Construction Engineering and Inspection Services Pembroke Road from Dykes Road to Silver Shores Boulevard Broward County, FL
|
|
- Valerie Elinor Carr
- 5 years ago
- Views:
Transcription
1 Construction Engineering and Inspection Services to Silver Shores Boulevard Broward County, FL R L I N O. R P 1
2 I. Experience and Qualifications with Roadway Construction a. Eisman & Russo b. Individual Team Members II. Construction Management Approach a. Scope b. Coordination c. Environmental III. Challenges and Solutions a. Access to Silver Shores Elementary b. Public Access c. Subsoil Excavation d. Utilities e. Perimeter Wall Installation f. Deep Drainage Installations g. Adjacent Projects
3 J. Scott Gombar, P.E. CEI Project Manager Principal with Eisman & Russo Over 22 Years in South East Florida Largest CEI Division of Eisman & Russo Extensive FDOT Roadway Construction Broward County Highway Engineering Municipal Roadway Construction
4 Similar Project Experience Pembroke Road from SW 145 th Avenue to Silver Shore Boulevard Javier Grass Sr. Inspector BROWARD COUNTY SR-7/US 441 Reconstruction from Fillmore Street to Stirling Road Jose Sotomayor, P.E. Project Engineer BROWARD COUNTY Hollywood Boulevard from US1 to Intracoastal Waterway Ido Shimony, P.E. Sr. Project Engineer BROWARD COUNTY Education Corridor Median Improvements, Coconut Creek Ido Shimony, P.E. Sr. Project Engineer BROWARD COUNTY
5 Team Experience Organization Chart QA/QC Team J. Scott Gombar, P. E. Leonardo Offredi, P. E. Chris Charvat Broward County HCED Project Manager Nirmal Datta, P.E. CEI Project Manager J. Scott Gombar, P. E. Senior Project Engineer Ido R. Shimony, P. E. Testing Lab GCES Engineering Services (CBE) Survey Aylward Engineering & Survey (CBE) Aerial Photograph Smith Aerial Photograph Inspector Mark Zuniga Project Engineer Jose Sotomayor, P.E. Senior Inspectors Michael Babcock Javier Grass Contract Compliance/Administrative Assistant Marielena Gombar
6 Team Member s Experience Qualifications & Certifications CTQP Final Estimates 1 CTQP Final Estimates 2 CTQP Asphalt Paving Level 1 CTQP Asphalt Paving Level 2 CTQP Earthwork Level 1 CTQP Earthwork Level 2 Nuclear Radiation Safety CTQP Concrete / ACI Level 1 CTQP Drilled Shaft Inspection CTQP QC Manager FDOT Critical Structures NPDES Florida Advanced MOT IMSA Traffic Signal Technician 1 IMSA Traffic Signal Inspector Eisman & Russo, Inc. FDOT Prequalification 10.1 Roadway Construction Engineering Inspection Position CEI Staff Project Manager J. Scott Gombar, P. E. Senior Project Engineer Ido R. Shimony, P. E. Project Engineer Jose Sotomayor, P.E. Senior Roadway Inspectors Michael Babcock S S Javier Grass S S Roadway Inspector Mark Zuniga S = Scheduled
7 Team Member s Experience Ido R. Shimony, P.E. Senior Project Engineer 20 years experience in design/construction of bridges and roadways Leadership role on similar scope projects Experience working with FPL, Broward County Traffic, SBDD, SFWMD Experience with Perimeter Noise Wall Construction Experience with Complete Streets Takes Ownership of Project Establish Project Specific Goals Manage Schedule and Budget
8 Team Member s Experience Similar Projects Ido Shimony, P.E. Roadway Construction Experience Drainage Earthwork Asphalt Signalization Lighting Landscaping and Irrigation Eller Drive and ICTF Overpass X X X X X X I-75 Segment D and Sheridan Street Interchange Hollywood Boulevard from US1 to Intracoastal Waterway West Hallandale Beach Boulevard from Lakeshore Dr. to Dixie Highway X X X X X X X X X X X X X X X X X X
9 Team Member s Experience Jose Sotomayor, P.E. Project Engineer 10+ years of experience as Contractor and CEI on bridge and roadway projects CEI Project Engineer for SR 7/US 441 Project Established trust with Contractor Has worked on construction projects with costs from $32 $86 M Experience working with FPL, Broward County Traffic, SBDD, SFWMD Experience in Scheduling Review Monthly Pay Requisitions
10 Team Member s Experience Similar Projects Jose Sotomayor, P.E. Roadway Construction Experience SR-7/US-441 From Filmore to Stirling Road Bear Cut Bridge and West Bridge Rehabilitation Project Golden Beach Bridge Replacements SR 823 Red Road from Okeechobee Rd to West 23 rd Street Drainage Earthwork Asphalt Signalization Lighting Landscaping and Irrigation X X X X X X X X X X X X X X X X X X X X X X
