ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

Size: px
Start display at page:

Download "ANNUAL ENVIRONMENTAL MANAGEMENT REPORT"

Transcription

1 ORICA KURRI KURRI ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2011 Revision Date Description Author Approver 0 25/07/ Annual Environmental Report K Millard Environmental Advisor N Davies Project Manager

2 TABLE OF CONTENTS 1 INTRODUCTION PROJECT DESCRIPTION PROJECT APPROVAL REQUIREMENT PROJECT STANDARDS AND PERFORMANCE MEASURES PROJECT STATUS PROJECT PROGRESS REVIEW PLANNED PROJECT PROGRESS Phase 1: ANE Plant Construction & Commissioning ENVIRONMENTAL MONITORING AND COMPLAINTS SUMMARY ENVIRONMENTAL MONITORING COMMUNITY COMPLAINTS PROJECT APPROVAL COMPLIANCE _Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page i

3 ABBREVIATIONS ANE CEMP CSS DPI EPL FHA FSS HAZOP ktpa OEH SH&E Ammonium Nitrate Emulsion Construction Environmental Management Plan Construction Safety Study Department of Planning and Infrastructure Environment Protection Licence Final Hazard Analysis Fire Safety Study Hazard and Operability Study kilo tonnes per annum Office of Environment and Heritage Safety, Health and Environment 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page ii

4 1 Introduction In October 2010 Orica Australia Pty Ltd commenced construction of an Ammonium Nitrate Emulsion (ANE) manufacturing facility located at its Kurri Kurri Technology Centre, NSW. The facility will produce a maximum of 250,000tonnes of ANE per annum once commissioned (Figure 1). This plant has been developed to meet increasing demand for ANE product and projected growth in the mining and quarry sector in South Eastern Australia. Approval for this project was granted in July 2010 by the Minister for Planning. This document has been prepared to comply with the requirement of the Project Approval (09_0090) that an Annual Environmental Management Report be prepared for the project. Figure 1: ANE Plant layout 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 1

5 1.1 Project Description The activities covered by the Project Approval include the following: Continuation of all existing operations undertaken at the Technology Centre Construction of ANE production facility to produce up to 250,000 tonnes of ANE per annum Construction of access roads and relevant services infrastructure Construction and operation of storages for raw materials used in manufacturing process including ammonium nitrate solution (ANS), fuel blend ingredients such as canola and diesel oil, thiourea, urea, acetic acid, caustic soda and water. Truck weighing, loading and unloading facilities An office, control room, switch room and quality control laboratory 2 Project Approval Requirement As a condition of project consent Orica is required to prepare an Annual Environmental Management Report by 26 July 2011 and annually following this. This report is required to include the following: 1. Within 12 months of this approval, and annually thereafter, the Proponent shall submit an Annual Environmental Report (AEMR) for the Project to the Director-General. The report must. a) identify the standards and performance measures for the Project; b) describe the works carried out in the past 12 months and the works to be carried out in the next 12 months; c) include a summary of complaints received in the past year and provide comparison with previous years; d) report results of all monitoring required by this approval and EPL for the Project; e) provide analysis of monitoring results in the context of relevant criteria and limits, previous monitoring results and the predictions made in the EA; f) identify any trends in monitoring results over the life of the Project; and g) report on compliance with the project approval, summarise non-compliances in the previous 12 months and report on actions taken to rectify non-compliances. 3 Project Standards and Performance Measures The project is required to meet the standards and conditions detailed in the following documents: Project Approval dated 26 July 2010 Schedules 2 to 4 of Project Approval Environmental Approval dated December 2009 Response to Submissions report dated March 2010 The key standards and performance measures for the operating Project include: 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 2

6 Standard Performance Measure Comment Noise Management Noise generated from construction and operation of the project does not exceed 35dB(A) at nearest residential receptor at any time Proponent shall conduct a Noise Audit for the premises within 3 months of the commencement of operation of the ANE Facility or as otherwise agreed by the Director- General Large buffer area around plant. Noise controls have been incorporated into design and equipment selection. Air Quality Dust All trucks leaving or entering the Project site with loads have their loads covered; Trucks associated with the Project do not track dirt onto the public road network. Requirement incorporated into the Construction Environmental Management Plan. Soil and Water Discharges Section 120 of the Protection of the Environment Operations Act 1997 Bunding to comply with all relevant Australian Standards and the OEH s Storing and Handling Liquids: Environmental Protection, Participants Manual. Plant has been designed to meet bunding requirements. Lighting Australian Standard AS4282(INT)-Control of Obtrusive Effects of Outdoor Lighting Lighting complies with the requirements of the standard. Lighting compliance has been assessed during the design phase. Production Limits Production not to exceed prescribed levels. ANE 250ktpa Requirement incorporated into design. Performance standards for the construction phase of the project were incorporated into the Construction Environmental Management Plan (CEMP) and Environmental Approval (EA). These documents include requirements associated with air quality, water quality, sediment and erosion control, noise, traffic and heritage. 4 Project Status 4.1 Project Progress Review During the past 12 months there has been significant activity associated with the construction of the ANE Plant. Construction activities, as defined in the Project Approval, commenced in October 2010, and have included: Vegetation clearing for plant area and site access Construction of access roads Connection of services infrastructure 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 3

