Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

Size: px
Start display at page:

Download "Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati"

Transcription

1 Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati Steve Lamb The Robbins Company, Solon, Ohio, USA Steve Abernathy Midwest Mole, Inc., Indianapolis, Indiana, USA ABSTRACT: A Robbins Rockhead Ø1.8m double shield TBM is being used to excavate soft shale and harder limestone in Cincinnati, Ohio. Seven tunnels will be excavated, with lengths ranging from 250 to 610 meters (816 to 2,014 LF), for a total of 2,875 meters (9,430 LF). These are relatively long tunnel drives for such a small-diameter excavation. Primary support will be 100mm (4 in WF) steel ring beams on 1.5 meter (5 ft) centers. This paper will describe the special TBM, muck haulage, and launch shaft features which were carefully implemented to support rapid mobilization and excavation on this small diameter project. INTRODUCTION The Shayler Run Segment C project aims to update degraded and exposed sewer systems, and to protect the area surrounding environmentally sensitive Shayler Creek near Cincinnati, Ohio, USA. This USD $15 million project is a priority for the project owner, the Clermont County, Ohio Water Resources Department, because of severe pipeline erosion in the creek bed. Erosion of the creek bed has exposed the existing sewer pipe, which was installed in 1978, to the environment and put certain sections at high risk of failure. In fact, the exposed pipe has already dumped raw sewage into the creek. To address this problem, a new pipeline will be installed well below the creek bed, crossing the creek a total of seven times. Cover ranges from 3 to 30 m, with the majority of the pipeline running some distance from the waterway. The final carrier pipe will consist of 1.07 m (42 in) diameter Hobas Reline, which is much larger than the current 0.6 m (24 in) sewer line. The larger pipe diameter was decided on mainly to allow trenchless construction, though it has the added benefit of providing a larger capacity for future needs in the area as well. PROJECT LAYOUT The new pipeline consists of seven tunnels crisscrossing the creek, each connected by a 9.8 m (32 ft) diameter launch and receiving shaft, with a total of eight shafts in all. The shafts will eventually become fiberglass manhole structures to access the new pipeline. The original plan called for eleven shafts, but the general contractor for the project, Midwest Mole, Inc. based in Indiana, USA, proposed to eliminate three of the shafts. This partial redesign of the project resulted in a shorter project schedule and in substantial cost savings to be shared by the owner and contractor. The new drive lengths range from approximately 250 m to 610 m (816 ft to 2,014 ft), for a total of 2,875 m (9,430 ft). Both the original and modified plans are shown in Figure 1. The new plan calls for the removal of shafts four, eight, and ten, which results in longer drives through those areas. Boring will begin at the lower end of the pipeline from shaft eleven, and the machine will mine upward to the southern end near state route 32.

2 Shaft 11 Shaft 10 Shaft 9 Shaft 8 Shaft 7 Shaft 6 Shaft 5 Shaft 4 Shaft 3 Shaft 2 Shaft 1 Figure 1. Left: original pipeline route. Right: modified route with shafts 4, 8, and 10 removed Geology In addition to the long tunnel drives, the geology of the area poses a challenge as well. The seven tunnels, with their varying grades, result in a vertical change of 54 m (177 ft) over the course of the project. As a result of the elevation change, the tunnels travel through different strata consisting of softer shale and limestone for the first 900 m (2950 ft), changing to harder, drier shale and limestone in the later tunnels. The ground conditions range from wet and sticky to dry, with rock quality designations (RQDs) ranging from about 20% to 70%. Figure 2 shows average RQDs at each of the shaft locations. There is a clearly visible jump of approximately 45% between shafts six and seven, where the transition from mixed ground to hard rock is expected to occur. Figure 2. Rock quality designation at shaft locations

