Concrete Pavement Preservation Partial Depth Repairs
|
|
- Russell McCormick
- 5 years ago
- Views:
Transcription
1 Concrete Pavement Preservation Partial Depth Repairs National Concrete Pavement Technology Center North Dakota Ready Mix and Concrete Products Association Dan Frentress P.E. IGGA 1
2 Partial-Depth Repair Purpose: Repair surface distresses Reestablish joint reservoir Used for: Midslab surface spalling Joint spalling Severe scaling Remove and Replace Deteriorated Surface Concrete
3 Benefits Restores structural integrity Improves ride quality Extends the service life Restores a well-defined uniform joint sealant reservoir 3
4 Good Candidate Projects Spalls caused by: Incompressibles in joints Localized areas of weak material Joint inserts Surface deterioration caused by: Reinforcing steel too close to surface Poor curing or finishing practices Recommended evaluation procedures: Distress surveys Sounding and cores from pavement 4
5 Poor Candidate Projects Spalls due to dowel bar misalignment Spalls at working cracks due to shrinkage, fatigue, or foundation movement Spalls due to D-cracking or reactive aggregate 5
6 Good Candidate? PDR Placed in 1992 Picture taken in
7 Bad Candidate! 7
8 Good Candidate? 8
9 Material Selection Factors Allowable lane closure time Ambient temperature Cost Size of repair Estimated performance Normal opening strength for partial depth repairs to 1,800 to 3,000 psi Most agencies maintain a Qualified Products List that provides approved materials for use by the agency. 9
10 Construction Steps 1. Repair dimension selection 2. Concrete removal 3. Repair area preparation 4. Joint preparation 5. Bonding agent application 6. Patch material placement 7. Curing 8. Diamond grinding (optional) 9. Joint sealing 10
11 Repair Dimension Selection Sounding 11
12 Repair Dimension Selection (TOP VIEW) Boundary saw cuts min. 2 in. (50 mm) deep, 3 in. (76 mm) outside distressed area. Overlap cuts at corners and approx. 1 in. (25 mm) across joint. Saw cut approx. 2 in. (51 mm) away from joint for protecting opposite face. Saw cut skimming opposite joint to provide clean vertical face. 12
13 Concrete Removal Saw-and-Remove Diamond-bladed saws are used. Sawing provides vertical faces and square corners. The initial sawcut may be either at those marked boundaries at 2: deep or at the boundaries and in a criss-cross pattern. Material is removed with lightweight jackhammers. PROS: Very little spalling of remaining pavement occurs. Crews are typically familiar with this method. CONS: Water from sawing leaves area saturated, possibly delaying the repair process. Polished vertical edges may lead to poor bonding. 13
14 Concrete Removal Jackhammering Removal begins at center and extends outward Remove top 1/3 but no more Care not to fracture sound concrete Removal near joints should be done w/10-15 lb. hammer to avoid damage Operate hammer no greater than 35% 14
15 Concrete Removal Cold Milling Transverse Milling (small head, moves along joint) Longitudinal Milling (wide head, pick up & move over) Some states (at least MO, MI, WI, and MN) have had good success using cold milling. PROS: Rough, irregular surface that promotes bonding. Efficient and economical when repairing large areas. CONS: May cause spalling on adjacent pavement edges. Equipment may be difficult or expensive to obtain for some projects. Small patches (<3 ft2) cannot be fixed using this method. Creates a standard size, which may not conform to site needs. 15
16 Minnesota Standard This standard developed and used by the Minnesota DOT allows the contractor to choose milling or jack hammers for removal of deteriorated concrete. Milling Option Requires a taper of two inches difference between the bottom of the patch and the top of the patch. 10 bottom vs. 12 top. Allows the use of a rounded edge left be the mill and the use of light jack hammers to remove any delaminated concrete exposed by the milling operation. Sand is allowed under exposed dowel bars on a limited basis. Sawing and Chipping Option Saw around the removal area to a depth of 2 inches. Use a light jack hammer of 35 lbs or less to remove the deteriorated concrete. A taper of between degrees is required between the bottom of the repair to the top. 10 bottom vs. 12 top. Sand is allowed under exposed dowel bars on a limited basis. Exposed dowels must be coated with duct tape to prevent bonding to patch mix. 16
