1 Department of Estates Work Instructions TITLE: EMPLOYERS INFORMATION REQUIREMENTS BIM Reference: WI002/4 File Location: Quality Manual Author: Projects & Asset Team Status: Issue V2 Last Reviewed: Sept 2015 Review Date: Sept 2016 Other University documents to which reference should be made. WI002/3

2 Document Control Sheet Revision Date Amendment details Author Approved V EIR Rewritten to include BEP Guidance JL PA Table 1 (Document Control Sheet)

3 TABLE OF CONTENTS 1. INTRODUCTION Document Purpose Client Overview PROJECT STRATEGY Project Overview: MANAGEMENT Requirements for Facility / Asset Information Standards Roles & Responsibilities BIM Competency Assessments Planning the Work and Data Segregation Collaboration Process Coordination process Security System Performance Compliance Plan Health and Safety/Construction Design Management TECHNICAL Co-ordinates and Units Data Exchange Format Level of Detail / Level of Information Clash Detection Classification Software Platforms Training APPENDIX A - TERMINOLOGY APPENDIX B - STANDARD CODES FOR TYPES OF INFORMATION APPENDIX C - BIM COMPETENCY ASSESSMENT FORM APPENDIX D - TENDER RETURN... 35

4 1. INTRODUCTION 1.1. Document Purpose This Employer s Information Requirements (EIR) document must be included within tender documents issued as part of The University of Bath s procurement process for a Design Team and/or Contractor appointments The contents of this EIR is project-specific and should be read carefully as requirements are liable to change between projects. To provide increased clarity a colour-coding system has been adopted within this document to highlight areas for tenderers consideration. The following symbols and colours have been used: Indicator Owner The University of Bath Department of Estates Lead Consultant Contractor Duties pass from Lead Consultant to the Contractor on appointment The purpose of the EIR is to communicate the University s information requirements and establish information management principles. This EIR and Appendices has been generated using the following standards and guidance documentation for reference: BS 1192:2007 Collaborative production of architectural, engineering and construction information. Code of practice PAS :2013 Specification for information management for the capital/delivery phase of construction projects using building information modelling PAS91:2013 Construction prequalification questionnaires In accordance with PAS :2013 the Lead Designer is required as part of their tender response to issue a project-specific Pre-Contract BIM Execution Plan (BEP) to The University of Bath Estates Department, communicating how the Design Team will deliver the requirements described within this EIR.

5 Document Purpose (Continued) The BEP must as a minimum include the following content: Project Implementation Plan Project goals for collaboration and information modelling; Major project milestones consistent with the project programme Project Information Model deliverable strategy Asset Information Model deliverable strategy On appointment the Lead Consultant will be required to update the Pre-Contract BEP for project use. A compliant BEP will demonstrate how the requirements outlined in the EIRs will be met, including ownership and duties associated with each task. The BEP must also list all of agreed elements as outlined in the Brief, BS1192:2007, PAS1192-2:2013 and the contract documents. Contractors invited to tender will be issued with a copy of the project BEP adopted by the employed Design Team. In accordance with PAS :2013 the Contractor is required as part of their tender response to issue a Pre-Contract BIM Execution Plan (BEP) to the University of Bath communicating how the Contractor will deliver or exceed the requirements described within this EIR Client Overview The University of Bath received its Royal Charter in 1966 and is now firmly established as a top ten UK University with a reputation for research and teaching excellence. Over 15,000 students study at the University campus which overlooks the UNESCO World Heritage City of Bath. The University has a vision is to be recognised as an international centre of research and teaching excellence, achieving global impact through our alumni, research and strategic partnerships. The estate is managed by The University of Bath Department of Estates who maintain over ninety buildings located on campus and within Bath City centre, this includes state-of-the-art teaching facilities and two new academic buildings built as part of a rolling program of investment for the university.

6 Client Overview (Continued) Building Information Modelling (BIM) will provide the opportunity for The University of Bath Department of Estates to improve the delivery of new build and refurbishment projects in five key areas: Cost - reduction of capital expenditure Improved delivery - through the generation of clash resolved models prior to works on site Improved quality - reduction in defects and life-cycle expenditure Communications - improved project understanding for all stakeholders Hand-Over Robust structured information on time and ready for immediate facility management use BIM also supports The University of Bath Department of Estates culture of continual improvement, supported by the latest technological solutions and processes. The University of Bath Department of Estates is committed to: Develop and align a BIM Strategy with the University s vision and objectives. Meet Level 2 BIM compliance by In accordance with the UK Government mandate. Integrate BIM processes into the Department of Estates Facility Management Systems to support operational tasks. Train and educate staff to raise BIM skills and understanding across all parts of the Department of Estates. Continue to identify improvements to BIM processes and seek to monitor and adapt to changes evident in industry. Work with our supply chain to develop seamless systems and processes to deliver optimum cost savings.

7 2. PROJECT STRATEGY 2.1. Project Overview: Tenant: XXXX Project Duration: XXXX Project Name: XXXX Form of Contract: GC-Works Project Number: XXXX Contract Number: XXXX Building Typology: XXXX Plan of Work (PoW): RIBA Site Address: XXXX Current PoW Stage: XXXX Number of Storeys: XXXX Project Start Date: XXXX Internal Floor Area: XXXX Project Completion Date: XXXX Approximate Project Value: XXXX Project Handover Date: XXXX Lead Consultant XXXX Contractor XXXX The information received in accordance with this EIR will be used for the following purposes by The University of Bath. Client s Strategic Purpose Use and Utilisation Operations Maintenance and Repair Replacement Space Planning Assessment and Re-use Impacts Business Case Security and Surveillance Regulation and Compliance Marketing Required Y Y Y Y Y Y Y Y Y Y Y

8 Project Overview (Continued) The following project BIM objectives have been identified by The University of Bath Department of Estates, and considered areas where BIM processes will add value to this particular project, and therefore are required as part of a tenderer s response to this EIR. As a minimum The University of Bath Department of Estates requires: All organisations with design responsibility to generate their contractual documentation using BIM Authoring applications and share the resulting models with all parties. Adopt the standards as defined in this EIR, particular attention should be made regarding compliance with the project naming conventions. Use a Common Data Environment (CDE) to support the transaction of information between parties and the supporting technology platforms. Contractors should maximise the benefit of the BIM data generated through design to support project management processes and delivery. All design models to be clash resolved with zero defects prior to works progressing on site. Contractors and their supply chain must deliver at hand-over a structured set of asset data using the supplied Asset Data Import Sheets. It should be noted without this delivery BIM Level 2 will not have been delivered on this project, which is a University requirement. Tenderers are invited to describe how they intend to deliver the required objectives and information at Hand-Over as listed below. It should be noted: That any of the objectives listed can be offered as part of a tender return where it will benefit the project or individual s delivery. The inclusion or exclusion of the below objectives does not preclude the tenderer from delivering in accordance with requirements stated within the main appointment documents and contract.

