BSRIA Guide BG6 Why, What, How?

Size: px
Start display at page:

Download "BSRIA Guide BG6 Why, What, How?"

Transcription

1 BSRIA Guide BG6 Why, What, How? Martin Ronceray BSRIA Principal Consultant in Construction process 21 March

2 1994 TN8 A bit of history on BG BG6 (1 st ) 2012 BG6 (3 rd ) 2018 BG6 (5 th ) 1997 TN21 TN BG6 (2 nd ) 2014 BG6 (4 th ) Allocation of Design Responsibilities a code of conduct to avoid conflict Allocation of Design Responsibilities + example drawings A Design Framework for Building Services 2

3 BSRIA Guide BG6 Client Purpose Structure Activities Consultant Contractor Pro-formas Deliverables Lead Support Drawings Process B A C 3

4 BG6 Purpose Details of limitations not always explicit in contracts in specifications in drawings Several parties (stakeholders) involved at different time during the project Different deliverables 4

5 BG6 Purpose Enable more profitable project delivery Greater clarity of each designer s role Reduced conflict within the project team How Why Team design deliverables from each project stage Tighter definition of who designs what Defining who produces which drawing 5

6 BSRIA Guide BG6 Client Purpose Structure Activities Consultant Contractor Pro-formas Deliverables Lead Support Drawings 6

7 BG6 Structure Alignment with stages of RIBA PoW Broadly in line with ACE Sched. of Serv. Focus on MEP aspects Publication Front-end sections Appendices 7

8 BG6 Structure Front-end sections Design process on building projects Design coordination of building services Building Information Modelling (BIM) Level of details and information (LOD/LOI) Contractors designed portion (CDP) Process of using BG6 8

9 BG6 Structure Appendices Appendix A Pro-formas Definitions Illustrations Appendix B 9

10 BG6 Structure Appendix A Pro-formas One pro-forma for each stage Pro-forma acts as checklist for design activities Segmentation of activities General obligations Client and team liaisons Plant & specialist design MEP designs Commissioning Deliverables 10

11 BG6 Structure Appendix A Definitions Definitions for the illustrations Concept, Developed, Technical, Installation, Builders work, Manufacturers, As-built Based on outcome to be shown Typical use at the stage 11

12 BG6 Structure Appendix A Illustrations 3D views from a model Plant room and distribution Layout drawings MEP services Schematic drawings Mechanical and electrical 12

13 BG6 Structure Appendix B Allocating information production Link with pro-formas to identify deliverables Non-exhaustive list of deliverables illustrations (models, drawings) information (specifications, reports) 13

14 BG6 Structure Appendix B Matrix of deliverables List of stages List of services List of who is responsible to deliver what and when 14

15 BSRIA Guide BG6 Client Purpose Structure Activities Consultant Contractor Pro-formas Deliverables Lead Support Drawings Process B A C 15

16 BG6 Process Step 1 Complete pro-formas in Appendix A 16

17 BG6 Process Appendix A Pro-formas Complete the pro-forma for each required stage Identify the party who is going to undertake each design activity Allocate responsibility per party Lead/Review/Support but only one lead/activity Add comments to clarify the scope Remove activities not relevant to the project Additional activities at the end of the pro-forma 17

18 BG6 Process Step 2 Complete associated matrix in Appendix B 18

19 BG6 Process Appendix B Decide which illustrations and other deliverables are required Decide which engineering services are included in the project Assign the name of the team member who will be delivering them Add programme dates to produce a task information delivery plan (BIM Level 2) 19

20 BG6 Process Step 3 Issue the completed pro-formas as part of the contractual requirements Step 4 Review and update Appendix B as deliverables are issued by the project team 20

21 BG6 4 th to 5 th edition Needs for Changes Sub-divisions of Stages 3 and 4 creating confusions Illustrations for MEP services Appendix B (deliverables list) not used much 21

22 BG6 4 th to 5 th edition Stage sub-divisions Co-ordination of services within delivered outputs were sub-divided at Stage 3a, 3b and Stage 4a, 4b, 4c for handover points 22