17 Minnesota Standard Plate for PDR 17
18 Milling Machine-V Head for Partial Depth Patch Weight 9 Tons Little dust Removal rate 8 ft. / minute 18
19 Skid Steer for Milling Partial Depths Best suited for corner spalls and random cracks, it can maneuver better than the larger mills. Skid Steers weigh about 8000 pounds and can have removal rates of 2 3 feet per minute. Light weight skid steers can cause spalling at edges, but most minor spalls will be patched with concrete mix. It is easy to lift the front end off the ground during milling, but can be done with minor spalling. 19
20 Concrete Removal Cold Milling Milling Across the Joint Milling Along the Joint 20
21 Checking for Sound Concrete Done after the Mill Use lightweight jack hammer (15 30 lbs) for any debris removal 21
22 Joint Preparation joint 75 3 mm Remove bond breaker after patch finished & seal joint scoring 75 3 mm Plan View bond breaker Polystyrene Polyethylene patch pavement 25 1 mm 1 in = 25.4mm Profile View Fig. 5.3 on p
23 Partial-Depth Repair Need for Compressible Insert Point Bearing Popout & Breakage Joint Closure Debonding Expansion Expansion 23
24 Example of Compression Relief Failure of Partial Depth Joint Repair BELIEVE IT when it calls for Compression Relief 24
25 Repair Area Preparation Sandblasting 26
26 Repair Area Preparation Air Blowing Air blow to remove dust and debris Minimum 90 psi Free of oil and moisture Direct away from patches 27
27 Final Blowing of Debris with Leaf Blower 28
28 Milled Crack and Joint 29
29 Ankeny Partial Depth 30
30 Fill Void Below Joint Use Sand to provide compression relief in milled crack (no lockup) Must use caution when needing to do a lot of this before patching Repair will not last as long as one placed in sound concrete 31
31 Precautionary Note in Specs Sand can prevent locking of the joints together due to concrete infiltration when placing repairs. This will probably result in a reduced repair life. The following is an example of over using the sand principle. Duct tape is an excellent way to prevent bond on exposed old dowel bars. 32
32 Hole to Bottom 33
33 Minnesota Standard Plate 34
34 Bonding Agent Application Surface should be clean and in a saturated, surface-dry condition. Apply cementitious bonding agents with a wire brush; apply epoxy bonding agents with a soft brush. Coat all horizontal and vertical surfaces. Excess grout or epoxy should not be permitted to collect in pockets. Cement Grout The grout should be placed immediately before the repair material so that the grout does not set. Any bonding material that is allowed to set must be removed. Epoxy 35
35 2 Parts Type I Cement 1 Part Water 1 Part Sand Grout Recipe Mixed to the consistency of thick cream or kool whip Placement immediately before concrete. Has a shelf life of 60 minutes. 36
36 Grout used to Seal Edges of Partial Depth Repairs 37
37 Patch Material Placement Batch small quantities PCC materials should be placed when the temperature is above 4 C (40 F) and rising Some epoxy materials placed in lifts Overfill patch area by ~3 mm (1/8 in) Consolidate material with small spud vibrator Screed and hand trowel, working from the center of the patch to the edges 38
38 Mobile Concrete Batch Plant It has 5 bins that hold sand, aggregate and cement products to batch small quantities of material. It uses a belt scale to control the mix proportions for the patch mix being produced. 39
39 Hand Batching Methods Mixed by proportions on the back of a truck Buy prepackaged bags of material One such product is the Minnesota 3U18 mix 40
40 Sample Minnesota Partial Depth Mix 3U18 Partial Depth Mix Small Aggregate 100% passing 3/8 sieve Per Cubic Yard 850 lbs Type I Cement Uses 295 pounds of water Uses 1328 pounds of Coarse Aggregate Uses 1328 pounds of Sand A target W/C of 0.35 Type E Water Reducing and Accelerator 6.5% Air Maximum 1 inch slump Cure time of 12 hours Coarse Aggregate gradation will be the following 100% passing the 3/8 inch sieve 55% - 95% passing the #4 sieve Not more than 5% shall pass the #50 sieve 41
41 Patch Material Placement 42
42 Finishing Tip 43