11 Team Member s Experience Inspection Staff Javier Grass Senior Inspector 14 years of Experience East Pembroke Road Project and SR 7/US 441 Michael Babcock Senior Inspector 13 years of Experience Hallandale Beach Blvd, Red Road and I75 Improvements at Pembroke Road Mark Zuniga Inspector 14 years of Experience Earthwork specialist for Eller Drive and Turnpike Express Lanes projects Background in Quality Control Testing
12 Construction Management I. Project Scope Phases of Construction Traffic Control Plan Restrictions Perimeter Wall Construction Subsoil Excavation Drainage New Road Construction Concrete Elements Specialty Items Milling and Resurfacing II. III. Coordination Utility Companies Stakeholders Environmental Drainage work at Canal Irrigation Pumps
13 Phases of Construction Scope
14 Perimeter Wall Construction City of Miramar Walls City of Pembroke Pines Walls
15 Drainage 5,000 feet of Drainage Pipe Connecting to Existing Drainage Modifications to Existing Drainage New Drainage Inlets and Boxes 500 feet of French Drain
16 Concrete Asphalt 14,000 LF of Curb and Gutter Sidewalks and ADA Ramps 4 Bus Stops and 2 Bus Bays Mast Arm Foundations Widening New Roadway Construction Milling and Resurfacing Driveways
17 Traffic Signalization Equipment Solar School Flasher Overhead Mast Arm Lighting Landscaping and Irrigation
18 Value Engineering Alternatives that offer benefits in the areas of engineering design, equipment and material selection, construction and operations and maintenance. Primary objective to identify cost reductions without impairing essential functions, ease of maintenance Subsoil Excavation Wall Post and Panels
19 Stakeholders Broward County HCED, Traffic Engineering City of Miramar City of Pembroke Pines Broward County Transit Broward County Public Schools Emergency Services South Broward Drainage District Homeowners Associations Silver Shores Grand Palms Estates of Pembroke Shores Pembroke Shores Utilities AT&T Broward County City of Miramar City of Pembroke Pines Public Services Comcast Cable FPL Distribution FPL Fibernet Broward County Traffic Engineering
20 Challenges and Solutions Silver Shores Elementary School Entrance Challenge: Maintain Access to school for Drainage Crossing and Driveway Construction Solution: Broward County School Calendar Coordinate with Silver Shores Elementary School and Broward County School Board Reconstruct the drainage and driveway in phases Construct a temporary two way traffic driveway
21 Challenges and Solutions Public Access Challenge: Minimize impacts to bikes and pedestrians during construction. Solution: Maintain sidewalks Provide safe alternate routes around construction activities Coordinate alternate routes with Broward County Traffic Engineering Division and EOR in MOT Plans
22 Challenges and Solutions Subsoil Excavation Challenge: Some subsoil excavation in plans was already performed in east project Solution: Redefine limits of demuck to match as built plans of east project Demuck Previously Performed East of Pembroke Shores Blvd Demuck Work Shown in Plans
23 Challenges and Solutions 28,000 CY of Subsoil Excavation and Utilities Challenge: Avoid utility damage during excavation Solution: Maintain locates and soft dig utility Utilize As Built Plans from the Utility Owner Monitor high impact equipment near Utilities
24 Challenges and Solutions Installation of Perimeter Wall Under Utilities Challenge: Install wall posts and panels below overhead utilities lines Solution: Coordinate de energizing of lines Ensure Contractor meets OSHA and utility owners clearance regulations Flag overhead Utilities Contractor to assign a spotter
25 Challenges and Solutions Deep Drainage Installation Adjacent to Wall Challenge: Risk of damage to wall posts due to confined space between existing utilities, perimeter wall and right of way Solution: Temporarily bracing the perimeter wall posts while constructing french drain and adjacent structures Protection of the posts
26 Challenges and Solutions Adjacent Projects Grand Palms Entrance Challenge: Coordination between Pembroke Road construction and proposed Grand Palms Entrance. Solution: Facilitate coordination between Grand Palms HOA, Contractors and Broward County. Recommend adding plan note about proposed Grand Palms Entrance.
