1 Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007

2 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations, 2 shared with existing Blue Line 1500 spaces at 3 park and ride lots 27,000 Daily Riders by 2020 Project Completion Summer min travel time from Downtown to Culver City Estimated Cost - $808 million

3 Expo Phase 1 Alignment

4 Trousdale Station

5 Trousdale Station

6 Phase I Construction Overview Construction on the Exposition Light Rail Line commenced in October For the last several months, construction has consisted of utility relocation work and street improvements on Flower Street between 18 th and 23 rd in Downtown Los Angeles. Utility relocation work in the USC/Expo Park area began in April. Construction of the trench from Flower Street to Exposition Boulevard began in July. Over the next several months construction in this area will consist of the following activities: Utility Relocation Activities: Phone & Gas Power & Water Lines Sewer & Storm Drains Major Construction Work Trench Construction 61 Water Line

7 Construction Activities Construction Completed traffic re-routing along Exposition Blvd. west of Figueroa Street and began construction of the jacking pit required to relocate a 61 water line Completed temporary lighting on Flower Street, from Washington Blvd. to 23 rd Street Continue installation of Cast-In-Place Drilled-Holes, (CIDH), piles Continue drilling and installing secant piles for trench wall construction Continue fabrication of pre-cast girders for street crossings at trench structure

8 Phase I Trench Construction Trench Statistics: 2,500 feet in length Occasional weekend closures (8 estimated at this time) 826 CIDH piles form the trench wall Deepest piling is approximately 55 feet, the shallowest is approximately 15 feet Excavation will take approximately 13 months to complete 61,000 cubic yards of dirt will be excavated for the trench This is equal to the capacity of 6,500 dump trucks 13,007 cubic yards of concrete will be used 3.7 million pounds of rebar will be used Will allow Expo trains to run below intersections at Flower / Exposition and Figueroa / Exposition without interrupting vehicle traffic

9 Trench Construction Aerial View

10 Trench Design

11 Phase I Trench Construction Drilling of CIDH piles on Flower Street near the Galen Center

12 Phase I Trench Construction Trench construction activities on Flower Street near the Galen Center

13 Aerial view of 61 Water Line Construction Activities DWP 61 Water Line (relocated due to proximity to trench)

14 61 Water Line Construction Activities 61 Water Line Relocation: Current water line is 10 feet deep, due to trench construction, need to replace at 45 feet The water pipe is 220 feet Receiving pit will be stationed north of Exposition Blvd near Figueroa St Work and storage area will be stationed south of Exposition Blvd on Figueroa St (current triangle area) Exposition Blvd has been widened and shifted to the south closing the existing west bound lanes on Exposition Blvd from Flower St to Trousdale. The new road will still allow east west traffic on Exposition Blvd. Construction will take place from September 2007 thru March 2008

15 Traffic Advisories EXPOSITION BLVD. (westbound - Flower St. to Vermont Ave.): Night work only, one lane will be available for traffic, Sunday night through Friday morning (9 p.m. to 6 a.m.) FIGUEROA BLVD. (southbound and northbound - Jefferson Blvd. to MLK Blvd.): Night work only, various lane closures (ongoing through approximately November 30). Sunday night through Friday morning (9 p.m. to 6 a.m.) FIGUEROA BLVD. (southbound and northbound Jefferson Blvd. to MLK Blvd.): Night work only. Intermittent lane closures. Full closure dates to be determined. Notices will be disseminated 48 hours in advance FLOWER STREET (southbound Washington Blvd. to Exposition Blvd.): Through November 31, various lane closures for utility relocations, lane closures will occur daily from 9 p.m. to 6 a.m. TROUSDALE PKWY: Crosswalk is open for pedestrian use. The intersection is closed to vehicular traffic through end of November. EXPOSITION BLVD: Existing lane detours (westbound from Flower St. to Pardee Way) are in place to allow for LADWP water line relocation RIGHT TURN IMMEDIATELY before Figueroa Blvd. eastbound closed NEW RIGHT TURN at Figueroa Blvd. and Exposition Blvd. will be allowed.

16 Construction Mitigation Efforts Traffic Control Plan Pedestrian and Vehicular Access Noise Mitigation Advance Notification

17 Community Outreach Reminder - a 24-hour hotline phone number (213) has been setup for all construction complaints and emergencies. Team will respond to all construction complaints within 48 hours. All emergencies will be addressed immediately. Will continue to distribute construction notices to local communities prior to the start of new construction activities.

