TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE

Size: px
Start display at page:

Download "TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE"

Transcription

1 TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE Question 1: Question 2: Question 3: Question 4: Question 5: Question 6: When area configurations change within a room, ductwork needs to be relocated to cool each space, and sometimes air flow needs to be increased or decreased as well. Ductwork layouts and airflow calculations are typically completed by an engineer or licensed professional, and is required for permit. Pricing for these changes can vary significantly depending on what the engineer comes up with. For the purposes of the bid, should we provide a "base price" on what we think the HVAC might cost, pending the result of these calculations, which we will provide? Or should we simply figure on no HVAC ductwork or airflow changes? The Vendor will perform no HVAC ductwork or airflow changes. Thermostats will be relocated by FDOT immediately following demolition. Per our discussion at the pre-bid meeting, we are expecting one payment on this project. Please confirm whether we will be required to provide final subcontractor lien releases in advance of us being given this single payment. FDOT is entering into an agreement with the selected Vendor for this project. Payment will be made to the selected Vendor upon the FDOT Contract Manager s inspection and approval of the completed work. We would like to exclude ceiling grid repair in the areas where we are not scheduled to replace the ceiling. Is it possible to include a recommended contingency for this item in case it does in fact need to be replaced? At this time we cannot know what will be required. The Vendor is responsible for ceiling grid repair needs in the areas indicated on Exhibit A, Scope of Services and Construction Plans which include the area of renovation as well as interior offices and common areas where the Vendor is installing the replacement LED fixtures. We would like to confirm that the FDOT will handle low-voltage work, including phones, televisions, audio, and fire alarm. That work is not included in the Scope of Services. Please provide door and hardware schedules, paint schedules, and specifications for drywall as possible. Reference the Exhibit A, Scope of Services, Section II, Services to be Provided, Letter F. Please see questions 7, 8, and 9 below. We would like to confirm that no submittals will be required for this project. Reference the Exhibit A, Scope of Services, Section III, General Requirements, Letter A: Vendor shall complete all work in accordance with all local and state laws and codes. Reference Section IV, Vendor s Responsibilities, Letter B: Vendor shall be responsible for compliance with all Occupational Safety and Health Administration (OSHA) rules and regulations, and Letter C: All work shall

2 comply with all applicable codes and local regulations. Should a failure occur that is attributable to the substandard workmanship of the Vendor or their subcontractor, as verified by a professional with expertise in the designated area, then the Vendor will be responsible for making the necessary repairs needed to rectify the situation and bring the area to the intended condition. Question 7: What are the specifications for Paint? For the wall paint, the Vendor will use Valspar Signature Interior Eggshell Honey Milk paint, or equivalent. The brand designated is for reference purposes and not a statement of preference. The Vendor will patch/repair and paint all wall surfaces created and/or affected/damaged by the construction using the specified wall paint to create a finished uniform appearance of the space. Vendor is not responsible for painting the interior of the offices that are not directly affected by the construction. For the door frame paint, The Vendor will use Benjamin Moore Satin Impervo paint per the following label specifications. Due to compatibility needs with existing surfaces, there will be No Substitute: The Vendor will paint all doorframes in the approximately 11,000 square feet (sf) of renovation space using the specified door frame paint, including the offices that are not directly affected by the construction. Question 8: Question 9: What are the specifications for drywall finish? Vendor is to match existing drywall finish to the greatest extent possible. Vendor will finish new drywall in a manner that gives a consistent, uniform look to the space. What are the specifications for door frames, doors and hardware? Door frames Vendor is to provide new door frames for all relocated wooden

3 doors and all new wooden door installations. New door frames may be knock down door frames as long as they provide a consistent look, when painted, with the existing welded door frames in the space. Doors and hardware - FDOT will provide all wooden doors and door hardware necessary for this work. Vendor will re-use existing wooden doors and door hardware currently in the construction area of the space. FDOT will provide all additional wooden doors that are needed to meet the requirements of the Construction Plans. Door locks/handles in the existing doors to be relocated will remain in place for relocation. Existing door hinges will be used with the relocated doors. Door locks/handles in new doors will be pre-installed and hinges will be provided to the Vendor by FDOT for use in new door installations. No automatic door closers will be provided nor installed. Question 10: Question 11: Question 12: Question 13: What are the specifications for Permitting Documents? The Vendor has electronic and hard copy signed/sealed Construction Plans for this renovation. These Plans have been reviewed and approved by the State Fire Marshal. The Vendor has a copy of the Asbestos Survey for the renovation space confirming the area to be free from asbestos. The Vendor is responsible for all necessary paperwork that is required for permits, including anything additional, if required. What are the specifications for Carpeting and Cove Base? The Vendor is responsible for carpeting removal/demolition and cove base removal, per the scope of services, throughout the approximately 11,000 sf of renovation space, including the offices that are not directly affected by the construction. For offices with built in furniture, carpet removal by cut-around will be necessary as that specific furniture is not being removed for construction or carpeting replacement. Replacement/new carpeting and cove base will be installed by other upon conclusion of the construction/renovation. What are the specifications for vinyl tile flooring in the copy room? Vendor shall take care during demolition and construction to preserve existing vinyl flooring in the copy area that remains after construction per the Construction Plans. What are the specifications for data, phone and Ethernet cabling? The Vendor is not responsible for any replacement cable installation. All data, phone and Ethernet cabling will be provided and installed by other, upon conclusion of the construction/renovation.