43 Sealing Edges and Runouts The edges of the repair should be sealed with grout to help prevent moisture infiltration, as shown in the photo. 44
44 Curing P.D.P. Have large surface areas in relation to their volumes (which can lead to rapid moisture loss) Prevent moisture loss White-pigmented curing compound commonly used (some require 1.5 to 2 times normal rate) Opening to traffic Mix / temperature dependent Common values: 1,800 to 3,000 psi 45
45 Completed Partial Depth Repairs Transverse Joint done in 1987 Random Crack done in 1999 Picture taken in 1999 City Street in South St Paul, MN. 46
46 Rochester, Mn 2007 Patch Picture
47 CASH 22 East side of Rochester, Mn PDR in
48 Partial Depth Longitudinal Crack Repair 49
49 I-35 South of Duluth, Mn Project done in 1991 Picture taken in 2000 Centerline 8 miles long 50
50 Deteriorated Areas were not Repaired in Original Work (Joint and Crack had received a Partial Depth Repair on either side of Deteriorated Areas) 51
51 Key Factors For Success Proper selection of candidate projects Proper material selection Identification of repair boundaries Use of joint/crack reformers Achieving good bond Patch area clean and dry Sandblasting sidewalls Application of bonding agent Proper placement and curing 52
52 PDR and DBR Hwy 71 North of Windom, MN Built in 1962 with Quartzite Rock Partial Depth and Dowel Bar Retrofit, Diamond Grinding in
53 Mn/Road DBR in Existing Basket 54
54 Mn/Road Test Facility 55
55 Mn/Road Old WB I-94 First time the old concrete pavement is being used for research. Built in concrete thickness 24 wide 27 Reinforced panels with Skewed Joints 56
56 Faulted Slabs 57
57 Locate Old Dowels with MIT Scan 58
58 Old Dowels Marked in Red 59
59 Slot Removal Max 30 lb. Chipping Jack Hammers 60
60 Slot Removal Some existing dowel basket shipping wires found in rubble. Old dowels were 1 X 18 No epoxy coating 61
61 View of hole at side of Slot 62
62 Sheet Rock Compound House construction Sheet Rock compound used to fill hole next to slots. With Excessive compound use Performance is questionable!!! 63
63 Broken Dowel 64
64 Some Holes at bottom of Slot 65
65 Dowel Placement 66
66 Concrete Placement 67
67 Inside Wheel Paths 100 IWP - All Points (Before and After Joint) & Load Levels Fall IWP Spring IWP
68 Mn/Road DBR in Existing Basket 69
69 Questions? International Grooving and Grinding Association Website Daniel P. Frentress P.E. Office Phone Cell
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
More information550 Surface Treatments
Table of Contents 550 Surface Treatments... 550-1 550.1 Introduction... 550-1 551 Crack Sealing... 550-1 551.1 Project Selection... 550-1 551.2 Design Considerations... 550-1 552 Chip Sealing... 550-2
More informationDOWEL BAR RETROFIT DO S AND DON TS
DOWEL BAR RETROFIT DO S AND DON TS WA-RD 576.1 October 2003 Washington State Transportation Commission Strategic Planning and Programming in cooperation with the U.S. Department of Transportation Federal
More informationConcrete Pavement Preservation and Optimization
Concrete Pavement Preservation and Optimization State of the Art Treatments to Increase Pavement Longevity and Performance International Grooving and Grinding Association Priorities Have Shifted Minimal
More informationIGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction
IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction This standard developed, by the International Grooving and Grinding Association (IGGA), specifies the procedures
More informationSpecial Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:
FAST TRACK FULL DEPTH CONCRETE REPAIR Item No. FULL DEPTH CONCRETE REPAIR Item No. PARTIAL DEPTH CONCRETE REPAIR Item No. FAST TRACK PARTIAL DEPTH CONCRETE REPAIR Item No. Special Provision No. 399S43
More informationAlligator Cracking. Light. Medium. High
Alligator Cracking Description: A series of interconnecting cracks caused by fatigue failure on the asphalt concrete surface under repeated traffic loading. Causes: Loads in excess of the current pavement
More informationConcrete Pavement Preservation:
Concrete Pavement Preservation: Concrete Pavement Surface Restoration and Joint and Crack (Re-)Sealing Presented by: Mark B. Snyder, Ph.D., P.E. representing the National Concrete Pavement Technology Center
More informationTECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &
TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed
More informationMaintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments
Asphalt Pavement Preservation: Evaluation, Maintenance & Rehabilitation Maintenance & Rehabilitation Treatments Identification of Alternative Treatments Before selecting a treatment for a pavement, we
More informationSECTION SITE CONCRETE
SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationGeneral Information for Joints
Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-1 General Information for Joints A. General Information The need for a jointing system in concrete pavements results from the desire
More informationMaintaining your roads with Asphalt
Maintaining your roads with Asphalt Maintaining your roads with Asphalt Asphalt Overlays Rehabilitation of Concrete Roads Asphalt for Preventive Maintenance Asphalt Overlays Functional overlays Typically
More informationCONCRETE REPAIR IN ACTION: USING THE MANUAL AS A GUIDE. Christen Longoria, P.E. San Antonio District Project Engineer
CONCRETE REPAIR IN ACTION: USING THE MANUAL AS A GUIDE Christen Longoria, P.E. San Antonio District Project Engineer TxDOT CONCRETE REPAIR MANUAL Step-by-Step repair procedures for use on new and existing
More informationPavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center
Pavement Preservation with Thin Lift Concrete Overlays Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center Concrete Overlay Guide second edition Contents 1. Overview of
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More informationConcrete Pavement Preservation Guide
Concrete Pavement Preservation Guide Mid West Pavement Preservation Partnership Kansas City, Missouri September 28, 2015 Todd LaTorella Executive Director MO/KS Chapter, ACPA Kurt Smith Applied Pavement
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-03 01 30.71 (April 2006) ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-03930 (September 1999) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationFIVE STAR PRODUCTS, INC. (800)
FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 1 of 12 DESIGN-A-SPEC GUIDELINES FIVE STAR STRUCTURAL CONCRETE V/O CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS
More informationIn Service Replacement of Box Girder Bottom Slab
In Service Replacement of Box Girder Bottom Slab WSDOT Bridge No. 5/537S - Span 11 Craig R. Boone, P.E., S.E. Lynn Peterson Secretary of Transportation 2015 Western Bridge Engineers Seminar Reno, Nevada
More informationPavement Management Systems
Pavement Management Systems Basics and Benefits David R. Johnson, P.E. Regional Engineer Asphalt Institute Rocky Mountain Region djohnson@asphaltinstitute.org Presentation Outline Definition Requirements
More informationThis specification refers to the following standards, specifications, or publications:
PRECAST CONCRETE SLAB REPAIR - Item No. Special Provision No 363S01 February 2013 Amendment to OPSS 363, April 2008 OPSS 363, Construction Specification for Repairing Rigid Pavement with Precast Concrete
More informationPORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer)
PORTLAND CEMENT CONCRETE OVERLAYS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Bonded Concrete Overlays Over Concrete B. Bonded Concrete Overlays Over Asphalt C. Unbonded Concrete Overlays Over Concrete (with
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing
More informationOptimization of Concrete Maintenance to Extend Pavement Service Life
Optimization of Concrete Maintenance to Extend Pavement Service Life Craig White 1 and David K. Hein 2 ABSTRACT The Highway 407 ETR concession in Ontario, Canada, is responsible for the management of a
More informationChapter 4 Portland Cement Concrete Pavement Guidelines and Policies Publication Edition Change 1 CHAPTER 4
CHAPTER 4 PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) GUIDELINES AND POLICIES 4.1 CONCRETE PAVEMENT RESTORATION (CPR) A. Preliminary Engineering. The major considerations in the design of a rehabilitation
More informationSemstone Construction Details
Semstone Construction Details SP01-94 Treatment for Expansion Joints, Control Joints, and Structural Cracks, Vertical and Horizontal, for Non-Vehicular Traffic 1. Maintain joint/crack through coating.