27 Your Solutions Team Thank You!
PRESENTATION FOR: Construction Engineering and Inspection-Wiles Road from Riverside Drive to Rock Island Road. RFP No. J P1
PRESENTATION FOR: Construction Engineering and Inspection-Wiles Road STAFFING MATRIX Construction Engineering and Inspection-Wiles Road JAMES JEFFERS, P.E. Senior Project Engineer Years of Experience:
More informationCEI Services Transit Bus Stop Infrastructure
Presentation for: Broward County Board of County Commissioners sioners V2114585P1 CEI Services Transit Bus Stop Infrastructure Presented by: SOLID Consulting Engineers, Inc. (CBE/SBE) COMPANY AND TEAM
More informationIntroduction Who We Are
Introduction Who We Are We offer a diverse scope of professional services that often enables us to serve as a reliable one-source partner, efficiently tackling time-sensitive projects with customized solutions.
More informationMEET THE AE TEAM YOUR CEI SOLUTION YOUR PARTNERS
BROWARD COUNTY Broward County Project Number 5413 Qualifications for Construction Engineering and Inspection Services CEI Services for Wiles Road from Riverside Drive to Rock Island Road YOUR CEI SOLUTION
More informationNOVEMBER 13, 2017 S O L I C I T A T I O N N O. V P
NOVEMBER 13, 2017 PRE QUALIFICATIONS R.J. Behar & Company, Inc. (RJB) has overseen in excess of $1 billion in construction projects throughout the state of Florida. Our team is fully qualified in the following
More informationOverview. Construction Engineering and Inspection Services for Wiles Road from Riverside Drive to Rock Island Road
Construction Engineering and Inspection Services for Wiles Road from Riverside Drive to Rock Island Road Presentation for March 3, 2017 Overview Staffing Project Understanding Approach Past Performance
More informationProject Type: Drainage and Storm Systems
580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install
More informationFlorida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four
DISTRICT FOUR PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Four. In fiscal years 2014 and 2015, current Turnpike projects total over $127
More informationMAINTENANCE OF TRAFFIC NOTES
MAINTENANCE OF TRAFFIC NOTES GENERAL: 1. THE REGULATORY SPEED USED FOR MOT CALCULATIONS FOR EACH FACILITY ARE NOTED BELOW. MODIFICATIONS TO THE REGULATORY SPEED MAY REQUIRE RESUBMITTAL OF THE MOT PLAN.
More informationSR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.
Palm Beach County, Florida Palm Beach Metropolitan Planning Organization April 217 Project Study Area LIMITS: SR 9/I-95: from S of 45th Street to N of 45th Street 45th Street: From Village Boulevard to
More informationCITY OF SAFETY HARBOR ENGINEERING
CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,
More informationPalm Beach County Engineering Overview & Implementation Plan for the One Penny Sales Surtax
Palm Beach County Engineering Overview & Implementation Plan for the One Penny Sales Surtax Engineering Sales Tax Projects Bridges $ 43.4 m (27) Roads (Resurfacing) $ 77.6 m (121) Roads (Restriping) $
More informationADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012
ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle
More informationEXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE
EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE The Existing Roadway Condition Assessment Report (ERCAR) should include the evaluation of all elements against new construction criteria.