7 Installation of foundations and construction of site sheds Commencement of installation of plant and equipment Commencement of installation of weigh bridge 4.2 Planned Project Progress Phase 1: ANE Plant Construction & Commissioning Construction of the ANE Plant is expected to be completed during October 2011, following which commissioning will commence. Prior to the commencement of operation of the Ammonium Nitrate Emulsion Plant the following key activities are to be undertaken: Hydrostatic testing of tanks and equipment Installation of remaining plant, tanks and equipment including pipework and cabling Completion of landscaping works Pre-commissioning of equipment Operation is expected to commence in early December Environmental Monitoring and Complaints Summary 5.1 Environmental Monitoring The Project Approval and Environment Protection Licence (EPL) do not include any requirements for the undertaking of Project specific environmental monitoring during the construction phase of the Project. Following the commissioning of the ANE Plant monitoring will be undertaken to assess compliance with relevant conditions as outlined in the Project Approval. 5.2 Community Complaints During the first 12 months of the Ammonium Nitrate Plant construction project there were no community complaints received by the site in relation to Project activities. 6 Project Approval Compliance A review of the current status of compliance with the Project Approval is detailed in the table below. Where there was not complete compliance with the condition actions to address the issues are detailed. 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 4

8 SUMMARY OF KEY PROJECT APPROVALS Issue Condition Requirement Compliance Status Schedule 2: Administrative Conditions 1 Implement all reasonable and feasible measures to prevent and/or minimise any harm to the environment that may result from the construction and/or operation of the Project 2 Project to be carried out in accordance with the EA, Statement of Commitments, Submissions Report and the Project Approval. 3 Conditions of approval prevail in the event of inconsistency. Management plans and project management activities have been undertaken to ensure that environmental harm during construction activities is minimised. 4 Comply with the requirements of the Director-General No issues were identified 5 Production capacity limits for Ammonium Nitrate Emulsion Plant and equipment has been designed to a maximum annual production capacity of 250ktpa 6 Surrender of Existing Development Consents Surrendered to Cessnock City Council on 6 July Plan, studies and documents may be submitted on a progressive basis. 8 All new buildings and structures on the Project Site are constructed in accordance with the relevant requirements of the Building Code of Australia. 9 The Proponent is required to repair any public infrastructure damaged as a result of the Project. Buildings are being designed in accordance with the relevant requirements. Construction certificates have been obtained for relevant buildings. No repairs were required to be undertaken. 10 Undertaking of a dilapidation report prior to the commencement of construction. The report is to be undertaken in consultation with the RTA and a copy submitted to the Director General 11 Obtain approval from service providers prior to commencement of utility construction activities A dilapidation report was prepared in consultation with RTA and submitted to DPI on 25 February 2011 Approval was obtained from Energy Australia for the electrical infrastructure. 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 5

9 Issue Condition Requirement Compliance Status Schedule 3: Specific Environmental Conditions 12 Ensure all equipment is maintained and operated in a proper and efficient manner. 1 Undertake the following studies and submit to DPI Director-General for approval: The CEMP details the systems installed to ensure compliance with this condition. a) Fire Safety Study (FSS) The FSS was submitted on 9 February 2011 and a response was received from Fire Rescue NSW (FRNSW) on 3 May Further information is currently being prepared for FRNSW. b) Hazard & Operability Study The HAZOP was submitted to the DPI 15 February DPI approved the study on 18 February c) Final Hazard Analysis The Phase 1 FHA was submitted to the DPI on 8 February DPI approved the study on 18 March d) Construction Safety Study The Construction Safety Study was submitted to DPI on 8 February Approval was obtained from DPI on 18 February Undertake the following studies and submit to DPI Director-General for approval: Emergency Plan (update) Safety Management Plan These studies were not required to be submitted 3 Submission of Pre-Startup Compliance Report This report was not required to be submitted 4 Submission of Post-Startup Compliance Report This report was not required to be submitted 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 6

10 Issue Condition Requirement Compliance Status 5 Undertake a Hazard Audit of the site and submit a report to the Director- General 6 Comply with the requirements of the Director-General in relation to conditions Site access, roadways and parking to be designed in accordance with relevant Australian Standards. 8 Prepare and implement a Concept Design Plan for the intersection of George Booth Drive and Echidna Drive. 9 Enter into a Works Authorisation Deed with RTA for upgrade work to intersection 10 Prepare a Road Transport Protocol prior to the commencement of construction and operation. This report was not required to be submitted Requirements have been incorporated into the project management plan. The roadways, access and parking have been designed in accordance with relevant standards. The intersection upgrade was not required The intersection upgrade was not required A Road Transport Protocol was included in the CEMP. Operational traffic will be considered when relevant. 11 Independent Traffic Audit Not required to be undertaken 12 Within 6 months of approval implement the offset strategy to the satisfaction of the director general 13 Biodiversity Offset Area conservation mechanism not to be altered without consent of the Director-General 14 Implement a Vegetation Management Plan for the long term management of the Biodiversity Offset Area. An application was submitted to OEH to enter into a Voluntary Conservation Agreement. This report was not required to be submitted 15 Implement Vegetation Clearing Protocol Vegetation Clearing Protocol was included in the CEMP and followed for clearing of the site prior to the commencement of construction. 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 7