3 MACHINE SELECTION The nature of the extensive gravity sewer made the machine selection challenging. To effectively excavate in the conditions, Midwest Mole needed a solution to mine in mixed ground as well as hard rock up to 165 MPa (24,000 psi) UCS. The original contract allowed for either microtunneling or two-pass tunneling, which allows for installation of a primary liner before placing the carrier pipe. Despite the highly changeable conditions, the contractor chose a single machine solution for the pipeline, a 1.8 m (72 in) diameter Double Shield Rockhead manufactured by The Robbins Company. Midwest Mole had a wealth of experience with similar Robbins machines, and felt the tunnels could be completed in a timely manner with the two-pass option. There are several factors that make the two-pass method a more attractive option despite the apparently greater complexity. First, the rockhead machine allows for cutter changes to be made in mid bore should the need arise. In a microtunneling machine of this size, cutters would only be able to be changed in the receiving shafts. Additionally, muck disposal is far simpler with the two-pass method. Using this method, the muck can easily be used as backfill around the manholes in the shafts and as fill on private property in the area. The wet, treated slurry produced in a microtunneling operation would be considerably more difficult to dispose of, particularly from this remote site. There are also additional costs that would be incurred using the microtunneling approach. In order to run the high capacity slurry treatment plant year round, a winterized enclosure would need to be constructed. The jacking quality pipe required for the microtunneling operation is also more expensive than the flush reline used in the two-pass method. The remoteness of the job site is also a factor, since the additional power and water required by the microtunneling slurry plant would need to be supplied by a generator and brought in by truck, respectively. Furthermore, the large cost savings associated with removing three shafts was made possible by the Robbins machine s ability to mine such long distances. This savings would not have been easily achieved with the microtunneling approach due to limitations of jacking lengths. Figure 3. Double Shield Rockhead used to excavate seven gravity sewers MACHINE FEATURES The 1.8 m (72 in) Double Shield Rockhead is designed and operates much like The Robbins Company s large Tunnel Boring Machines (TBMs). The operation sequence of the machine is based on a Double Shield design using a machine belt conveyor for spoils transfer through the machine. The TBM advances with the machine cutterhead thrust transferred to the cutting face by hydraulic thrust cylinders mounted inside the TBM. Upon completion of this stroke, large forward shield stabilizers extend and hold the cutterhead as the telescopic shield is retracted. If necessary the auxiliary thrust cylinders can be used to thrust against the tunnel liner for advancement. A schematic of this system is shown in Figure 4.

4 Articulating front shield Drive assembly Cutterhead Operator station Auxiliary thrust Belt conveyor Stabilizer pad Thrust cylinder Bearing housing assembly Gripper assembly Figure 4. Schematic of rockhead machine The TBM has an articulation system that allows it to be steered to a simple pipeline laser or a more advanced laser pipe jacking system with data logging print out. This laser system is installed in the pit above the concrete thrust block or in the rock roof of the tunnel on longer runs. The tunnel alignment is surveyed regularly to verify proper line and grade. Torque reaction from the cutterhead is countered by the gripper shield, roll correction cylinders, and torque keys inside the telescopic shield. A tail shield protects workers and facilitates construction of the 1.8 m (72 in) OD steel ring sets on 1.5 m (5 ft) centers. An operator s area in the rear shield holds all the required controls, auxiliary power pack, and machine lighting. Auxiliary power was installed for both electricity and hydraulics. This auxiliary power is used for the hydraulic ring expander and the portable welder. A three-way communication system is used to link the TBM operator, muck car operator, and site foreman. Provisions for Long Drives To rotate the cutterhead, the machine uses a variable-speed electric drive motor, gearbox, and torque protection device assembly. Power cables for this drive train run from a machine mounted electrical connection box to a surface mounted electrical disconnect cabinet installed in a 20 ft shipping container. A sine wave filter is used to filter the output of the VFD, eliminating harmful wave effects to the motors which would normally be caused by the long cable lengths. This feature enables the machine to mine up to 640 m (2,100 ft) at optimum productivity, allowing for the longer tunnels of the redesigned project. The machine s muck haulage system is also instrumental in making the long drives of this project possible. As the hard rock is excavated from the face, it is gravity fed through a muck opening onto a machine belt conveyor. The conveyor, when fully extended, reaches 30.5 m (100 ft) in total length, allowing for three muck cars to be filled in one train cycle. The three car train has the capacity for two pushes of excavated material, or 1.5 m (5 ft) of advancement, which equates to one ring set. This allows workers to build a ring set while the muck cars are being emptied, making efficient use of the relatively long train cycle time in the longer tunnels. The muck cars are moved in and out of the tunnel with a 96 V/5 ton locomotive. Cutterhead Solutions Because of the changing conditions over the course of the project, two different cutterhead solutions have been provided. For sections of the tunnel with low RQD, Robbins supplied a mixed ground cutterhead with 165 mm (6.5 in) single disc steel cutters and carbide cutter bits. The mixed ground cutterhead has carbide bits which are mounted 13 mm (0.5 in) back from the leading edge of the disc cutters. This allows for the disc cutters to do the job when the rock is solid and competent, and as the rock becomes fractured or mixed with soil the carbide bits begin to dig. With the carbide bits clearing the soft soil, the soil is prevented from clogging the cutterhead and locking down the cutters. This style of cutterhead, shown in Figure 5, has been very effective in multiple mixed ground conditions.