23 BG6 4 th to 5 th edition Stage sub-divisions However hybrid of these sub-divisions have been used in the procurement market place Stage 4a+ deliver a more developed design Stage 4b- deliver a quite co-ordinated design with some known components Stage 4b+ deliver an almost co-ordinated design with procured plant and components Stage 4c- deliver a co-ordinated design with almost all specialist details 23

24 BG6 4 th to 5 th edition Stage sub-divisions In 5 th edition sub-divisions removed Stage 3 stands as only one stage Stage 4 stands as only one (long) stage with technical design division Feasible design using generic objects Coordinated design using generic objects Coordinated design using specific objects New Appendix C to present examples 24

25 BG6 4 th to 5 th edition New Appendix C Examples for different design responsibility scenarios Aim at presenting some particularities in the pro-formas when consultant and contractor have to interact Some variations when the consultant is appointed by the client or by the main contractor 25

26 BG6 4 th to 5 th edition New Appendix C Example 1 26

27 BG6 4 th to 5 th edition New Appendix C Example 1 MEP consultant (lead) 27

28 BG6 4 th to 5 th edition Illustrations for MEP services Views revised in line with updated definitions Addition of public health services Additional example on electrical services 28

29 BG6 4 th to 5 th edition Appendix B Moved to digital version only Include all deliverables: illustration and other documents Comprehensive matrix of deliverables 29

30 BG6 5 th edition Finalisation and production in the coming months Aim to be published late Spring 30

PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN

PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN PDG PROJECT DESIGN GUIDES D02 PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-D02.0 Date Created: 2 nd May 2012 Date Revised: R01

More information

Employer s information requirements (EIR) An overview of facilities management requirements

Employer s information requirements (EIR) An overview of facilities management requirements Employer s information requirements (EIR) An overview of facilities management requirements > page 1 This document provides an overview of the BIFM employer s information requirements (EIR) template and

More information

STRUCTURAL ENGINEER S SERVICES SCOPE

STRUCTURAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick

More information

Title of presentation. goes here CDM2015. Implementing the role of Principal Designer

Title of presentation. goes here CDM2015. Implementing the role of Principal Designer Title of presentation CDM2015 goes here Implementing the role of Principal Designer Secondary Andrew Leslie title or 26 presenters May 2016 name Andrew Leslie Technical and Standards Manager The Association

More information

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015 BIM 2016 and the NEC Simon Rawlinson, 20 April 2015 Presentation overview Commercial requirements of BIM BIM and NEC Working Together Government requirements for a collaborative digital model Supporting

More information

CONSULTANCY GATEWAY STANDARD OPERATING PROCEDURE (SOP)

CONSULTANCY GATEWAY STANDARD OPERATING PROCEDURE (SOP) CONSULTANCY GATEWAY STANDARD OPERATING PROCEDURE (SOP) STANDARD OPERATING PROCEDURE REFERENCE. PROTECTIVE MARKING PORTFOLIO OWNER SOP/210/10 Finance and Corporate Services Director of Finance START DATE

More information

Promoting better business outcomes through the use of BIM and digital technologies.

Promoting better business outcomes through the use of BIM and digital technologies. Promoting better business outcomes through the use of BIM and digital technologies. Introduction The Role of the BIM Manager Agenda 18:00 Introduction + BIM update by Mike Turpin, Innovating Futures 18:10

More information

CIF BIM Guide Standards & Policies August 2017

CIF BIM Guide Standards & Policies August 2017 BIM Guide August 2017 www.cif.ie BIM Guide Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions?

BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions? BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions? CIC/BIM Pro (2013) Overview Background: Personal / BIM BIM Protocol: Purpose / Scope USA Precedents Protocols: AIA: Document E202

More information

also report to the Project Manager on a day to day basis).

also report to the Project Manager on a day to day basis). Job Title Department Reports to Project Design Manager (PDM) Production Design Manager. (Whilst site based and a member of the project management team, the PDM will also report to the Project Manager on

More information

BIDDING FOR BIM. CIF Bidding for BIM. September

BIDDING FOR BIM. CIF Bidding for BIM. September BIDDING FOR BIM CIF September 2017 www.cif.ie Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

COSCSMO05 SQA Unit Code H99M 04 Prepare and agree a project brief and outline programme in construction management