11 Issue Condition Requirement Compliance Status 16 Carry out all reasonable and feasible measures to minimise dust generated by the Project 17 Trucks entering or leaving the Project site must have their loads covered and must not track dirt onto public roads 18 Noise generated from the construction and operation of the project shall not exceed 35dB(A) at nearest residential receptor 19 The Proponent shall conduct a Noise Audit for the premises within 3 months of the commencement of operation of the ANE facility or as otherwise directed by the Director-General 20 Implement the recommendations of the Bushfire Threat Assessment included with the EA and also any additional bushfire hazard reduction measures outlines in the Submissions Report CEMP included measures to control dust. Measures for the control of dust were included in the CEMP. Measures for the control of noise were included in the CEMP. Not required to be completed during the period Requirements included in the design. 21 Compliance with s120 of Protection of the Environment Operation Act 1997 There were no water pollution related incidents associated with the Project. 22 Ensure that all chemicals are stored in appropriately bunded areas. CEMP included requirements for management of materials. Design incorporates bunding requirements. 23 Prepare a Soil and Water Management Plan Measures for the control of erosion and sediment were included in the Construction Environmental Management Plan. 24 A Stormwater Management Plan must be included in the design. CEMP included these requirements, where applicable to construction. 25 An Erosion and Sediment Control Plan is to be prepared. CEMP included an Erosion and Sediment Control Plan. 26 Ensure that lighting associated with the Project complies with the latest version of Australian Standard AS 4282(INT)-Control of Obtrusive Effects of Outdoor Lighting A consultant was engaged to provide a report on external lighting to ensure compliance. 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 8

12 Issue Condition Requirement Compliance Status Schedule 4: Environmental Management, Reporting and Auditing 27 Waste to be classified in accordance with DECCW Guidelines 2008 and disposed of to approved premises 28 In the event that skeletal remains, or an Aboriginal object is identified, all construction activities that will or would have the potential to impact on indigenous heritage item(s), shall cease until the DECCW is consulted and their directions complied with 1 Prepare and implement an Environmental Management Strategy for the Project to the satisfaction of the Director-General. 2 Prepare an Annual Environmental Management Report and submit to the DPI Director-General 3 Notify the Director-General and any other relevant agencies of any incident with actual or potential significant off-site impacts 4 An independent Environmental Audit within two years of commencement of operations at the ANE Facility and every 3 years thereafter 5 The following information regarding the Project is to be included on the website: Copy of all current statutory approvals Copy of the current environmental management strategy and associated plans and programs Copy of any Annual Reports (over the last 5 years) Copy of any Independent Environmental Audit, and the Proponent s response to the recommendations in any audit; and Any other matter required by the Director-General Measures for the control of waste were included in the Construction Environmental Management Plan. CEMP included requirements. Aboriginal groups were consulted during the construction period. The CEMP was submitted on 29 September 2010 and DPI approved the document on 7 October Submission of this report by 26 July 2011 There were no incidents relating to the Project that required reporting Not required Copies of information relating to the project were included on the Orica Mining Services website ( 2011_Kurri Annual Environmental Management Report_Rev 0.docx 28/11/2010 Page 9

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KOORAGANG ISLAND ANNUAL ENVIRONMENTAL MANAGEMENT REPORT DECEMBER 2013 Revision Date Description Author Approver 0 14/12/2013 2013 Annual Environmental Report A Taylor S Woodroffe Annual Environmental

More information

Section 75J of the Environmental Planning & Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979 Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 I approve the project application referred to in schedule 1, subject to the conditions in schedule 2. These conditions are

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in Schedule 1, subject to the conditions in Schedule 2.

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

STAGING REPORT ENTIRE PROJECT

STAGING REPORT ENTIRE PROJECT WAREHOUSE & LOGISTICS HUB PROJECT STAGING REPORT ENTIRE PROJECT STATE SIGNIFICANT DEVELOPMENT APPROVAL (SSD 7173) Lot 2171 in DP 1153854 585-649 Mamre Road, Orchard Hills Revision: 1 December 2016 Controlled

More information

Construction Environmental Management Plan

Construction Environmental Management Plan Document Control Title: General Description: Document Path: Construction Environmental Management Plan Document No/Ref: NCX-LLB-07-0001-NN-PL-0001 Revision History Revision Date Description Section/Page

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Independent Environmental Audit

Independent Environmental Audit 1. Macquarie Generation 12-Sep-2013 Independent Environmental Audit Bayswater Power Station Water Management Upgrade Bayswater Power Station Water Management Upgrade Client: Macquarie Generation ABN: 18

More information

Section 75O of the Environmental Planning and Assessment Act 1979

Section 75O of the Environmental Planning and Assessment Act 1979 Concept Approval Section 75O of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, under the Environmental Planning and Assessment Act 1979 (the Act), determine: a) pursuant