4 Question 14: Question 15: Question 16: Question 17: Question 18: Question 19: Question 20: Question 21: What are the specifications for Fire Alarm strobes, horns and sprinkler heads and please provide Vendor contact information. The Vendor is not responsible for any Fire Alarm strobe or horn or sprinkler head relocation, installation or testing upon completion of the project. The Vendor is not responsible for any conduit or wiring needs associated with the installation or relocation of horns, strobes or sprinklers. All Fire Alarm strobes, horns and sprinklers will be installed/relocated and tested via contracted vendor by FDOT. FDOT contracts with Critical Systems Solutions for installation, maintenance and monitoring of our Fire Alarm systems. What is the Vendor s responsibility in the case of a discrepancy between the Construction Plans and the scope of services, for any items not specifically covered in the Technical Questions? In the case of a Vendor Responsibility discrepancy between the Construction Plans and the scope of services, for items not addressed in the Technical Questions and Answers document, the scope of services shall prevail. There is no Engineer s estimate for the project? Correct. There is no Engineer s estimate. There will be no liquidated damages? Correct. There is no liquidated damages on this project. There are no bonds required for this project? Correct. There are no bonds required for this project. Contractors are to include sales tax in their prices? See Exhibit C, Bid Sheet. The bidder is to submit a lump sum price that shall contain all costs to include travel, labor, materials, equipment, overhead, general and administrative, incidental expenses, operating margin, and subcontractor cost, if any. Method of compensation will be lump sum at the conclusion of the project? Exhibit B, Method of Compensation, Section II, Compensation. All permitting will be through the City of Tampa? The Vendor has electronic and hard copy signed/sealed Construction Plans for this renovation. These Plans have been reviewed and approved by the State Fire Marshal. The Vendor has a copy of the Asbestos Survey for the renovation space confirming the area to be free from asbestos. The Vendor is responsible for all necessary paperwork that is required for permits, including anything additional, if required.

5 Question 22: Question 23: Question 24: Question 25: Expected project duration is 40 days from notice to proceed. Any permitting delays will be added onto the back end of the schedule without penalty to the contractor? See Exhibit A, Scope of Services, Section VI, Beginning and Length of Services. Fire Marshall has approved the drawings and is not requiring any additional fire extinguishers or modifications to the fire suppression systems under this contract? Contractor to provide and install conduit necessary to relocate strobes and alarms, but costs associated with the relocation of strobes and alarms are the recertifying of the system is outside of this contract? The Vendor is not responsible for any Fire Alarm strobe or horn or sprinkler head relocation, installation or testing upon completion of the project. The Vendor is not responsible for any conduit or wiring needs associated with the installation or relocation of horns, strobes or sprinklers. All Fire Alarm strobes, horns and sprinklers will be installed/relocated and tested via contracted vendor by FDOT. FDOT contracts with Critical Systems Solutions for installation, maintenance and monitoring of our Fire Alarm systems. See Addendum 2, Change 2. There are no badging requirements for this project? There are no specific requirements for access badges. The Vendor is responsible for insuring the safety and security of our facility by the actions of their employees and subcontractors. Question 26: Question 27: Question 28: Contractor is not required to have full time supervision on the project but is responsible for the conduct of all subcontractors and employees on site? The space adjacent to the work area will be occupied during construction; noise shall be kept to a minimum including, but not limited to, radios? See Exhibit A, Scope of Services, Section IV, Vendor s Responsibilities, Letters E and F. Owner will provide electricity, water, and parking? Yes. See Exhibit A, Scope of Services, Section VII, Services/Materials Provided by the Department, paragraph four. Question 29: Demolition should be performed outside of working hours (8am to 5pm)? See Exhibit A, Scope of Services, Section II, Services to be Provided, Letter B. Question 30: Location for dumpster to be determined?

