1 Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction Co., Inc. Revised Change Order: $414,550 Contract Start: June 15, 2009 Contract Completion: August 15, 2009 Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.the parking lot will be adjacent to the existing Main Instructional Building located on the Chino Campus. Status: Phase I is near completion, with asphalt and parking stall striping completed. Security blue phones and parking ticket machines will be installed the week of August 10, 2009, in anticipation of the fall 2009 semester. Phase II, installation of parking lights, will be complete by mid September Chino Campus parking lot, view looking east. Language Arts/Social Science-HVAC Project Architect: P2S Engineering Contract Amount: $2,700,000 Construction Manager: Chaffey College Approved Change Orders: $95,164 Contractor: Siemens Revised Change Order: $2,795,164 Contract Start: May 15, 2009 Contract Completion: August 14, 2009 Scope: This is an energy project upgrade to the Language Arts and Social Science buildings, which will include installation of new air handling equipment and new lighting systems. Status: The renovation work in the Social Science building is complete. Siemens will be substaintially complete in the Language Arts building in early August The Language Arts and Social Science buildings will be ready for the fall 2009 semester. 1.Language Arts-interior view of the classroom. Page 1 of 13

2 Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders: $0 Contractor: T and D Communications, Inc. Revised Contract: $154,882 Contract Start: May 14, 2009 Contract Completion: November 6, 2009 Scope: This project is the installation of data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building. Status: T and D Communications, Inc. has completed Phase I, which included placing new media to the Fashion, Ceramics, and Music buildings of the Visual and Performing Arts Complex, as well as to the Physical Science building. T and D Communications, Inc. began working on this phase at the end of the spring 2009 semester. Phase II for this project is scheduled to begin August 17, 2009, which includes the placement of new media to the New Gymnasium and the Stadium. 1. Installed underground conduits for new media placement from the New Gymnasium to Stadium. Page 2 of 13

3 Projects under Construction Fontana Phase III-Parking Lot Architect: HMC Architects Original Contract: $1,089,000 Construction Manager: Bernards Approved Change Orders: $0 Contractor: Bogh Engineering, Inc. Revised Contract: $1,089,000 Contract Start: May 11, 2009 Contract Completion: October 5, 2009 Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus. Status: Bogh Engineering, Inc. has constructed the curbs and gutter. The cobblestones have been placed at the bio-swale, and installation of the irrigation lines in the parking lot planters is complete. The planting of trees has begun, and the base for the walkway pavers has been placed. Bogh Engineering, inc. has also installed the electrical conduit, and constructed the light pole bases. Asphalt is scheduled to be laid mid August Phasing and Logistics plan for the parking lot. 2. Cobblestones and constructed curbs. 3. Planted trees and constructed light pole bases. Page 3 of 13

4 Projects under Construction Visual and Performing Arts Complex/Music Building Architect: Hammel, Green & Abrahamson, Inc. Original Contract: $22,145,000 Construction Manager: Bernards Approved Change Orders: $ 956,191 Contractor: ProWest Constructors Revised Contract: $ 23,101,191 Contract Start: February 2008 Contract Completion: - Bldg. B & C- Ceramic Lab/Art Studio Summer Bldg. F Art Complex Fall Bldg. E- Music Building Summer 2009 Scope: This project is comprised of four buildings two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a threestory structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000 sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art Studio. Status: At the Performing Arts building, ProWest Constructors continues to install the exterior sheathing. Drywall installation continues at the main level walls and has also started at the upper level. The upper level mechanical, electrical, and plumbing rough in is on going. The installation of roofing material is on going at the Performing Arts building, and the casework, tack boards, and marker boards have been installed on the lower level. At the Music building, the installation of acoustical wall panels, tack board marker boards, and carpet tiles is complete. ProWest Constructors is continuing to install the cement board panels at the exterior of the building, and is preparing 1. Exterior rendering of the main building. 2. Completed light fixture installation at the Ceramics building. for a punch list walk. At the Fashion and Ceramic buildings, lighting fixtures have been installed, and ProWest Constructors is working to complete the punch list items in both buildings. 3. West side of the Music building. 4. Exterior sheathing and lath at the Performing Arts building. Page 4 of 13