9 Project Overview (Continued) Key Project BIM Objectives Existing Conditions Modelling Cost Estimation Sustainability (BREEAM) Evaluation Phase Planning (4D Modelling) Visualisation Site Analysis Design Authoring Design Reviews Spatial Requirements Code Validation Energy Analysis Structural Analysis Mechanical Analysis Lighting Analysis 3D Coordination (including clash resolution) Site Utilisation Planning Construction System Design (Virtual Mock-up) Digital Fabrication 3D Control and Planning (Digital Layout) Building Systems Analysis (operational) Asset Management Disaster Planning Space Management and Tracking Record Modelling Building Maintenance Scheduling Supporting Marketing Required Optional Optional Optional Optional Optional Optional Optional Optional Information Hand-Over (Asset Information Models) Geometric model Drawings Completion of and accuracy of completed Asset Data Import Sheets COBie 2012 format as described in BS1192:4 Required No

10 3. MANAGEMENT 3.1. Requirements for Facility / Asset Information The geometric as-built models are to be issued as separate discipline models. The geometric as-built models must be issued in the following file formats Native file format used by the BIM authoring software Industry Foundation Class (IFC) file The University of Bath Department of Estates uses ARCHIBUS, CAFM software for portfolio management and requires information to be provided at hand-over in a structured format. This will enable the direct importing of data into ARCHIBUS to support the delivery of Facility Management duties implemented by The University of Bath Estates Department. To deliver this primary requirement, asset data must be collected by completing Asset Data Import Sheets. The Asset Data Import Sheets will be issued as Microsoft Excel templates and provided by The University of Bath Department of Estates. An example of an Asset Data Import Sheet is shown below. The accuracy of data inputted and supplied is the responsibility of the Contractor. It is recommended that associated quality assurance processes and methods to ensure data accuracy are described within the Contractor s tender return. Tenderers will be issued a copy of Work Instruction WI007 - Asset Numbering Protocol for adoption. To ensure: compliance with the above requirements provide opportunities for checking progress provide additional advice where required

11 Requirements for Facility / Asset Information (Continued) All asset Information must be issued to The University of Bath Department of Estates in an iterative manner at agreed project stages. The Contractor should provide in their tender return a description how they intend to comply with this requirement and confirm frequency of issue of information. The advantage to all parties is that the progress and quality of the Asset Data Import Sheets can be checked during the project avoiding any potential issues at hand-over. The diagram below is provided as an example only Standards The following standards will be adopted on all University projects with a BIM requirement. These must be applied without exception to ensure a BIM Level 2 compliance is achieved as a minimum standard. BS 1192:2007 Collaborative production of architectural, engineering and construction information. Code of practice PAS :2013 Specification for information management for the capital/delivery phase of construction projects using building information modelling It should be noted that the document naming principles as described in BS1192:2007 must be used at all times. No alternative document naming standards will be accepted.

12 Standards (Continued) The following optional field/s available with BS1192:2007 have not been included: Classification Between each field, sometimes referred to as a container; an underscore should be included in the file name. At the end of the file name a description is included to provide additional clarity of the file contents. The table below indicates the required fields and order. The generated file name would be: 1226_ABC_28_01_M3_A_0001_S1_A_First Floor Model Project Originator Zone/Building Level Type Role Number Suitability Revision Description 1226 ABC M3 A 0001 S1 A Text Reference tables for each field are listed within Appendix B. The tables indicate the codes to be used as specified within BS1192:2007. Where fields are project specific these must be outlined within the projects BIM Execution Plan (BEP) The following table and descriptions provide example file naming structures for a model, drawing and spreadsheet for information: Model number 1226-ABC-28-ZZ-M3-A-0002-S2-A-Building Model indicates an Architectural model of all floors for Building No.1 at revision A and issued for information only. Drawing number 1228_DEF_01_01_DR_E_5005_S1_C-First Floor Lighting Layout indicates an Electrical Lighting Layout 1 st floor drawing for Building number 1 at revision C issued for co-ordination purposes.

13 Standards (Continued) In this example the sequential number is using a 5000 series to indicate all layout drawings, as an example a 2000 series may indicate all detail drawings. This approach adds further clarity and speeds up the locating of documentation. This is an option that can be used by the Design Team and the Contractor as required. Spreadsheet number 1228_UOB_00_XX_SC_W_0003_D1_E indicates a University of Bath Department of Estates schedule covering the whole site at revision E and suitable for costing Roles & Responsibilities The purpose of this section is to communicate required roles and duties associated with the management of the model and project information. All the roles defined and their respective responsibilities and authorities are stated only in connection with information management and it is anticipated will be incorporated within existing roles. Each organisation must ensure appropriate roles, duties and authorities are assigned to an individual or individuals within their organisation. It is expected that the Design Team, the Contractor and its Supply Chain will already have within their organisations individuals already undertaking these duties or capable of doing so. The following table outlines the project roles and authorities associated with the management of the models and project information. Role Owner Authority Project Information Manager The University of Bath Department of Estates - Project Management Team. Enforce the Project BIM Standards and ensure delivery of the Information requirement in the EIR. BIM Co-ordinator Lead Consultant / Contractor Coordinating design of all elements, including work by design consultants/sub-contractors. Design/Tech Leader Design Consultants / Contractor / Contractors Supply Chain Main point of contact for technical and design based questions. Enforce spatial coordination.

14 Role Owner Authority Organisation specific role title Design Consultants / Contractor / Contractors Supply Chain Enforce documentation standards Reject non-compliant models, drawings & documents Negotiate space allocation Main point of contact for modelling based questions. Enforce CAD related BIM standards 3.4. BIM Competency Assessments The University of Bath Department of Estates require that all participants to the BIM process complete a BIM Competency Assessment Form. A copy of the assessment form is located in Appendix C. The completed BIM Assessment form is a constitute part of the selection process and should be included as part of a tender return Planning the Work and Data Segregation Information will be managed in accordance with PAS and BS1192:2007 The University of Bath Department of Estates Project Information Manager and the Lead Consultant will agree Zone/Building number and Levels for the project. Planning the Work and Data Segregation must be fully documented within the BEP by the Lead Consultant. As a minimum the tables within Appendix C must be included, with supporting plan layouts to aid communication and understanding. Room numbering policy is defined within Work Instruction WI002/2, which will be issued to tenderers for adoption. Room numbering policy should not be defined within the BEP and instead should only be cross referenced to WI002/2.

15 3.6. Collaboration Process Common Data Environment (CDE) To improve project controls, quality and efficiency the Lead Consultant will be responsible for the provision of a Common Data Environment (CDE) and supporting technologies applying the principles outlined with BS1192: 2007 and PAS1192:2. On appointment the Contractor will be responsible for the provision of the Common Data Environment (CDE) and supporting technologies applying the principles outlined with BS1192: 2007 and PAS1192:2. All project related documentation, including models will be shared using the agreed CDE supporting technology. No alternative methods of transaction such as attachments within s are to be used. Each consultant and contractor will be responsible for uploading the files onto the CDE in a timely manner following updates and changes to the relevant models. The Lead Consultant and the Contractor on appointment; if introducing new technology solutions; will be required to provide CDE training to The University of Bath Department of Estates. The University of Bath Department of Estates will require full access rights to the selected CDE platform. The University of Bath Department of Estates Project Manager will organise a BIM project start-up workshop following the selection process to communicate the BIM strategy and provide a forum for the Lead Consultant/Contractor to present the BEP. Attendance is mandatory. During project delivery in addition to design team meetings, BIM co-ordination meetings will be scheduled in accordance with the main project schedule. The duration and frequency of these meetings will be kept to a minimum and will be dependent on project team performance during delivery. For the purpose of tendering it can be assumed that BIM Co-ordination meetings will be held every two weeks and facilitated by the Lead Consultant. The above collaboration processes must be fully detailed in the BIM Execution Plan (BEP)

16 3.7. Coordination process The University of Bath Department of Estates requires evidence that all geometric models have been fully reviewed and checked for co-ordination issues including maintenance access prior to works proceeding on site. The Lead Consultant will be required to ensure this process is applied at all design stages. Evidence must be provided in the form of clash resolution reports indicating zero issues and uploaded onto the project CDE. Each discipline must ensure their models are clash resolved prior to submitting information onto the CDE. The method used should be included within the BIM Capability Assessment form. The co-ordination process will be managed directly by the Lead Consultant who will federate all discipline models and run clash detection and resolution processes. It is anticipated that these will be aligned with the project program and scheduled every two weeks Security All data storage, exchanges and use should be in line with recommendations made within PAS for the entirety of this project. It should be noted that the use of mobile devices connected to cloud based servers are permitted on this project if they are compliant with PAS System Performance The Lead Consultant must investigate the IT systems used by all parties and set a maximum file size for model files to maintain system performance for all participants. The agreed allowable maximum file size for model files must be stated in the BIM Execution Plan (BEP) Compliance Plan The University of Bath Department of Estates requires each organisation to have appropriate systems and controls in place to achieve and comply with all requirements and principles defined within this EIR. This should include processes to identify, monitor and manage risks to the achievement of all outcomes. Within the project specific BEP details must be provided and should include quality assurance and control procedures.