6 Question 31: See Exhibit A, Scope of Services, Section V, Access to the Site, Delivery and Installation Location, paragraph three. Owner representative has determined that radar of slab is not required? See Exhibit A, Scope of Services, Section III, General Requirements, Letter A: Vendor shall complete all work in accordance with all local and state laws and codes. See Section IV, Vendor s Responsibilities, Letter B: Vendor shall be responsible for compliance with all Occupational Safety and Health Administration (OSHA) rules and regulations, and Letter C: All work shall comply with all applicable codes and local regulations. Should a failure occur that is attributable to the substandard workmanship of the Vendor or their subcontractor, as verified by a professional with expertise in the designated area, then the Vendor will be responsible for making the necessary repairs needed to rectify the situation and bring the area to the intended condition. Question 32: Question 33: Question 34: There will be no modifications to the HVAC system or ducts? The Vendor will perform no HVAC ductwork or airflow changes. Thermostats will be relocated by FDOT immediately following demolition. LED lights will be owner furnished and contractor installed? Yes. See Exhibit A, Scope of Services, Section II, Services to be Provided, Letter D. See Addendum 2, Change 2. Contractor to leave carpet at entry points to limit tracking debris into occupied space? See Exhibit A, Scope of Services, Section II, Services to be Provided, Letter J. Question 35: Question 36: Question 37: Question 38: Wall System shall be industry standard: 3 5/8 20ga Steel Stud with 5/8 Gypsum Wallboard. Any necessity for soundproofing with acoustical batt insulation will be addressed by addendum if needed? The Department is not anticipating the use of sound barriers. Wall adjacent to copy center is a fire wall. All other walls are 9 feet above finish floor? All finishes are to match existing. Specifications for Paint, ACT, and Door Frames will be provided by addendum? See responses to technical questions 7, 8 and 9 above for specifications.

7 Question 39: Question 40: Note A108 on Sheet 7 A01 is incorrect. Existing Doors are to be reused on new frames. Additional doors will be provided by owner from storage. New Door Frames may be either welded or knockdown frames? In the case of a Vendor Responsibility discrepancy between the Construction Plans and the scope of services, for items not addressed in the Technical Questions and Answers document, the scope of services shall prevail. Walls shall receive finish to within ¾ of finish floor? See Exhibit A, Scope of Services, Section II, Services to be Provided, Letter G. Question 41: Question 42: Question 43: Door frames adjacent to construction are to be repainted in new color scheme? Yes. Please see response for technical question 7 for door frame specifications. Signage and Smart Boards will be by owner? Vendor is not responsible signage or smart board purchase or installation. Department will remove current smart boards and signs prior to construction. Note A109 on Sheet 7 A101 to be amended. Installation of carpet and base will be by others? Yes. In the case of a Vendor Responsibility discrepancy between the Construction Plans and the scope of services, for items not addressed in the Technical Questions and Answers document, the Scope of Services shall prevail.

WAYNE COUNTY COMMUNITY COLLEGE DISTRICT DAVENPORT UNIVERSITY SUITE RENOVATION

WAYNE COUNTY COMMUNITY COLLEGE DISTRICT DAVENPORT UNIVERSITY SUITE RENOVATION WAYNE COUNTY COMMUNITY COLLEGE DISTRICT DAVENPORT UNIVERSITY DESIGN DIVISION SOUTHFIELD ROAD SOUTHFIELD, MI 80 o (8) -00 I f (8) - SUITE RENOVATION GENERAL RUIREMENTS The General Provisions of the Contract

More information

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in

More information

Budget Estimate Basic Tenant Improvement

Budget Estimate Basic Tenant Improvement Building work rules, conditions and insurance: 1. Review the work rules. If they are not available no budget should be provided. 2. Hours available for construction 3. Insurance requirements 4. Entities

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...

More information

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

INVITATION TO BID. WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226

INVITATION TO BID. WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226 INVITATION TO BID WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226 February 23, 2016 DESCRIPTION OF SERVICES The intent of this invitation

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS ADVERTISEMENT FOR BIDS 1. INVITATION Sealed proposals for the following work will be received by the University of Kentucky, Construction Procurement Section, Peterson Service Building, 411 South Limestone,

More information

11/1/2016. Smoke detectors will be furnished by MHA and installed by contractor.