More informationFIVE STAR PRODUCTS, INC. (800)
FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 Page 1 of 11 DESIGN-A-SPEC GUIDELINES FIVE STAR RS ANCHOR GEL CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS PART
More informationConstruction Specification for Concrete Bus Pad
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.41 June 2017 for Concrete Bus Pad Table of Contents SCOPE... 3 REFERENCES... 3 DEFINITIONS... 3 DESIGN AND SUBMISSION
More informationDesign and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation
Design and Construction of Concrete Overlays By: James K. Cable, P.E. Cable Concrete Consultation PCC OVERLAY AGENDA Current design & construction features What is needed in a PCC overlay set of plans?
More informationCon-Spec Industries Ltd.
CON-SPEC COUNTER-CRETE Con-Spec Counter-Crete is a unique preblended cementitious material for casting concrete countertops. It is a non-shrinking concrete that requires only potable water for mixing.
More informationMix Design & Construction -1-
Mix Design & Construction -1- AGENDA RCC Mix Design RCC Mix Production RCC Construction Process -2- THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL Natural
More informationSECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS
SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material
More informationIntroduction to Pavement Overlays
Introduction to Pavement Overlays Course No: C02-046 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980
More informationDIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340
DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340 PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. The General provisions of the contract, including GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS AND
More informationAsphalt Pavement Maintenance and Rehabilitation Strategies
Asphalt Pavement Maintenance and Rehabilitation Strategies 2016 CAPTG Workshop: How to Assess and Extend the Service Life of Airfield Pavements Presented by: Genevieve Long, P.E. Monday, September 19,
More informationConcrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay
Overlays February 22, 2012 ACPA Pennsylvania Chapter Overlays John M. Becker, P.E. ACPA Penn Chapter February 22, 2012 One of 25 state paving associations affiliated with ACPA National Comprised of approximately
More information12/11/ th Annual Illinois Bituminous Paving Conference December 11, 2013
PCC Pavement Rehabilitation with Hot Mix Asphalt 54th Annual Illinois Bituminous Paving Conference December 11, 2013 Kevin Burke III, P.E. Illinois Asphalt Pavement Association burkeiii.kevin@comcast.net
More informationBASE CONSTRUCTION MATERIALS A Aggregate
BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3
More informationINDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT SCOPE Pre-Construction Meeting... 3
INDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT 830. 1 SCOPE... 3 1.1 Pre-Construction Meeting... 3 Page 830. 2 MATERIALS... 3 2.1 Sampling and Testing... 3 2.2 Supply... 3 2.3 Cement... 4 2.4 Fly Ash...
More informationOhio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 11/21/2014 Project 140560 Addendum No. 2 PID No. 82972 HAM IR 275
More informationSection 504. MICRO-SURFACING
504.01 Section 504. MICRO-SURFACING 504.01. Description. This work consists of preparing existing pavement and providing and placing a micro-surfacing mixture. 504.02. Materials. Provide materials in accordance
More informationREINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026
(Page 1 of 8) REINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026 1026.1 SCOPE. To establish procedures for the inspection of reinforced concrete pipe and the approval of modified
More informationSURFACE PREPARATION INSTRUCTIONS: CONCRETE
SURFACE PREPARATION INSTRUCTIONS: CONCRETE DEFINITION OF TERMS The terms listed will be used frequently throughout this article and listed in boldface for ease of reference. They describe, in detail, the
More informationTools and Tactics for Roadway Pavement Preservation: An Implementation Guide to Preserving High-Traffic-Volume Roadways
Appendix B Preventive Maintenance Treatment Technical Profiles Tools and Tactics for Roadway Pavement Preservation: An Implementation Guide to Preserving High-Traffic-Volume Roadways Preventive Maintenance
More informationSECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES
GUIDE SPECIFICATION SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES PART 1 - SCOPE 1.01 WORK INCLUDED: 1.1.1 This guide covers the
More informationOPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT
OPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT PREPARED BY: JODY WALL, P.E. DIRECTOR OF RESEARCH AND DEVELOPMENT CAROLINA STALITE COMPANY RESEARCH LAB GOLD HILL, NORTH CAROLINA Optimized 3/4" Gradation
More informationA. This Section includes resinous flooring systems with epoxy body coat(s).