5 Projects under Construction Physical Education Athletics-New Gymnasium Architect: NTD Architecture Original Contract: $8,560,543 Construction Manager: Bernards Approved Change Orders: $51,127 Contractor: Edge Development, Inc. Revised Contract: $8,611,670 Contract Start: September 29, 2008 Contract Completion: December 23, 2009 Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar. Status: At the New Gymnasium, EDGE Development, Inc. has completed installation of the structural steel for the metal deck roofing, canopy, and storefront. CMU block at the site walls and transformer enclosure have been completed. EDGE Development, Inc. is continuing installation of chilled and hot water supply and return piping for the existing gymnasium. Installation of the electrical, fire alarm, plumbing, fire sprinklers, and duct work have been completed on the east end of the New Gymnasium with completion at the main and west end to continue through the beginning of August Metal stud 1. Exterior rendering of the building. framing has been completed inside the building, and the transformer in the electrical room has been set. 2. Rough in of mechanical, electrical, and plumbing at the east end locker rooms. 3. Completion of CMU transformer enclosure. 4. Metal stud framing installation. 5. Installation of metal deck roofing. Page 5 of 13

6 Projects in Pre-Bid/Planning Campus Center West Architect: MDA Johnson Favaro Contract Amount: To Be Announced Construction Manager: Bernards Approved Change Orders: To Be Announced Contractor: To Be Announced Revised Contract Amount To Be Announced Contract Start: To Be Announced Contract Completion: To Be Announced Scope: The existing Campus Center West building will be demolished, and construction of a new 16,454 sq. ft. Campus Center West will be constructed in its place. Select modernization of the Campus Center East will occur as well. Status: Project has completed the design verification process with the College Design Standards and College User Groups. Swing space plans are in the development stage for this project. MDA Johnson Favaro expects final Division of the State Architect approval of all back check comments by mid August The project bid documents are in process. 1. Rendering of interior cooridor. 2. Floor plan of new building. 3. Rendering of interior dining area. Page 6 of 13

7 Projects in Pre-Bid/Planning Fontana Phase III-Academic Building Architect: HMC Architects Original Contract: To Be Announced Construction Manager: Bernards Approved Change Orders: To Be Announced Contractor: To Be Announced Revised Contract: To Be Announced Contract Start: To Be Announced Contract Completion: To Be Announced Scope: Comprised of 30,400 sq ft., this will be a new academic building with four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices. Status: The Division of the State Architect has approved the main building, and HMC Architects is working on the back check comments. The project will be resubmitted to the Division of the State Architect for final approval by early August Upon final approval, the project will be submitted to the State Chancellor s office for approval to proceed to bid and award of the contract. Tentative construction is to start in fall 2009, subject to approval of state funding. 1. Exterior rendering of the building looking north. 2. First floor plan layout. 3. Second floor plan layout. Page 7 of 13

8 Projects in Pre-Bid/Planning Omnitrans Transit Center Architect: HMC Architects Contract Amount: To Be Announced Construction Manager: Bernards Approved Change Orders: To Be Announced Contractor: To Be Determined Revised Contract: To Be Announced Contract Start: To Be Determined Contract Completion: To Be Determined Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus. Status: The project is in the pre-design development / pre-construction phase. HMC Architects is working with Omnitrans and the College on the design issues of the Transit Center. Based upon the approval process with DSA and Omnitrans, tentative construction is scheduled for summer Page 8 of 13