COSCSMO05 SQA Unit Code H99M 04 Prepare and agree a project brief and outline programme in construction management programme in construction Overview This unit is about managing projects and the team that delivers design solutions to meet the project brief. It is about ascertaining stakeholders' requirements, exploring

More information

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract

More information

1 For definition of a suitable project refer to the competency standards outlined in this document.

1 For definition of a suitable project refer to the competency standards outlined in this document. 3 1 For definition of a suitable project refer to the competency standards outlined in this document. . . . Getting started . In the table below read the evidence required for each unit of competence

More information

Feasibility Consulting & Successful Study Completion

Feasibility Consulting & Successful Study Completion Feasibility Consulting & Successful Study Completion Philippines Mineral Exploration Association Manila ~ 04 July 2011 Hugh Thompson Principal Mining Consultant Brisbane The views and opinions expressed

More information

AT THE FOREFRONT OF THE CONSTRUCTION INDUSTRY WITH BUILDING INFORMATION MODELING (BIM): THE CHALLENGES

AT THE FOREFRONT OF THE CONSTRUCTION INDUSTRY WITH BUILDING INFORMATION MODELING (BIM): THE CHALLENGES AT THE FOREFRONT OF THE CONSTRUCTION INDUSTRY WITH BUILDING INFORMATION MODELING (BIM): THE CHALLENGES 19 th October 2016 BY: IR. SHARIFAH AZLINA RAJA KAMAL What is BIM? WHAT IS BIM? TECHNOLOGY? SOFTWARE?

More information

Inform Practice Note #32

Inform Practice Note #32 Inform Practice Note #32 September 2014 (Version 1 - September 2014) Application of the Potentially Emerging (PE) Status cidb s Inform Practice Notes provide guidance and clarity in achieving client objectives

More information

ISO 14001:2015. EMS Manual.

ISO 14001:2015. EMS Manual. www.iso-9001-checklist.co.uk Insert your company s name or logo, and address. This EMS manual is the property of Your Company. It must not be reproduced in whole or in part or otherwise disclosed without

More information

A Practical Guide To Building Thermal Modelling

A Practical Guide To Building Thermal Modelling BG 48-13 (Building Thermal Modelling)_D3-2010 Legislation cover.qxd 13/08/2013 12:08 Page 1 A BSRIA Guide www.bsria.co.uk A Practical Guide To Building Thermal Modelling By Richard Tudor BG 48/2013 Acknowledgements

More information

Occupational Health and Safety. Improvement Standard

Occupational Health and Safety. Improvement Standard Premier s Department New South Wales Occupational Health and Safety Improvement Standard A tool for measuring OHS performance within NSW Government Agencies OHS IMPROVEMENT STANDARD NSW GOVERNMENT - REVIEW

More information

Part Q Equipment Planning Guidelines

Part Q Equipment Planning Guidelines Part Q Equipment Planning Guidelines Health Facility Guidelines Version 2 May 2017 Table of Contents 1 Preface... 4 2 Introduction to Equipment Planning... 4 2.1 Objectives and Outcomes... 5 3 Key Performance

More information

CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety

CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety Health and and Safety Executive CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety What this event is about A brief background to the changes An outline

More information

Procedure for Stage 8 Post Project Evaluation. Procedure No. 017

Procedure for Stage 8 Post Project Evaluation. Procedure No. 017 Procedure for Stage 8 Post Project Evaluation Procedure No. 017 Print Name Title Date Prepared by C Hanratty CATSO 16 th Feb 05 Reviewed by Corporate Authorisation J.G. MacNamara J.G. MacNamara T.S.O.

More information

CDM 2015: The regulator s experience to date

CDM 2015: The regulator s experience to date Health and and Safety Executive CDM 2015: The regulator s experience to date Simon Longbottom Head of Construction Sector, HSE What is CDM 2015(16) about? CDM applies to all construction work requirements

More information

ENGINEERING MANAGEMENT

ENGINEERING MANAGEMENT ENGINEERING MANAGEMENT Identification Selection Definition Execution Develop engineering to sufficient detail to enable a Class 4 or 5 capital estimate to be prepared for the alternative. Use benchmarking,

More information

CDM Note 002: Principal Designer Appointment

CDM Note 002: Principal Designer Appointment Introduction The part of Network Rail discharging the Client duties, will have to take a key decision when and who to appoint as the Principal Designer, for a change to the infrastructure. This note provides