SECTION 096723 - RESINOUS FLOORING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes resinous flooring systems with epoxy body coat(s). 1. Application Method: Troweled (Slurry, Seeded or Broadcast
More informationSession 11: Concrete Overlays
Session 11: Concrete Overlays Learning Outcomes Define Concrete Resurfacing Define Bonded & Unbonded Overlays List Benefits of Overlays Describe Evaluation Considerations Describe Primary Design Considerations
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3
CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3
More informationWYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT
WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT SS-400G Page 1 of 3 This supplementary specification replaces Section 414, Portland Cement Concrete
More information1. Rapid Set Cement. 2. Methods of preparation. 3. How to stage a job site. 4. Installation Mix, place, finish. 5. Coloring the TRU.
1. Rapid Set Cement 2. Methods of preparation 3. How to stage a job site 4. Installation Mix, place, finish 5. Coloring the TRU natural TRU Rapid Set is NOT Portland Cement Rapid Set is a Calcium Sulfoaluminate
More informationA. Drawings and general provisions of the contract, including General and Supplementary Conditions, apply to this section.
SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE SECTION 03 01 40 MAINTENANCE OF PRECAST CONCRETE SECTION 03 01 50 MAINTENANCE OF CAST DECKS AND UNDERLAYMENT SECTION 03 01 60 MAINTENANCE OF GROUTING
More informationSection 602. CONCRETE PAVEMENT CONSTRUCTION
Section 602. CONCRETE PAVEMENT CONSTRUCTION 602.02 602.01. Description. This work consists of constructing a jointed portland cement concrete pavement, unbonded concrete overlay, base course, or shoulder,
More informationSection 811. PERMANENT PAVEMENT MARKINGS
811.01 Section 811. PERMANENT PAVEMENT MARKINGS 811.01. Description. This work consists of providing and applying retroreflective permanent pavement markings in accordance with the Michigan Manual on Uniform
More informationPRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT
PRECAST PRESTRESSED CONCRETE PAVEMENT The Standard Specifications are revised as follows: SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION 509 - PRECAST PRESTRESSED CONCRETE PAVEMENT 290 509.01
More informationSPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013
SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR
More informationConcrete Paving Association of Minnesota CPAM Annual Workshop March 11, Gordy Bruhn- Senior Engineering Specialist
Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, 2016 Gordy Bruhn- Senior Engineering Specialist FDR Removals I-94 Monticello, MN FDR Removals TH 2 Erskine, MN Revised Reinforcing
More informationITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS
ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown
More informationSHRP2 R21 Composite Pavement Systems Project Overview
SHRP2 R21 Composite Pavement Systems Project Overview Michael I. Darter & Shreenath Rao Applied Research Associates, Inc. 2100 Louisiana Transportation Conference Baton Rouge, LA 10 January 2011 SHRP2
More informationOverlays. HCC Deck Overlays. Key Decisions for Concrete Deck Overlays
Key Decisions for Concrete Deck Overlays Virginia Concrete Conference March 7, 2007 Michael Sprinkel, P.E. Associate Director Virginia Transportation Research Council Overlays Overlays are usually placed
More informationDeterioration of Concrete Roads
Deterioration of Concrete Roads Concrete Roads Joint Spalling Punch outs Cracking Faulting Slab failures Riding Quality Models From USA Chile 2 Types of Deterministic Models Absolute (Concrete HDM-4) Predicts
More informationFIVE STAR PRODUCTS, INC. (800)
FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 Page 1 of 14 DESIGN-A-SPEC GUIDELINES FIVE STAR NOVOLAC GROUT CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS PART
More informationMS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES
MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES INTENT: To provide a system for reconstruction of concrete or masonry structures to stop inflow, infiltration, exfiltration, and
More informationSection 708. PRESTRESSED CONCRETE BEAMS Description. Manufacture and erect prestressed concrete beams.