18 Contact Information For more information regarding this project, please contact: Greg Starosky Expo Light Rail Line Phase 1 Representative or gstarosky@exporail.net Gabby Gonzalez Expo Light Rail Line Phase 1 Representative or ggonzalez@exporail.net Adrienne Sasser-Gardner FFP Community Relations Manager or adrienne.gardner@parsons.com

19 Phase 2 Projected Schedule Expo Phase 2 Projected Schedule Project Kickoff January 2007 Public Scoping February/March 2007 Definition of AA/DEIS/DEIR Alternatives October 2007 Public Comment on DEIS/DEIR Spring 2008 Adoption of Locally Preferred Alternative Summer 2008 Circulation of FEIS/FEIR Fall 2009 Begin Construction 2010 Begin Revenue Service

20 ROW and Venice/Sepulveda Alignments

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015 Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update January 14, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 78% complete Construction Packages

More information

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 INFORMATION IS CURRENT AS OF APRIL 19, 2018 AND SUBJECT TO CHANGE 2 Agenda Caledonia Station Update Fairbank Station Update Oakwood Station Update

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Appendix H Mitigation Plan

Appendix H Mitigation Plan Appendix H Appendix H The mitigation plan for Federal Way Link Extension (FWLE) describes Sound Transit s mitigation commitments that will be implemented to avoid or minimize the impacts of the Preferred

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

4.12 Public and Emergency Services

4.12 Public and Emergency Services 4.12 Public and Emergency Services Public services include schools, community centers, cemeteries, and social service providers. Emergency services include fire and police stations and services, hospitals,

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

Final Recommendations Identification of Improvements, Strategies, and Solutions

Final Recommendations Identification of Improvements, Strategies, and Solutions Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...

More information

ADDENDUM TO THE EIR. Specifically, Section of the CEQA Guidelines states:

ADDENDUM TO THE EIR. Specifically, Section of the CEQA Guidelines states: ADDENDUM TO THE EIR Section 15160 of the CEQA Guidelines explains that there are several mechanisms, and variations in environmental documents, that can be tailored to different situations and intended

More information

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018 City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House March 27, 2018 Agenda 1. Construction Team 2. Anticipated Construction Staging 3. Anticipated Construction Schedule

More information

RPM Phase One: Lawrence to Bryn Mawr Modernization

RPM Phase One: Lawrence to Bryn Mawr Modernization RPM Phase One: Lawrence to Bryn Mawr Modernization Public Update April 2018 Chicago Transit Authority RPM program history 2009-2010 2011 2012-2013 2014-2015 2016-2017 2018 2019-2025 Vision Study Environmental

More information

Venice Pumping Plant Dual Force Main Project Draft EIR

Venice Pumping Plant Dual Force Main Project Draft EIR 6.0 PROJECT ALTERNATIVES ANALYSIS 6.1 INTRODUCTION TO PROJECT ALTERNATIVES ANALYSIS The Initial Study for this Project determined that the Project would not impose any long-term or lasting negative impacts

More information

COMPARISON OF PROJECT AGAINST EXISTING CONDITIONS

COMPARISON OF PROJECT AGAINST EXISTING CONDITIONS Chapter 10 COMPARISON OF PROJECT AGAINST EXISTING CONDITIONS The December 2010 court ruling in Northern California, Sunnyvale West Neighborhood Assn, et al v. City of Sunnyvale City Council, has underscored

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Roosevelt Station Construction Kristin Hoffman, Station Project Manager Next Steps

More information

6.2.2 Environmental Consequences and Mitigation Measures

6.2.2 Environmental Consequences and Mitigation Measures 6.2 6.2.1 Introduction The existing conditions, regulatory setting, and methods of analysis for transportation under CEQA are described in Chapter 3, NEPA and CEQA Analysis. Impacts that would result from

More information

I-10 CONNECT. Public Meeting #1

I-10 CONNECT. Public Meeting #1 I-10 CONNECT Public Meeting #1 The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Seismic Boring Study Advance Utility Relocation

More information

Metro Board Action: Motion 22.1

Metro Board Action: Motion 22.1 Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016 Background Motion 22.1 October

More information

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016 Overall project Johnson County Gateway Interchange Project Improvements 87th Street The $288 million Phase 2 DesignBuild project starts construction this spring, with completion by December 31, 2016 Phase

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

Appendix H Mitigation Monitoring Plan

Appendix H Mitigation Monitoring Plan Appendix H Mitigation Monitoring Plan Appendix H No. Impact/Mitigation Measure Implementation & Monitoring 1. Traffic and Transportation Impacts All traffic control plans and mitigation measures, prepared