9 Projects in Pre-Bid/Planning Gymnasium Remodel Architect: NTD Architecture Contract Amount: To Be Announced Construction Manager: Bernards Approved Change Orders: To Be Announced Contractor: To Be Announced Revised Change Order: To Be Announced Contract Start: To Be Announced Contract Completion: To Be Announced Scope: Renovation of the 30,843 sq. ft. existing athletics building. Status: Project is Division of the State Architect approved and is in design verification process with the College Design Standards and College User Groups. Swing space plan is in the development stage for this project before the start of construction can be scheduled, tentatively in fall 2009, after completion of the New Gymnasium. 1. View looking south of the existing Gymnasium. Measure L Build Out Future Projects Central Plant Build -Out Status: This project is scheduled as an energy project and is in the design development phase with P2S Engineering, Inc. Physical Science-Northwest Section and Southeast Section Remodel Status: This project is in the design development/programming phase with WWCOT Architects. Liberal Arts and Letters Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure. Library Remodel / Expansion Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure. Page 9 of 13

10 Projects Completed Physical Science Complex-Roof Replacement Architect: WWCOT Architects Original Contract: $623,636 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Cabral Roofing and Waterproofing Corp. Revised Contract: $623,636 Contract Start: May 21, 2009 Contract Completion: July 17, 2009 Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof. 1. Completed roof at the Physical Science building. Library Lawn/Fontana Phase II Landscaping Architect: Steve Frenken Landscape Architecture Original Contract: $385,000 Construction Manager: Bernards Approved Change Orders: ($450) Contractor: Land Forms Landscape Construction Revised Contract: $384,550 Contract Start: August 20, 2008 Contract Completion: November 25, 2008 Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga Campus. 1. Landscaping at the Fontana Campus. 2. Landscaping at the Rancho Cucamonga Campus. Page 10 of 13

11 Projects Completed Health and Life Science (HLS) Re-Roofing Architect: WWCOT Architects Original Contract: $456,169 Construction Manager: Bernards Approved Change Orders: $16,383 Contractor: Best Contracting Services, Inc. Revised Contract: $472,552 Contract Start: January 1, 2008 Contract Completion: June 13, 2008 Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof. 1. Newly installed metal roof. Physical, Health, Life Science (PHLS) Renovations Architect: WWCOT Architects Original Contract: $8,196,500 Construction Manager: Bernards Approved Change Orders: $871,357 Contractor: PW Construction, Inc. Revised Contract: $9,067,857 Contract Start: June 16, 2007 Contract Completion: Phase 1: June 18, 2008 Phase 2: August 15, 2008 Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings. 1. Completed dental lab at Physical Science. Page 11 of 13

12 Projects Completed New Marquee Sign Architect: Hammel, Green & Abrahamson, Inc. Original Contract: $180,000 Construction Manager: Bernards Approved Change Orders: $1,500 Contractor: Quiel Bros. Electric Sign Revised Contract: $181,500 Contract Start: December 27, 2007 Contract Completion: June 2008 Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces. 1. New marquee sign at Haven Avenue entrance. Parking Lot #12/Elevator Architect: GKK Works Original Contract: $1,897,007 Construction Manager: Bernards Approved Change Orders: $68,534 Contractor: Edge Development, Inc. Revised Contract: $1,965,541 Contract Start: May 16, 2007 Contract Completion: November 11, 2007 Scope: This project completely re-constructs Parking Lot 12 (Phase I) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase II) was also constructed connecting the VSS facility to Parking Lot Elevator tower and stairs leading to VSS. Page 12 of 13