5 Figure 5. Mixed ground cutterhead provided for the double shield rockhead machine For the later tunnels with more competent rock where more thrust pressure is required, the mixed ground cutterhead is replaced with a second cutterhead more suited to the conditions. For this, Robbins supplied a standard hard rock cutterhead, similar to the one shown in Figure 6, with 292 mm (11.5 in) single disc steel cutters. The hard rock cutterhead allows for operation at thrust forces as high as 400,000 lbs. The cutterhead is supported by a heavy duty bearing housing assembly and attached to a heavy walled steel front casing assembly. This front casing assembly includes four hydraulic stabilizer cylinders required to hold the cutterhead for a consistent cutting pattern, known as kerf cutting. Figure 6. Hard rock cutterhead with 292 mm (11.5 in) single disc cutters JOBSITE OPERATION Excavation of the first tunnel began on May 19, 2010 from an 11 m (36 ft) deep shaft, and progress has been generally good. Recorded production rates have been as high as 21 m (70 ft) in one 12 hour shift, and are consistently in the range of 12 to 18 m (40 to 60 ft) per shift. The swift advance comes despite some unforeseen difficulties, including a section directly below the creek bed with significant groundwater and gripper slippage in the soft, wet ground during machine pushes. The high production rate can be attributed in part to the very systematic way in which the rib sets are installed, which does not hinder machine progress. The Robbins rockhead completed its first 474 m (1,555 ft) long drive in three months, holing through on August 18th into the receiving shaft. Even after this distance, Midwest Mole crews found almost no perceptible wear on the cutterhead (see Figure 7).

6 Figure 7. Left: initial machine launch in May Right: cutterhead after 474 m (1,555 ft) The machine was launched from its receiving shaft to bore a second 575 m (1,886 ft) long tunnel on August 30, 2010 following some maintenance and modifications. Changes included modifying the hydraulic system for increased gripper and roll correction cylinder pressure. The increases allow the machine to grip and roll correct in the extremely soft, often wet rock. Launching the machine is a fairly simple operation, which is important because of the number of times it must be done over the course of the project. With the hydraulics toward the front of the machine and electrical components on the surface, the gripper and auxiliary thrust portions can easily be removed with minimal disruption of the system. This allows the machine to be shortened to allow adequate space in the launch shaft. The conveyor is also shortened at startup. Once the rockhead has been sufficiently buried, the rear sections are reattached and the conveyor extended. Figure 8. Launch of the machine on its second tunnel, August 2010 Operation of the machine has been smooth and well coordinated. To aid in construction of the primary liner, Midwest Mole designed and built a materials cart which attaches to the last muck car. It is used to haul the ring sets like those shown in Figure 9 to the back of the TBM, and it has a hydraulic push plate for easy unloading of the stacks at the rear of the tail shield. Workers can then assemble the rings in the safety of the tail shield as the machine bores.