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a

More information

APPENDIX 8. Noise Impact Assessment

APPENDIX 8. Noise Impact Assessment APPENDIX 8 Noise Impact Assessment Orica Australia Pty Limited Noise Impact Assessment for Proposed Ammonium Nitrate Emulsion Production Facility and Continued Operation of Orica Mining Services Technology

More information

Moolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment ATTACHMENT 3. Stage 2 Project Approval (08_0135)

Moolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment ATTACHMENT 3. Stage 2 Project Approval (08_0135) Moolarben Coal Complex Open Cut Optimisation Modification Environmental Assessment ATTACHMENT 3 Stage 2 Project Approval (08_0135) Project Approval Section 75J of the Environmental Planning & Assessment

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20593 20-December Licensee HI-QUALITY QUARRY (NSW) PTY LTD PO BOX 42 KEMPS CREEK NSW 2171 Premises HI QUALITY KEMPS CREEK CENTRAL 1503-1519 ELIZABETH DRIVE KEMPS

More information

Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project

More information

The Hon Pru Goward MP Minister for Planning SCHEDULE I. sst Roads and Maritime Services. Land in the suburbs of Hornsby, North Wahroonga,

The Hon Pru Goward MP Minister for Planning SCHEDULE I. sst Roads and Maritime Services. Land in the suburbs of Hornsby, North Wahroonga, I nfrastructu re approval Section 1152;8 of the Environmental Planning & Assessment Act 1979 I grant approval to the State significant infrastructure application referred to in schedule 1, subject to the

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

WILPINJONG COAL ENVIRONMENTAL MANAGEMENT STRATEGY

WILPINJONG COAL ENVIRONMENTAL MANAGEMENT STRATEGY WILPINJONG COAL ENVIRONMENTAL MANAGEMENT STRATEGY WI-ENV-MNP-0001 June 2017 Document Owner Environment and Community Manager Document Approver General Manager Version Approval Date Approver Name 4 June

More information

Environmental Management Strategy

Environmental Management Strategy Document Table of Contents 1 Commitment and Policy... 4 1.1 Introduction... 4 1.2 Purpose and Scope... 8 1.3 Glencore Corporate Practice... 8 1.3.1 EMS Supporting Documents... 9 1.4 Consultation... 12

More information

Balranald Mineral Sands Project

Balranald Mineral Sands Project Balranald Mineral Sands Project NSW Environmental Impact Statement Prepared for Iluka Resources Limited May 2015 Volume 2 Appendix A - Secretary's Environmental Impact Assessment Requirements Appendix

More information

Subsidence Monitoring Program

Subsidence Monitoring Program Subsidence Monitoring Program West Wallsend Colliery Page 1 of 27 Contents West Wallsend Colliery 1.Introduction... 3 1.1 Background... 3 1.2 Purpose and Scope... 3 1.3 Relationship with Other Documents...

More information

Compliance Tracking Program

Compliance Tracking Program Number Project: M4 East Design and Construct Contract Number: 15.7105.1373 Number: Revision Date: 7 April 2016 Rev Date Prepared by Reviewed by Approved by Remarks 0 16/03/2016 CSJ DP&E Submission to DP&E

More information

2.0 Description of Existing Mine Operations

2.0 Description of Existing Mine Operations 2.0 2.1 Mine History Austar Coal Mine is an amalgamation of several older mines and operates within a number of mining leases under 12 separate development consents issued by Cessnock City Council between

More information

Bass Point Quarry. Environmental Management Strategy. Bass Point Quarry Environmental Management Strategy

Bass Point Quarry. Environmental Management Strategy. Bass Point Quarry Environmental Management Strategy Bass Point Quarry Environmental Management Strategy Bass Point Quarry Environmental Management Strategy July 2014 Table of Contents Table of Contents... 1 List of Figures... 2 List of Tables... 2 1.0 Introduction...

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20076 12-June Licensee CLEANWAY ENVIRONMENTAL SERVICES PTY LTD PO BOX 5179 MINTO NSW 2566 Premises 12 SHAW ROAD 12 SHAW ROAD INGLEBURN NSW 2565 Scheduled Activity

More information

Report. PWCS Combined Environmental Compliance Audit /01/01. Prepared for: Port Waratah Coal Services. Prepared by URS Australia Pty Ltd

Report. PWCS Combined Environmental Compliance Audit /01/01. Prepared for: Port Waratah Coal Services. Prepared by URS Australia Pty Ltd a Report PWCS Combined Environmental Compliance Audit 2015 43177954/01/01 Prepared for: Port Waratah Coal Services Prepared by URS Australia Pty Ltd AUSTRALIA DOCUMENT PRODUCTION / APPROVAL RECORD Issue

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 767 01-January Licensee METROPOLITAN COLLIERIES PTY. LTD. PO BOX 402 HELENSBURGH NSW 2508 Premises METROPOLITAN COLLIERY PARKES STREET HELENSBURGH NSW 2508 Scheduled