More informationMEMORANDUM. DATE: December 12, Steve Joseph, P.E. J. Philip Cooke, P.E. Monique Durand, P.E. Wastewater Flow Projections
4000 Hollywood Boulevard Seventh Floor, North Tower Hollywood, Florida 33021 (954) 987-0066 Fax: (954) 987-2949 MEMORANDUM DATE: December 12, 2012 TO: FROM: PROJECT: Steve Joseph, P.E. J. Philip Cooke,
More informationExhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate
0.0 Separation of work Types and Cost Estimate Exhibit A Scope of Work 0.1 Prepare scope of work and cost estimate for MnDOT efforts relating to all items numbered less than 20.0. 0.2 Prepare scope of
More informationFTBA 2018 Construction Conference Major Projects Update
FTBA 2018 Construction Conference Major Projects Update Bill Jones, P.E. FDOT District 7 Director of Transportation Development 1 2 3 FUNDED PROJECTS Howard Frankland Bridge Industry Forum September 2018
More informationForsyth County Procurement
July 7, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 BID 17-63-3150 For: Providing all labor, materials and equipment for the construction of the Brookwood
More informationProject Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce
Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,
More informationConstructability Guidelines
Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final
More informationENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)
EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 8 Final As Built Plans 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 8 1 Final As-Built Plans are important to construction,
More informationThe Gateway Expressway FTBA Conference. February 2-3, 2017
The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north
More informationMDX Contract #: RFP MDX Work Program #: ETDM #: 11501
SR 874/Don Shula Expressway Ramp Connector Project Development & Environment (PD&E) Study PUBLIC HEARING December 8, 2011 MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 1 This Public
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated June 27, 2016 BEAVER COUNTY SR 7446(LBB) #92912 PROPOSAL:$54.72 PLANS:$42.46 12X18:$52.11 24X36:$752.70 EXSTRUCT:$48.62 12X18:$59.67 24X36:$861.90 The description and location of the project is
More informationETS. Scripps Networks Expansion Knoxville, Tennessee. Services Provided: Subsurface Exploration - drilling geotechnical engineering
Scripps Networks Expansion Knoxville, Tennessee drilling drilled shaft observation steel erection observation Located at the existing Scripps Network facilities in Knoxville, this $40+ million expansion
More information1/2017. Atkins North America, Inc W. Boy Scout Boulevard Tampa, FL 33607
Request for Proposal (RFP) No. J2111758P1 1. Ability of Professional Personnel: A. Describe the qualifications and relevant experience of the proposed Senior Project Engineer and all key personnel that
More information2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017
2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017 2017 CBD Improvements Agenda Meeting Agenda Introduction Scope of Improvements Time frames for improvements May vary
More informationSandstone Curb Replacement Standards
Sandstone Curb Replacement Standards Division of Infrastructure Management SCOPE OF CURB REPLACEMENT (Funding Dependent) Sandstone Curb Section I - Purpose: Sandstone curb may be replaced only if existing
More informationCONSULTANT OF THE YEAR
CONSULTANT OF THE YEAR 1 P a g e HISTORY Stone Engineering Group, in business since 1989, is an outgrowth of the firm, H.C. Stone, founded in 1973. Stone Engineering Group began in 1989 as Stone Joca
More informationTABLE OF CONTENTS SECTION
PREFACE This manual contains current information for designing and submitting transportation plans for proposed projects to be constructed in unincorporated Hillsborough County. This manual is a readily
More informationEXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description. US 41 (SR 45) From Winkler Avenue to SR 82
EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description US 41 (SR 45) From Winkler Avenue to SR 82 Financial Project ID(s): 431313-1-62-01 Federal Project No.: N/A
More informationEXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description
EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description CEI Services for I-95 /I-595 Express Lanes Direct Connect and bridge painting from Stirling Road to Broward
More informationCity of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)
FREQUENTLY ASKED S (FAQ) The purpose of this document is to provide detailed information about the Harvard Road Reconstruction & Water Main Replacement Project. This project will directly affect residents
More informationMaintenance, Construction & Secondary Roads. Terry Gibson, PE Chief Engineer February 20, 2013