17 3.11. Health and Safety/Construction Design Management All H&S deliverables are to be uploaded onto the CDE. As part of the selection process, tenderers are invited to outline in the Capability Assessment form how BIM enabled processes will be used to manage The University of Bath Department of Estates and the supplier s H&S/CDM obligations. Tenderers will be provided with a copy of Work Instruction WI H&S and O&M Manual for adoption. The Lead Consultant should propose how the design authoring process will support H&S/CDM requirements. The Contractor should propose how BIM will assist the collation of information for Operation and Maintenance manuals throughout the construction period. Particular attention should be made to the collation of structured data as outlined in section 3.1.Requirements for Facility / Asset Information. The Contractor must ensure that all relevant documents including commissioning certificates and record drawings are provided and indexed within the building manual and uploaded onto the CDE. The CDE must remain available with full access for a minimum period of twelve weeks. 4. TECHNICAL 4.1. Co-ordinates and Units The Lead Consultant is to agree with the Project Team and define within the BEP the co-ordinates and units to be used across the entire project Data Exchange Format Information Type Drawings Schedules Asset Data Collection Sheets Models Reports Manufacturers Information Exchange Formats DWG, PDF XLS, PDF XLS RVT (or alternative with prior agreement) DOC, PDF PDF

18 4.3. Level of Detail / Level of Information The Level of Detail and Level of Information required within the models will be defined post tender award and agreed with each BIM participant individually. For those packages providing models it can be assumed that minimum LOD will be between 200 and 400 as defined by the American Institute of Architects (AIA) or a LOD between 2 to 5 as defined within the NBS BIM Toolkit. The following table is provided for reference only LOD200 LOD300 LOD350 LOD400 Schematic layout with approximate size, shape, and location of mains and risers; shaft requirements modelled; design performance parameters as defined in the BEP to be associated with model elements as non-graphic information. Modelled as design-specified size, shape, spacing, and location of duct, dampers, fittings, and insulation for risers, mains, and branches; approximate specified allowances for spacing and clearances required for all hangers, supports, vibration and seismic control that are to be utilized in the layout of all risers, mains, and branches; actual access/code clearance requirements modelled. Modelled as actual size, shape, spacing, and location/connections of duct, dampers, fittings, and insulation for risers, mains, and branches; actual size, shape, spacing, and clearances required for all hangers, supports and vibration control that are utilized in the layout of all risers, mains, and branches; actual floor and wall penetrations modelled. Supplementary components added to the model required for fabrication and field installation. Information exchanges will be aligned with the project schedule, for the purposes of tendering it can be assumed that model exchanges will be required every two weeks Clash Detection It should be noted that Autodesk s Navisworks is The University of Bath Department of Estates preferred software for clash detection and co-ordination activities, alternative software applications may be put forward for consideration. The clash detection and coordination process must be defined in the BIM Execution Plan (BEP) by the Lead Consultant and updated by the Contractor on appointment. It is anticipated the coordination and will be similar to the example diagram below:

19 Clash Detection (Continued) 4.5. Classification This project will use the Uniclass 2015 classification system for all objects in the project Software Platforms Currently approved software platforms and versions for use on this project are listed below. Additional software platforms and versions can be proposed by tenderers for approval by The University of Bath Department of Estates Project Information Manager. Task Platform Version Remarks 3D Clash Detection Autodesk Navisworks Manage 2015 Used for clash detection, commenting, reporting and federating models 3D Viewer Autodesk Navisworks Freedom D Planning TBC Modelling 4D Planning TBC Programming 5D Cost Planning TBC 6D FM ARCHIBUS V20.2 For estate management BIM Authoring Autodesk Revit 2015

20 4.7. Training All training associated with modelling and analysis tools rests with the design consultants / contractor and their supply chain. The Lead Consultant / Contractor must provide instruction in the use of all CDE supporting technologies to the project team and The University of Bath Department of Estates..

21 APPENDIX A - TERMINOLOGY Aggregation is the action of bringing together more than one model into a common environment Archive is a component of the common data environment (as defined by PAS :2013) Asset is an item, thing or entity that has potential or actual value to an organization Asset Information Management is the discipline of managing asset-related organizational data and information to a sufficient quality to support organizational objectives and outcomes (as defined by PAS :2014) Asset Management is the coordinated activity of an organization to realize value from assets (as defined by PAS :2014) Asset Management System is the management system for asset management whose function is to establish the asset management policy and asset management objective (as defined by PAS :2014) Building Information Model is a digital representation of the physical and functional characteristics of the project (as defined by AIA Document E ) Building Information Modelling is the process of designing, constructing or operating a building or infrastructure asset using electronic object-oriented information (as defined by PAS :2013) Building Information Modelling Execution Plan (BEP) is a plan prepared by the project team to explain how the information modelling aspects of a project will be carried out (as defined by PAS :2013) BIM Level 2 - BIM Level 2 consists of multiple models from various sources brought together for coordination and with some basic relevant information attached to those models. BIM Level 3 BIM Level 3 has not been defined as yet Clash Detection is detecting possible collisions between elements in a building information model which would not otherwise be desired or buildable on site (as defined by Bond Bryan Architects) Clash Rendition (CR) is rendition of the native format model file to be used specifically for spatial coordination processes. To achieve clash avoidance or to be used for clash detection (as defined by PAS :2013)

22 Classification is a systematic arrangement of headings and sub-headings for aspects of construction work including the nature of assets, construction elements, systems and products (as defined by PAS :2013) Client is the individual or organisation commissioning a built asset (as defined by PAS :2013) Common Data Environment (CDE) is a single source of information for any given project, used to collect, manage and disseminate all relevant approved project documents for multi-disciplinary teams in a managed process (as defined by PAS :2013) OR a single source of information for the Project which collects, manages and disseminates relevant approved documents relating to the project (as defined by the CIC Outline Scope of Services for the Role of Information Management) OR is a single source of information for any given project or asset, used to collect, manage and disseminate all relevant approved files, documents and data for multi-disciplinary teams in a managed process (as defined by PAS :2014) Computer-Aided Facilities Management (CAFM) is the support of Facility Management by information technology Construction Sequencing is the process of adding a time line to a model. This can be incorporated into both design or construction models Data is information stored but not yet interpreted or analysed (as defined by PAS :2013) OR observations that in context yields information (as defined by PAS :2014 / Skyrme & Amidon, Knowledge management, Institute of Management, Corby, 1997) Deliverables are the specific requirements for the project which may be generated directly from the model or from other sources. They may include the building information model, drawings, fly-through's, images, data, schedules or reports Design Lead is the role of setting design standards and co-ordinating the design (as defined by the CIC Outline Scope of Services for the Role of Information Management) Design Team means the architect(s), engineer(s) and technology specialists responsible for the conceptual design aspects of a building, structure or facility and their development into models, drawings, specifications and instructions required for construction and associated processes. The design team is part of the project team (bases on the definition by the RICS) Document is a container for persistent information that can be managed and interchanged as a unit (as defined by BS1192: ) OR information for the use in the briefing, design, construction, operation, maintenance or decommissioning of a construction project, including but not limited to correspondence, drawings, schedules, specifications, calculations, spread sheets (as defined by PAS :2013)