7 Figure 9. Left: ring and board sets ready to load. Right: ring beams and lagging installed in the tunnel Work on the launch/receiving shafts is ongoing; five shafts are now complete using a combination of drill and blast techniques and manual excavation. Some open cut operations are also connecting existing, peripheral lines to the new sewer line. Midwest Mole recently utilized a 0.8 m (30 in) diameter Robbins SBU-A for a 46 m (150 ft) long crossing of the creek, which will connect a 0.5 m (18 in) diameter PVC sewer to the main line. The project s success to date can be attributed largely to close cooperation between Midwest Mole, Robbins field service, and the project owner. All seven of the tunnels and the eight manhole shafts are expected to be complete by May 2012.

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations

More information

TBM Selection and Specification

TBM Selection and Specification By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

DIFFICULT GROUND SOLUTIONS:

DIFFICULT GROUND SOLUTIONS: Tunnelling April/May 2016 www.tunnellingjournal.com journal The international journal for the tunnelling industry SEE PAGE 6 SEE PAGE 12 SEE PAGE 27 WORLD NEWS MONITOR PROGRESS CUTTER CARE HIGHLIGHTS FROM

More information

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City

More information

Small Diameter Rock TBM Tunneling in Baltimore

Small Diameter Rock TBM Tunneling in Baltimore Small Diameter Rock TBM Tunneling in Baltimore LESTER M. BRADSHAW, JR. / TODD BROWN / JORDAN BRADSHAW BRADSHAW CONSTRUCTION CORPORATION ELDERSBURG, MARYLAND Alternative Title Luke. Let Go. Use the Force

More information

HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY

HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY Chapter 11 HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY Brian B. Khalighi and Joseph J. Diehl Atlas Copco Robbins Inc. and Grow Tunneling Corp. ABSTRACT

More information

PIPE JACKING & TUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS

PIPE JACKING & TUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS PIPE JACKING & TUNNELING SYSTEMS 6(721 6(*'( 35$+6 '1$ 6558% //$ (920(5 DRIVEN FOR CUSTOMER SUCCESS OUR EQUIPMENT SYSTEMS Since inception, Akkerman has grown with the evolution of industry demands. We

More information

BRADSHAW CONSTRUCTION CORPORATION

BRADSHAW CONSTRUCTION CORPORATION BRADSHAW CONSTRUCTION CORPORATION TUNNELING SPECIALISTS From a Contractor s Perspective Bradshaw s Experience 54 years as a tunneling contractor 26 years as a microtunneling contractor 25 years using conventional

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

MICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS

MICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS MICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS OUR EQUIPMENT SYSTEMS Since inception, Akkerman has grown with the evolution of industry demands. We offer pipe jacking, microtunneling, guided boring

More information

Pipetron Tunnel Construction Issues

Pipetron Tunnel Construction Issues Pipetron Tunnel Construction Issues James E. Friant Colorado School of Mines and Excavation Engineering Associates, Inc., 1352 SW 175th St., Seattle, WA 98166 Robert A. Bauer and David L. Gross Illinois

More information

Service Automation. Making the way

Service Automation. Making the way Industrial Hydraulics Electric Drives and Controls Linear Motion and Assembly Technologies Pneumatics Service Automation Mobile Hydraulics profile Drive & Control Niles-Simmons Engineering on the cutting

More information

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA Miranda Roman D. *, LaFaso Edward Iseki, Inc. 7518 Carroll Road, San Diego, Calif. 92121-2402 USA This paper will discuss the

More information

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc. Pipejacking Tunnel Boring Machines TBMs Michael Frenke, LOVAT Inc. Pipejacking Tunnel Boring Machines (TBMs( TBMs) Introduction Pipejacking Sequence TBM Design Features Types of Jacking Pipe Pipejacking

More information

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Introduction Purpose Provide engineers and owners

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

Hydraulic Excavators

Hydraulic Excavators Chapter 8 Hydraulic Excavators Hydraulic excavators are designed to excavate below the ground surface on which the machine rests. These machines have good mobility and are excellent for general-purpose

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Earth Boring Co. Limited Trenchless Since 1947 Founded in Streetsville

More information

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Michigan Department Of Transportation 3703F (11/06) SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Page 1 of 5 1 Materials 1.1 Pipe (a) Pipe shall be specifically designed and certified for microtunneling

More information

Tel: Neil: Tony: Website:

Tel: Neil: Tony: Website: Australian Tunnelling Services are a consortium that has been formed to offer specialist underground services to both clients and contractors in the Civil Engineering, Mining & Building Industries. The

More information

Design Data 4. Jacking Concrete Pipe

Design Data 4. Jacking Concrete Pipe Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

FOR HIGHWAY TUNNEL GALLERIA SPARVO.