More information

Looking After Our Environment

Looking After Our Environment Item: 12.06 Subject: DRAFT BIODIVERSITY CERTIFICATION ASSESSMENT AND APPLICATION - PORT MACQUARIE AIRPORT AND SURROUNDING LAND Presented by: Development and Environment Services, Matt Rogers Alignment

More information

WILPINJONG COAL NOISE MANAGEMENT PLAN

WILPINJONG COAL NOISE MANAGEMENT PLAN WILPINJONG COAL NOISE MANAGEMENT PLAN WI-ENV-MNP-0011 June 2017 Document Owner Environmental Advisor Document Approver Environment and Community Manager Version Approval Date Approver Name 3 June 2017

More information

Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS

Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS TASMAN EXTENSION PROJECT PRELIMINARY HAZARD ANALYSIS FEBRUARY 2012 Project No. DCL-09-01 Document No. PHA-C

More information

M4 Widening Motorway: Pitt Street at Parramatta and Homebush Bay Drive at Homebush

M4 Widening Motorway: Pitt Street at Parramatta and Homebush Bay Drive at Homebush M4 Widening Motorway: Pitt Street at Parramatta and Homebush Bay Drive at Homebush Operational Environmental Management Plan April 2017 Sydney Motorway Corporation (ACN 601 507 591) and its controlled

More information

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment Pollution Incident Response Management Plan Newell Highway Trewilga Realignment Contents 1 Introduction... 2 1.1 Purpose and scope... 2 2 Statutory requirements... 3 2.1 Project approval... 3 2.2 Protection

More information

Springvale MPPS Water Treatment Project

Springvale MPPS Water Treatment Project Springvale MPPS Water Treatment Project Construction Environmental Management Plan SMPPS-O-00-M13-00-03 DOCUMENT CONTROL Rev Date Revision Comments Prepared by Reviewed by Approved by 0 18/08/2017 Draft

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Relevant legislation (Administering Authority Commonwealth legislation

Relevant legislation (Administering Authority Commonwealth legislation Commonwealth legislation Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) [Commonwealth Department of Sustainability, Environment, Water, Population and Communities (SEWPaC)] New

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

AUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN

AUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN AUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN Issue 1: January 2007 Final Austar Coal Mine Carbon Based Environmental Pty Limited 2006. This document was prepared solely for the original

More information

Technical Guidance Document for Operational Environmental Management Plan (OEMP)

Technical Guidance Document for Operational Environmental Management Plan (OEMP) Technical Guidance Document for Operational Environmental Management Plan (OEMP) EAD-EQ-PCE-TG-06 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20850 24-November Licensee MACH ENERGY AUSTRALIA PTY LTD LEVEL 2, 179 GREY STREET SOUTH BANK QLD 4101 Premises MOUNT PLEASANT OPERATION 1100 WYBONG ROAD MUSWELLBROOK

More information

Appendix General Environmental Risk Analysis

Appendix General Environmental Risk Analysis Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified

More information

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2012

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2012 MINING LEASE No. 1616 ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2012 MOP Commencement : 1 January 2008 MOP Completion : 1 January 2015 AEMR Commencement : 1 April 2011 AEMR Completion: 31 March 2012

More information

CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN. Kurnell Refinery Conversion Project

CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN. Kurnell Refinery Conversion Project CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Kurnell Refinery Conversion Project January 2014 Table of Contents 1. BACKGROUND... 1 1.1. Introduction... 1 1.2. Project Background... 1 1.3. Site Description...

More information

Construction Environmental Management Plan. Newcastle Gas Storage Facility Main Power Supply Document Number: NGSF-PSV-NAS-EN-PLN-0001

Construction Environmental Management Plan. Newcastle Gas Storage Facility Main Power Supply Document Number: NGSF-PSV-NAS-EN-PLN-0001 Construction Environmental Management Plan Document Number: NGSF-PSV-NAS-EN-PLN-0001 Construction Environmental Management Plan Document Number: Version: 2.0 NGSF-PSV-NAS-EN-PLN-0001 Date: 11 November

More information

Date of Inspection 13/09/2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Aaron Hawkins

Date of Inspection 13/09/2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Aaron Hawkins Manildra Solar Farm ER Site Inspection Report Manildra Solar Farm Construction Environmental Representative (ER) Inspection Report For internal project use only. Document not for external release or use.

More information

1. The impacts of development and settlement intensification on biodiversity and Aboriginal cultural heritage;

1. The impacts of development and settlement intensification on biodiversity and Aboriginal cultural heritage; Your reference Our reference: DOC13/40624 Contact: Liz Mazzer (02) 68835325 Date 8 th August 2013 General Manager Lithgow City Council PO Box 19 Lithgow NSW 2790 Attention: Ms Sherilyn Hanrahan, Strategic

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20734 26-February Licensee JOHN HOLLAND PTY LTD SAMSUNG C&T CORPORATION CPB CONTRACTORS PTY LIMITED PO BOX 411 BURWOOD NSW 1805 Premises WESTCONNEX M4 EAST, HOMEBUSH