23 Drawing is a document used to present graphic information (as defined by BS1192: ) OR static, printed, graphical representation of part or all of a project or asset (as defined by PAS :2013) Employer is the individual or organisation named in an appointment or building contract as the employer (as defined by PAS :2013 and PAS :2014) Employer s Information Requirements (EIR) is a document setting out the information to be delivered, and the standards and processes to be adopted by the supplier as part of the project delivery process (as defined by PAS :2013) Element is a construction entity part which, in itself or in combination with other such parts, fulfils a predominating function of the construction entity (as defined by ISO : ) Facility Management is management during the operational phase of a facility or building s life cycle, which normally extends over many decades. It represents a continuous process of service provision to support the client s core business and one where improvement is sought on a continuous basis Federated Model means a model consisting of linked but distinct component models, drawings derived from the models, texts, and other data sources that do not lose their identity or integrity by being so linked, so that a change to one component model in a federated model does not create a change in another component model in that federated model (as defined by ConsensusDOCS 301 BIM Addendum, US) OR is a model consisting of connected but distinct individual models (CIC BIM Protocol. First Edition. 2013) Graphical Data is data conveyed using shape and arrangement in space (as defined by PAS :2013) Graphical File is a file format designed specifically for representing graphical images (as defined by PAS :2013) Handover is the stage of a capital/delivery project where the asset is made available for use or occupation (as defined by PAS :2014) Information Management Process (IMP) is the process to manage information related to the operational phase of an asset (as defined by PAS :2014) Industry Foundation Classes (IFC) is a neutral and open specification that is not controlled by a single vendor or group of vendors. It is an object-based file format with a data model developed by buildingsmart to facilitate interoperability in the building industry (as defined by Nemetschek - source taken from Wikipedia)

24 Information is the representation of data in a formal manner suitable for communication, interpretation or processing by human beings or computer applications (as defined by PAS :2013) OR data arranged and processed into meaningful patterns, put into context (as defined by PAS :2014 / Skyrme & Amidon, Knowledge management, Institute of Management, Corby, 1997) Information Exchange is the structured collection of information at one of a number of pre-defined stages of a project with defined format and fidelity (as defined by PAS :2013) Information Management means measures that protect and defend information and information systems with respect to their availability, integrity, authentication, confidentiality, and nonrepudiation. These measures include providing for restoration of information systems by incorporating protection, detection, and reaction capabilities (as defined by ConsensusDOCS 301 BIM Addendum, US) OR are tasks and procedures applied to inputting, processing and generation activities to ensure accuracy and integrity of information (as defined by PAS :2013) Information Model is a model comprising: documentation, non-graphical information and graphical information (as defined by PAS :2013) OR is all documentation, non-graphical information which the Project Team is required to provide into the Information Model by the Scope of Services for the Project Team and which is provided for the purpose of delivering Project Outputs (as defined by the CIC Outline Scope of Services for the Role of Information Management) Levels of Model Detail is a description of graphical content of models at each of the stages defined for example in the CIC Scope of Services (as defined by PAS :2013) Levels of Model Information is a description of non-graphical content of models at each of the stages defined for example in the CIC Scope of Services (as defined by PAS :2013) Main Contractor (or Prime Contractor) means the contractor responsible for the total construction and completion process of the building project. The term prime contractor is often used in central civil government and the defence sector to mean main contractor (as defined by RICS) MEP Model is a model made up solely of mechanical, electrical and plumbing components (note: other information may exist within this model that is referenced from others but this is only used for reference purposes)

25 Model is a collection of containers organised to represent the physical parts of objects, for example a building or a mechanical device (as defined by BS1192: ) OR a three-dimensional representation in electronic format of building elements representing solid objects with true-to-scale spatial relationships and dimensions. A model may include additional information or data (as defined by ConsensusDOCS 301 BIM Addendum, US) OR means a digital representation of part of the physical and/or functional characteristics of the Project. (CIC BIM Protocol. First Edition. 2013) Non-graphical Data is data conveyed using alphanumeric characters (as defined by PAS :2013) Object is any part of the perceivable or conceivable world (as defined by ISO : ) OR an item having state, behaviour and unique identity - for example, a wall object (as defined by PAS :2013) Organizational Information Requirement (OIR) is data and information required to achieve the organization s objectives (as defined by PAS :2014) Origin is a setting out point for a project or programme using co-ordinate geometry or related to the OS or geospatial reference (as defined by PAS :2013) Parameters are variables used in a function or equation to assign values: coordinate, dimension, material, distance, angle, colour, unit price, energy coefficient, and so forth Project Stage is a period of time in the duration of a construction project identified by the overall character of the construction process which occurs within it (as defined by ISO : ) Project Team Member means the person appointed by the Employer pursuant to the Agreement. (CIC BIM Protocol. First Edition. 2013) OR any person having responsibilities in relation to the production, delivery and/or use of the content of the Information Model and appointed by the Employer in relation to the Project (as defined by the CIC Outline Scope of Services for the Role of Information Management) Published information refers to documents and other data from Shared information. Typically this will include exported data, contract drawings, reports and specifications (reference BS1192:2007) (as defined by AEC (UK) BIM Standard Version 2 Page 8) OR a component of the CDE for drawing renditions that have been approved as suitable for a specific purpose - for example, suitable for construction (as defined by PAS :2013) Requirements are the documented expectations of facility owners/commissioners for sharable structured information. These are also referred to as the Employers Information Requirements (EIR) (alternatively, the Clients Information Requirements) (as defined by PAS :2013)

26 Shared information that has been checked and approved and is made available across the project team such as information for data exchange between BIM software, like gbxml, CIS/2 and IFC files. (reference BS1192:2007) (as defined by AEC (UK) BIM Standard Version 2 Page 8) OR component of the CDE. The shared section of the CDE is where information can be made available to others in a safe environment. The early release of information assists in the rapid development of the design solution. To allow this to be achieved, the concept of information status/suitability has been adopted (as defined by PAS :2013) Soft Landings are graduated handovers of a built asset from the design and construction team to allow structured familiarisation of systems and components and fine tuning of controls and other building management systems (as defined by PAS :2013) Space three dimensional, material construction result contained within, or otherwise associated with, a building or other construction entity (as defined by ISO : ) Space a logical volume of space within a project normally a room in a building. A Space contains objects within it and is served by objects that supply it. Status defines the suitability of information in a model, drawing or document. Not to be confused with the status in architectural documentation as new build, retain or demolish (as defined by PAS :2013) Structural Model A model made up solely of structural components Subcontractor means a contractor employed by the main contractor to undertake specific work within the building project; also known as specialist, works, trade, work package, and labour only contractors (as defined by the RICS) Supplier is the provider of services or goods either directly to the employer or to another supplier in a supply chain (as defined by PAS :2013) System is a group of components that work together to provide a specific building service such as envelope, ventilation or fire protection (as defined by PAS :2013) System (IFC) are organised combination of related parts, composed for a common purpose or function or to provide a service. System is essentially a functionally related aggregation of products (as defined by PAS :2013) Volume is manageable spatial subdivision of a project, defined by the project team as a subdivision of the overall project that allows more than one person to work on the project models simultaneously and consistent with analysis and design process (as defined by PAS :2013) Note: this term is defined as zone in BS 1192:2007

27 Work In Progress (WIP) Each individual company or discipline s own work. This is information that has not been approved or verified as fit to share across the project team (reference BS1192:2007) (as defined by AEC (UK) BIM Protocol Version 2 Page 7/8) Workflow the process or processes used to create a design, object, project or document.

28 APPENDIX B - STANDARD CODES FOR TYPES OF INFORMATION Project Originator Zone/Building Level Type Role Number Suitability Revision Description 1226 ABC M3 A 0001 S1 A Text Project Project number will follow The University of Bath Department of Estates standard project numbering convention. Originator There are no standard codes mandated for the originator field but should comprise of three characters. Zone / Level The project should be divided into manageable sub-divisions using two criteria: a) Zones (sometimes referred to as plots) b) Levels (sometimes referred to as locations) Zone The zone indicator should be typically three characters 000 represents all zones or plots on a project This list should be expanded into the project specific codes P01 P02 P03, etc. Z01 Z01 Z02, etc etc. Are all acceptable codes Level The level indicator should be two characters as follows: ZZ Multiple levels XX No level applicable GF Ground floor

29 Level (Continued) For floor levels above ground floor, the floor number should be used as follows: 01 Floor 1 02 Floor 2, etc.. For mezzanine the prefix M should be used as follows: M1 Mezzanine above level 01 M2 Mezzanine above level 02, etc. For all levels below the ground floor the prefix B should be used: B1 B2, etc. NOTE For floor notation, see BS EN ISO and BS EN ISO The standard codes for file containers holding models and drawings the code should be exactly two characters as listed below. Project specific type codes should be defined for documents TYPE DR M2 M3 MR VS SC SP BQ SC DESCRIPTION Drawing Two dimensional model Three dimensional model Model rendering Visualisation Schedule or table Specification Bill of quantity Structure calculation

30 The standard codes for role should be exactly one character as listed below: ROLE A B C D E F G H I K L M P Q S T W X Y Z DESCRIPTION Architect Building Surveyor Civil Engineer Drainage, Highways Engineer Electrical Engineer Facilities Manager Geographical and Land Surveyor Heating and Ventilation Designer Interior Designer Client Landscape Architect Mechanical Engineer Public Health Engineer Quantity Surveyor Structural Engineer Town and Country Planner Contractor Subcontractor Specialist Designer General (non-disciplinary) Number The numbering for standard coding should be exactly four integer numeric digits, used sequentially. Leading zeros should be used. Using coding to indicate detail, section, elevation and layout drawings through one thousand series of numbers such as 1000 for layouts, 2000 for sections is permitted. There is no further restriction for project specific coding but care should be taken not to embody information present in other fields where possible.