FOR HIGHWAY TUNNEL GALLERIA SPARVO. HERRENKNECHT EPB SHIELD S-574 FOR HIGHWAY TUNNEL GALLERIA SPARVO. PRODUCT PORTFOLIO OF HERRENKNECHT GROUP. MECHANIZED TUNNELLING TECHNOLOGY. STEEP TUNNELLING. St. Petersburg 30 downhill EPB Shield Access

More information

The Robbins Company. Bheri Babai Diversion Multipurpose Project (BBDMP) Company Facts. Headquarters

The Robbins Company. Bheri Babai Diversion Multipurpose Project (BBDMP) Company Facts. Headquarters Bheri Babai Diversion Multipurpose Project (BBDMP) Presented by Jim Clark, Projects Manager India The Robbins Company THE ROBBINS COMPANY THE ROBBINS COMPANY Company Facts More than 50 years of innovation

More information

Design Data 4M. Jacking Concrete Pipe

Design Data 4M. Jacking Concrete Pipe Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing

More information

Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT

Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT A fuzzy logic excavation system for tunnel boring machines, which

More information

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro S. Smading The Robbins Company, Singapore ABSTRACT: Today s mega metro projects are using multiple TBMs in difficult ground, short

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

BREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT

BREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT BREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT Russell Connors 1 ABSTRACT The Airport Link Project (APL) was constructed in the Northern Suburbs of Brisbane and connects the Central

More information

ROCK HAWG TECHNOLOGY. Hardcore Solutions for the Toughest Applications

ROCK HAWG TECHNOLOGY.     Hardcore Solutions for the Toughest Applications Hardcore Solutions for the Toughest Applications Unit 3F Lyncastle Way Appleton Thorn Trading Estate Warrington Cheshire WA4 4ST Telephone +44 (0) 1925 265333 Fax; +44 (0) 1925 211700 Enquiries@westquaytrading.co.uk

More information

Design and Implementation of the South Hartford CSO Tunnel

Design and Implementation of the South Hartford CSO Tunnel Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected. Microtunnelling Building infrastructures and power supply systems underground, while life above continues unaffected. 2 Comprehensive Microtunnelling Solutions A reliably functioning infrastructure which

More information

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de

More information

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e. No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for

More information

How we would build the proposed storm relief sewer

How we would build the proposed storm relief sewer Counters Creek storm relief sewer How we would build the proposed storm relief sewer We would build the proposed Counters Creek storm relief sewer using the most advanced construction methods and we would

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking - 2 Minor changes JP JP JP JP 1 June 2015 1 General Revisions JC MI NH JP 03 Feb 2010 0 Issued for Use Client

More information

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

2 Support of the cavity and settlement Support of the face Natural support Mechanical support... Table of Contents The authors... VII Foreword to the 2nd Edition... IX 1 Introduction... 1 1.1 Basic principles and terms... 3 1.2 Types of tunnel boring machine according to DAUB... 5 1.2.1 Categories

More information

Previous Tunnel News

Previous Tunnel News Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION Proceedings of the 1999 Winter Simulation Conference P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds. SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION Simaan M.