More information

Operation Environmental Management Plan

Operation Environmental Management Plan PORT WARATAH COAL SERVICES LIMITED Operation Environmental Management Plan - KCT 120Mtpa Modified Project Approval MP 06_0189 MOD1 Prepared By: Samantha Spicer Revision: 2 Date: 4 th May 2012 Doc Id No.:

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 1552 01-June Licensee PORT WARATAH COAL SERVICES LTD PO BOX 57 CARRINGTON NSW 2294 Premises PWCS KOORAGANG COAL TERMINAL CURLEW STREET KOORAGANG NSW 2304 Scheduled

More information

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY S1014-0340-0008MPW NTS Rev1.doc Print Date 19 February 2009 ISSUE NUMBER 1 DATE 19/02/09 AUTHOR CHECKED MPW SMO Title Page

More information

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2014

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2014 MINING LEASE No. 1616 ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2014 MOP Commencement : 1 January 2008 MOP Completion : 1 January 2015 AEMR Commencement : 1 April 2013 AEMR Completion: 31 March 2014

More information

Central NSW Regional Contaminated Land Policy Template

Central NSW Regional Contaminated Land Policy Template Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction

More information

Planning Proposal - Amendment to Lake Macquarie Local Environmental Plan 2014 Biodiversity Offsets PP_2016_LAKEM_001_00

Planning Proposal - Amendment to Lake Macquarie Local Environmental Plan 2014 Biodiversity Offsets PP_2016_LAKEM_001_00 Planning Proposal - Amendment to Lake Macquarie Local Environmental Plan 2014 Biodiversity Offsets PP_2016_LAKEM_001_00 Local Government Area: ame of Draft LEP: Lake Macquarie City Planning Proposal Biodiversity

More information

STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan

STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan STRATFORD MINING COMPLEX AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN Revision Status Register Section/Page/ Annexure Revision

More information

Energy from Waste Electricity Generation Plant - Preliminary Environmental Impact Statement

Energy from Waste Electricity Generation Plant - Preliminary Environmental Impact Statement 31 October 2013 Director General Department of Planning and Infrastructure 23-33 Bridge Street SYDNEY NSW 2000 Dear Sir, Energy from Waste Electricity Generation Plant - Preliminary Environmental Impact

More information

Version 1 July Ash Management Strategy

Version 1 July Ash Management Strategy Version 1 July 2012 Ash Management Strategy Table of Contents 1. Introduction... 3 2. Regulatory Issues... 3 3. Traditional Ash Markets... 4 4. New Ash Markets and New Technology... 5 5. Ash Management

More information

EMM. Mount Pleasant Project Construction Water Management Plan. Planning + Environment + Acoustics

EMM. Mount Pleasant Project Construction Water Management Plan. Planning + Environment + Acoustics EMM EMGA Mitchell McLennan Mount Pleasant Project Construction Water Management Plan Prepared for Coal & Allied Operations Pty Limited 23 July 2012 Planning + Environment + Acoustics This page has been

More information

Dangerous Goods Safety Management Regulation 2001

Dangerous Goods Safety Management Regulation 2001 Queensland Dangerous Goods Safety Management Act 2001 Dangerous Goods Safety Management Regulation 2001 Reprinted as in force on 25 June 2010 Reprint No. 2B This reprint is prepared by the Office of the

More information

The following documentation was tabled:

The following documentation was tabled: Extract from the 564th meeting of the Agency held on 21 November 2008, in Headquarters, Johnstown Castle Estate, CO Wexford. 3. Report on the Oral Hearing of the Objections to a Proposed Decision on a

More information

Independent Environmental Audit

Independent Environmental Audit April 2016 Independent Environmental Audit Cowal Gold Operations Photo courtesy of Cowal Gold Operations APPLIED ENVIRONMENTAL MANAGEMENT CONSULTANTS REPORT: CGO/REV1/JULY 2016 Independent Environmental

More information

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Contents Page number 4. Planning and statutory requirements 4-1 4.1 Approval under the EPBC Act 4-1 4.1.1 Controlled

More information

Pacific Highway Upgrade Frederickton to Eungai ENVIRONMENTAL MONITORING DATA EPL 20318

Pacific Highway Upgrade Frederickton to Eungai ENVIRONMENTAL MONITORING DATA EPL 20318 Pacific Highway Upgrade Frederickton to Eungai ENVIRONMENTAL MONITORING DATA EPL 20318 May 2014 1 INTRODUCTION The publishing of data refers to the compliance of the Frederickton to Eungai Project (the

More information

BANKSMEADOW TRANSFER TERMINAL ENVIRONMENTAL IMPACT STATEMENT

BANKSMEADOW TRANSFER TERMINAL ENVIRONMENTAL IMPACT STATEMENT BANKSMEADOW TRANSFER TERMINAL ENVIRONMENTAL IMPACT STATEMENT Hyder Consulting Pty Ltd ABN 76 104 485 289 Level 5, 141 Walker Street Locked Bag 6503 North Sydney NSW 2060 Australia Tel: +61 2 8907 9000