13 Chaffey Community College District Measure L Program July 2009 Program Fund Sources: Program Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Program Budget Other Funds, $130,546,644 Accrued Bond Interest, $8,737,680 Original Measure L Bond, $229,830,000 Bond Refinance Proceeds, $2,300,000 Accrued Bond Interest, $8,737,680 Bond Refinance Proceeds, $2,300,000 Original Measure L Bond, $229,830,000 Fund Source Amount Percentage of Total Fund Source Amount Percentage of Total Original Measure L Bond $229,830, % Original Measure L Bond $229,830, % Bond Refinance Proceeds $2,300, % Bond Refinance Proceeds $2,300, % Accrued Bond Interest $8,737, % Accrued Bond Interest $8,737, % Other Funds $130,546, % Total Measure L Bond Funds $240,867, % Total Program Funds $371,414, % Program Committed Costs: Program Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Remaining Balance, $123,013,104 Remaining Balance, $49,124,261 Committed (Expensed or Encumbered), $248,401,219 Committed (Expensed or Encumbered), $191,743,419 Total Program Funds $371,414, % Total Measure L Bond Funds $240,867, % Committed (Expensed or Encumbered) $248,401, % Committed (Expensed or Encumbered) $191,743, % Remaining Balance $123,013, % Remaining Balance $49,124, % Page 13 of 13

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN. CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS AUBURN. GARDEN OF MEMORY AUBURN MEMORIAL STUDENT AFFAIRS HOLCOMBE NORTON PARTNERS LANDSCAPE SERVICES The Auburn Memorial wall includes excerpts from the Auburn

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction Phase 1 Overview The Re-routed Q train will

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY 1.1 Campus Program Summary There are five (5) projects in pre-design and programming; four (4) are in design; and five (5) in construction. A summary of the Trade-Tech construction

More information

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

Construction Look Ahead February 2018

Construction Look Ahead February 2018 To our 9 th and Colorado redevelopment neighbors: Construction Look Ahead February 2018 Block 7South Exterior Bridge walkway between Block 7 South building and the existing Parking Garage the installation

More information

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN. CONSTRUCTION UPDATE June THIS IS AUBURN. RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Lobby of the Risk Management and Safety

More information

FUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013

FUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013 Project Summary and Total Project Cost NEW CONSTRUCTION PROJECTS A. Campus Center Replacement $ 29,474,691 B. East Campus Classroom and Office Building(s) $ 34,674,804 C. Wake Center Replacement $ 40,051,128

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

LOVEJOY Independent School District

LOVEJOY Independent School District Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $

More information

Commercial Remodel Permit

Commercial Remodel Permit Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Mount Vernon Elementary School Grades PK 5

Mount Vernon Elementary School Grades PK 5 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803

More information

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER SUMMARY OGDENSBURG, NY The New York Main Street program (NYMS) is administered by the Office of Community Renewal (OCR) under the direction of the New York State Housing Trust Fund Corporation (HTFC).

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No Laker Hall Program Study Intercollegiate Athletics Preferred Concept & Project Phasing SUCF Project No. 101009 26 January 2017 Agenda Preferred Concept - Existing Site Plan - Existing Floor Plans - Space

More information

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath Trade Package Base Bid P and P BOND Alternate #1: drop off canopy Alternate #2: bike rack canopies Alternate #3: courtyard Alternate #4 Unit Door Alternate #5 Solid Surface Alternate #6A Bath Alternate

More information

Central Michigan University Meeting Date: February 7, 2007 Project No.: Page 1 of 6

Central Michigan University Meeting Date: February 7, 2007 Project No.: Page 1 of 6 Project No.: 7105.037 Page 1 of 6 Topic: Location: Time: Present: Project Cost Estimate + Schedule Review Design Discussion 50% CD Owner Review Comments Architectural, Landscape and Civil Power Plant Conference

More information

East Los Angeles College Project Priority List Occupancy Date

East Los Angeles College Project Priority List Occupancy Date East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media

More information

Operational Services Facility Innovation & Readiness Stakeholder Team

Operational Services Facility Innovation & Readiness Stakeholder Team Operational Services Facility Innovation & Readiness Stakeholder Team A great place for kids to learn. A great place for employees to work. A place our community can be proud of. 21 st Century School District!