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

Woodbine Station Upgrades

Woodbine Station Upgrades Community Update Danforth Mennonite Church 1 Easier Access Program Wide Committed to making all stations accessible by 2025 Almost half way there with 34 stations completed Working with the Advisory Committee

More information

LAS VEGAS STREET RAILROAD CROSSING RR/PUC CONNECTION AND PRELIMINARY DESIGN

LAS VEGAS STREET RAILROAD CROSSING RR/PUC CONNECTION AND PRELIMINARY DESIGN LAS VEGAS STREET RAILROAD CROSSING RR/PUC CONNECTION AND PRELIMINARY DESIGN Prepared for: City of Colorado Springs Prepared by: Felsburg Holt & Ullevig 508 South Tejon Street Colorado Springs, CO 80903

More information

EXCAVATION / RIGHT OF WAY PERMIT

EXCAVATION / RIGHT OF WAY PERMIT $25 Application Fee PERMIT# EXCAVATION / RIGHT OF WAY PERMIT NOTE: No permit shall be issued without current Montana Contractors License, Insurance and Bonding on file with the Public Works Department.

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 11. TRANSPORTATION AND CIRCULATION 1. TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 11. TRANSPORTATION AND CIRCULATION 1. TRAFFIC 4. EVIROMETAL IMPACT AALYSIS 11. TRASPORTATIO AD CIRCULATIO 1. TRAFFIC 1. ITRODUCTIO The following section summarizes the information provided in the Traffic Impact Study, SMC Malibu Satellite Campus Project,

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

Maryland Transportation Authority (MDTA)

Maryland Transportation Authority (MDTA) Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David

More information

Executive Summary. Overview

Executive Summary. Overview Executive Summary Overview The Genesee-Finger Lakes Diversion Route Initiative identifies the most suitable diversion routes for Principal Arterial roads in the nine-county Genesee-Finger Lakes Region.

More information

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence. THE PROJECT A freeway segment ranked 6th worst in the Nation, with levels of congestion, pollution and accidents that are simply unacceptable and which have Statewide and National implications. Executive

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

SR 99 Incident Response After- Action Plan

SR 99 Incident Response After- Action Plan SR 99 Incident Response After- Action Plan Background On June 10, 2014 at 1:52 PM, a pickup truck and a passenger car collided on southbound SR 99 (E Marginal Way S), just south of S Spokane St. The SDOT

More information

3.6 GROUND TRANSPORTATION

3.6 GROUND TRANSPORTATION 3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to

More information

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

CROSSTOWN LRT Construction Liaison Committee November 1, 2017 CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole

More information

Florida Gas Transmission Section #3 Hydrostatic Test

Florida Gas Transmission Section #3 Hydrostatic Test Florida Gas Transmission Section #3 Hydrostatic Test 14-Inch Saint Petersburg Lateral Pipeline From East of Lake Magdalene to West of County Line Hillsborough and Pinellas Counties Today s Outline Who

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La

More information

Progress update (November to March) 03/23/2009 2

Progress update (November to March) 03/23/2009 2 Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)

More information

RE: Jackson Row - truck route

RE: Jackson Row - truck route Will Rasbach From: Sent: To: Cc: Subject: Mayor Pat Patterson Tuesday, January 13, 2015 3:46 PM Will Rasbach; Bart Robinson; Randy Barber (rbarber@oxfordms.net); jowens@oxfordpolice.net

More information

Executive Summary October 2017

Executive Summary October 2017 Executive Summary The King of Prussia Rail Draft Environmental Impact Statement/Draft Section 4(f) Evaluation (DEIS) describes and summarizes the transportation and environmental benefits and impacts of

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

CHAPTER 12 TRANSPORTATION. Introduction Setting Impacts and Mitigation Measures of the 2015 Plan Alternatives

CHAPTER 12 TRANSPORTATION. Introduction Setting Impacts and Mitigation Measures of the 2015 Plan Alternatives CHAPTER 2 TRANSPORTATION Introduction Setting Impacts and Mitigation Measures of the 205 Plan Alternatives CHAPTER 2 TRANSPORTATION INTRODUCTION This chapter presents the traffic impact analysis conducted

More information

Center City Connector 101

Center City Connector 101 Center City Connector 101 1 Our mission, vision, and core values Mission: deliver a high-quality transportation system for Seattle Vision: connect people, places, and products Committed to 5 core values

More information

Elizabeth River Tunnels Project. ASHE October Technical Meeting ERT Project Overview October 8, 2015