More information

Managing Contractors (Scotland)

Managing Contractors (Scotland) Managing Contractors (Scotland) University Health and Safety Policy Author: Health & Safety Services 1 Managing Contractors Procedures (Scotland) to support University Health and Safety Policy CONTENT

More information

For Portfolio, Programme, Project, Risk and Service Management. APMP for PRINCE2 Practitioners Graham Williams, Principle Consultant, GSW Consulting

For Portfolio, Programme, Project, Risk and Service Management. APMP for PRINCE2 Practitioners Graham Williams, Principle Consultant, GSW Consulting For Portfolio, Programme, Project, Risk and Service Management for Practitioners Graham Williams, Principle Consultant, GSW Consulting White Paper January 2010 2 for Practioners 2009 Introduction The main

More information

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM Page 1 of 5 The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM By Rick Oehmcke, S.E. Not that many years ago, few structural engineers

More information

BIM (incl. GSL) from an FM Perspective. Mike Packham, BIFM

BIM (incl. GSL) from an FM Perspective. Mike Packham, BIFM BIM (incl. GSL) from an FM Perspective Mike Packham, BIFM Contents Setting the Scene Soft Landings The Benefits The Barriers Conclusions 2 Setting the Scene (1) 3 Setting the Scene (2) There is too much

More information

State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0

State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0 State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements Version 1.0 April 22, 2013 Table of Contents 1. Introduction...... 1 1.1. Mission of the TN OSA

More information

Safety in Building Services Design

Safety in Building Services Design BG 55-14 Safety in BDS COVER_BSRIA Guide Cover 29/07/2014 09:20 Page 1 A BSRIA Guide www.bsria.co.uk Safety in Building Services Design By Richard Tudor BG 55/2014 Acknowledgements 1 This guide was authored

More information

CIC Guidelines Preliminary Design

CIC Guidelines Preliminary Design Version 1.0 / August 2016 Stage 3 of 8 Approval: Of previous stage, design documentation, updated programme and cost plan. List matters from previous stage to be addressed in current stage. Documentation:

More information

Integrating BIM into NEC Contracts webinar

Integrating BIM into NEC Contracts webinar Improvement through collaboration Integrating BIM into NEC Contracts webinar Ian Heaphy and Richard Patterson Today s speakers Ian Heaphy NEC4 Contract Board and Director at IN Construction Consulting

More information

Building Information Modelling (BIM) Implementation Plan September 2015

Building Information Modelling (BIM) Implementation Plan September 2015 Building Information Modelling (BIM) Implementation Plan September 2015 Collaborative, Efficient, Sustainable and Outcomes Focused Procurement in Construction Contents Executive Summary 2-3 1.0 Horizon

More information

An Introduction to Engineering Design in the Nuclear Industry

An Introduction to Engineering Design in the Nuclear Industry An Introduction to Engineering Design in the Nuclear Industry Nuclear Supply Chain Event 28 th April 2016 Part 2: The Design Process Rob Barrand Lead Process Engineer Robert.barrand@nnl.co.uk Overview

More information

Building Services Engineer (mechanical) model career pathway Version 1.0

Building Services Engineer (mechanical) model career pathway Version 1.0 April 2013 Building Services Engineer (mechanical) model career pathway Version 1.0 AIRAH Strategic aim #2 - Closing the skills gap Prepared by: The Australian Institute of Refrigeration Air Conditioning

More information

DATA ITEM DESCRIPTION TITLE: TRAINING EVALUATION DOCUMENT Number: DI-PSSS-81524C Approval Date:

DATA ITEM DESCRIPTION TITLE: TRAINING EVALUATION DOCUMENT Number: DI-PSSS-81524C Approval Date: DATA ITEM DESCRIPTION TITLE: TRAINING EVALUATION DOCUMENT Number: DI-PSSS-81524C Approval Date: 20141120 AMSC Number: N9493 Limitation: DTIC Applicable: No GIDEP Applicable: No Office Of Primary Responsibility:

More information

Annex G to Loughborough University Facilities Management Health and Safety Procedure