31 Suitability The suitability code should be one or two characters. The codes below should be used. NOTE: Use of particular document management software used as part of a CDE such as 4Projects will control suitability directly using in-built functionality. In this instance the suitability code will not be required in the document naming convention. CODE Work in Progress S0 Shared (Non-Contractual) S1 S2 S3 S4 S5 DESCRIPTION Initial status or WIP Master document index of file identifiers uploaded into the extranet. Suitable for Co-ordination The file is available to be shared and used by other disciplines as a background for their information. Suitable for Information Suitable for Internal Review & Comment Suitable for Construction Approval Suitable for Manufacture S5 Suitable for PIM Authorization (Information Exchanges 1-3) S6 Suitable for AIM Authorization (Information Exchange 6) D1 D2 D3 D4 AM Suitable for Costing Suitable for Tender Suitable for Contractor Design Suitable for Manufacture/Procurement As Maintained Published Documentation (Contractual) A B AB Suitable for Construction Partially signed-off: For Construction with minor comments from the Client. All minor comments should be indicated by the insertion of a cloud and a statement of in abeyance until the comment is resolved, then resubmitted for full authorization. As-Built Handover documentation, PDF, native models, COBie etc.

32 Revisions Revisions should be referred to alphabetically using capital letters: - (No revision/first Issue) A (First revision) B (Second revision) etc. C D The following character letters are not permitted I, O to ensure clarity. Commented [MK1]: Meaning? Where all letters have been exhausted due to a high number of revisions then use two characters: AA AB AC Description Descriptive text derived from the other fields and used consistently can be used to aid recognition. NOTE 1: Avoid long, unwieldy and poorly worded descriptions. NOTE 2: There are no standard codes mandated for the description field..

33 APPENDIX C - BIM COMPETENCY ASSESSMENT FORM General Q1 Do you have the capability of working with a project using a Common Data Environment as described in PAS 1192:2:2013? Q2 Do you have documented policy, systems and procedures to achieve Level 2 BIM maturity as defined in the government s BIM Strategy? You will be expected to demonstrate that your organization understands the concept of a Common Data Environment as described in PAS 1192:2:2013 and is able to exchange information between supply chain members in an efficient and collaborative manner. If you have delivered a project in this way, you may use this to demonstrate your capability. Your explanation should be clear and concise. You will be expected to provide evidence that you or your organization has a policy authorized by the Chief Executive or equivalent and regularly reviewed. The policy and procedures should be able to be applied to both large and small projects efficiently.

34 Q3 Q4 Do you have the capability of developing and delivering or working to (depending upon the role(s) that this EIR covers) a BIM Execution Plan (BEP) as described in PAS 1192:2:2013? Do you have arrangements for training employees in BIM related skills and do you assess their capabilities? You will be expected to demonstrate that your organization understands the requirements of PAS 1192:2:2013, in particular with respect to BEP. This will include how to create reliable information and exchange it between supply chain members in an efficient and collaborative manner, and where appropriate, to the Employer, in the form specified. If you have delivered a project in this way, you may present an example BEP. You will be expected to demonstrate that your organization has in place training arrangements to ensure that its staff/ workforce have sufficient skills and understanding to implement and deliver projects in accordance with the policy and procedures established to achieve Level 2 BIM maturity. Project Specific Q5 Please briefly outline how you intend to comply or exceed the requirements outlined in the EIR. You will be expected to demonstrate that your organization understands the project requirements in full, particular attention should be made regarding project management of the process and quality assurance.

35 Q6 Please outline how you intend to ensure your models are clash resolved prior to issue. You will be expected to demonstrate understanding of the clash resolution process within your answers, including consideration for maintenance access where applicable. Q7 Please outline how you intend; where applicable; to use BIM processes to manage H&S/CDM obligations. Designers should consider how the design authoring process will support H&S/CDM requirements. Sub-contractors should consider how BIM will assist the collation of information for operation and maintenance Particular attention should be made regarding the collation of structured data for hand-over using the Asset Data Import Sheets.

36 APPENDIX D - TENDER RETURN Tenderers are invited to document below how they will comply fully with all the requirements described within the Employers Information Requirements (EIR) and how Building Information Modelling (BIM) processes will be used to benefit the project and the Employer. Please use 11 point size font with a1.5 spacing when providing your response below. The use of supporting diagrams and images to assist communication are encouraged. A maximum of six pages of A4 will be accepted as part of the tender return.

37

38

39

Autodesk and the UK BIM Level 2 Mandate

Autodesk and the UK BIM Level 2 Mandate Autodesk and the UK BIM Level 2 Mandate BIM Level 2 Mandate The UK Cabinet Office is in the midst of a multi-year effort to reform the way in which the UK government procures construction helping to ensure

More information

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015 BIM 2016 and the NEC Simon Rawlinson, 20 April 2015 Presentation overview Commercial requirements of BIM BIM and NEC Working Together Government requirements for a collaborative digital model Supporting

More information

BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE

BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE Presented by Chloe Obi 25 th January 2017 Presentation Structure 1. BIM Level 2 Requirements 2. Benefits for Industry

More information

BIDDING FOR BIM. CIF Bidding for BIM. September

BIDDING FOR BIM. CIF Bidding for BIM. September BIDDING FOR BIM CIF September 2017 www.cif.ie Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER PROJECT NAME BIM EXECUTION PLAN PROJECT INFORMATION CLIENT PROJECT NAME PROJECT NUMBER XX XXXXX XX XXXXX XXXXXXXXXXXXXXXXXXXXXXXXX DATE XXXXXXXX 2016 PROJECT LOCATION & ADDRESS XXXXX, XXXXX. INTRODUCTION...

More information

Promoting better business outcomes through the use of BIM and digital technologies.

Promoting better business outcomes through the use of BIM and digital technologies. Promoting better business outcomes through the use of BIM and digital technologies. Introduction The Role of the BIM Manager Agenda 18:00 Introduction + BIM update by Mike Turpin, Innovating Futures 18:10

More information

Employer s information requirements (EIR) An overview of facilities management requirements

Employer s information requirements (EIR) An overview of facilities management requirements Employer s information requirements (EIR) An overview of facilities management requirements > page 1 This document provides an overview of the BIFM employer s information requirements (EIR) template and

More information

PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN

PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN PDG PROJECT DESIGN GUIDES D02 PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-D02.0 Date Created: 2 nd May 2012 Date Revised: R01

More information

State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0

State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0 State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements Version 1.0 April 22, 2013 Table of Contents 1. Introduction...... 1 1.1. Mission of the TN OSA

More information

BUILDING INFORMATION MODEL (BIM) PROTOCOL

BUILDING INFORMATION MODEL (BIM) PROTOCOL BUILDING INFORMATION MODEL (BIM) PROTOCOL CIC/BIM Pro first edition 2013 Standard Protocol for use in projects using Building Information Models The CIC acknowledges the technical input and leadership