Elizabeth River Tunnels Project. ASHE October Technical Meeting ERT Project Overview October 8, 2015 Elizabeth River Tunnels Project ASHE October Technical Meeting ERT Project Overview October 8, 2015 Project Location: Hampton Roads, VA ERT Project Scope New, two-lane, WB tunnel Rehab and lifesafety improvements

More information

ES Executive Summary. Introduction. Overview of the Project Area

ES Executive Summary. Introduction. Overview of the Project Area ES.1 Introduction ES Executive Summary The California Department of Transportation (Caltrans), as Lead Agency under the California Environmental Quality Act (CEQA), in cooperation with the Santa Clara

More information

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles

More information

I-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation

I-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation I-11 Project 2017 Nevada Transportation Conference Ryan Wheeler, P.E. NDOT, Senior Project Manager Nevada Department of Transportation nevadadot.com About NDOT NDOT Core Values: Respect treating others

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # )

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # ) H.O. 03/24/14 SP-14-01 Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS #201400001) Request: Approval of a Special Permit for major earthmoving in the A (General Agriculture)

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

4.17 Environmental Justice

4.17 Environmental Justice 4.17 4.17.1 Regulatory Framework and Methodology 4.17.1.1 Regulatory Framework The applicable federal, state, and local regulations that are relevant to an analysis of the proposed project s environmental

More information

Glenmore Causeway Upgrades Project. Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd.

Glenmore Causeway Upgrades Project. Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd. Glenmore Causeway Upgrades Project Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd. Paper prepared for presentation At the Bridges - Links to a Sustainable

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6 UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN CONSTRUCTION, INC. PG. 6 TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT TRAUTWEIN CONSTRUCTION, INC. TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT

More information

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT TAC Agenda Item 09 Mailout 7/12/17 APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT Background The Texas Department of Transportation, in cooperation with the Federal Highway

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

THE KOSCIUSZKO BRIDGE PROJECT. The New York State Department of Transportation. Page 1

THE KOSCIUSZKO BRIDGE PROJECT. The New York State Department of Transportation. Page 1 THE KOSCIUSZKO BRIDGE PROJECT The New York State Department of Transportation Page 1 THE KOSCIUSZKO BRIDGE PROJECT Constructed 70 years ago, the existing Kosciusko Bridge serves more than 160,000 vehicles

More information

Highway 15 Project Hutchinson, MN

Highway 15 Project Hutchinson, MN Highway 15 Project Hutchinson, MN Adjacent Properties and Businesses Meeting Hutchinson Area Chamber of Commerce 1 Agenda Topic 1) Introduce the project scope 2) Project goals and benefits 3) Project timeline

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

FACT SHEETS SAN BERNARDINO COUNTY

FACT SHEETS SAN BERNARDINO COUNTY FACT SHEETS SAN BERNARDINO COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares

More information

TRANSPORTATION MOBILITY PLAN GUIDELINES

TRANSPORTATION MOBILITY PLAN GUIDELINES TRANSPORTATION MOBILITY PLAN GUIDELINES for Development Applications November 2016 Executive Summary The Regional Municipality of York (the Region) is located in the heart of the Greater Toronto Area (GTA)

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority CALL FOR ARTISTS - PUBLIC ART CLIFTON ENHANCEMENT PROJECT CFA NO. 1-2014 Due Date: Friday, March 14, 2014 4:00 P.M. Official Time February 14, 2014 Prospective

More information

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 INTERCHANGE MODIFICATION REPORT FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 PREPARED BY: VIRGINIA DEPARTMENT OF TRANSPORTATION STAUNTON DISTRICT DECEMBER 13, 2006

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY? WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities

More information

Woodburn Interchange Project Transportation Technical Report

Woodburn Interchange Project Transportation Technical Report Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS Prepared for: City and County of Denver 201 West Colfax Avenue, Department 509 Denver,

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

II. Corrections and Additions

II. Corrections and Additions II. Corrections and Additions This section of the Final EIR provides changes to the Draft EIR that have been made to clarify, correct, or add to the environmental impact analysis for the Project (Project).