Maintenance, Construction & Secondary Roads Terry Gibson, PE Chief Engineer February 20, 2013 State versus local responsibility Division structure Allocations Flexibility in funding Implications of not
More informationRAIL-HWY PROJECT DEVELOPMENT GUIDE AND
RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT
More informationFor Public Input Period
20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)
FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could
More informationKeys Edge Community Development District. Engineer s Report Infrastructure Improvements
Keys Edge Community Development District Engineer s Report Infrastructure Improvements Prepared for Keys Edge Community Development District Board of Supervisors Miami-Dade County, Florida Prepared by
More informationI-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012
I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings Tier II June 11 th & 13 th, 2012 Agenda Introduction & Background Study Area Purpose & Need Project Status Tier Methodology & Tier I Evaluation
More informationANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore
More informationSouth Carolina Department of Transportation. Engineering Directive
South Carolina Department of Transportation Engineering Directive Directive Number: ED-17 Effective: May 5, 2015 Subject: Encroachment Permits References: S.C. Code of Laws, Sections 57-3-110, 57-5-1080,
More informationRequest for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2
Addendum Number 1 Request for Proposals No. 17-001 Various On-call Professional Design and Engineering Services To all prospective firms under specifications for Request for Proposals (RFP) No. 17-001,
More informationTxDOT Houston District Permit Requirements (Information contained herein is subject to change)
Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three
More information2018 FTBA CONSTRUCTION CONFERENCE February 8-9, 2018 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW
Florida Department of TRANSPORTATION 2018 FTBA CONSTRUCTION CONFERENCE February 8-9, 2018 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW Presenter: Brian Blanchard, Assistant Secretary Engineering and
More informationDesign-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection
DESIGN-BUILD Design-Build Authorization Project Selection Criteria Selection/Award Process Warranties Design-Build Construction Engineering and Inspection Materials Acceptance DESIGN-BUILD AUTHORIZATION
More informationEXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description
EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description CEI services for ITS infrastructure and patterned pavement crosswalks for SR-706/Indiantown Road from Turnpike
More informationAPPENDIX H. Capital Improvement Program Detail Project Costs NORTH PERRY AIRPORT MASTER PLAN UPDATE APPENDICES
MASTER PLAN UPDATE APPENDICES APPENDIX H Capital Improvement Program Detail Project Costs Montgomery Consulting Group August 11, 2009 Appendix H CAPITAL IMPROVEMENT PROGRAM Short Term (0-5 years) SUB-
More informationFLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT
FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT District 2 1109 South Marion Avenue Lake City, FL 32025-5874 INTERSTATE 10 (SR 8) / SR
More informationCarpinteria Avenue Bridge Replacement Project Description Introduction
Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with
More informationEXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description
EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description I-275 (Howard Frankland) from N. of SR 687 (4 th St N.) to N. of Howard Frankland I-275 (Howard Frankland)
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ADVANCED INFORMATION LETTING JULY 17, 2014 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
ASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ADVANCED INFORMATION LETTING JULY 17, 2014 Updated June 30, 2014 LUZERNE COUNTY SR 309(W02) #102354 PROPOSAL:$25.20 PLANS:$6.24 The description and location
More informationCity of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT
City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT TO: Planning and Zoning Board FROM: Carlos M. Rivero, City Planner DATE: August 10, 2015 RE: Storage Facility P&Z ITEM # 15-010 OWNER
More informationHIGHLANDS COUNTY BOARD OF COUNTY COMMISSIONERS Tuesday, February 20, :30 PM 600 S. Commerce Ave. Sebring, FL AGENDA
HIGHLANDS COUNTY BOARD OF COUNTY COMMISSIONERS Tuesday, February 20, 2018 5:30 PM 600 S. Commerce Ave. Sebring, FL 33870 AGENDA 1 MEETING CALLED TO ORDER: Invitation to fill out "citizens not on the agenda
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MAY 24, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
