems a. Conduct 100% check of reporting points. 2. Full integration with existing systems. D. SYSTEMS TO BE COMMISSIONED BY OWNER 1. General Contractor shall provide assistance and participate in the commissioning of the following systems: a. Process Control System Integration

4 3.02 PROCESS A. Construction Activities: 1. CxA will review the commissioning process with the General Contractor and Subcontractors at the pre-construction meeting. 2. Within 60 days of Contract Award, the CxA will schedule and conduct a commissioning kickoff meeting to be attended by the Design Professional, Owner s Representative, CCxC, and General Contractor, and Subcontractors and Suppliers of systems, equipment and components to be commissioned. The purpose of the meeting is to review commissioning requirements, procedures, and documentation. 3. General Contractor shall submit manufacturer's material and equipment shop drawings and documentation to the Design Professional per Section Submittals. 4. CxA shall review the submittal data and prepare final Construction Checklists and Functional Performance Testing Procedures. 5. General Contractor and Subcontractors shall complete the Construction Checklists and any additional testing requirements found in the Construction Documents. 7. CCxC shall review Construction Checklists for completeness and verify that all documentation requirements have been met. 8. After verifying correct installation of systems, equipment and components and approval of Construction Checklist, the CCxC shall schedule and coordinate startup and checkout of equipment, systems, and components. 9. General Contractor and Subcontractors shall provide operators to assist with startup and Functional Performance Testing. Owner will operate equipment and systems during startup and testing. 10. CxA shall witness commissioning-related testing. 11. Systems, equipment or components which fail to meet the Functional Performance Testing requirements shall be corrected by the General Contractor and the tests shall repeated at no additional cost to the Owner. 12. CCxC shall review, schedule, coordinate and document required Owner training CONSTRUCTION CHECKLISTS A. See sample Construction Checklist, attached at the end of this section. B. The objective of Construction Checklists is to verify and document that systems, equipment and components are installed in accordance with manufacturer s instructions and Contract Documents. The CxA shall create Construction Checklists after the shop drawings have been submitted and reviewed. 1. Pre-Installation Verification (PIV) Checklists: This verification is performed as equipment arrives to the project site and is being staged for installation to verify equipment and instrumentation match Contract Document and approved submittals. 2. Pre-Startup Verification (PSV) Checklists: This verification is performed after equipment is installed, but prior to startup to certify equipment and systems have been installed, inspected, complete and ready for startup. 3. Startup Testing Verification (STV) Checklists: This verification is performed after prestartup verification and must be completed prior to Functional Performance Testing to verify equipment and systems are properly connected and ready for operation. C. General Contractor shall complete the Construction Checklists during the course of system, equipment and component installation and not as an activity at the end of the project. Construction Checklists shall certify the individual verification items have been performed, inspected and found to be complete for all systems, equipment and components. (Random sampling and testing of equipment and components is not acceptable.) D. Construction Checklists for a given system must be successfully completed prior to its startup. By completing and signing the Construction Checklists, the CCxC certifies that system, equipment and components are properly installed and ready for startup and functional performance testing. E. CCxC shall notify the Owner s Representative and CxA when Construction Checklists are complete

5 F. Construction Checklists may be in addition to other testing, verification, and startup required elsewhere in Contract Documents (i.e. pipe cleaning, pipe hydraulic testing, etc.) FUNCTIONAL PERFORMANCE TESTING A. See sample Functional Performance Test, attached at the end of this section. B. The objective of functional performance testing is to demonstrate that systems, equipment and components operate in accordance with the Contract Documents. C. CxA shall prepare Functional Performance Testing procedures based on the system sequences of operation and the manufacturer's product data. D. All tests that will impact the operations of existing building or utility systems are to be identified by the CCxC and coordinated with Owner s Representative. E. CxA shall oversee and document the results of the Functional Performance Testing. F. General Contractor shall provide assistance as needed to complete the Functional Performance Testing, including, but not limited to, providing access to equipment and components, including use of ladders, lifts, scaffolding and platforms, Personal Protective Equipment, removal of access panels, opening of equipment, manipulation or operation of equipment or components, etc. G. CxA shall test each system through all modes of operation where there is an expected system response. 1. Normal and Maintenance Operations: Each system shall be tested through all modes and sequences of operation (maintenance, seasonal changes, occupied, unoccupied, warmup, cool-down, etc.). Testing shall also demonstrate that system has the required access, etc., for proper maintenance, adjusting, and cleaning. 2. Abnormal, Failure, and Emergency Operations: Each system shall be tested to simulate conditions such as power failure, freezing, low/no flow, deviation from standard operating conditions, human error, etc., to verify proper system responses, shutdowns, alarms and annunciation, and inter-system communications. E. Systems or equipment that fail all or portions of Functional Performance Tests shall be corrected and tests repeated TRAINING A. CxA will facilitate all training. All training will be incorporated into a comprehensive on-site training and demonstrations sessions to train facility operating and maintenance personnel in proper operation and maintenance procedures. B. CCxC shall review, schedule, and coordinate required Owner training. C. Owner training shall consist of four (4) on-site training and demonstrations sessions. Refer to Training defined in Section D. Training and demonstration to start after system is commissioned (Functional Performance Testing completed), but prior to final acceptance testing DEFICIENCIES A. The terms "failure", "deficiency" and "non-conformance" shall be used interchangeably and shall be defined as any condition in the installation or function of a system, piece of equipment or component that is not in compliance with Contract Documents. B. CxA shall track all deficiencies on CxA s Issues Log. Items on the Issues Log are to be corrected by the Contractor prior to Substantial Completion. Any remaining open Items not accepted by Owner may be added to project punch list at the discretion of Owner s Representative