More information

COBie and the Demanding Client

COBie and the Demanding Client COBie and the Demanding Client Bob Wakelam AEC3 About me Bob Wakelam AEC3 bw@aec3.com 37 years in architecture and construction 30 years in what is now called BIM Joined AEC3 UK Limited in 2010 Involved

More information

CIF BIM Guide Standards & Policies August 2017

CIF BIM Guide Standards & Policies August 2017 BIM Guide August 2017 www.cif.ie BIM Guide Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

BIM Design & Construction Requirements. Follow-up Seminar. September 10,

BIM Design & Construction Requirements. Follow-up Seminar. September 10, BIM Design & Construction Requirements Follow-up Seminar September 10, 2009 www.indiana.edu/~uao/iubim.html Opening Comments Two years ago Indiana University began the process of embracing the use of Building

More information

WHOLE LIFECYCLE INFORMATION FLOW UNDERPINNED BY BIM: TECHNOLOGY, PROCESS, POLICY AND PEOPLE

WHOLE LIFECYCLE INFORMATION FLOW UNDERPINNED BY BIM: TECHNOLOGY, PROCESS, POLICY AND PEOPLE WHOLE LIFECYCLE INFORMATION FLOW UNDERPINNED BY BIM: TECHNOLOGY, PROCESS, POLICY AND PEOPLE Nashwan N. Dawood 1, and Vladimir Vukovic 2 1) Ph.D., Prof., Director of the Technology Futures Research Institute,

More information

IV.E.8 - BIM Standards

IV.E.8 - BIM Standards Contents 1. General... 3 1.1. Strategy & Objective... 3 1.2. Road Map... 4 2. Process... 7 2.1. Start... 7 2.2. Plan... 9 2.3. Execute... 12 2.4. Monitor... 14 2.5. Close-out... 16 3. Execution... 19 3.1.

More information

Pre-contract Building Information Modelling (BIM) Execution Plan (BEP)

Pre-contract Building Information Modelling (BIM) Execution Plan (BEP) Pre-contract Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Client: Project Address: Project Number: KT4BIM Development Atarii Developments Ltd 1 St Chad s Terrace Shrewsbury Shropshire

More information

This part of the Works Information sets out the obligations of the Contractor with regards to:

This part of the Works Information sets out the obligations of the Contractor with regards to: Works Information Volume 2B Part 13 Assurance, Records and Certification Part 13 Assurance, Records and Certification 13.1 Introduction The Contractor self-certifies the quality of the works. This part

More information

- DATA REQUIREMENTS BIM

- DATA REQUIREMENTS BIM UHS BIM Protocol S E C T I O N 1 - DATA REQUIREMENTS BIM authoring software: The design team is required to use parametric BIM authoring software for creation of models that include all geometry, physical

More information

UK BIM programme Munich Nick Tune Director BuildingSMARTUK & International

UK BIM programme Munich Nick Tune Director BuildingSMARTUK & International UK BIM programme Munich 2013 Nick Tune Director BuildingSMARTUK & International The Government Strategy What is BIM & why is the Government seeking its adoption? Hypothesis Government as a client can derive

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

BSRIA Guide BG6 Why, What, How?

BSRIA Guide BG6 Why, What, How? BSRIA Guide BG6 Why, What, How? Martin Ronceray BSRIA Principal Consultant in Construction process 21 March 2018 1 1994 TN8 A bit of history on BG6 2006 BG6 (1 st ) 2012 BG6 (3 rd ) 2018 BG6 (5 th ) 1997

More information

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE

More information

Building Information Modelling (BIM) Implementation Plan September 2015

Building Information Modelling (BIM) Implementation Plan September 2015 Building Information Modelling (BIM) Implementation Plan September 2015 Collaborative, Efficient, Sustainable and Outcomes Focused Procurement in Construction Contents Executive Summary 2-3 1.0 Horizon

More information

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM Page 1 of 5 The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM By Rick Oehmcke, S.E. Not that many years ago, few structural engineers

More information

Cookham Wood and BIM: Practical Lessons Learnt Fiona Moore Cirrus Consultant Services 10 July 2014

Cookham Wood and BIM: Practical Lessons Learnt Fiona Moore Cirrus Consultant Services 10 July 2014 Cookham Wood and BIM: Practical Fiona Moore 10 July 2014 Topics Covered: Project Overview BIM Early Adopter Project: Why Cookham Wood and how we got involved Ministry of Justice (MoJ) and BIM Key Client

More information

HS2 s approach to BIM and Beyond

HS2 s approach to BIM and Beyond HS2 s approach to BIM and Beyond Britain s New High Speed Railway HS2: the new backbone of Britain s rail network HS2 s Timeline Fast, Frequent & Reliable National College for High Speed Rail Birmingham

More information

The BIM Toolkit. Sarah Delany February 2015 v2.0

The BIM Toolkit. Sarah Delany February 2015 v2.0 The BIM Toolkit Sarah Delany February 2015 v2.0 BIM Government Construction Strategy Completing Level-2 BIM Suite The Missing Pieces The Project Clients Brief Team Industry 2014 2015 Jan Feb Mar Apr May

More information

CAPITAL DELIVERY HUB. Programme Manager Education Construction. Permanent Placement Package to 67,000. Background

CAPITAL DELIVERY HUB. Programme Manager Education Construction. Permanent Placement Package to 67,000. Background CAPITAL DELIVERY HUB Programme Manager Education Construction Permanent Placement Package to 67,000 Background The Education Programme manager is responsible for delivering the Council s education construction

More information

INTEGRATED LIFECYCLE MANAGEMENT BIM/VDC REQUIREMENTS IMPLEMENTATION PLAN

INTEGRATED LIFECYCLE MANAGEMENT BIM/VDC REQUIREMENTS IMPLEMENTATION PLAN INTEGRATED LIFECYCLE MANAGEMENT BIM/VDC REQUIREMENTS IMPLEMENTATION PLAN Manual for VDC, BIM/VDC and Lifecycle Data for design and construction projects at UNC Charlotte. February 2018 Integrated Lifecycle

More information

Building Information Modeling to Facilities Information Management and Beyond

Building Information Modeling to Facilities Information Management and Beyond Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas

More information

Indiana University. Vice President for Capital Planning and Facilities

Indiana University. Vice President for Capital Planning and Facilities Indiana University Vice President for Capital Planning and Facilities DELIVERABLES REQUIREMENTS for CONSTRUCTION DOCUMENTS and AS-BUILT & RECORD DOCUMENTS Revised June 1, 2014 1 Overview of Project Document

More information

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company?

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company? Organisation Type The first national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 67% of the industry sample possessed confidence in their skills

More information

CIC Guidelines Construction Administration and Observation

CIC Guidelines Construction Administration and Observation Version 1.0 / August 2016 Construction Administration Stage 7 of 8 Approval: To commence post-contract award activities. Documentation: From previous stage that forms the basis of the ongoing design. Approval:

More information

CIC Guidelines Preliminary Design

CIC Guidelines Preliminary Design Version 1.0 / August 2016 Stage 3 of 8 Approval: Of previous stage, design documentation, updated programme and cost plan. List matters from previous stage to be addressed in current stage. Documentation:

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

BIM for infrastructure, Paul King Bentley Systems 2016 Bentley Systems, Incorporated

BIM for infrastructure, Paul King Bentley Systems 2016 Bentley Systems, Incorporated BIM for infrastructure, Paul King 1 WWW.BENTLEY.COM 2016 Bentley Systems 2016 Bentley Systems, Incorporated 3D infrastructure pic Bentley one! - green Role of the owner Defining better business outcomes

More information

BIM TECHNOLOGY THE IMPACT ON THE PLANNING AND UTILIZATION PHASE HDR TMK, all rights reserved.