ASSOCIATED PENNSYLVANIA CONSTRUCTORS Updated May 4, 2018 FULTON COUNTY SR 0000(FMC) #109343 PROPOSAL:$21.36 PLANS:$9.02 12X18:$11.07 24X36:$159.90 X-SEC:$7.48 12X18:$9.18 24X36:$132.60 This project involves
More informationEXHIBIT 3 CORRESPONDENCE 1 8/15/16 BCT Broward Next Policy Concept EXHIBIT A Legend Qualified Transit Areas Areas highlighted in orange are within 0.5 miles of a rail station or 0.25 miles of a bus
More informationDOCUMENT CONTROL PANEL
August 2013 DOCUMENT CONTROL PANEL File Name: I-95 Integrated Corridor Management System, Broward County File Location: 11555 Heron Bay Boulevard, Suite 200, Coral Springs, FL 33076 Document Tracking Number:
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationENGINEERING SERVICES REPORT FOREST LAKES BOULEVARD PAVEMENT EVALUATION TAMPA ROAD TO COUNTY LINE FOR PINELLAS COUNTY, FL. May 21, 2010 URS CORPORATION
ENGINEERING SERVICES REPORT FOREST LAKES BOULEVARD PAVEMENT EVALUATION TAMPA ROAD TO COUNTY LINE FOR PINELLAS COUNTY, FL May 21, 2010 URS CORPORATION May 21, 2010 Mr. Brent D. Hall Senior Department Administrative
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationTRANSPORTATION ELEMENT
Goal 3.0. Establish and support within Broward County a complete public multimodal transportation system that provides, in a context sensitive fashion, safe, convenient and comfortable travel and access
More informationLIST OF STANDARD DRAWINGS H2-2 - SERIES 2: Grading
LIST OF STANDARD DRAWINGS H- - SERIES : Grading 00.0 Undivided Highway - Earth Grading Sections Earth Grading - Undivided Rural Earth/Shale Grading - Undivided Rural 9 04 7 00.00 Earth/Shale Grading -
More informationEXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description
6/23/2017 EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description Group 163: SR 423 (John Young Parkway) from SR 50 to Shader Rd. Financial Project ID: 239496-3-62-01
More informationPERMITTING AND CONSTRUCTION MANUAL
PUBLIC RIGHT-OF-WAY CONTENTS PERMITTING AND CONSTRUCTION MANUAL 1. INTRODUCTION 2. PUBLIC SERVICE PROVIDER REGISTRATION 3. CONSTRUCTION PERMITTING PROCEDURE 3.1 Permitting Process 3.2 Permit Application
More informationDouglas Woods Wind Farm
Traffic Evaluation and Access Management Report Douglas Woods Wind Farm Douglas,Massachusets Prepared for American Pro Wind 195 Libbey Parkway - Unit Two Weymouth, MA 02189 Prepared by Transportation,
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationGreater Cleveland Regional Transit Authority
Greater Cleveland Regional Transit Authority CALL FOR ARTISTS - PUBLIC ART CLIFTON ENHANCEMENT PROJECT CFA NO. 1-2014 Due Date: Friday, March 14, 2014 4:00 P.M. Official Time February 14, 2014 Prospective
More informationProvidence Corner HOA Upper Providence Township, Pennsylvania
DEFICIENCY REPORT FOR THE Providence Corner HOA Upper Providence Township, Pennsylvania Project Number: 15-1064 Date: July 8, 2016 W:\2015\15-1064\CORR\Deficiency\Providence Corner Deficiency Report 07
More informationSection XXV Preconstruction Assessments and Damage Mitigation Procedures
Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationMaryland Transportation Authority (MDTA)
Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David
More informationFlorida Department of Transportation
Florida Department of Transportation Major Projects Update Report District 6 September 2017 Table of Contents Table of Contents Project Development and Environment (PD&E) Study Phase S.R. 9A/I-95 from
More informationFlorida Department of Transportation Notice to Contractors / Consultants:
Florida Department of Transportation Notice to Contractors / Consultants: The Department of Transportation is soliciting contracting and consulting services for the Design-Build projects identified below.
More informationA T L A N T I C O C E A N
39 CHIPLEY PENSACOLA 0 FORT WALTON BEACH PANAMA CITY TALLAHASSEE 0 LAKE CITY 95 95 JACKSONVILLE ST AUGUSTINE GAINESVILLE CONTRACT PLANS LOCATION OF PROJECT OCALA DELAND 4 DAYTONA BEACH NEW PORT RICHEY
More informationENCROACHMENT/EXCAVATION PERMIT APPLICATION
PERMIT / PROJECT INFORMATION: PARCEL INFO: APPLICANT S INFO: Public Works/Engineering 595 SILVER LACE BLVD, FERNLEY, NV 89408 (775)-784-9910 ENCROACHMENT/EXCAVATION PERMIT APPLICATION PERMIT APPLICATIONS,
More informationJune 19, 2015 Set 2. FROM: Anita Hoover, Procurement Specialist 3
TO: All Potential Respondents RFB 1414 River Tower Shoreline Restoration and Water Quality Improvement Project FROM: Anita Hoover, Procurement Specialist 3 SUBJECT: QUESTION 1: QUESTION 2: Response to
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationCITY OF LAWRENCE RESIDENTIAL DRIVEWAY PERMIT CHAPTER 16, ARTICLE 3, ADOPTED BY THE CITY COMMISSION ON JULY 10, 1996.