11/1/2016. Smoke detectors will be furnished by MHA and installed by contractor. 11/1/2016 Request for Proposal: Make Ready Services McKinney Housing Authority (MHA) requests proposals for vendors to perform make ready services on vacant units within the authority. All bidders must

More information

SECTION MODULAR GALVANIZED RF SHIELDING SYSTEM SPECIFICATIONS

SECTION MODULAR GALVANIZED RF SHIELDING SYSTEM SPECIFICATIONS SECTION 13096 MODULAR GALVANIZED RF SHIELDING SYSTEM SPECIFICATIONS Prepared by: NELCO 125 Chenoweth Lane, Ste. 206 Louisville, KY 40207 (502) 899-3726 13096-1 MODULAR GALVANIZED RF SHIELDING SYSTEM PART

More information

Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan.

Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Addenda - Documents used by the Owner to incorporate interpretations or clarifications, modifications,

More information

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732)

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732) THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ 08904 PHONE (732)572-4420 February 10, 2017 Window Replacements at Samuel J Kronman Building and Park Terrace

More information

PROFESSIONAL DESIGN MANUAL INDEX

PROFESSIONAL DESIGN MANUAL INDEX PROFESSIONAL DESIGN MANUAL INDEX DIVISION A--GENERAL PROJECT REQUIREMENTS... A2-A15 A.1 INTRODUCTION... A-2 A.2 CODES COMPLIANCE (VERIFY CITY REQUIREMENTS)... A-5 A.3 SPECIAL SUBSURFACE AND LAND CONDITIONS...

More information

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO. 16-01 RESTORATION OF THE HISTORIC TRANSPORTATION CENTER PHASE III BID RECEIPT: o Sealed bids shall be received

More information

Vandalia-Butler City Schools

Vandalia-Butler City Schools Vandalia-Butler City Schools Vandalia-Butler City Schools 306 S. Dixie Drive Vandalia, Ohio 45377 www.vbcsd.com Instructions to Bidders and General Conditions Vandalia-Butler City Schools 1 Article 1 Proposal

More information

Building Permit Application Instructions INFORMATION REQUIRED FOR ISSUANCE OF A BUILDING PERMIT

Building Permit Application Instructions INFORMATION REQUIRED FOR ISSUANCE OF A BUILDING PERMIT Building Permit Application Instructions NOTICE: Keep these instructions for your records. Please read and understand these instructions completely prior to completing and submitting your building permit

More information

SIMEILINGS TORSION SPRING CEILING SYSTEM SPECIFICATION

SIMEILINGS TORSION SPRING CEILING SYSTEM SPECIFICATION TORSION SPRING CEILING SYSTEM SPECIFICATION NOTICE: Consult your local Sound Concepts representative or contact Sound Concepts at 204.783.6297 before specifying any optional or custom element as shape,

More information

SPACE TYPE: ENHANCED OFFICE

SPACE TYPE: ENHANCED OFFICE SPACE TYPE: ENHANCED OFFICE Construction Criteria The unit costs for Enhanced Office space types are based on the construction quality and design features in the following table. This information has been

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department Date: March 30, 2011 ADDENDUM No. 3 BID NO.: 10-11/27 PCCD Smart

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

SECTION SPECIAL PROCEDURES. A. Section includes: Administrative and procedural requirements for special project procedures.

SECTION SPECIAL PROCEDURES. A. Section includes: Administrative and procedural requirements for special project procedures. PART 1 - GENERAL 1.1 SUMMARY SECTION 01 35 00 A. Section includes: Administrative and procedural requirements for special project procedures. B. Related Requirements: 1. General Conditions 2. Section 01

More information

Commercial Remodel Permit

Commercial Remodel Permit Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each

More information

DATE: December 15, 2009 BID NO.: FWC 09/ CALENDAR OF EVENTS-BID OPENING DATE CHAGED FROM DECEMBER 18, 2009 to DECEMBER 22, 2009 AT 3:00 PM

DATE: December 15, 2009 BID NO.: FWC 09/ CALENDAR OF EVENTS-BID OPENING DATE CHAGED FROM DECEMBER 18, 2009 to DECEMBER 22, 2009 AT 3:00 PM DATE: December 15, 2009 ADDENDUM NO.: 1 BID NO.: FWC 09/10-48 BID TITLE: CHANGE: ADD: RENOVATION OF THE PRAIRIE LAKES FIELD OFFICE AT THE THREE LAKES WMA CALENDAR OF EVENTS-BID OPENING DATE CHAGED FROM

More information

Florida Army National Guard Construction Facilities Management Office. Scope of Work:

Florida Army National Guard Construction Facilities Management Office. Scope of Work: Florida Army National Guard Construction Facilities Management Office Florida Armory Revitalization Program (FARP) Design Guidelines October 2008 Scope of Work: To provide complete design for the renovation/alterations

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 CONTENTS A. PURPOSE B. DESIGNATED RESPONSIBILITIES C. DEFINITIONS D. PROJECT SUBMITTAL PROCEDURE E. REQUIREMENTS

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL DATE: February 24, 2015 Shimizu North America LLC 909 3rd Avenue, 28th Floor New York, NY 10022 RFP Queries (646) 205-4722 Fax (212) 223-1930 PROJECT: The Japan Foundation New York

More information

ALL-ALUMINUM DOOR & WINDOW FRAMING

ALL-ALUMINUM DOOR & WINDOW FRAMING ALL-ALUMINUM DOOR & WINDOW FRAMING WITH INTEGRATED ALUMINUM DOOR STOP SECTION 08 41 13 ALUMINUM FRAMED ENTRANCES AND STOREFRONTS SPECIFICATION PART 1 GENERAL 1.1 SECTION INCLUDES: A. Prefinished aluminum

More information

CITY OF SANTA ANA PROPOSAL PROJECT NOS.: , , , DOWNTOWN PARKING FACILITY IMPROVEMENTS

CITY OF SANTA ANA PROPOSAL PROJECT NOS.: , , , DOWNTOWN PARKING FACILITY IMPROVEMENTS PROPOSAL BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined

More information

COMMERCIAL CONSTRUCTION GLOSSARY

COMMERCIAL CONSTRUCTION GLOSSARY Michael McCormick September 7, 2012 Contents A... 3 B... 3 C... 4 D... 5 E... 6 F... 6 G... 7 H... 7 I... 7 J... 7 L... 8 M... 8 N... 8 O... 9 P... 9 R...10 S...11 T...12 W...12 About the Author Michael

More information

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements 700 Paris Ave. PO Drawer 9 Port Royal, SC 29935 Application for Permit - P O Drawer 9, Port Royal South Carolina Permit

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Minnesota Healthcare Engineers Association, Fall Conference Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Categories of Rehabilitation Work in Healthcare Facilities Bob Dehler, P.E. robert.dehler@state.mn.us

More information

How to estimate the cost of new air conditioning system to an existing storage warehouse.

How to estimate the cost of new air conditioning system to an existing storage warehouse. How to estimate the cost of new air conditioning system to an existing storage warehouse. 1 How to estimate the cost of new air conditioning system to an existing storage warehouse. Table of Contents Section

More information

DOCUMENT AGREEMENT FORM STIPULATED SUM (SINGLE-PRIME CONTRACT)

DOCUMENT AGREEMENT FORM STIPULATED SUM (SINGLE-PRIME CONTRACT) DOCUMENT 00 52 13 AGREEMENT FORM STIPULATED SUM (SINGLE-PRIME CONTRACT) THIS AGREEMENT IS MADE AND ENTERED INTO THIS DAY OF, 2014, by and between the Ohlone Community College District ( District ) and

More information

Demolition Plan A1 A3. Scale: 3/32" = 1'-0" Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender.

Demolition Plan A1 A3. Scale: 3/32 = 1'-0 Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender. inc. 400-7 avenue edmonton, alberta, canada tr y t: (780) 48 47 f: (780) 48 00 e: lesnider@shaw.ca 4 door to North Common Corridor doors to door to F. H. C. Men Women ELEC/TEL UP Stairs DN F. H. C. DN

More information

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID Solicitation #: ITB 151-2017 Title: Description: SEMINOLE TRIBE OF FLORIDA INVITATION TO BID General Home Repairs (Big Cypress Reservation) The Housing Department of the Seminole Tribe of Florida is requesting

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, CT BUILDING RFP NO.: RFP OPENING DATE: APRIL 16, 3:00 PM ADDENDUM #4.

OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, CT BUILDING RFP NO.: RFP OPENING DATE: APRIL 16, 3:00 PM ADDENDUM #4. OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, RFP NO.: 618-009 RFP OPENING DATE: APRIL 16, 2018 @ 3:00 PM ADDENDUM #4 April 9, 2018 THIS ADDENDUM IS TO PROVIDE ANSWERS TO THE FOLLOWING QUESTIONS: NOTE:

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Scope of Work Bid Package C-4 - West Polished Concrete

Scope of Work Bid Package C-4 - West Polished Concrete Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

Location 1: 7800 Jane St., Vaughan, Ont. Retrofit. Location 2: 6750 Winston Churchill, Mississauga, Ont. Build-out of new leased premises

Location 1: 7800 Jane St., Vaughan, Ont. Retrofit. Location 2: 6750 Winston Churchill, Mississauga, Ont. Build-out of new leased premises Project Name Date: February 2, 2011 To: Re: Bidder COSTI Location 1: 7800 Jane St., Vaughan, Ont. Retrofit Location 2: 6750 Winston Churchill, Mississauga, Ont. Build-out of new leased premises Location

More information

Communications Page 1 of 9

Communications Page 1 of 9 Page 1 of 9 Last Update: April 23 rd, 2014 Introduction Design In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a

More information

Limited Asbestos Demolition Survey

Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Former Fire Station Facility 25 to 45 S. Orlando Avenue Cocoa Beach, Florida Client: City of Cocoa Beach Public Works Department 1600

More information

INVITATION FOR BIDS IFB NO FOR CDCA BATHROOMS/KITCHEN UPDATES. Dr. Julius R. Scruggs, Pastor

INVITATION FOR BIDS IFB NO FOR CDCA BATHROOMS/KITCHEN UPDATES. Dr. Julius R. Scruggs, Pastor INVITATION FOR BIDS First Missionary Baptist Church The Church that is striving to become one of the most loving churches in all the world. 3509 Blue Spring Road, Huntsville, Alabama 35810 256-852-4318,

More information

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO SECTION 01010 - SCOPE OF WORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General provisions of Contract, General Conditions and Technical Specification Sections, apply to this Section. 1.02 PROJECT DESCRIPTION

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES BID PACKAGE DESCRIPTION REQUIRED LICENSE Bid Package No. 1 Asbestos Abatement C-22 Bid Package No. 2 Hard Demolition C-21 Bid Package No.

More information

All Plan Holders 3/3/

All Plan Holders 3/3/ All Plan Holders 3/3/2017 14-044 Marina Middle School Window Replacement and Seismic Retrofit 5 Window Replacement and Seismic Retrofit 11 DSA No. 01-116273 San Francisco Unified School District 16 SFUSD

More information

Building Program Example. Eric Anderson

Building Program Example. Eric Anderson Building Program Example Eric Anderson MINIMUM SPATIAL/FUNCTIONAL REQUIREMENTS SPACE NUMBER OF OCCUPANTS USE TYPE Activity Room 100-200 Assembly Meeting Rooms (5) Referenced at Room Descriptions Business

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services...

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services... EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services...A-1 B. Pre-Design and Start-Up Services...A-3 1. Project Initiation...A-3 2. Development of Architectural Program...A-4

More information

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF WELDED SYSTEM PART 1 GENERAL 1.1 SECTION

More information

(ADDENDUM COVER SHEET) PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA A D D E N D U M NO. 2

(ADDENDUM COVER SHEET) PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA A D D E N D U M NO. 2 (ADDENDUM COVER SHEET) PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA A D D E N D U M NO. 2 BROWARD COUNTY MAIN LIBRARY WIND MITIGATION (NON-SHELTERED MARKET) TO ALL PROSPECTIVE

More information

Construction Indoor Air Quality (IAQ) Management Plan

Construction Indoor Air Quality (IAQ) Management Plan Denver School of Science & Technology Middle School 2000 Valentia Street Denver, CO 80238 Telephone: 303-643-5775 Main Fax: 303-673-5776 Construction Indoor Air Quality (IAQ) Management Plan Denver School

More information

CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL MRI

CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL MRI Architecture Interiors Planning 1165 BRITTMOORE ROAD HOUSTON, TEXAS 77043 (T) 713.626.4300 (F) 713.626.4301 in association with: www.garnerfritsche.com CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL An HCA

More information

APPLICATION FOR CONTRACTOR REGISTRATION AND RENEWAL OF REGISTRATION INSTRUCTIONS AND CHECKLIST

APPLICATION FOR CONTRACTOR REGISTRATION AND RENEWAL OF REGISTRATION INSTRUCTIONS AND CHECKLIST City of North Royalton Mayor Robert A. Stefanik Community Development, Building Division Dan Kulchytsky Building Commissioner 11545 Royalton Road, North Royalton, OH 44133 Phone: 440-582-3000 Fax: 440-582-3089

More information

Interior Remodeling Proposal

Interior Remodeling Proposal Date Prospect Name Address Interior Remodeling Proposal General & Administrative Project supervision Dust protection & site preparation (add Build Clean filtration system during remodeling to control dust)

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R

Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R Product Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433

More information

HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO R

HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO R HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO. 2017-26R Stone Group Architects Project No. 1731 ADDENDUM DATE: September 14, 2017 BID DATE: September 18, 2017 2:00 P.M. C.S.T. SCOPE OF THIS ADDENDUM:

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

New Beautifully Designed Office Condominium Complex. Heading

New Beautifully Designed Office Condominium Complex. Heading FOR SALE DOYLESTOWN EXECUTIVE QUARTERS COMMERCIAL INDUSTRIAL INVESTMENT 2003 Lower State Road Doylestown, Bucks County, PA New Beautifully Designed Office Condominium Complex Heading PRESENTED BY: Kurt

More information

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc.