6 C. At the discretion of Owner s Representative, costs associated with retesting systems, equipment and/or components due to deficiencies may be assigned to General Contractor. 1. General Contractor s incomplete or inaccurate Construction Checklists may be considered cause for retesting. D. Failure of systems or equipment to successfully complete Functional Performance Testing or other commissioning requirements shall not be a cause for delay claims ENDURANCE PERIOD A. An Endurance Period is not required for this project

7 SAMPLE CONSTRUCTION CHECKLISTS Pre-Installation Verification (PIV) Checklist Pre-Startup Verification (PSV) Checklist Startup Testing Verification (STV) Checklist

8 Construction Checklist - SAMPLE Absorption Chiller - MECHANICAL PRE-INSTALLATION VERIFICATION (PIV) THIS VERIFICATION IS COMPLETED AS EQUIPMENT ARRIVES TO THE PROJECT SITE AND IS BEING STAGED FOR INSTALLATION. COMPLETE ALL TASKS BY CHECKING 'YES', 'NO, OR N/A IN DESIGNATED BOXES. FOR ALL NO ANSWERS RECORD DESCRIPTION OF FINDINGS UNDER ISSUE. MAKE NOTE OF ANY NON- COMPLIANCE ITEMS BETWEEN PROJECT DRAWINGS, SPECIFICATIONS, AND EQUIPMENT SHIPPED TO PROJECT SITE, RECORD ANY DESCREPANCIES UNDER ISSUE. 3 STEP 1: PRECONDITIONS The preconditions below have been successfully carried out and all system equipment described herein has been addressed. 4 The precondition tasks are completed and have been checked off by parties having DIRECT KNOWLEDGE of each item. 5 Record and secure all installation manuals, parts lists, warrantee forms, operation and maintenance manuals, etc. for later use. 6 The UNIT has been prepared and protected for storage during staging. 7 AT TIME OF DELIVERY all pre-installation activities per manufacturer requirements have been completed. 8 Pre-installation procedure DOCUMENTATION, per manufacturer, for UNIT completed. 9 PRIOR TO PLACEMENT of UNIT, all pre-installation ACTIVITIES have been completed per manufacturer requirements hours advance notification of CxA expected equipment delivery dates has been completed. 11 STEP 2: MODEL VERIFICATION The verifications below have been successfully carried out. Document delivered equipment in designated column Answer Detail with each piece of equipment delivered. 12 Delivered equipment matches submittal data Complete: 13 Manufacturer Confirmation: [enter manufacturer s name from approved submittal] 14 Model Number Confirmation: [enter model number from approved submittal] 15 Serial Number: [enter serial number of the UNIT] 16 Capacity Confirmation: [enter capacity (TONS) from approved submittal] 17 Refrigerant Confirmation: [enter refrigerant type from approved submittal] 18 Evaporator Flow Confirmation: [enter flow (GPM) from approved submittal] 19 Condenser Flow Confirmation: [enter flow (GPM) from approved submittal] 20 Heat Recovery Flow Confirmation: [enter flow (GPM) from approved submittal] 21 Evaporator Entering Water Temperature Confirmation: [input the entering water temperature (deg F) from approved submittal] 22 Evaporator Leaving Water Temperature Confirmation: [input the leaving water temperature (deg F) from approved submittal] 23 Condenser Entering Water Temperature Confirmation: [input the entering water temperature (deg F) from approved submittal] 24 Condenser Leaving Water Temperature Confirmation: [input the leaving water temperature (deg F) from approved submittal] 25 Heat Recovery Entering Water Temperature Confirmation: [input the entering water temperature (deg F) from approved submittal] 26 Heat Recovery Leaving Water Temperature Confirmation: [input the leaving water temperature (deg F) from approved submittal] 27 Unit Volts / Phase / Hz Confirmation: [ enter unit V / PH/ Hz from approved submittal] 28 STEP 3: PRE-INSTALLATION CHECKS The verifications below have been successfully carried out by parties having DIRECT KNOWLEDGE of each item. 29 Unit Complete: 30 Inspect UNIT for shipping damage. Record all damage and attach unit sketches as necessary for record purposes. 31 Verify nameplate against the approved submittal data and verify receipt of the proper item model (refer to above checklists) 32 Verify that UNIT delivered to the site is stored in a manner that provides adequate protection. 33 Verify continued protection during handling and storage