CITY OF LAWRENCE RESIDENTIAL DRIVEWAY PERMIT CHAPTER 16, ARTICLE 3, ADOPTED BY THE CITY COMMISSION ON JULY 10, 1996. DATE ADDRESS OF INSTALLATION OWNER ADDRESS CITY STATE ZIP CODE NATURE OF WORK: (check
More informationCity of San Angelo, Texas Capital Improvements Program. 50th Street Extension
50th Street Extension Responsible Division: Public Works / Engineering Services Project Manager: Clinton Bailey Years 280,000 2,000,000 11/12 Future - 2,280,000 Extension of 50th Street from Travis Street
More informationCITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way
CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY Guidance on restoration of City Rights-of-Way Public Works Department Directors Office 747 Market Street Suite 408 Tacoma, WA 98402 253-591-5525 Right-of-Way
More informationTRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM
VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational
More informationConstruction Inspection for the FUTURE. Presented By: Gary Angles, PE Lyle Flower, PE
Construction Inspection for the FUTURE Presented By: Gary Angles, PE Lyle Flower, PE History of Prequalification Firms were Prequalified 20 years ago Judged to be ineffective and ended ODOT began requiring
More information1441 East 104 th Street, Suite 105 Kansas City, MO Tel (816) Fax (816)
1441 East 104 th Street, Suite 105 Kansas City, MO 64131 Tel (816) 874-4655 Fax (816) 874-4675 www.trekkdesigngroup.com November 15, 2013 Mr. Kenny Voss, P.E. Local Program Administrator - Missouri Local
More informationSTANDARDS FOR CONSTRUCTION AND USE OF PUBLIC RIGHTS-OF-WAY AND EASEMENTS
STANDARDS FOR CONSTRUCTION AND USE OF PUBLIC RIGHTS-OF-WAY AND EASEMENTS EFFECTIVE October 19, 2009 CITY OF WEST PALM BEACH ENGINEERING SERVICES DEPARTMENT 401 CLEMATIS STREET WEST PALM BEACH, FLORIDA
More informationContact Clark Public Utilities Construction Services department at (360) to initiate a request for service.
CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation
More informationAPPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)
APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) PROJECT DESCRIPTION: (Enter Type of Project Planning Cost Estimate as Title)
More informationADMS Installation MP Financial Project Number: Extinguish the Torch Summary Report
MP 58 86 Financial Project Number: 435617 1 52 01 Extinguish the Torch Summary Report CEI: Turnpike CPM: GEC Project Manager: EOR: RS&H, Inc. Jaime Gomez Terry L. Miller, P.E. James Sumislaski, P.E. (Kimley
More informationRoute 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building
PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer
More informationI-64 Pavement Rehabilitation
LETTER OF SUBMITTAL I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) A Design-Build Project Norfolk, Virginia Proposal Submitted
More informationTS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS
TORONTO TRANSPORTATION January 2012 TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS 1. DRAWINGS TTD 801.001 ELECTRICAL ABBREVIATIONS AND SYMBOLS TTD 801.005 ELECTRICAL LEGEND I TTD 801.006 ELECTRICAL
More informationInterstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager
Interstate 66 Widening from Gainesville to Haymarket RFQ Information Meeting January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager John C. Daoulas, P.E. APD Project Manager and POC Introduction
More informationc h a p t e r 4 d e s i g n e x a m p l e s f o r s a n m a t e o c o u n t y A typical residential street intersection
LOW-DENSITY RESIDENTIAL STREETS: Stormwater Curb Extensions A typical residential street intersection This residential street example illustrates how stormwater curb extensions can be easily retrofitted
More informationFlorida Department of Transportation
Florida Department of Transportation Major Projects Report District 6 April 2018 Table of Contents Table of Contents Project Development and Environment (PD&E) Study Phase S.R. 9A/I-95 from U.S. 1 to Broward
More informationCITY OF LOS ANGELES Sidewalk Repair Program. Amber Elton, PE
CITY OF LOS ANGELES Sidewalk Repair Program Amber Elton, PE Sidewalk Repair Program Civil Engineer APRIL 20, 2017 Century Plaza Towers 2029 Century Park East City s Goal BEFORE AFTER Improve Mobility in
More informationCITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application
CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application Good for 90 days from the Date Issued This permit is only required if the work location is owned or controlled by the City of Homestead and
More informationCITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application
CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY
More informationPermission for Routine Infrastructure Works Letter of Approval Qualification Criteria
Permission for Routine Infrastructure Works Letter of Approval Qualification Criteria INTERIM PROTOCOL Authority Meeting #10/07, Res. #A293/07, January 4, 2008 1. The works outlined in Table 1 must classify
More informationHosted by: M Squared Engineering on behalf of the Illinois Department of Transportation Thursday, February 9, 2012 Eiger Lab, Rockford, IL
Hosted by: M Squared Engineering on behalf of the Illinois Department of Transportation Thursday, February 9, 2012 Eiger Lab, Rockford, IL TECHNICAL SUPPORTIVE SERVICES IN IDOT DISTRICTS 2 & 3 FOR CERTIFIED
More informationDIVISION 5 STORM DRAINAGE CRITERIA
DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the