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc. P a g e 1 PART I. GENERAL 1.01 Scope A. Furnish and install SoftWalls HIGH-TENSION Acoustical & Tackable Stretch Fabric Systems B. Related Work Specified Elsewhere: 1.Preparation of a smooth, flat and

More information

ADDENDUM NO. A. April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR

ADDENDUM NO. A. April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR ADDENDUM NO. A April 18, 2017 BIDDING AND CONTRACT DOCUMENTS FOR LOTHIAN RESIDENCE HALL SEISMIC UPGRADES BID PACKAGE 4 PROJECT NO. 956366 CONTRACT NO. 956366-LF-2017-163 UC Rev. 0, August 1, 2007 UCR Rev

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS 1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new

More information

HIR 1 ACOUSTICAL, IMPACT RESISTANT, TACKABLE WALL PANEL SPECIFICATION

HIR 1 ACOUSTICAL, IMPACT RESISTANT, TACKABLE WALL PANEL SPECIFICATION HIR 1 ACOUSTICAL, IMPACT RESISTANT, TACKABLE WALL PANEL SPECIFICATION NOTICE: Consult your local Sound Concepts representative or contact Sound Concepts at 204.783.6297 before specifying any optional or

More information

Request for Quotation: S&E Door replacement

Request for Quotation: S&E Door replacement Request for Quotation: S&E Door replacement March 2, 206 Belmont College 68094 Hammond Road St. Clairsville, OH 43950 TABLE OF CONTENTS Overview...3. General Description...4 2. Installation Schedule...4

More information

Facilities Planning Policy & Procedure #20

Facilities Planning Policy & Procedure #20 Facilities Planning Policy & Procedure #20 TITLE: OBJECTIVE AND PURPOSE RESPONSIBILITY MINOR PROJECTS To establish a procedure for proper initiation, implementation, filing and closeout for projects included

More information

SECTION SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS REVISED PART 1 GENERAL 1.1 DESCRIPTION:

SECTION SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS REVISED PART 1 GENERAL 1.1 DESCRIPTION: SECTION 13 05 41 SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS REVISED 1-25-13 PART 1 GENERAL 1.1 DESCRIPTION: A. Provide seismic restraint in accordance with the requirements of this section

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 1 RFP-DOT-15/16-4006PM FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 1 DATE: December 2, 2015 RE: RFP Number: RFP-DOT-15/16-4006PM Description: Districtwide Storm Sewer Inspection QUESTION:

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

The following shall be incorporated into the Contract Documents dated 26 MAR 2018.

The following shall be incorporated into the Contract Documents dated 26 MAR 2018. ADDENDUM NO. 2 DATE: April 12, 2018 PROJECT: OWNER: BID DATE: Munising Public Schools Mather Elementary Renovation Munising Public Schools Friday, April 20, 2018 at 10:00 a.m. The following shall be incorporated

More information

DIVISION 9 FINISHES. This Article on Codes, Regulation and Standards shall apply to all Divisions of the Building Standards

DIVISION 9 FINISHES. This Article on Codes, Regulation and Standards shall apply to all Divisions of the Building Standards DIVISION 9 FINISHES This Article on Codes, Regulation and Standards shall apply to all Divisions of the Building Standards 1 Table of Contents SECTION 09 05 13 COMMON FINISHES 2 SECTION 09 51 23 ACOUSTICAL

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 8113.53 - SUSTAINABLE DESIGN REQUIREMENTS - GREEN GLOBES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

GAYLORD COMMUNITY SCHOOLS PROJECT SF SINKING FUND PROJECTS

GAYLORD COMMUNITY SCHOOLS PROJECT SF SINKING FUND PROJECTS PROJECT MANUAL for GAYLORD COMMUNITY SCHOOLS PROJECT SF2.20 BID PACKAGE NO. 2 Gaylord High School Remodeling; and Annex Building (NCMC) Air-Conditioning Project PROJECT NO. 0151-18-Y March 30, 2018 and