More information

PORT OF THURSDAY ISLAND PORT RULES

PORT OF THURSDAY ISLAND PORT RULES PORT OF THURSDAY ISLAND PORT RULES Far North Queensland Ports Corporation Limited ABN: 38 657 722 043 ACN: 131 836 014 PO Box 594 CAIRNS QLD 4870 Telephone: 07 4052 3888 INTRODUCTION DEFINITIONS "Act"

More information

Environmental and Social Management Plan

Environmental and Social Management Plan Environmental and Social Management Plan Capital Works State Highway 205 / Schist Street Intersection Upgrade 21 September 2015 NZTA142200 Page ii Record of amendment Amendment number Description of change

More information

Understanding the State Planning Policy July 2017 Changes to state interest statements, policies and assessment benchmarks

Understanding the State Planning Policy July 2017 Changes to state interest statements, policies and assessment benchmarks Understanding the State Planning Policy July 2017 Changes to state statements, policies and assessment benchmarks This fact sheet outlines the key policy changes to the state statements, policies and assessment

More information

NOISE Management Plan

NOISE Management Plan Bulli Seam Operations NOISE Management Plan Schedule 4, Condition 5 - BSO Project Approval 08_0150 Review History Revision Description of Changes Date By New Document September 2012 As per below 1.0 Revised

More information

5 INFORMATION UPDATE TRAFFIC NOISE ASSESSMENT TESTON ROAD CITY OF VAUGHAN

5 INFORMATION UPDATE TRAFFIC NOISE ASSESSMENT TESTON ROAD CITY OF VAUGHAN Report No. 3 of the Transportation Services Committee Regional Council Meeting of March 24, 2011 5 INFORMATION UPDATE TRAFFIC NOISE ASSESSMENT TESTON ROAD CITY OF VAUGHAN The Transportation Services Committee

More information

Section 3.19 Indigenous Cultural Heritage

Section 3.19 Indigenous Cultural Heritage Section 3.19 Indigenous Cultural Heritage Terminal 0 Environmental Impact Statement Abbot Point Coal Terminal 0 EIS Adani 3.19 Indigenous Cultural Heritage In accordance with the Project guidelines, the

More information

Sydney Port Botany Terminal 3 Project

Sydney Port Botany Terminal 3 Project Construction Environmental Management Plan Sydney Port Botany Terminal 3 Supply and Installation of 11kVPower Cables and Construction and Commissioning of 11kV Main substation Downer Number: 11-484 Revision

More information

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows: SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities

More information

BRAMBLES TAKES LEGAL ACTION AGAINST THE COMMONWEALTH GOVERNMENT IN LAND AND ENVIRONMENT COURT

BRAMBLES TAKES LEGAL ACTION AGAINST THE COMMONWEALTH GOVERNMENT IN LAND AND ENVIRONMENT COURT Brambles Limited ABN 89 118 896 021 Level 40 Gateway 1 Macquarie Place Sydney NSW 2000 Australia GPO Box 4173 Sydney NSW 2001 Tel +61 2 9256 5222 Fax +61 2 9256 5299 www.brambles.com 11 August, 2009 MEDIA

More information

Report for Agenda Item: 2

Report for Agenda Item: 2 QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage

More information

AIRCRAFT MAINTENANCE PTY LTD

AIRCRAFT MAINTENANCE PTY LTD AIRCRAFT MAINTENANCE PTY LTD Operational Environmental Management Plan Prepared by Chief Engineer Date: 30 th December 2008 Version 1.0 INTRODUCTION is an aircraft engineering business that has been operating

More information

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT 13 J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\13. LNG Facility Environmental Management Plan\13 LNG Facility EMP () FINAL PUBLIC track.doc GLNG Project - Environmental Impact Statement

More information

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance South Australia s Environment Protection Authority Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance Clive Jenkins, Ruth Ward and Lara Settimio Outline

More information

Ceres Wind Farm Project Scope Construction and Environmental Management Plan

Ceres Wind Farm Project Scope Construction and Environmental Management Plan REpower Ceres Wind Farm Project Scope Construction and Environmental Management Plan 14 August 2013 Document information Client: REpower Title: Ceres Wind Farm Project Subtitle: Scope Construction and

More information

Tallawarra Stage B - Open Cycle Gas Turbine Power Station Project PRELIMINARY ENVIRONMENTAL ASSESSMENT

Tallawarra Stage B - Open Cycle Gas Turbine Power Station Project PRELIMINARY ENVIRONMENTAL ASSESSMENT Tallawarra Stage B - Open Cycle Gas Turbine Power Station Project PRELIMINARY ENVIRONMENTAL ASSESSMENT Final 29 March 2007 Tallawarra Stage B - Open Cycle Gas Turbine Power Station Project PRELIMINARY

More information

13 Section 32 Summary for the Residential Chapter

13 Section 32 Summary for the Residential Chapter 13 Section 32 Summary for the Residential Chapter The purpose of this section is to present a summary of the evaluation of the objectives, policies and methods of the Residential Zone Chapter of the Proposed

More information

Pollution & Environmental Harm

Pollution & Environmental Harm Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental

More information

Noise Management Plan

Noise Management Plan Boggabri Coal Operations Pty Ltd Noise Management Plan January 2016 Revision Control Chart Rev No Original 1 2 3 4 5 6 7 8 9 Revision Date Prepared by Reviewed by Approved by 25 Jan 2012 N Pennington 4