9 34 Place UNIT in weather protective environment or otherwise protect from the elements until UNIT is installed in its final location. 35 Verify that UNIT has been shipped with vibration isolators. 36 Piping Complete: 37 Verify that all piping connections have been shipped with protective caps or plugs intact. 38 Record all open piping conditions and inspect piping internals. All piping found to be shipped open shall be cleaned and flushed prior to installation. 39 Verify that all pipe openings and connection point covers are intact and adequate for continued protection during handling and storage. 40 Verify that all unit openings and connection point covers are intact and adequate for continued protection during handling and storage. 41 Confirm all components shipped under vacuum, pressure charge, or nitrogen charge has maintained integrity during shipping and handling. 42 Accessories Complete: 43 Verify that all UNIT components delivered to site are stored in a manner that provides adequate protection. 44 Place all components in weather protective environment or otherwise protect from the elements until UNIT is installed in its final location. 45 Confirm control board / factory controls are mounted and free of damage. PRE-STARTUP VERIFICATION (PSV) THIS VERIFICATION IS COMPLETED AFTER EQUIPMENT IS INSTALLED AND PRIOR TO STARTUP. COMPLETE ALL TASKS BY CHECKING 'YES', 'NO, OR N/A IN DESIGNATED BOXES. FOR ALL NO ANSWERS RECORD DESCRIPTION OF FINDINGS UNDER ISSUE. RECORD ANY DESCREPANCIES UNDER ISSUE. 3 STEP 1: REQUESTED DOCUMENTATION The documents below have been submitted (to CxA) by parties having DIRECT KNOWLEDGE of each item. 4 Performance data (fan curves, coil data, etc.) 5 Installation and startup manual. 6 Operations and Maintenance manuals (O&Ms) 7 Warranty Certificates 8 Pipe pressure testing reports 9 STEP 2: UNIT VERIFICATION The verification below has been successfully carried out by parties having DIRECT KNOWLEDGE of each item. 10 Verify model number to documented PIV model verification sheet. 11 Verify serial number to documented PIV model verification sheet. 12 Location of unit correct. 13 STEP 3: PHYSICAL INSTALLATION VERIFICATION The verification below has been successfully carried out by parties having DIRECT KNOWLEDGE of each item. 14 General Installation: 15 Installation on concrete inertia pad. 16 Installation on housekeeping pad. 17 Visible damage present. 18 Permanent labels affixed. 19 Seismic restraints in place. 20 Temperature, pressure, and flow gauges and sensors installed near all control sensors. 21 Maintenance access acceptable for unit and components. 22 Vibration isolation equipment installed & released from shipping blocks. 23 Access to control panel of UNIT is sufficient for maintenance. 24 Refrigerant Piping Complete: 25 Piping system properly flushed / cleaned. 26 Piping properly insulated. 27 Piping properly labeled. 28 Piping properly supported. 29 Valves properly tagged. 30 Piping (suction/liquid lines) properly pitched towards either end per manufacturer s installation directions. 31 Provisions for suction and discharge pressure readings. 32 Pipes properly insulated. 33 Pipes properly labeled

10 34 Absorption Chiller Complete: 35 Evaporator Air Vent piping complete. 36 Refrigerant relief piping complete. 37 Refrigerant level verified. 38 Oil Level verified. 39 Oil Heater installation correct. 40 Oil Filter confirmed clean. 41 Confirm no leaks. STARTUP TESTING VERIFICATION (STV) THIS VERIFICATION IS COMPLETED AFTER PRE-STARTUP CHECKS ARE COMPLETE AND MUST BE COMPLETED PRIOR TO FUNCTIONAL PERFORMANCE TESTING WITH THE CxA. COMPLETE ALL TASKS BY CHECKING 'YES', 'NO, OR N/A IN DESIGNATED BOXES. FOR ALL NO ANSWERS RECORD DESCRIPTION OF FINDINGS UNDER ISSUE. RECORD ANY DESCREPANCIES UNDER ISSUE. 3 STEP 1: PRECONDITIONS The preconditions below have been successfully carried out and all system equipment described herein has been addressed. 4 The precondition tasks are completed and have been checked off only by parties having DIRECT KNOWLEDGE of each item. 5 Startup and operation of UNIT shall not proceed until satisfactory completion of the pre-startup checks is complete and reviewed by CxA. 6 All portions of the distribution system serving components not fully installed at the time of system startup shall have been fully isolated. 7 All startup procedures and data sheets shall be completed in conjunction with UNIT startup 8 Manufacturer s startup sheet complete and submitted for review. 9 Installation and application comply with the manufacturer s recommendations. 10 Warranty sheet complete. 11 STEP 2: OPERATIONAL VERIFICATION The verification below has been successfully carried out by parties having DIRECT KNOWLEDGE of each item. 12 Noise level and/or vibration acceptable. 13 STEP 3: SYSTEM VERIFICATION NOT USED

11 THIS PAGE INTENTIONALLY LEFT BLANK

12 SAMPLE FUNCTIONAL PERFORMANCE TEST

13 Functional Performance Test - SAMPLE Absorption Chiller MECHANICAL FUNCTIONAL PERFORMANCE TEST (FPT) TEST MODE: SHUTDOWN OPP/OCWP PLC-BASED CONTROLS & MANUAL CONTROL 2 MODE TYPE: 3 Occupied. 4 UNIT STATUS: 5 Off. 6 TEST SEQUENCE: The absorption chillers shall be capable of being disabled manually or when future connections temperatures are below 138 F (adj). If the absorption chillers are disabled, the associated condenser and cooling water 2-way isolation valves shall be closed. The associated primary hot water pumps and chilled water distribution pumps shall be de-energized. 7 TEST PROTOCOL: Using the OPP/OCWP PLC-based control Operator Workstation, raise the absorption chiller enable setpoint (based on hot water return temperature) above current hot water return temperature. Verify the absorption chillers and pumps are disabled and the 2-way isolation control valves are closed. 8 What was the initial absorption chiller enable setpoint (hot water return temperature) and the current return water temperature? 9 What temperature was the chiller enable setpoint overridden to? 10 TEST ACTION/RESULTS: 11 Absorption Chillers 12 Is Absorption Chiller CWS-CHLR-003 de-energized? 13 Is Absorption Chiller CWS-CHLR-004 de-energized? 14 Primary Hot Water Pumps 15 Is Primary Hot Water Pump HWS-P-CNT-002A de-energized? 16 Is Primary Hot Water Pump HWS-P-CNT-002B de-energized? 17 Chilled Water Distribution Pumps 18 Is Chilled Water Distribution Pump CWS-P-CNT-003 de-energized? 19 Is Chilled Water Distribution Pump CWS-P-CNT-004 de-energized? 20 Chiller Condenser Water Isolation Valves 21 Is the 2-way condenser water isolation control valve closed for CWS-CHLR-003? 22 Is the 2-way condenser water isolation control valve closed for CWS-CHLR-004? 23 Chiller Chilled Water Isolation Valves 24 Is the 2-way chilled water isolation control valve closed for CWS-CHLR-003? 25 Is the 2-way chilled water isolation control valve closed for CWS-CHLR-004? 26 Has the chiller enable setpoint override been released? 27 Any additional comments? 28 PRINT/CAPTURE SCREENSHOT OF OPP/OCWP PLC-BASED CONTROL GRAPHIC ASSOCIATED WITH TEST ABOVE TEST MODE: STARTUP 30 MODE TYPE: 31 Occupied. 32 UNIT STATUS: 33 Off. 34 TEST SEQUENCE: When the hot water return temperature from the distribution system or future connections temperatures are above 138 F (adj), the absorption chiller plant shall be initialized. The lead absorption chiller condenser and chilled water isolation control valve shall open. The lead absorption chiller, lead primary heating water pump and lead chilled water pump shall be energized. 35 TEST PROTOCOL: Using the OPP/OCWP PLC-based control Operator Workstation, override the absorption chiller enable setpoint (based on heating return water temperature) below current heating return water temperature. Verify the lead absorption chiller 2-way isolation control valves are open and the lead absorption chiller, lead primary heating and lead primary chilled water pumps energized. 36 What was the initial chiller enable setpoint (hot water return temperature) and the current return water temperature? 37 Record the pretest condenser water temperature. 38 Record the pretest chilled water temperature