708.0 Section 708. PRESTRESSED CONCRETE BEAMS 708.0 Description. Manufacture and erect prestressed concrete beams. 708.02 Materials. Use materials meeting the following. Mortar and Grout... 702 Cement...
More informationRecommended Specifications For Portland Cement Pervious Pavement
Recommended Specifications For Portland Cement Pervious Pavement Foreword Portland Cement Pervious Concrete Pavements have become increasingly popular as a method to meet water quality water run off regulations
More informationSPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket
1993 Specifications CSJ 0331-04-045 SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket 1. Description. This Item shall govern for the furnishing, installing and energizing a sacrificial
More informationStanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings
SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2
More informationBIO-AQUIFER STORM SYSTEM
BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone
More informationLS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION
LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete
More informationSECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS
SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationUFC March 2001 CANCELLED UNIFIED FACILITIES CRITERIA (UFC) CONCRETE REPAIR APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED
UNIFIED FACILITIES CRITERIA (UFC) CONCRETE REPAIR APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED UNIFIED FACILITIES CRITERIA (UFC) CONCRETE REPAIR Any copyrighted material included in this UFC is
More informationSurface Repair Using Form-and- Pour Techniques
ACI RAP Bulletin 4 American Concrete Institute Advancing concrete knowledge FIELD GUIDE TO CONCRETE REPAIR APPLICATION PROCEDURES Surface Repair Using Form-and- Pour Techniques Surface Repair Using Form-and-Pour
More informationEvaluation of Premature PCC Pavement Longitudinal Cracking in Colorado
Evaluation of Premature PCC Pavement Longitudinal Cracking in Colorado Ahmad Ardani, Shamshad Hussain, and Robert LaForce Colorado Department of Transportation 4201 East Arkansas Avenue Denver, CO 80222
More informationSPALL REPAIR TEST AND EVALUATION (BRIEFING SLIDES)
POSTPRINT AFRL-RX-TY-TP-2008-4585 SPALL REPAIR TEST AND EVALUATION (BRIEFING SLIDES) Michael I. Hammons, PhD, PE Applied Research Associates P.O. Box 40128 Tyndall Air Force Base, FL 32403 AUGUST 2008
More informationMNDOT PAVEMENT DESIGN MANUAL
MNDOT PAVEMENT DESIGN MANUAL Chapter 9 truction and Rehabilitation Alternates MnDOT Pavement Engineer Date Contents Introduction... 1 900 Existing Pavement-Types... 2 910 Rehabilitation with HMA Overlay
More informationRapid Overlays for Deck Preservation Virginia Concrete Conference Richmond, Virginia March 8-9, 2012
Rapid Overlays for Deck Preservation Virginia Concrete Conference Richmond, Virginia March 8-9, 2012 Michael M. Sprinkel, P.E. Associate Director Virginia Center for Transportation Innovation & Research
More informationINDOT Thin Concrete Overlay Initiatives. Tommy E. Nantung INDOT Division of Research and Development
INDOT Thin Concrete Overlay Initiatives Tommy E. Nantung INDOT Division of Research and Development System of Concrete Overlays Thinner Concrete Overlays Thicker Bonded Overlay System Unbonded Overlay
More informationRapid Repair Materials and Construction Rapid Bridge Repair Workshop Holiday Inn Tanglewood-Roanoke, Virginia May 21 and 22, 2009
Rapid Repair Materials and Construction Rapid Bridge Repair Workshop Holiday Inn Tanglewood-Roanoke, Virginia May 21 and 22, 2009 Michael Sprinkel, P.E. Associate Director Virginia Transportation Research
More informationSurface Repair Using Form-and-Pour Techniques
RAP-4 www.concrete.org Surface Repair Using Form-and-Pour Techniques Reported by ACI Committee E 706 Brian F. Keane * Chairman J. Christopher Ball H. Peter Golter Jay H. Paul Floyd E. Dimmick, Sr. Bob
More informationSECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS
SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3
More informationA. Submittal Procedures: See Article 13 of the General Conditions.