More information

Chapter ES Executive Summary. Introduction

Chapter ES Executive Summary. Introduction ES.1 Introduction Chapter ES The Federal Transit Administration (FTA) and the Santa Clara Valley Transportation Authority (VTA) have prepared this combined Supplemental Environmental Impact Statement (SEIS),

More information

Venice Pumping Plant Dual Force Main Project Draft EIR

Venice Pumping Plant Dual Force Main Project Draft EIR City of Los Angeles Venice Pumping Plant Dual Force Main Project Draft EIR 4.0 ALTERATIVES UDER COSIDERATIO Alternatives under consideration for this Project are defined by the alignment and construction

More information

PERMITTING AND CONSTRUCTION MANUAL

PERMITTING AND CONSTRUCTION MANUAL PUBLIC RIGHT-OF-WAY CONTENTS PERMITTING AND CONSTRUCTION MANUAL 1. INTRODUCTION 2. PUBLIC SERVICE PROVIDER REGISTRATION 3. CONSTRUCTION PERMITTING PROCEDURE 3.1 Permitting Process 3.2 Permit Application

More information

Public Informational Meeting November 8, 2007 Route 110 and 113 Methuen Rotary Interchange Study

Public Informational Meeting November 8, 2007 Route 110 and 113 Methuen Rotary Interchange Study Public Informational Meeting November 8, 2007 Route 110 and 113 Methuen Rotary Interchange Study Welcome and Introductions Review of Planning Process Prior Study vs. Current Study Timeline and Implementation

More information

Technical Advisory Committee / Policy Advisory Committee. Solution Assessment 5/25/2017. Photo: City of Richmond COMMERCE CORRIDOR STUDY 1

Technical Advisory Committee / Policy Advisory Committee. Solution Assessment 5/25/2017. Photo: City of Richmond COMMERCE CORRIDOR STUDY 1 COMMERCE CORRIDOR STUDY Technical Advisory Committee / Policy Advisory Committee Solution Assessment 5/25/2017 Photo: City of Richmond COMMERCE CORRIDOR STUDY 1 Agenda Welcome and Roll Call Barbara Nelson,

More information

S-09: Auburn Station Access Improvements

S-09: Auburn Station Access Improvements Project Number S-09 Subarea South King Primary Mode Commuter Rail Facility Type Infrastructure Improvements Length Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE

More information

Chapter 6 Avoidance, Minimization, and Mitigation

Chapter 6 Avoidance, Minimization, and Mitigation Chapter 6 Avoidance, Minimization, and Mitigation This chapter provides a summary of the mitigation measures that the City could implement to avoid, minimize, rectify, or compensate for impacts from the

More information

Logistics Park Kansas City (LPKC) Edgerton, KS. Infrastructure, Development And Transportation. September 30, 2013

Logistics Park Kansas City (LPKC) Edgerton, KS. Infrastructure, Development And Transportation. September 30, 2013 Logistics Park Kansas City (LPKC) Edgerton, KS Infrastructure, Development And Transportation September 30, 2013 LPKC Location LPKC Intermodal Facility Progress Photo courtesy of Superior Bowen Asphalt.

More information

A D M I N I S T R A T I V E U S E P E R M I T

A D M I N I S T R A T I V E U S E P E R M I T Planning and Development Department Land Use Planning Division A D M I N I S T R A T I V E U S E P E R M I T 1449 Oxford Street Administrative Use Permit #ZP2015-0075 Project Description: To install a

More information

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing April 2018 Study Purpose and Goals Initiated to address concerns about impacts resulting from cut-and-cover construction

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

Robinson Landing: Pre-Demo Meeting July 6, 2016

Robinson Landing: Pre-Demo Meeting July 6, 2016 Robinson Landing: Pre-Demo Meeting July 6, 2016 Table of Contents 1. Team Introductions 2. Project Overview 3. Phase I Activities Schedule Buildings for Demolition 226 Strand Demolition Cut & Cap of Utilities

More information

VDOT ASSESSMENT DRAFT ENVIRONMENTAL DULLES AIR CARGO, PASSENGER METRO ACCESS HIGHWAY

VDOT ASSESSMENT DRAFT ENVIRONMENTAL DULLES AIR CARGO, PASSENGER METRO ACCESS HIGHWAY LOUDOUN COUNTY PROJECT NUMBER: R000-053-032, P101; UPC NO. 103929 FEDERAL PROJECT NUMBER: STP-5A01(454) VDOT U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION & VIRGINIA DEPARTMENT OF TRANSPORTATION

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

DC Circulator 2018 Service Changes. Outreach Results Report May 2018

DC Circulator 2018 Service Changes. Outreach Results Report May 2018 DC Circulator 2018 Service Changes Outreach Results Report May 2018 2018 Service Changes Outreach results report Table of Contents 1.0 Proposed Major Service Changes... 4 2.0 Comments Collection Methodology...

More information

Bellows Falls Tunnel

Bellows Falls Tunnel Bellows Falls Tunnel Track Lowering Project for Modified Double Stack Container Cars and Auto-Racks ECI Rail Constructors, Inc. Kenneth A Pidgeon, PE Circa 1913 during flood Project Background Project

More information