14 39 What temperature was the absorption chiller enable setpoint overridden to? 40 Is the location of the building return water temperature sensor located prior to the decoupled connection from the heating side of the absorption chiller system? 41 TEST ACTION/RESULTS: 42 Record the current absorption chiller enable setpoint. 43 Record the current condenser water temperature. 44 Record the current chilled water temperature. 45 Absorption Chillers 46 Is Absorption Chiller CWS-CHLR-003 de-energized? 47 Is Absorption Chiller CWS-CHLR-004 de-energized? 48 Is the runtime of absorption chiller CWS-CHLR-003 being monitored? 49 Is the runtime of absorption chiller CWS-CHLR-004 being monitored? 50 How many run hours are required before the lead absorption chiller is rotated? 51 Primary Hot Water Pumps 52 Is Primary Hot Water Pump HWS-P-CNT-002A de-energized? 53 Is Primary Hot Water Pump HWS-P-CNT-002B de-energized? 54 Is the runtime of HWS-P-CNT-002A being monitored? 55 Is the runtime of HWS-P-CNT-002B being monitored? 56 How many run hours are required before the lead primary heating water pump is rotated? 57 Chilled Water Distribution Pumps 58 Is Chilled Water Distribution Pump CWS-P-CNT-003 de-energized? 59 Is Chilled Water Distribution Pump CWS-P-CNT-004 de-energized? 60 Is the runtime of CWS-P-CNT-003 being monitored? 61 Is the runtime of CWS-P-CNT-004 being monitored? 62 How many run hours are required before the lead primary chilled water pump is rotated? 63 Chiller Condenser Water Isolation Valves 64 Is the 2-way condenser water isolation control valve closed for absorption chiller CWS-CHLR-003? 65 Is the 2-way condenser water isolation control valve closed for absorption chiller CWS-CHLR-004? 66 Was the isolation control valve opened before the pump and absorption chiller were energized (5 min (adj.) delay)? 67 Was flow proven through condenser via the differential pressure switch before absorption chiller was allowed to start? Record enable differential pressure setting. 68 Chiller Chilled Water Isolation Valves 69 Is the 2-way chilled water isolation control valve closed for absorption chiller CWS-CHLR-003? 70 Is the 2-way chilled water isolation control valve closed for absorption chiller CWS-CHLR-004? 71 Was the isolation control valve opened before the pump and absorption chiller were energized (5 min (adj.) delay)? 72 Was flow proven through evaporator via the differential pressure switch before absorption chiller was allowed to start? Record enable differential pressure setting. 73 Has the absorption chiller enable setpoint override been released? 74 Any additional comments? 75 PRINT/CAPTURE SCREENSHOT OF OPP/OCWP PLC-BASED CONTROL GRAPHIC ASSOCIATED WITH TEST ABOVE TEST MODE: ADDITIONAL CHILLER CONTROL 77 MODE TYPE: 78 Occupied. 79 UNIT STATUS: 80 On. 81 TEST SEQUENCE: The OCWP shall maintain a minimum heating supply temperature of 140 F (adj). The additional chiller shall be enabled to maintain this setpoint as needed. As a safety measure, additional absorption chiller(s) may be enabled if the maximum flow of the operating chiller is exceeded as measured by the chilled water or condenser water differential pressure sensors. 82 TEST PROTOCOL: Using the OPP/OCWP PLC-based control Operator Workstation, raise the current heating supply temperature setpoint. Verify the additional chiller is enabled and the setpoint is reached. Verify the heating supply temperature reset schedule. Simulate an excess flow condition through the operating chiller on the chilled water and condenser water sides. Verify the additional absorption chiller is enabled. 83 Are the condenser water and chilled water differential pressure sensors installed? Record the current settings of each. 84 Record the pretest heating supply temperature