Annex G to Loughborough University Facilities Management Health and Safety Procedure Annex G to Loughborough University Facilities Management Health and Safety Procedure Working with Contractors Including the Construction (Design and Management Regulations) 2015 General 1. The Construction

More information

WE ARE UNDERWAY! CDM 2015 CDM 2015 HAS NOW KICKED OFF. ARE YOU AWARE OF THE CHANGES? WALKER MANAGEMENT

WE ARE UNDERWAY! CDM 2015 CDM 2015 HAS NOW KICKED OFF. ARE YOU AWARE OF THE CHANGES? WALKER MANAGEMENT WE ARE UNDERWAY! CDM 2015 CDM 2015 HAS NOW KICKED OFF. ARE YOU AWARE OF THE CHANGES? What are the main changes? A simplification of the regulations with issue of information aimed at individuals (Clients,

More information

Facilities Controller Job Description

Facilities Controller Job Description Job Title: Employer: Location: Responsible to: Responsible for: Facilities Controller Torus 62 Ltd St Helens and Warrington Compliance & Assurance Manager (Facilities and Energy) Operation and coordination

More information

Generic Scope of Works for: Financial Closure. Version: 1 Date: Lead Author: QA d by:

Generic Scope of Works for: Financial Closure. Version: 1 Date: Lead Author: QA d by: Generic Scope of Works for: Financial Closure Version: 1 Date: Lead Author: QA d by: Contents Contents... 2 Objectives... 3 Scope of Work... 3 Overview of scope of work... 3 Detailed Scope of Works...

More information

Core Skills: Contributing Skills: Role Title: Senior Project Manager EXAMPLE. Reference: SFIA level 5

Core Skills: Contributing Skills: Role Title: Senior Project Manager EXAMPLE. Reference: SFIA level 5 Role Title: Senior Project Manager EXAMPLE Reference: SFIA level 5 Core Skills: Requirements definition and management Stakeholder relationship management (REQM) Level 5 (RLMT) Level 5 Financial management

More information

BUSINESS CASE FRAMEWORK AND PROCEDURES

BUSINESS CASE FRAMEWORK AND PROCEDURES BUSINESS CASE FRAMEWORK AND PROCEDURES Section Finance Contact National Capital Manager Last Review May 2014 Next Review May 2017 Approval N/A Document Purpose: This document establishes Massey University

More information

PLACES FOR PEOPLE DEVELOPMENTS JOB PROFILE

PLACES FOR PEOPLE DEVELOPMENTS JOB PROFILE PLACES FOR PEOPLE DEVELOPMENTS JOB PROFILE Job Title: DEVELOPMENT ASSISTANT Report To: PROJECT IMPLEMENTATION MANAGER A. Job Purpose To assist in the delivery of development projects for all of the Group

More information

Quality Management System Manual

Quality Management System Manual March 2017 This manual is proprietary and no part thereof shall be copied without written authorisation from Cracknell Document Control Title Document Number Quality Management System Manual QM-PO-006

More information

ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY

ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 5 LAST MODIFIED 2 December 2010 DATE PRINTED RIBA stages JK JK 5 ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE

More information

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report June 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 06/07/17 Strand Plaza - Liverpool Status Report @ End of

More information

CHANGES TO THE CDM REGULATIONS

CHANGES TO THE CDM REGULATIONS CHANGES TO THE CDM REGULATIONS WHAT DEVELOPERS NEED TO KNOW INTRODUCTION The Construction (Design and Management) Regulations 2015 (CDM 2015) came into force on 6 April 2015 and replace the Construction

More information

CONSULTANCY POLICY Approved by Council 30 June 2011 (minor revisions 19 June 2012)

CONSULTANCY POLICY Approved by Council 30 June 2011 (minor revisions 19 June 2012) CONSULTANCY POLICY Approved by Council 30 June 2011 (minor revisions 19 June 2012) Equality and Diversity This Policy will be applied in a non-discriminatory way, irrespective of an employee s age, disability,

More information

Strategic procurement in capital expenditure the use of program management & delivery

Strategic procurement in capital expenditure the use of program management & delivery Strategic procurement in capital expenditure the use of program management & delivery Project Scope Changes Changing Client Needs Environment of Uncertainty Diverse Stakeholder Interests Community Involvement