More information

SECTION GRAVITY WASTEWATER LINES

SECTION GRAVITY WASTEWATER LINES SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS

More information

Multiple Large Diameter Microtunnels with Limited Ground Cover

Multiple Large Diameter Microtunnels with Limited Ground Cover North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 Paper No. TM2-T5-04 Multiple Large Diameter Microtunnels with Limited Ground Cover Steve

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Concrete Pipe Association of Australasia ACN 007 067 656 TECHNICAL BULLETIN CONTENTS ABSTRACT 1 INTRODUCTION 2 METHOD OF INSTALLATION 3 CONCRETE PIPE DESIGN 4 CONCRETE PIPE JOINT

More information

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Dr. Moustafa Kassab Systems Design Engineering / Civil Engineering Departments

More information

Hardrock Tunnel Boring Machines

Hardrock Tunnel Boring Machines Bernhard Maidl, Leonhard Schmid, Willy Ritz, Martin Herrenknecht Hardrock Tunnel Boring Machines In co-operation with Gerhard Wehrmeyer and Marcus Derbort -=rnst & Sohn '-A Wiley Company Contents 1 Historical

More information

Main Page The Company The Technology Safety Locks Electric Lifts. Air Lifts

Main Page The Company The Technology Safety Locks Electric Lifts. Air Lifts Incorporated date: 1985 Location: Walled Lake, Michigan Lot size: Approximately 3 acres Building: Approximately 33,000 square feet Military Application Employees: 40 Strengths: ISO certified Long Term

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.2 MICRO TUNNELING 7.2.1 General Where indicated on the Drawings, or where field

More information

E-Power Pipe : A new trenchless method for underground cable installation

E-Power Pipe : A new trenchless method for underground cable installation E-Power Pipe : A new trenchless method for underground cable installation Dr. Gerhard Lang Jan 31, 2018 - UCT 2018, Track XI High Voltage Power Grid in Germany. Intention to replace nuclear power plants

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

MIAH, INC SEABED TRENCHING OVERVIEW. P.O. Box 3685 Salem, OR (503) FAX# (503)

MIAH, INC SEABED TRENCHING OVERVIEW. P.O. Box 3685 Salem, OR (503) FAX# (503) MIAH, INC SEABED TRENCHING OVERVIEW P.O. Box 3685 Salem, OR 97302 (503)-581-1988 FAX# (503) 581-3441 WWW.MIAHTRENCHERS.COM 1 MIAH TRENCHERS MILLENIUM CLASS SUBSEA HEAVY DUTY ROCK TRENCHERS Hydro-jet Rock

More information

A New Concept for Selective Mechanical Mining of Hard Rock

A New Concept for Selective Mechanical Mining of Hard Rock A New Concept for Selective Mechanical Mining of Hard Rock Brian Asbury 1, Jamal Rostami 1, and Levent Ozdemir 1 1 EARTH MECHANICS INSTITUTE, MINING ENGINEERING DEPARTMENT, COLORADO SCHOOL OF MINES 1 ABSTRACT

More information

1.0 Micro Tunnelling An overview

1.0 Micro Tunnelling An overview 1.0 Micro Tunnelling An overview Micro tunnelling (also known as slurry pipejacking) is not a new method. It is preformed extensively across the world with rapid expansion every year. Herrenknecht, manufactured

More information

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TM1-T2-03 Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

More information

Brief of evidence Tunnelling construction

Brief of evidence Tunnelling construction Brief of evidence Tunnelling construction 1 Personal Information and Qualification My name is Dr. Tim Jaguttis. I am a mechanical engineer and carry a PhD in mechanical engineering. Since 2008 I m a managing

More information

An introduction to. pipe jacking

An introduction to. pipe jacking An introduction to pipe jacking The pipe jacking technique The major applications for pipe jacking and microtunneling include new sewerage and drainage construction, sewer replacement and lining, gas and

More information

2

2 Company(ผ บรรยาย): Shimizu Corporation Technical Name(ห วข อเทคโนโลย ): High Performance TBM TBM ค ณภาพส ง Presenter: 水戸聰 Akira Mito 1 2 Example of Water Supply Tunnel High Overburden Ing-Yot Tunnel L=50.9km

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

NO DIG BERLIN 2015 Symposium and Exhibition March. Paper 5-3. Increasing requirements move boundaries in Pipe Jacking