15 85 Record the pretest heating supply temperature setpoint. 86 Record the pretest condenser and chilled water flows through chiller. 87 TEST ACTION/RESULTS: 88 Record the current heating supply temperature. 89 Record the current heating supply temperature setpoint. 90 Record the current condenser and chilled water differential pressure settings. 91 Record the current condenser and chilled water flows through chiller (during 2 chiller operation). 92 Absorption Chillers 93 Is Absorption Chiller CWS-CHLR-003 de-energized (lead chiller)? 94 Is Absorption Chiller CWS-CHLR-004 de-energized (lead chiller)? 95 Did the additional absorption chiller energize when required? 96 Primary Hot Water Pumps 97 Is Primary Heat Water Pump HWS-P-CNT-002A de-energized (lead pump)? 98 Is Primary Heat Water Pump HWS-P-CNT-002B de-energized (lead pump)? 99 Chilled Water Distribution Pumps 100 Is Primary Chilled Water Pump CWS-P-CNT-003 de-energized? 101 Is Primary Chilled Water Pump CWS-P-CNT-004 de-energized? 102 Has the setpoint overrides been released? 103 Any additional comments? 104 PRINT/CAPTURE SCREENSHOT OF OPP/OCWP PLC-BASED CONTROL GRAPHIC ASSOCIATED WITH TEST ABOVE TEST MODE: PRIMARY HEATING SUPPLY TEMPERATURE CONTROL 106 MODE TYPE: 107 Occupied. 108 UNIT STATUS: 109 On. 110 TEST SEQUENCE: The OCWP shall maintain a minimum heating supply temperature of 140 F (adj). The primary heating supply temperature reset schedule will affect the actual setpoint. The additional absorption chiller shall be enabled to maintain this setpoint as needed. The primary heating water supply temperature setpoint shall be reset to maintain a maximum of 10 F (adj.) temperature rise above the heat recovery return water temperature. 111 TEST PROTOCOL: Using the OPP/OCWP PLC-based control Operator Workstation, override the heating supply temperature setpoint. Verify the operating absorption chiller modulates accordingly. Adjust the setpoint further and verify the additional absorption chiller enables. Simulate a change in the heating return water temperature and verify the heating supply setpoint offsets accordingly. 112 Is there a primary heating supply temperature setpoint schedule? Record the reset range and what it is based on. 113 Record the pretest heating supply temperature setpoint. 114 Record the pretest condenser and chilled water flows through chiller. 115 Record the pretest differential temperature between heating water supply and return. 116 TEST ACTION/RESULTS: 117 Record the current heating supply temperature. 118 Record the current heating supply temperature setpoint. 119 Record the current condenser and chilled water differential pressure settings. 120 Record the current condenser and chilled water flows through chiller (during 2 absorption chiller operation). 121 Absorption Chillers 122 Is Absorption Chiller CWS-CHLR-003 de-energized (lead chiller)? 123 Is Absorption Chiller CWS-CHLR-004 de-energized (lead chiller)? 124 Did the additional absorption chiller energize when required? 125 Primary Hot Water Pumps 126 Is Primary Heat Water Pump HWS-P-CNT-002A de-energized (lead pump)? 127 Is Primary Heat Water Pump HWS-P-CNT-002B de-energized (lead pump)? 128 Chilled Water Distribution Pumps 129 Is Primary Chilled Water Pump CWS-P-CNT-003 de-energized? 130 Is Primary Chilled Water Pump CWS-P-CNT-004 de-energized? 131 Has the setpoint overrides been released? 132 Any additional comments? 133 PRINT/CAPTURE SCREENSHOT OF OPP/OCWP PLC-BASED CONTROL GRAPHIC ASSOCIATED WITH TEST ABOVE

16 END OF SECTION THIS PAGE INTENTIONALLY LEFT BLANK

17 Division 02 Existing Conditions The University of Iowa Oakdale Chilled Water Plant Capacity Upgrades Install Chillers UI Project Division 02

18 THIS PAGE INTENTIONALLY LEFT BLANK

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section. SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA PRE-START-UP/START-UP CHECKLIST CHILLED WATER SYSTEM NOTE: University s Representative must be notified and scheduled to witness test prior to any start up of equipment. A. Chilled Water Pumps 1. Submittal

More information

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions. SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary

More information

B. OPR and BoD documentation may be included by reference for information only.

B. OPR and BoD documentation may be included by reference for information only. SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process. SECTION 23 99 50 - (ADD#4) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems

More information

Capital Projects Group Mechanical Work Commissioning Specification

Capital Projects Group Mechanical Work Commissioning Specification Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction February 17, 2015 Re: Request for Proposals- Commissioning Services Madison Street Residence Hall Construct Facility University of Iowa The University

More information

SECTION COMMISSIONING

SECTION COMMISSIONING SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery

More information

SECTION COMMISSIONING

SECTION COMMISSIONING SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery

More information

Absolute Energy Raters Commissioning Plan Outline Template

Absolute Energy Raters Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction November 26, 2014 Re: Request for Qualifications - Commissioning Services Bowen Science Building Modernize Building Systems University of Iowa The

More information

Higher Value Commissioning

Higher Value Commissioning Higher Value Commissioning Presented by: Erik Jeannette, PE May 2011 Commissioning What is it? Commissioning (Cx) is a comprehensive and systematic process to verify and document the systems of a facility

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018 SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS GENERAL 1.1 SUMMARY The Owner has retained an independent Commissioning Authority (CxA) to coordinate commissioning activities for this project. The

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction February 26, 2015 Re: Request for Proposals- Commissioning Services College of Public Health Building - Fit Out Fifth Floor University of Iowa The

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 PART 1 GENERAL 1.1 REFERENCES SECTION 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 The publications listed below form a part of this specification to the extent referenced. The publications

More information

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 25 0800 - COMMISSIONING OF INTEGRATED AUTOMATION GENERAL 1.1 SUMMARY This section defines responsibilities of the Integrated Automation Contractor to facilitate the Commissioning process for the

More information

SECTION COOLING TOWER

SECTION COOLING TOWER PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue

More information

Low Voltage Switchgear Construction Checklist (under 500 kva)

Low Voltage Switchgear Construction Checklist (under 500 kva) Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa

More information

~fied1tr: SLONE . I. Submittal #39. Title - Commissioning of HV AC Systems Plan Specification Section ,00 10 SD# 02,03,07.