More information

Supplier Panel User Guide Interactive Technologies

Supplier Panel User Guide Interactive Technologies Supplier Panel User Guide Interactive Technologies Prepared by: Procurement, Strategy Finance IT and Commercial, Massey University, January 2016 Updated: 26/1/2017. Sitech contact details corrected. Target

More information

UNICEF/EAPRO, Bangkok

UNICEF/EAPRO, Bangkok UNICEF/EAPRO, Bangkok TERMS OF REFERENCE - LONG TERM ARRANGEMENT ********************************************************************************** 1. Background As a joint contribution towards the achievement

More information

Experience at Hinkley Point C: building Information Modelling (bim) and Enterprise Lifecycle Management Solutions Presented By: Sue Hewish & Jason

Experience at Hinkley Point C: building Information Modelling (bim) and Enterprise Lifecycle Management Solutions Presented By: Sue Hewish & Jason Experience at Hinkley Point C: building Information Modelling (bim) and Enterprise Lifecycle Management Solutions Presented By: Sue Hewish & Jason Walker Agenda: Introductions Section 1: Introduction to

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of figures Foreword Acknowledgements 1 Introduction 01 2 What is project planning? 03 3 Why plan? 08 3.1 Reasons to plan 08 3.2 Relevance to different types of organisation 09 4 When to plan

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

PROJECT MANAGEMENT ESSENTIALS. Project Management Plans

PROJECT MANAGEMENT ESSENTIALS. Project Management Plans PROJECT MANAGEMENT ESSENTIALS Project Management Plans BS6079, the British Standard for Project Management, offers guidelines on the level and type of information that should be defined in the early stages

More information

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2014 Rail Safety and Standards Board Limited GE/GN8640 Method on Risk Evaluation and Assessment Issue One; June 2014 Rail

More information

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi Management of BIMProject: BIM Management Plan Cairo University, Faculty of Engineering MSc in Integrated Engineering Design Management IEDM 611: BIM for Facility Management Prepared and Presented by: Mohamed

More information

Government of Saskatchewan. Procurement Standards Involving Conflict of Interest

Government of Saskatchewan. Procurement Standards Involving Conflict of Interest Government of Saskatchewan Procurement Standards Involving Conflict of Interest October 14, 2015 Contents Introduction... 2 Definitions... 2 Application... 2 Other Forms of Prohibited Vendor Conduct...

More information

UK BIM programme Munich Nick Tune Director BuildingSMARTUK & International

UK BIM programme Munich Nick Tune Director BuildingSMARTUK & International UK BIM programme Munich 2013 Nick Tune Director BuildingSMARTUK & International The Government Strategy What is BIM & why is the Government seeking its adoption? Hypothesis Government as a client can derive

More information

Business Case Our Challenge. Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects

Business Case Our Challenge. Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects Business Case Our Challenge How to move from the current position of; Intelligent schematics (P&ID s)

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Measures for Assuring Projects

Measures for Assuring Projects Measures for Assuring Projects APM toolkit June 2016 1 @Association for Project Management 2016 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted,

More information

Health and Safety Toolkit

Health and Safety Toolkit Health and Safety Toolkit H&S Conception, Design & Planning Checklist This checklist is for use at the outset of a project and should be regularly reviewed as the concept and design phases progress. The

More information

Guide - Alternative Procurement - Unsolicited Proposals

Guide - Alternative Procurement - Unsolicited Proposals 1 Introduction 1.1 The Guidelines Good ideas are not the preserve of the public sector. AT welcomes unique, innovative and opportune proposals from business and individuals that support its vision and

More information

Quantity Surveying and Construction

Quantity Surveying and Construction Quantity Surveying and Construction August 2014 Pathway guide Published by: RICS, Parliament Square, London SW1P 3AD. All rights in this publication, including full copyright or publishing right, content

More information

Project Planning: Making partnership work. Discussion with the Real Property Institute of Canada June 15, 2011

Project Planning: Making partnership work. Discussion with the Real Property Institute of Canada June 15, 2011 Project Planning: Making partnership work Discussion with the Real Property Institute of Canada June 15, 2011 Today s discussion The Project Management System at PWGSC The Project Leader role The Project

More information

Please complete this checklist by referencing locations where the relevant material can be found in the OBC document