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

RATIONALE AND REASONING

RATIONALE AND REASONING RATIONALE AND REASONING Background The main tenant residing in BMH is the Anthropology Department. Most of the building systems constructed in the building are over forty years old and are at the end of

More information

CARL E. SCHLUTER ELEMENTARY SCHOOL

CARL E. SCHLUTER ELEMENTARY SCHOOL CARL E. SCHLUTER ELEMENTARY SCHOOL Carl E. Schluter Elementary School Campus Data CARL E. SCHLUTER ELEMENTARY SCHOOL 1220 Mesa Crest Drive, Haslet, Texas 76052 Year Built 2011 Approx. Total Square Footage

More information

John T Pirie Fine Arts & Academic Center ES 650 E 85th St Chicago, IL 60619

John T Pirie Fine Arts & Academic Center ES 650 E 85th St Chicago, IL 60619 E 8th St Chicago, IL 19 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

3D/International. Facility Condition Assessment Report. Coast Community College District

3D/International. Facility Condition Assessment Report. Coast Community College District Facility Condition Assessment Report Coast Community College District February 28, 2003 INTRODUCTION...2 Table of Contents ASSESSMENT OF EXISTING FACILITIES...4 Background Facilities Summary of Findings

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Facilities and Planning Department Measure E Update March 2017

Facilities and Planning Department Measure E Update March 2017 State Seismic Mitigation Program (SSMP) The District s application for SSMP funds for Horace Mann Building A will be reviewed for approval by the State Allocation Board at its next scheduled meeting on

More information

CODE COMPLIANCE PLAN REVIEW PROCEDURES

CODE COMPLIANCE PLAN REVIEW PROCEDURES CODE COMPLIANCE PLAN REVIEW PROCEDURES 1. All construction for state agencies on state-owned or state leased-purchased properties or facilities are to submit design documents for code compliance plan reviews

More information

CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST

CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST Check off each item that is included within the submitted Contract Documents Review Package. Provide a written explanation for any omissions. The following items,

More information

MANHATTAN COLLEGE STUDENT COMMONS

MANHATTAN COLLEGE STUDENT COMMONS MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

Project Information Session / Meet and Greet # 3

Project Information Session / Meet and Greet # 3 ATL WEST DECK COMPONENT Project Information Session / Meet and Greet # 3 Holder-Austin-Moody-Bryson, a Joint Venture October 10 th, 2017 Agenda 1. HAMB, a JV Company Overview 2. ATL West Deck Project Description

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

SYLLABUS 8/14/2012 CONE- 231 Construction Estimating Fall, 2012 Rev. 0. Course Syllabus. Fall, 2012

SYLLABUS 8/14/2012 CONE- 231 Construction Estimating Fall, 2012 Rev. 0. Course Syllabus. Fall, 2012 Course Syllabus Fall, 2012 COURSE DESCRIPTION This semester will be entirely focused on the application of BIM (Building Information Modeling) to the estimating process through the application of three

More information

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects PROVINCE OF NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND INFRASTRUCTURE RENEWAL DTIR Document DC350 APPENDICES DESIGN REQUIREMENTS Appendix A Performance Criteria for Design Projects 2010 EDITION Printed

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Madison School District. Strategic Five-Year Facility Maintenance Plan

Madison School District. Strategic Five-Year Facility Maintenance Plan Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since

More information

Penns Valley Area School District

Penns Valley Area School District Penns Valley Area School District Table of Contents District Overview... Tab 1/Page 1 Educational Program Overview... Tab 2/Page 3 Existing Conditions Analysis... Tab 3/Page 7 Enrollment Report... Tab

More information

Creative Performing Media Arts Middle School

Creative Performing Media Arts Middle School Dawne St Kilkee St Enelra Pl Creative Performing Media Arts Middle School 5050 Conrad Ave. San Diego, CA 92117 Sub-district: A Cluster: Madison Year School Opened: 2002 Grades: 6-8 Arlene Pl 3 2 Conrad