SECTION 321313 - CONCRETE PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Driveways. 2. Roadways. 3. Parking lots. 4. Curbs and gutters. 5. Walks. B. Proposed Substitutions: See Article 2,
More information2001 SCOPE. This section covers all cast-in-place concrete, including reinforcing steel, forms, finishing, curing, and other appurtenant work.
SECTION 2000 - CONCRETE 2001 SCOPE. This section covers all cast-in-place concrete, including reinforcing steel, forms, finishing, curing, and other appurtenant work. 2002 GENERAL. All cast-in-place concrete
More informationApplication Guides for BASF Floor Products
Application Guides for BASF Floor Products Installation of Mastertop Anvil Top 300 Heavy-Duty Floor Topping Important: Read This First: These suggestions may be followed, modified, or rejected by the owner,
More informationULTRA-HIGH STRENGTH SHEAR KEY GROUT
ULTRA-HIGH STRENGTH SHEAR KEY GROUT 187 April 30, 2015 SPECIFICATION FOR ULTRA-HIGH STRENGTH SHEAR KEY GROUT SCOPE This specification consists of the proper material selection and production of Ultra-High-
More information1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.
SECTION 1300 - ASPHALTIC CONCRETE PAVEMENT 1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas. 1302 GENERAL. Pavement shall be constructed to the lines, grades,
More informationCONSTRUCTION SUMMARY REPORT
Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard
More informationSection 505. CHIP SEALS
Section 505. CHIP SEALS 505.01. Description. This work consists of preparing the pavement surface and providing and placing a single chip seal, double chip seal, or shoulder chip seal. 505.02. Materials.
More informationSECTION GROUT. A. American Society for Testing and Materials (ASTM):
SECTION 03600 GROUT PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03300 - Cast-In-Place Concrete. 2. 03600 - Grout. 1.02 REFERENCES A. American Society for Testing and Materials (ASTM): 1. C109-95
More informationHDX TECHNICAL SPECIFICATION
HDX TECHNICAL SPECIFICATION SafeLane surface overlay Pavement Substrate A Cargill Deicing Technology Product Providing customers with deicing solutions that save lives and enhance commerce. Helping to
More informationPolymer Concrete Patching Materials. Todd Donmyer P.E. Area Engineer District 61
Polymer Concrete Patching Materials Todd Donmyer P.E. Area Engineer District 61 LADOTD Todd Donmyer Area Engineer District 61 CRAFCO Cheryl Jones Marketing Associates Chris Carwie Title Here TechCrete
More informationSECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT
SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating
More informationSECTION CONTROLLED LOW STRENGTH MATERIAL
SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including
More informationCONSTRUCTION BULLETIN
CONSTRUCTION BULLETIN State Construction Office Engineering and Regional Operations Bituminous Surfacing on Structure Decks: Specification Language Bulletin #2016-06, Page 1 of 3 Date: November 2 nd, 2016
More informationElectronic Machinery Grouting Manual
ITW Philadelphia Resins Foundation Systems Electronic Machinery Grouting Manual Proven Solutions Index & Quick Reference This Specification Manual is furnished by Engineered Grouting Systems ITW Philadelphia
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationWhat s New in Concrete Paving? G o rdon K. R ay
What s New in Concrete Paving? G o rdon K. R ay Portland Cement Association IN TRO D U C TIO N The concrete being placed in pavements today is much the same as it was 10 and 20 years ago. Cement, aggregate,
More informationSECTION CONCRETE LINED CANALS AND RESERVOIRS
SECTION 02511 CONCRETE LINED CANALS AND RESERVOIRS PART 1 GENERAL 1.01 SECTION INCLUDES Canal linings shall be constructed where shown on the drawings. The lining will be unreinforced concrete containing
More informationPROJECT CONTRIBUTORS
PROJECT CONTRIBUTORS PERVIOUS CONCRETE Making the Impossible Possible Construction of the I-81 Exit 140 Park-n-Ride in Salem, VA Travis Higgs, P.E. VDOT Salem Materials Exit 140 Park-n-Ride location The
More information