~fied1tr: SLONE . I. Submittal #39. Title - Commissioning of HV AC Systems Plan Specification Section ,00 10 SD# 02,03,07. I SLONE ASSOCIATES, INC. Repair FRC Building 1553 Naval Station, Mayport, Florida Submittal #39 Title - Commissioning of HV AC Systems Plan Specification Section - 23 0800,00 10 Index SD# 02,03,07 Item

More information

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS 23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters

More information

H59-N944-PD ATTACHMENT C: SECTION GENERAL COMMISSIONING REQUIREMENTS

H59-N944-PD ATTACHMENT C: SECTION GENERAL COMMISSIONING REQUIREMENTS ATTACHMENT C: SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SCOPE A. This section provides for commissioning of the project equipment and systems as specified herein. The commissioning

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.

More information

Commissioning Guidelines for the Arkansas Energy Performance Contracting Program

Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Version 1.1 March 2014 Arkansas Economic Development Commission Energy Office 900 West Capitol Avenue Little Rock, Arkansas

More information

LUNA SECONDARY PREPARATORY SCHOOL DALLAS, TEXAS ADDENDUM NO. 1

LUNA SECONDARY PREPARATORY SCHOOL DALLAS, TEXAS ADDENDUM NO. 1 LUNA SECONDARY PREPARATORY SCHOOL DALLAS, TEXAS ADDENDUM NO. 1 PROJECT: Luna Secondary Preparatory School HKS Project No. 16389.000 DATE: 17 December 2013 TO: All Offerors The Proposal Documents shall

More information

Retro-Commissioning for Existing Facilities

Retro-Commissioning for Existing Facilities Retro-Commissioning for Existing Facilities Tom Meyer Director, Technical Programs National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, Maryland 20877 (301) 977-3698 www.nebb.org

More information

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION 1.07 SUPPLEMENTS d. Complete using typewriter or electronic printing. 3. Include detailed lubrication instructions and diagrams showing points to be greased or oiled; recommend type, grade, and temperature

More information

LOCKOUT / TAGOUT PROGRAM

LOCKOUT / TAGOUT PROGRAM Page: Page 1 of 11 Purpose The purpose of this program is to establish procedures for affixing appropriate lockout/tagout equipment to energy isolating devices and to otherwise disable machines or equipment

More information

ESSENTIAL SAFETY RESOURCES

ESSENTIAL SAFETY RESOURCES ESSENTIAL SAFETY RESOURCES GS-3023 LOCKOUT / TAGOUT PROGRAM Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager s Signature: Type

More information

THE COTTAGE at THORNAPPLE Hastings, Michigan

THE COTTAGE at THORNAPPLE Hastings, Michigan THE COTTAGE at THORNAPPLE ADDENDUM NO. 2 March 07, 2012 The Cottage at Thornapple 2580 Nashville Road Hastings, MI 49058 Owner: Barry County / Thornapple Manor 2700 Nashville Road Hastings, MI 49058 Architect:

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction March 7, 2013 Re: Request for Proposals- Commissioning Services Mayflower Hall Permanent Flood Recovery & Mitigation (UI# 0200201) University of Iowa

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 ADDENDUM 1 Date: June 13, 2018 Bid No.: Title: 18-11/AL Repair and Maintenance of Landfill Gas Chiller System Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 This Addendum

More information

B. System Design and Performance Requirements

B. System Design and Performance Requirements 15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes

More information

Capital Projects Group Air Terminal Units Specification

Capital Projects Group Air Terminal Units Specification Capital Projects Group Air Terminal Units Specification Specification 23 36 00 Revision 0 Date: August 2018 Air Terminal Units Specification Specification 23 36 00 Publication Date: August 2018 COPYRIGHT

More information

University of Delaware

University of Delaware SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality

More information

SECTION INSTALLATION OF OWNER-FURNISHED PRODUCTS

SECTION INSTALLATION OF OWNER-FURNISHED PRODUCTS SECTION 13 00 50 INSTALLATION OF PART 1 GENERAL 1.1 GENERAL A. Furnish and install all tools, supplies, materials, equipment, appurtenances, and labor necessary for the installation, testing, and placing

More information

2. Representatives of the facility user and operation and maintenance personnel.

2. Representatives of the facility user and operation and maintenance personnel. PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according

More information

SECTION AIR TERMINAL UNITS

SECTION AIR TERMINAL UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA 02210 (T) 617-423-7423 (F) 617-423-7401 mwalsh@vanderweil.com Module

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS

More information

Fact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY?