More information

WATER CONSERVATION ACTION PLAN

WATER CONSERVATION ACTION PLAN WATER CONSERVATION ACTION PLAN CONTENTS Purpose History Regulations Monitoring & Verification Water Conservation Measures Program Notes PURPOSE This plan is written to provide an actionable continuous

More information

Arlington Independent School District Board of Trustees Communication

Arlington Independent School District Board of Trustees Communication Arlington Independent School District Board of Trustees Communication Meeting Date: September 21, 2017 Consent Item Subject: Bids Purpose: To provide the Board of Trustees the opportunity to review the

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

SACRAMENTO CITY UNIFIED SCHOOL DISTRICT Sustainable Facilities Master Plan

SACRAMENTO CITY UNIFIED SCHOOL DISTRICT Sustainable Facilities Master Plan Albert Einstein Albert Einstein Campus Entry Student Centered Education School Mission Statement EXORE, DISCOVER, CREATE Mirandy Drive Site Plan of Campus Narrative Summary The site is just over 20.5 acres

More information

Section 4 - Design and Construction Overview

Section 4 - Design and Construction Overview Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

PERFORMANCE PROGRESS REPORT SF-PPR. 2. Federal Grant or Other Identifying Number Assigned by Federal Agency 60NAN B

PERFORMANCE PROGRESS REPORT SF-PPR. 2. Federal Grant or Other Identifying Number Assigned by Federal Agency 60NAN B Print Form PERFORMANCE PROGRESS REPORT SF-PPR 1.Federal Agency and Organization Element to Which Report is Submitted National Institute of Standards and Technology (NIST) 2. Federal Grant or Other Identifying

More information

BOWIE LEARNING CENTER

BOWIE LEARNING CENTER BOWIE LEARNING CENTER Bowie Learning Center BUILDING DATA BOWIE LEARNING CENTER 900 North Elm St., Weatherford, TX 76086 Year Built 1936 No. of Buildings No. of Portables 0 Approx. Total Square Footage

More information

WATER CONSERVATION ACTION PLAN

WATER CONSERVATION ACTION PLAN WATER CONSERVATION ACTION PLAN CONTENTS Purpose History Regulations Monitoring & Verification Water Conservation Measures Program Notes PURPOSE This plan is written to provide an actionable continuous

More information

Auburn University Facilities Management Policy :

Auburn University Facilities Management Policy : 1. Policy Statement: This document establishes policy for the Auburn University community regarding the funding of Installed and/or Movable Equipment with Deferred Maintenance on maintenance, repair, alterations

More information

Monthly Progress Report November 1, 2011

Monthly Progress Report November 1, 2011 LOS ANGELES MISSION COLLEGE PROPOSITION A/AA BOND PROGRAM & PROPOSITION J BOND PROGRAM Monthly Progress Report November 1, 2011 Health & PE Fitness Center Lobby Page 1 of 14 THIS PAGE IS LEFT INTENTIONALLY

More information

555 Eighth Avenue (Suite 1603) New York, NY Tel: Fax:

555 Eighth Avenue (Suite 1603) New York, NY Tel: Fax: 555 Eighth Avenue (Suite 1603) New York, NY 10018 Tel: 212-868-6961 Fax: 212-868-6963 www.dhallerinc.com A PROFILE OF OUR FIRM D. Haller, Inc. is a construction management firm that works directly for

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Facilities Condition Assessment Qualcomm Stadium

Facilities Condition Assessment Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment Qualcomm Stadium Facilities Condition Assessment AECOM San Diego, California April 2011 Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment

More information

HISTORICAL OVERVIEW OPN ARCHITECTS. Home Office Building of The Bankers Life Building, 1940

HISTORICAL OVERVIEW OPN ARCHITECTS. Home Office Building of The Bankers Life Building, 1940 OPN ARCHITECTS Home Office Building of The Bankers Life Building, 1940 HISTORICAL OVERVIEW Designed as the home office of The Bankers Life Insurance Company by architects Tinsley, McBroom & Higgins in