Please complete this checklist by referencing locations where the relevant material can be found in the OBC document Large Local Major Schemes: Bid for construction funding Part Two: Checklist Please complete this checklist by referencing locations where the relevant material can be found in the OBC document Strategic

More information

Private Public Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management

Private Public Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management Presented by Allan Rotman Sr. Environmental Specialist Context for DBO for SWM in MNA Initiated

More information

Coordination of Consultants

Coordination of Consultants Coordination of Consultants Ontario Association of Architects Practice Tip PT.27 Version 1.0 May 21, 2012 2012 OAA, all rights reserved. Persons who are not members of the OAA must obtain written permission

More information

Implementing Category Management for Common Goods and Services

Implementing Category Management for Common Goods and Services Implementing Category Management for Common Goods and Services Darbi Dillon Office of Federal Procurement Policy 1800 G Street NW, Washington DC 20006 Audit Tax Advisory Grant Thornton LLP 333 John Carlyle

More information

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference: Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File

More information

Developing, Appraising and Approving an Activity Design

Developing, Appraising and Approving an Activity Design Developing, Appraising and Approving an Activity Design Guideline Last updated: 22 September 2016 Approver: PDLT Contents Overview... 2 Drafting Terms of Reference... 3 Terms of Reference drafted by MFAT...

More information

Sample Organizational Chart

Sample Organizational Chart Organisational Structures Basic Concepts Organizational Structure: The formal configuration between individuals and groups with respect to the allocation of tasks, responsibilities, and authorities within

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

Sustainable Design Services

Sustainable Design Services Point. Advisory Sustainable Design Services Building Information Modeling (BIM) Step 1. Download.bimar App p on Google Play or scan the QR code. Step 2. Point device at cover to view it in 3D augmented

More information

Promoting PPP Excellence

Promoting PPP Excellence Promoting PPP Excellence Geoffrey Hamilton Chief, Cooperation and Partnerships Section United Nations Economic Commission for Europe Committee on Sustainable Energy Week 22-26 November 2010 Overview PPPs

More information

Convergence of industrial classification between NACE and NAICS First report of the working group October 2000

Convergence of industrial classification between NACE and NAICS First report of the working group October 2000 Convergence of industrial classification between NACE and NAICS First report of the working group October 2000 The agreement signed by the heads of the statistical agencies of Canada, the European Union

More information

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 26th May 2016 1. Purpose of this Invitation to Tender (ITT) 1.1. This invitation to tender is for appointment to a three-year framework

More information

Planning Construction Procurement. A guide to health and safety and employment standards at work

Planning Construction Procurement. A guide to health and safety and employment standards at work Planning Construction Procurement A guide to health and safety and employment standards at work First published October 2015 Revised October 2016 ISBN: 978-1-98-851709-4 (Online) New Zealand Government

More information

Competitive Procurement Evaluation Process Audit

Competitive Procurement Evaluation Process Audit 1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor Competitive Procurement Evaluation Process Audit August 28, 2017 City of Edmonton 16417 Procurement Evaluation

More information

Managing Contractors Safely

Managing Contractors Safely March 2017 Managing Contractors Safely Occupational Health and Safety Service HSD015M (rev 4) Health and Safety Division Feb 2009 Contents Introduction... 1 Large Projects... 3 Vacating Premises... 3 Planning

More information

Themed Audits Safe Recruitment

Themed Audits Safe Recruitment Internal Audit Report Themed Audits Safe Recruitment 2016/17 Issued to: Simon Newland Assistant Director (Education Provision and Access) Marcus Cooper - Senior Education Manager Copied to Report Status:

More information

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide National Commissioning Board Leading Integrated and Collaborative Commissioning A Practice Guide March 2017 Introduction The short practical guide is intended to stimulate commissioners and other senior

More information

15 April Dear Sirs:

15 April Dear Sirs: KPMG Global Resource Centre Bay Adelaide Centre 333 Bay Street Suite 4600 Toronto ON M5H 2S5 Telephone: 416-777-8500 Fax: 416-777-8450 15 April 2014 Dear Sirs: IAESB Exposure Draft (December 2013), Proposed

More information

Mine Production Management

Mine Production Management Mine Production Management Keeps the focus on the project. mpxsoftware.com DRIVING EXCELLENCE Cube Consulting are specialist consultants in the mining, energy, industrial and government sectors. We back