Fact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY? Commissioning Fact Sheet Funding for this publication is provided by the Northwest Energy Efficiency Alliance. OCTOBER 2017 VOLUME 1, ISSUE 2 WHAT IS THE PURPOSE OF THIS REQUIREMENT? There is a saying

More information

REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I

REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I Dover School District (Owner) requests written proposals to secure commissioning authority (CxA) services for the renovations project at the Garrison Elementary School in Dover, New Hampshire. The Owner

More information

LOCKOUT TAGOUT SAFETY PROGRAM

LOCKOUT TAGOUT SAFETY PROGRAM 1. PURPOSE To establish procedures for affixing appropriate lockout/tagout equipment to energy isolating devices and to otherwise disable machines or equipment to prevent unexpected energization, start

More information

START-UP CHECKLIST. Date: Job Name: Customer Name: Address: City: State: Zip: Model Number: Serial Number: Qualified Start-up Technician:

START-UP CHECKLIST. Date: Job Name: Customer Name: Address: City: State: Zip: Model Number: Serial Number: Qualified Start-up Technician: START-UP INSTRUCTION SERIES 20 J**YC/YD 90000 To 300000 BTU S SPLIT SYSTEM CONDENSING UNITS 7.5 To 25 TON START-UP CHECKLIST Date: _ Job Name: Customer Name: Address: City: State: Zip: Model Number: Serial

More information

Executive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX:

Executive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX: Executive Summary Sample Company BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA 17070 PHONE: 717-697-6300 FAX: 717-697-1699 Executive Summary Sample Company has constructed a 80,000 sf. addition

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL QVIB INSPECTION PROCEDURE 70702 PART 52, INSPECTION OF PREOPERATIONAL TEST PERFORMANCE PROGRAM APPLICABILITY: 2504 70702-01 INSPECTION OBJECTIVES 01.01 To provide guidance for inspection

More information

FORM WCCL-PC1 WCCL WITNESS TEST PROCEDURE AND CHECKLIST

FORM WCCL-PC1 WCCL WITNESS TEST PROCEDURE AND CHECKLIST FORM WCCL-PC1 WCCL WITNESS TEST PROCEDURE AND CHECKLIST AHRI CERTIFICATION PROGRAM FOR WATER-COOLED WATER CHILLING AND HEAT PUMP WATER-HEATING (WCCL) PACKAGES WCCL Participant: Date of Test: Witness Test

More information

ARMSTRONG DESIGN ENVELOPE FAQ

ARMSTRONG DESIGN ENVELOPE FAQ ARMSTRONG DESIGN ENVELOPE FAQ File No: 100.202 Date: december 28, 2015 Supersedes: 100.202 Date: september 22, 2015 q1 a1 Armstrong is the greenest, most cost effective and most flexible building mechanical

More information

SECTION FUEL-FIRED UNIT HEATERS

SECTION FUEL-FIRED UNIT HEATERS SECTION 23 55 33 PART 1 - GENERAL 1.1 DESCRIPTION A. This Section includes gas-fired unit heaters. SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable

More information

EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS

EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS DISTRICT VII, HEADQUARTERS FACILITY AND TAMPA BAY SUNGUIDE REGIONAL TRAFFIC MANAGEMENT CENTER I. PURPOSE: DISTRICT VII, HEADQUARTERS FACILITY

More information

MINNESOTA STATE SECTION ADVERTISEMENT FOR BIDS

MINNESOTA STATE SECTION ADVERTISEMENT FOR BIDS MINNESOTA STATE SECTION 00 11 13 ADVERTISEMENT FOR BIDS Sealed Bids for: will be received by: Ridgewater College Commercial Chiller Purchase Ridgewater College Willmar Campus 2101 15 th Ave. N.W Willmar,

More information

Architect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition

Architect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 23 81 00 DECENTRALIZED HVAC EQUIPMENT A. The other Contract Documents complement the requirements of this section. The General requirements apply to the work

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,

More information

SECTION LINEAR MOTION SLUDGE MIXERS

SECTION LINEAR MOTION SLUDGE MIXERS SECTION 11480 LINEAR MOTION SLUDGE MIXERS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. The Contractor shall furnish, install, adjust, finish paint and test one (1) linear motion sludge mixer for mounting

More information

Capital Projects Group Gas Fired Warm Air Furnace Specification

Capital Projects Group Gas Fired Warm Air Furnace Specification Capital Projects Group Gas Fired Warm Air Furnace Specification Specification 23 54 16 Revision 1 Date: September 2018 Gas Fired Warm Air Furnace Specification Specification 23 54 16 Publication Date:

More information

GUIDELINE. A Guide to. Testing and Commissioning Guidelines PED/SDQS/MN-TNC(V)1/R/0807(116)

GUIDELINE. A Guide to. Testing and Commissioning Guidelines PED/SDQS/MN-TNC(V)1/R/0807(116) GUIDELINE A Guide to Testing and Commissioning Guidelines PED/SDQS/MN-TNC(V)1/R/0807(116) LIST OF SECTION 1.0 INTRODUCTION 1 2.0 DEFINITIONS AND INTERPRETATION 1 3.0 PRE-COMMISSIONING 2 3.1 General 2 3.2

More information

University of Delaware

University of Delaware SECTION 23 05 00_COMMON WORK FOR HVAC SYSTEMS University Contact: Energy & Engineering Group (302) 831-1744 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality Control

More information

SECTION CONVECTORS

SECTION CONVECTORS SECTION 23 82 33 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

HEAT PUMP POOL HEATERS CERTIFICATION PROGRAM

HEAT PUMP POOL HEATERS CERTIFICATION PROGRAM HEAT PUMP POOL HEATERS CERTIFICATION PROGRAM AHRI HPPH OM JANUARY 2017 2111 Wilson Blvd, Suite 500 Arlington, Virginia 22201 (703) 524-8800 Sponsored and administered by: PREFACE The following manual outlines

More information

SECTION PROJECT CLOSEOUT

SECTION PROJECT CLOSEOUT PART 1 - GENERAL 1.01 SCOPE OF WORK A. This Section specifies administrative and procedural requirements for project closeout, including but not limited to: 1. Close-out procedures 2. Final cleaning 3.