BIM TECHNOLOGY THE IMPACT ON THE PLANNING AND UTILIZATION PHASE HDR TMK, all rights reserved. BIM TECHNOLOGY THE IMPACT ON THE PLANNING AND UTILIZATION PHASE 2014 HDR TMK, all rights reserved. Since 2008 Vorstandsbereichsleitung Infrastructure, Technique and Services kbo Kliniken des Bezirks Oberbayern,

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

28.00 Project Briefing & Procurement

28.00 Project Briefing & Procurement 28.00 Project Briefing & Procurement 28.01 Generally A new building marks a significant investment in the future of the University. For many years hence it will reflect the changing role of the University

More information

White Paper Microsoft SharePoint for Engineering Document Management and Control

White Paper Microsoft SharePoint for Engineering Document Management and Control www.cadac.com White Paper Microsoft SharePoint for Engineering Document Management and Control Microsoft SharePoint is a powerful platform for document management and project collaboration. Many project-driven

More information

BIM Checklist. Introduction

BIM Checklist. Introduction Introduction This Building Information Modeling (BIM) Checklist is intended to be used as a guide for project stakeholders who are looking to implement BIM/VDC in a design-build project. Since integration

More information

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months?

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months? November 2016 Executive Summary The second national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 76% (67% 2015) of respondents possessed confidence

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

BLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE

BLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE BLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE DISTRIBUTED DATABASES SUPPLY CHAINS, WHOLE LIFE COSTING & ASSET MANAGEMENT KEEPING COST OS UPDATED FOR NEW STANDARDS COST OS NRM 3 MODULE, RELEASED

More information

APC Requirements and Competencies

APC Requirements and Competencies APC Requirements and Competencies August 2015 Published by: RICS, Parliament Square, London SW1P 3AD. All rights in this publication, including full copyright or publishing right, content and design, are

More information

POLICY ON MANAGING POLICIES, PROCEDURES AND GUIDANCE DOCUMENTS

POLICY ON MANAGING POLICIES, PROCEDURES AND GUIDANCE DOCUMENTS POLICY ON MANAGING POLICIES, PROCEDURES AND GUIDANCE DOCUMENTS Version: 6 Date Ratified: February 2017 Review Date: February 2020 Applies to: Senior Managers and staff who produce procedural documents.

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS DEPARTMENT SUITE 209S - LOGAN OFFICE CENTER ONE HARBORSIDE DRIVE EAST BOSTON, MASSACHUSETTS 02128-2909 REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT

More information

O10 BIM for specialist sub-contractors and trades BIM IN PRACTICE

O10 BIM for specialist sub-contractors and trades BIM IN PRACTICE O O10 BIM for specialist sub-contractors and trades O BIM IN PRACTICE O O10 BIM for specialist sub-contractors and trades Contributors: Dominik Holzer, AEC Connect Sumit Oberoi, AMCA Philip Shanks, Jackson

More information

Digicon / IBC National BIM Survey Survey Results

Digicon / IBC National BIM Survey Survey Results Digicon / IBC National BIM Survey 2013 Survey Results Digicon / IBC National BIM Survey During the beginning of 2013 NBS, and Digicon / IBC worked together to survey attitudes towards BIM in Canada. The

More information

Building Services Engineer (mechanical) model career pathway Version 1.0

Building Services Engineer (mechanical) model career pathway Version 1.0 April 2013 Building Services Engineer (mechanical) model career pathway Version 1.0 AIRAH Strategic aim #2 - Closing the skills gap Prepared by: The Australian Institute of Refrigeration Air Conditioning

More information

NBS National BIM Survey 2011

NBS National BIM Survey 2011 NBS National BIM Survey 2011 NBS National BIM Survey: Participants What is your main discipline? 5% 1 2 25% 3 35% 4 45% 5 Architect Architectural Technologist Other (please specify) Quantity Surveyor Structural

More information

Careers List Professional Careers in Construction

Careers List Professional Careers in Construction Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize

More information

Sylvia Kendra Associate Director Facilities Knowledge Management. January 11, 2017

Sylvia Kendra Associate Director Facilities Knowledge Management. January 11, 2017 Developing a 3D Building Information Management Practice Sylvia Kendra Associate Director Facilities Knowledge Management January 11, 2017 Find Us On Line Google search: Smithsonian AE Center Or Full url:

More information

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM WHAT S INSIDE: 1 BENEFITS Keep constructability top-of-mind Improve project margins Make better

More information

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into

More information

BIM in Hong Kong: Time to Leap. Ivan WONG Senior Manager Council Services

BIM in Hong Kong: Time to Leap. Ivan WONG Senior Manager Council Services BIM in Hong Kong: Time to Leap Ivan WONG Senior Manager Council Services 2013-11-9 Why is CIC here? Back to Year 2011.. CIC organised a seminar on Building Information Modelling in 2011 With overwhelming

More information

Building Information Modeling (BIM) Execution Plan

Building Information Modeling (BIM) Execution Plan 10/19/2017 for [Stanford Project Name] [Stanford Project Number] Developed by [Primary A/E] TABLE OF CONTENTS USE OF THE BIM EXECUTION PLAN... 3 1. PROJECT INFORMATION... 3 2. PROJECT SCHEDULE AND MILESTONES...

More information

Facilities Management

Facilities Management Facilities Management October 6, 2017 THIS PAGE INTENTIONALLY LEFT BLANK University of South Florida BIM Guidelines and Standards Page 2 of 30 BIM Guidelines and Standards Table of Contents SECTION 1:

More information

BIM Execution Plan Template. CPG-DGN-PLN-085 Revision 0 08/08/2016

BIM Execution Plan Template. CPG-DGN-PLN-085 Revision 0 08/08/2016 BIM Execution Plan Template CPG-DGN-PLN-085 Revision 0 08/08/2016 Contents Section Page References... 1 Acronyms and Abbreviations... 1 Capital Projects Group BIM Execution Plan Template Guide... 2 Tables

More information

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study 89 Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3

More information

Procurement Policy. (June 11, 2015)

Procurement Policy. (June 11, 2015) Procurement Policy (June 11, 2015) Table of Contents 1. PURPOSE AND OVERVIEW... 4 1.1. About MPAC... 4 1.2. Purpose... 4 1.3. Procurement Governance... 4 2. SCOPE AND APPLICATION... 4 2.1. Scope... 4 3.

More information

(iii) Senior Management Course, lasting not less than 4 weeks from a recognized Institution;

(iii) Senior Management Course, lasting not less than 4 weeks from a recognized Institution; VACANT POSTS V/No. 01/2018 PRINCIPAL HOUSING OFFICER, JOB GROUP N, TEN (10) POSTS Salary Scale: Kshs.51,660 69,990 p.m. (a) Duties and Responsibilities Duties and responsibilities at this level involve

More information

IM Scope of Work for Contracts

IM Scope of Work for Contracts IM Scope of Work for Contracts Information Management Version 3.0 Released 6 th June 2014 Document Owner Document Author Knowledge Manager Information Analysis Manager Review Date 6 th June 2016 Document

More information

CASE STUDY: Wellington City Council Bracken Road Flats

CASE STUDY: Wellington City Council Bracken Road Flats CASE STUDY: Wellington City Council Bracken Road Flats BIMinNZ CASESTUDY: WELLINGTON CITY COUNCIL BRACKEN ROAD FLATS 02 WHAT IS BIM: Building Information Modelling (BIM) is a digital representation of

More information

BIM and the Consultant / Client s Quantity Surveyor

BIM and the Consultant / Client s Quantity Surveyor BIM and the Consultant / Client s Quantity Surveyor Mark McKane MRICS, MSc, PGCF&HEd Lecturer in Quantity Surveying School of the Built Environment BSc (Hons) Quantity Surveying & Commercial Management

More information

CRC-CI Project EP National BIM Guidelines and Case Studies

CRC-CI Project EP National BIM Guidelines and Case Studies CRC-CI Project 2007-002-EP National BIM Guidelines and Case Studies Tom Fussell - Team Leader Executive Director and Chief Architect, QLD Department of Public Works Scott Beazley - Project Manager BIM

More information

AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM

AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM Introduction AIA 2009 BIM AWARDS Category B: Design/Delivery Process Innovation Using BIM Project: UNIVERSITY OF COLORADO - DENVER HEALTH SCIENCE CENTER RESEARCH COMPLEX II Owner s Statement Architect

More information

NHS SOUTH DEVON AND TORBAY CLINICAL COMMISSIONING GROUP INFORMATION LIFECYCLE MANAGEMENT POLICY

NHS SOUTH DEVON AND TORBAY CLINICAL COMMISSIONING GROUP INFORMATION LIFECYCLE MANAGEMENT POLICY NHS SOUTH DEVON AND TORBAY CLINICAL COMMISSIONING GROUP INFORMATION LIFECYCLE MANAGEMENT POLICY Version Control Version: 2.0 dated 17 July 2015 DATE VERSION CONTROL 04/06/2013 1.0 First draft of new policy

More information

ESTATES SERVICES. Soft Landings An Introduction

ESTATES SERVICES. Soft Landings An Introduction ESTATES SERVICES Soft Landings An Introduction 2013 Capital Projects - Context Capital projects have responsibility for all new major build and refurbishment projects A major project is a project with

More information

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev - February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February

More information

Invitation to Tender. Development Legal Services. August 2015

Invitation to Tender. Development Legal Services. August 2015 Development Legal Services August Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 5 1.5. Copyright...