More information

MATERIAL ALLOWANCES AND UNIT PRICES

MATERIAL ALLOWANCES AND UNIT PRICES PART 1 - GENERAL 1.1 SECTION INCLUDES ADDITIONS AND RENOVATIONS TO WEST YORK AREA HIGH SCHOOL - #1231 SECTION 012200 MATERIAL ALLOWANCES AND UNIT PRICES A. Measurement and payment criteria applicable to

More information

City of Forest Park Urban Redevelopment Agency (URA) Request for Proposal

City of Forest Park Urban Redevelopment Agency (URA) Request for Proposal City of Forest Park Urban Redevelopment Agency (URA) Request for Proposal INTERIOR DEMOLITION AND REMOVAL OF MOLD, LEAD-BASED PAINT, AND ASBESTOS- CONTAINING MATERIALS Building 101 - First Army Headquarters

More information

Electrical System, Maintenance and Repair Services For the PennDOT District 6-0 Office and Lab Buildings Statement of Work

Electrical System, Maintenance and Repair Services For the PennDOT District 6-0 Office and Lab Buildings Statement of Work Provisions - Governing Specifications - Publication 408 Requirements - Contract Validity Period - Option To Extend - Estimated Quantities - Experience Requirements - Subcontracting - Work Performance Requirement

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

4. Number of drawings required: ( ) Locations of nearest streets

4. Number of drawings required: ( ) Locations of nearest streets CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us COMMERCIAL BUILDING PLAN REQUIREMENTS

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

ADDENDUM NO. 2 PROJECT: Omaha Nation Food Distribution Building Macy, Nebraska Project No ARCHITECT:

ADDENDUM NO. 2 PROJECT: Omaha Nation Food Distribution Building Macy, Nebraska Project No ARCHITECT: ADDENDUM NO. 2 PROJECT: ARCHITECT: Omaha Nation Food Distribution Building Macy, Nebraska Project No. 7-7 PETERS AND ASSOCIATES, ARCHITECTS, P.C. 427 Dayton Circle, Suite Omaha, Nebraska 6837-5558 Date

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST

CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST Check off each item that is included within the submitted Contract Documents Review Package. Provide a written explanation for any omissions. The following items,

More information

Pre-Bid Meeting Minutes Invitation to Bid #15-14-KO

Pre-Bid Meeting Minutes Invitation to Bid #15-14-KO Pre-Bid Meeting Minutes Invitation to Bid #15-14-KO Normal Avenue Bridge Superstructure Replacement Project Normal Avenue over Sacony Creek Borough of Kutztown, Berks County, PA Date: August 5, 2015 Location:

More information

SOLICITATION ADDENDUM NO. 1 RFP THE FOLLOWING CHANGES TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED.

SOLICITATION ADDENDUM NO. 1 RFP THE FOLLOWING CHANGES TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED. Beaverton School District Capital Program Purchasing 16550 SW Merlo Road, Beaverton, OR 97006 Phone: 503-591-4539 SOLICITATION ADDENDUM NO. 1 RFP 15-0013 THE FOLLOWING CHANGES TO THE ABOVE CITED SOLICITATION

More information

Commercial Plans Application Checklist

Commercial Plans Application Checklist Botetourt County, Virginia Development Services Construction Compliance 5 West Main Street, Suite 100 Fincastle, Virginia 24090 Phone: (540) 473-8248 Fax: (540) 473-2018 www.botetourtva.gov Commercial

More information

ATTACHMENT N LEED PROJECT PROCEDURES

ATTACHMENT N LEED PROJECT PROCEDURES ATTACHMENT N LEED PROJECT PROCEDURES 1. All subcontractors, sub-subcontractors and suppliers at all tiers are to include the following items in their trade scope of work: a. Submit data and documentation

More information

ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS Mr. & Mrs. FL Schlagle Library Improvements Kansas City Kansas Public Schools USD 500 IFB 16-043 ADVERTISEMENT FOR BIDS 1.1 PROJECT INFORMATION A. Notice to Bidders: Qualified bidders may submit bids for

More information

ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012

ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012 ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012 RE: Putnam County Emergency Services Disaster Response and Logistical Storage 410 S. State Road 19 Palatka, Florida Architect s Project No. 1132 FROM:

More information

ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS 1. INVITATION ADVERTISEMENT FOR BIDS Sealed proposals for the following work will be received by the University of Kentucky, Capital Construction Procurement Section, Room #322 Peterson Service Building,

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information