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014 NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings March 5, 2014 0 Moderator Jim Huber, NEBB President-Elect and President of Complete Commissioning Jim Huber

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Fire Protection Contractor QA/QC Plan Sample

Fire Protection Contractor QA/QC Plan Sample Fire Protection Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Fire Protection Standards & Inspection Forms Contact: Ed

More information

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC. B. Testing, adjustment, and balancing of refrigerating systems.

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC. B. Testing, adjustment, and balancing of refrigerating systems. SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 GENERAL 1.1 SECTION INCLUDES A. Testing, adjustment, and balancing of air systems. B. Testing, adjustment, and balancing of refrigerating

More information

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408).

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). The application of the Commissioning Process starts at the beginning of the project

More information

I. Development, Submittal, and Acceptance of a Quality Management System

I. Development, Submittal, and Acceptance of a Quality Management System I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

Selected pages (not a complete plan)

Selected pages (not a complete plan) Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Contact: FirstTimeQuality 410 451 8006 Pat [Pick the date] PROJECT-SPECIFIC

More information

SECTION ROTARY SCREW WATER CHILLERS

SECTION ROTARY SCREW WATER CHILLERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

CLARIFICATIONS: REVISIONS AND ADDITIONS:

CLARIFICATIONS: REVISIONS AND ADDITIONS: CLARIFICATIONS: 1. G.C. shall be responsible for Erosion & Sediment Control Plan and all associated work. 2. G.C. shall be responsible for coordination and installation of parking lot and site lighting.

More information

FORM WCCL-PC6 WCCL TEST STAND APPROVAL PROCEDURE AND CHECKLIST OF THE THIRD-PARTY LABORATORY

FORM WCCL-PC6 WCCL TEST STAND APPROVAL PROCEDURE AND CHECKLIST OF THE THIRD-PARTY LABORATORY FORM WCCL-PC6 WCCL TEST STAND APPROVAL PROCEDURE AND CHECKLIST OF THE THIRD-PARTY LABORATORY AHRI CERTIFICATION PROGRAM FOR WATER-COOLED WATER CHILLING AND HEAT PUMP WATER-HEATING (WCCL) PACKAGES WCCL

More information

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON- APPLICABILITY (NA). 1. HEATING SYSTEMS: A. GENERAL

More information

Mt. Diablo Unified School District Purchasing Department 2326 Bisso Lane Concord, CA (925) , ext (925) fax

Mt. Diablo Unified School District Purchasing Department 2326 Bisso Lane Concord, CA (925) , ext (925) fax ADDENDUM NO.: 2 Mt. Diablo Unified School District Purchasing Department 2326 Bisso Lane Concord, CA 94520 (925) 825-7440, ext. 3740 (925) 687-5044 fax DATE: March 19, 2019 PROJECT: Prop 39 Energy Management

More information

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service Installation Service - 1 - InfraStruXure InRow SC Assembly and Start-Up Statement of Work 1.0 Executive Summary InfraStruXure InRow SC Assembly & Start-Up Service Table of Contents 1.0 Executive Summary

More information

Maintenance Program Guideline for Owners of Ammonia Plants

Maintenance Program Guideline for Owners of Ammonia Plants Maintenance Program Guideline for Owners of Ammonia Plants Contents Maintenance Program Guideline for Owners of Ammonia Plants... 0 a) Title Page, owner/operator, the plant location.... 4 b) Contents Page...

More information

TECHNICAL SPECIFICATIONS

TECHNICAL SPECIFICATIONS TECHNICAL SPECIFICATIONS ITEM 00520 WEIGHING AND MEASURING EQUIPMENT 520.1 Description. This item shall govern for the weighing and measuring equipment utilized where materials are specified to be measured

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

CONSTRUCTION REQUIREMENTS

CONSTRUCTION REQUIREMENTS CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION HVAC PUMPS. A. Provide centrifugal HVAC pumps, called for in drawing schedule, and as needed for a complete and proper installation.

SECTION HVAC PUMPS. A. Provide centrifugal HVAC pumps, called for in drawing schedule, and as needed for a complete and proper installation. PART 1 - GENERAL 1.01 DESCRIPTION OF WORK SECTION 15540 HVAC PUMPS A. Provide centrifugal HVAC pumps, called for in drawing schedule, and as needed for a complete and proper installation. B. Provide variable

More information

Incentives. After work is complete:

Incentives. After work is complete: SAVE your WAY Create your own Energy Demand Savings with OUC s Commercial & Industrial Custom Incentive Program Overview OUC is committed to helping your business become more energy efficient. We understand

More information

Attachment 1: RAE Corporation Technical Specification

Attachment 1: RAE Corporation Technical Specification Attachment 1: RAE Corporation Technical Specification RAE Corporation Phone: 918-825-7222, ext. 105 Steve Corbin Quote# XXXX Qty Customer Tag Technical Systems Model Number 1 ACC-4 10A0-162-S General Scope

More information

T-Series SPLIT SYSTEM UNITS TSA R-410A - 60 HZ

T-Series SPLIT SYSTEM UNITS TSA R-410A - 60 HZ REFRIGERANT CONDENSERS Guide Specifications T-Series SPLIT SYSTEM UNITS TSA R-410A - 60 HZ September 5, 2012 Note: This Specification is for Allied Commercial T-Series 6- to 20-ton, outdoor air conditioner

More information

Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015

Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015 Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015 Lockout / Tagout CONTENTS I. PURPOSE II. SCOPE III. DEFINITIONS

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information