More information

Procurement manual for activities funded through the National Land Transport Programme

Procurement manual for activities funded through the National Land Transport Programme Procurement manual for activities funded through the National Land Transport Programme NZ Transport Agency www.nzta.govt.nz Copyright information This publication is copyright NZ Transport Agency. Material

More information

CDM comes into force on 6 April 2015

CDM comes into force on 6 April 2015 CDM 2015 comes into force on 6 April 2015 Why the change? The Client adviser role of the CDM coordinator is not working as well as many had hoped Industry views the regulations as being too bureaucratic,

More information

Induction Policy. Document author Assured by Review cycle. 1. Introduction Policy Statement Purpose or Aim Scope...

Induction Policy. Document author Assured by Review cycle. 1. Introduction Policy Statement Purpose or Aim Scope... Induction Policy Board library reference Document author Assured by Review cycle P091 Head of Learning and Development Quality and Standards Committee 3 Year This document is version controlled. The master

More information

CONTRACTORS ON SITE POLICY

CONTRACTORS ON SITE POLICY THE BURTON BOROUGH SCHOOL A Specialist Arts College CONTRACTORS ON SITE POLICY Policy Reviewer Sarah McElduff Date of Review September 2013 Date Presented to Governors 14 October 2013 Date of next Review

More information

In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK.

In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK. CDM Regulations at Retail Expo 2018 In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK. In April 2015 the Construction (Design and

More information

LEXIS PSL MODERN SLAVERY ACT 2015 SAMPLE CHECKLIST

LEXIS PSL MODERN SLAVERY ACT 2015 SAMPLE CHECKLIST LEXIS PSL MODERN SLAVERY ACT 2015 SAMPLE CHECKLIST Expertise Experience Modern Slavery Act 2015 Awareness Sample Checklist INTRODUCTION Section 54 of the Modern Slavery Act 2015 ("MSA") introduces a requirement

More information

G2.4 CONFLICT OF INTEREST

G2.4 CONFLICT OF INTEREST G2.4 CONFLICT OF INTEREST Applies to: Board of Management Staff Specific responsibility: Chief Executive Officer Version: 1 Date approved: 20/12/2011 Next review date: 2014 Policy context: This policy

More information

Professional relationships in play Some Practicalities to consider- Assigned & Design Certifier

Professional relationships in play Some Practicalities to consider- Assigned & Design Certifier Professional relationships in play Some Practicalities to consider- Assigned & Design Certifier Presentation at CMG Royal Marine Hotel Dun Laoghaire- September 2017 Kevin Sheridan EurBE, MSc, CEnv, MICE,

More information

JOB DESCRIPTION. Service Line Manager for [one of Education/Research/Business/Infrastructure] Job Family/Level: Professional Services, level 6

JOB DESCRIPTION. Service Line Manager for [one of Education/Research/Business/Infrastructure] Job Family/Level: Professional Services, level 6 JOB DESCRIPTION Job Title: Department/Division/Faculty: Campus location: Service Line Manager for [one of Education/Research/Business/Infrastructure] ICT (Information and Communication Technologies), South

More information

This part of the Works Information sets out the obligations of the Contractor with regards to:

This part of the Works Information sets out the obligations of the Contractor with regards to: Works Information Volume 2B Part 13 Assurance, Records and Certification Part 13 Assurance, Records and Certification 13.1 Introduction The Contractor self-certifies the quality of the works. This part

More information

Certificate IV in Project Management Student Assessment Guide

Certificate IV in Project Management Student Assessment Guide Overview The assessment for the Certificate IV in Project Management comprises Team Assignment Development of a detailed Project Management Plan for chosen case study - 30% for blended classes Individual

More information

Main Contractor Pre-Qualification Questionnaire. French consulate Guangzhou relocation project. 4 th Nov 2016

Main Contractor Pre-Qualification Questionnaire. French consulate Guangzhou relocation project. 4 th Nov 2016 Main Contractor Pre-Qualification Questionnaire French consulate Guangzhou relocation project 4 th Nov 2016 1 Contents 1. Introduction 1 2. Project Information 1 2.1 Background 1 2.2 Site 1 2.3 Scope of

More information