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

Service Level Agreement for University Facilities

Service Level Agreement for University Facilities Service Level Agreement for University Facilities Facilities-related departments within the Office of the Executive Vice President and Chief Operating Officer (EVP & COO) will provide services to university

More information

Mueller Laboratory Renovation

Mueller Laboratory Renovation Mueller Laboratory Renovation Technical Report #1 By Mark Jackson Construction Management Option 9/19/14 Executive Summary The Mueller Laboratory building on the Penn State University Park campus was built

More information

Office of Planning, Design and Construction. Capital Program Update May 10, 2017

Office of Planning, Design and Construction. Capital Program Update May 10, 2017 Office of Planning, Design and Construction Capital Program Update May 10, 2017 Projects Under Construction Translational Research Center Translational Research Center Phase I Site work Status: Completed

More information

UAA Science Renovation Phase 2 Narrative EXISTING BUILDING SITE

UAA Science Renovation Phase 2 Narrative EXISTING BUILDING SITE UAA Science Renovation Phase 2 Narrative A EXISTING BUILDING SITE The existing building is situated along the campus spine and connected by elevated walkways to the engineering building toward the west

More information

HQ Building Renovation. Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO

HQ Building Renovation. Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO HQ Building Renovation Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO Agenda Roll Call Introduction Presentation of Design Concepts and Cost Estimate Financing Options and Recommendation

More information

Exhibit A EXISTING RTU TO BE SCREENED ' BUILDING A EXISTING TO BE RENOVATED 2,100 SF EXISTING LANDSCAPE AREA TO REMAIN NEW ENTRANCE AREA

Exhibit A EXISTING RTU TO BE SCREENED ' BUILDING A EXISTING TO BE RENOVATED 2,100 SF EXISTING LANDSCAPE AREA TO REMAIN NEW ENTRANCE AREA Received April 9, 08 - AR Exhibit A MIXED USE WITH RESIDENTIAL 44' PROPOSED BUILDING TO MIXED USE BUILDING 6.8' LOT TO LOT DISTANCE TO RESIDENTIAL USE 87.5' BUILDING TO MIXED USE BUILDING 0' 78' 4.6' 0.64'

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (05/15) 02050 Demolition (Create for each existing building)

More information

REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION. University of Wisconsin-Whitewater.

REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION. University of Wisconsin-Whitewater. REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION University of Wisconsin-Whitewater March 2008 Project No. 08B21 TABLE OF CONTENTS PAGE Table of Contents... 2 Project

More information

Appendix A. Facilities Condition Assessment

Appendix A. Facilities Condition Assessment Appendix A Facilities Assessment Facilities Assessment Facilities Assessment s on the Harford Community College campus have been well-maintained and are in excellent condition. Recent renovations to Havre

More information

TENANT CRITERIA MANUAL INSERT PHOTO HERE

TENANT CRITERIA MANUAL INSERT PHOTO HERE G TENANT CRITERIA MANUAL GREENWOOD MALL INSERT PHOTO HERE General Growth Properties, Inc. 110 N. Wacker Drive Chicago, IL 60606 (312)-960-5000 Tenant shall supply and install an electrical meter

More information

CAREERS. in the Construction TRADES

CAREERS. in the Construction TRADES CAREERS in the Construction TRADES Electrical Modern life would not be possible without electricians. If you like to know how electric currents make things work, then this is the trade for you. Qualified

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

MADISON HIGH SCHOOL // Executive Summary

MADISON HIGH SCHOOL // Executive Summary MADISON HIGH SCHOOL // Executive Summary community + wrap-around services arts courtyard arts commons courtyard commons entry Construction Cost $95,000,000 Student Design Capacity 1,700 Project Cost $145,909,717*

More information

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2 OMAHA BASEBALL STADIUM May 21, 2009 Report No. 2 METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska

More information