More information

Construction Environmental Management Plan

Construction Environmental Management Plan Construction Environmental Management Plan Document Reference: Nyngan - CPP CEMP_Rev5.0.docx CPP Project No: 10427 Client Project Ref: Nyngan Solar Farm Connection Current Revision Revision: Date of Issue:

More information

DEVELOPMENT CONSENT MODIFICATION Statement of Environmental Effects

DEVELOPMENT CONSENT MODIFICATION Statement of Environmental Effects BENGALLA MINE DEVELOPMENT CONSENT MODIFICATION for Bengalla Mining Company Pty Limited August 2015 BENGALLA MINE DEVELOPMENT CONSENT MODIFICATION STATEMENT OF ENVIRONMENTAL EFFECTS Prepared by: HANSEN

More information

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17 Quality Manual DRAFT Page 1 of 17 Document Acceptance and Release Notice This is Revision A1 of the East Coast Designer Builders Quality Manual. The Manual is a managed document. For identification of

More information

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695] LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695] 1. Notwithstanding all other permits and clearances, the following clearances shall be obtained prior to

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

aemc Wambo Coal Mine Independent Environmental Audit - June August 2011 Prepared for: Wambo Coal Pty Limited PMB 1 Singleton NSW 2330

aemc Wambo Coal Mine Independent Environmental Audit - June August 2011 Prepared for: Wambo Coal Pty Limited PMB 1 Singleton NSW 2330 Wambo Coal Mine Independent Environmental Audit - June 2011 18 August 2011 Prepared for: Wambo Coal Pty Limited PMB 1 Singleton NSW 2330 Report by: Trevor Brown & Associates ABN: 23 084 906 963 3 Forwood

More information

Coal Mine Particulate Matter Control Best Practice Site-specific determination guideline. November 2011

Coal Mine Particulate Matter Control Best Practice Site-specific determination guideline. November 2011 Coal Mine Particulate Matter Control Best Practice Site-specific determination guideline November 2011 2011 State of NSW and Office of Environment and Heritage With the exception of photographs, the State

More information

State Significant Development and State Significant Infrastructure

State Significant Development and State Significant Infrastructure Planning, Development & Heritage State Significant Development and State Significant Infrastructure Last updated: July 2015 These Fact Sheets are a guide only and are no substitute for legal advice. To

More information

Basic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa

Basic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa Basic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa Open House Public Meeting Insert then choose Picture select your picture. 30 June 2016 Right click your picture and Send

More information

The White Certificate Scheme in New South Wales, Australia

The White Certificate Scheme in New South Wales, Australia The White Certificate Scheme in New South Wales, Australia Dr David Crossley Managing Director Energy Futures Australia Pty Ltd IEA Demand Side Management Programme Task 14 Workshop on White Certificates

More information

(1) Site Suitability PURPOSE

(1) Site Suitability PURPOSE 3.3 Code for Development and Use of Rural Service Industries PURPOSE This purpose of this code is to encourage the development and use of suitable rural service industries on rural, industrial or suitable

More information

SUMMARY OF COMMENTS/RECOMMENDATIONS

SUMMARY OF COMMENTS/RECOMMENDATIONS SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: Shelmerdine Ltd. PROPOSAL NAME: Biomass Energy System CLASS OF DEVELOPMENT: 1 TYPE OF DEVELOPMENT: Gasification Plant CLIENT FILE NO.: 5380.00 OVERVIEW: On

More information

Environmental Management Plan Attachment 5 Environmental Incident Response Plan

Environmental Management Plan Attachment 5 Environmental Incident Response Plan Victorian Desalination Plant Response Plan Document No: ENV-000-PL-005 This Document is the property of Watersure and is protected by copyright. Other than for the purposes and subject to the conditions

More information

Timber harvesting in native State forests

Timber harvesting in native State forests OCTOBER 2008 PRIMEFACT 693 Timber harvesting in native State forests Forest Management There are approximately 2 million hectares of native State forests in NSW. In managing these areas, Forests NSW aims

More information

Environmental Impact Assessment in Western Australia

Environmental Impact Assessment in Western Australia Environmental Impact Assessment in Western Australia Fact Sheet Updated February 2011 An introduction to Environmental Impact Assessment in Western Australia Environmental impact assessment under the Environmental

More information

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES DECEMBER 2013 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)

More information

Operating Requirements Manual 11 October 2015 Version 1

Operating Requirements Manual 11 October 2015 Version 1 Operating Requirements Manual 11 October 2015 Version 1 Contents 1 Introduction 1 2 Interface Risk Management 2 2.1 Interface Risk Assessment 2 2.2 Interface Risk Management Plan 4 2.3 Provision of Assistance

More information

Section 9A 9A Purpose of the Hazardous Substances Provisions

Section 9A 9A Purpose of the Hazardous Substances Provisions Section 9A 9A Purpose of the Hazardous Substances Provisions The Council has a function under section 31 of the RMA to control any actual or potential effects of the use, development or protection of land

More information