More information

INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM

INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM TABLE OF CONTENTS Preamble... 1 1. Definitions... 1 2. Purpose... 2 3. Evaluation of Vendor Performance... 3 3.1 Vendor Performance Scorecard... 3 3.2

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

Notice is hereby given of the following changes to the above-referenced SOLICITAITON:

Notice is hereby given of the following changes to the above-referenced SOLICITAITON: FLORIDA DEPARTMENT OF TRANSPORTATION Procurement Office 605 Suwannee Street, MS 20 Tallahassee, Florida 32399-0450 Phone: (850) 414-4381 Fax: (850) 414-4951 ADDENDUM NO. 2 DATE: May 10, 2016 RE: BID #:

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

Implementing of Building Information Modelling in Public Works Projects in Ireland - Presentation

Implementing of Building Information Modelling in Public Works Projects in Ireland - Presentation Dublin Institute of Technology ARROW@DIT Conference papers School of Surveying and Construction Management 2012-7 Implementing of Building Information Modelling in Public Works Projects in Ireland - Presentation

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

Strategic Revit MEP Object Organization From BIM to Asset Management

Strategic Revit MEP Object Organization From BIM to Asset Management MEP20732 Strategic Revit MEP Object Organization From BIM to Asset Management Jorge Quiroz Director DCV Consultores Sebastian Zaje Senior Technical Specialist - LATAM Autodesk George Broadbent Director

More information

Sustainable Design Services

Sustainable Design Services Point. Advisory Sustainable Design Services Building Information Modeling (BIM) Step 1. Download.bimar App p on Google Play or scan the QR code. Step 2. Point device at cover to view it in 3D augmented

More information

BIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders

BIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders BIM enhances structural analysis regardless of project size By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders MARCH 2013 BIM enhances structural analysis regardless of project size By Jeffrey Yoders

More information

THE DESIGN PROCESS HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN AUGUST 2010 AUG. 02, 2010

THE DESIGN PROCESS HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN AUGUST 2010 AUG. 02, 2010 THE DESIGN PROCESS AUGUST 2010 HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN TAQ ASSOCIATES. ARCHITECTURE & INTERIOR DESIGN KARACHI PAKISTAN 1 SO A BLANK PIECE OF PAPER. HOW DO WE GET FROM

More information

PLANNING AND EVALUATION PRELIMINARY DESIGN

PLANNING AND EVALUATION PRELIMINARY DESIGN PLANNING AND EVALUATION Project Initiation Discuss and refine client requirements Project brief, Schedule, Budget Confirm client's space needs and program Establish scope of work Obtain client-supplied

More information

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3 Prescription of qualifications ARB Criteria at Parts 1, 2 and 3 Approved: January 2010 Effective From: 2011/2012 Introduction Under the Architects Act 1997, the Architects Registration Board (ARB) has

More information

Preparing for BIM. Construction Scotland Conference. Adrian Shilliday. Technical Director & BIM Lead, Galliford Try BIM Region Scotland

Preparing for BIM. Construction Scotland Conference. Adrian Shilliday. Technical Director & BIM Lead, Galliford Try BIM Region Scotland Preparing for BIM Construction Scotland Conference Adrian Shilliday Technical Director & BIM Lead, Galliford Try BIM Region Scotland Presented by Ryan Tennyson Chair of BIM Suppliers Group Scotland Associate

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

Building Information Modelling in the European Union: The case of the UK, France and the Netherlands

Building Information Modelling in the European Union: The case of the UK, France and the Netherlands Building Information Modelling in the European Union: The case of the UK, France and the Netherlands Dr. Mohamad Kassem Associate Professor, Teesside University, UK Federação das Indústrias do Estado de

More information

STRUCTURAL ENGINEER S SERVICES SCOPE

STRUCTURAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick

More information

Estates Services Introduction to the Philosophy Documents and Design Guides

Estates Services Introduction to the Philosophy Documents and Design Guides Estates Services Introduction to the Philosophy Documents and Design Guides Oxford University Estates Services. The Malthouse, Tidmarsh Lane, Oxford. OX1 1NQ 01865 278750 Introduction to the Philosophy

More information

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia JUNE 2017 BIM FOR SURVEYORS Survey Economics State of recovery Tracking Wildlife With a total station Measuring a Meridian Time in 1700s Philadelphia A NEW MODEL FOR SURVEYORS As BIM moves into more projects

More information

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2 Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our

More information

Assistant Regional Asset Manager EU, Wider Europe and Americas. Department/Country Global Estates. Duration of job

Assistant Regional Asset Manager EU, Wider Europe and Americas. Department/Country Global Estates. Duration of job Role Profile Job Description Job Title Ref no: Assistant Regional Asset Manager EU, Wider Europe and Americas Directorate or Region Resources/Busines s Support Services Department/Country Global Estates

More information

Entry Form Collaborative Working Partnership Award

Entry Form Collaborative Working Partnership Award Entry Form Collaborative Working Partnership Award This award recognises examples of collaborative working that have delivered outstanding outcomes on one or more new build or refurbishment projects. It

More information

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi Management of BIMProject: BIM Management Plan Cairo University, Faculty of Engineering MSc in Integrated Engineering Design Management IEDM 611: BIM for Facility Management Prepared and Presented by: Mohamed

More information

Roadmap for the BIM Implementation in Hong Kong s Construction Industry and CICHK s Upcoming Initiatives

Roadmap for the BIM Implementation in Hong Kong s Construction Industry and CICHK s Upcoming Initiatives Roadmap for the BIM Implementation in Hong Kong s Construction Industry and CICHK s Upcoming Initiatives Ms. Ada FUNG Chairperson, Working Group on Roadmap for BIM Implementation Construction Industry

More information

ASSET MANAGEMENT creative minds

ASSET MANAGEMENT  creative minds ASSET MANAGEMENT creative minds safe hands ASSET MANAGEMENT AN INTEGRATED SOLUTION Ensuring that your assets deliver optimum performance, without compromising budgets, health and safety or regulatory compliance.

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Building information modeling and intelligent green buildings

Building information modeling and intelligent green buildings White paper Building information modeling and intelligent green buildings Dr. T. C. Tan, DMTS, CommScope Labs B.Sc (Eng), DIC, PhD, CEng, FIET Contents Introduction 3 Building information modeling (BIM)

More information

Date: INFORMATION GOVERNANCE POLICY

Date: INFORMATION GOVERNANCE POLICY Date: INFORMATION GOVERNANCE POLICY Information Governance Policy IGPOL/01 Information Systems Corporate Services Division March 2017 1 Revision History Version Date Author(s) Comments 0.1 12/12/2012 Helen

More information

Dedicated to Building Information Modelling Technology (BIM) since 2002

Dedicated to Building Information Modelling Technology (BIM) since 2002 Building Information Modelling (BIM) technology for Architecture, Engineering and Construction Dedicated to Building Information Modelling Technology (BIM) since 2002 At a glance Unrivalled BIM coverage

More information