NO DIG BERLIN 2015 Symposium and Exhibition March. Paper 5-3. Increasing requirements move boundaries in Pipe Jacking NO DIG BERLIN 2015 Symposium and Exhibition 24 27 March Paper 5-3 Increasing requirements move boundaries in Pipe Jacking Dipl.-Ing. Peter Schmaeh Herrenknecht AG, Schwanau, Germany ABSTRACT Utility lines

More information

Venice Pumping Plant Dual Force Main Project Draft EIR

Venice Pumping Plant Dual Force Main Project Draft EIR City of Los Angeles Venice Pumping Plant Dual Force Main Project Draft EIR 4.0 ALTERATIVES UDER COSIDERATIO Alternatives under consideration for this Project are defined by the alignment and construction

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

Belt Systems & Belt Products

Belt Systems & Belt Products Belt Systems & Belt Products Advanced Technology Solutions Caterpillar offers a full range of rugged belt conveyor systems and products unsurpassed in performance and service life custom-designed solutions

More information

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India D.Harding 1 1 The Robbins Company, Solon, Ohio, USA 1 INTRODUCTION The AMR project has been planned since 1983 and will provide irrigation

More information

Feeder-Breakers Product Overview

Feeder-Breakers Product Overview Feeder-Breakers Product Overview Total control The latest in VFD technology... Various material types and belt Service Leader Zero Harm conveyor capacities require flexibility in the feeder-breaker discharge

More information

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley SELECTION OF TUNNEL METHODS By: Dr. Gary S. Brierley Successful Tunnel Design 2 Produce a satisfactory finished facility for no more money and in no more time than is required for the existing ground conditions.

More information

2.1.4 PROJECT CONSTRUCTION

2.1.4 PROJECT CONSTRUCTION Alignment 2C Alignment 2C is the preferred alternative. The new 36-inch force mains would follow the existing alignment along the existing utility road within the OCSD easement from the Bitter Point Pump

More information

Tunnel Boring Machines

Tunnel Boring Machines Tunnel Boring Machines IMIA WGP 60 Michael Spencer, Zurich London (Chairman) Alessandro Stolfa Generali Heiko Wannick Munich Re Ronan Gallagher Allianz John Forder Willis Beat Guggisberg Allianz Eric Bentz

More information

2 Technology of closed-face tunnelling machines

2 Technology of closed-face tunnelling machines 2 Technology of closed-face tunnelling machines 2.1 Machine types There are two basic types of pressurised closed-face tunnelling systems slurry tunnelling machines (STMs) and earth pressure balance machines

More information

T-WALL Retaining Wall System

T-WALL Retaining Wall System CONSTRUCTION MANUAL T-WALL Retaining Wall System The T-WALL Solution... THE NEEL COMPANY 8328 Traford Lane Springfield, VA 22152 Phone 703-913-7858 Fax 703-913-7859 T-WALL Retaining Wall System CONSTRUCTION

More information

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project Darrin Beckett, P.E. Kentucky Transportation Cabinet 49 th Southeastern Transportation Geotechnical Engineering Conference October

More information

The History of Spiral Wound Pipe Technology In Australia s Pipe Renewal Industry

The History of Spiral Wound Pipe Technology In Australia s Pipe Renewal Industry Ian Bateman Interflow Pty Limited The History of Spiral Wound Pipe Technology In Australia s Pipe Renewal Industry Spiral wound pipe technology has been the most widely used product in the Australian pipe

More information

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject 56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea

More information

Introduction to Tunnel Construction

Introduction to Tunnel Construction Introduction to Tunnel Construction David Chapman, Nicole Metje and Alfred Stark *< \ Spon Press an imprint of Taylor & Francis LONDON AND NEWYORK * V TECHNISCHE INFORMATION S8IBLIOTHEK UNIVERSITATSBIBUOTHEK

More information

The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions

The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions Detlef Jordan Robbins Europe GmbH, Germany ABSTRACT: The tunneling industry is abuzz about the upcoming Brenner Base Tunnel Project.

More information

Pipe Express - Ideal for pipeline installations in environmentally sensitive areas.

Pipe Express - Ideal for pipeline installations in environmentally sensitive areas. Pipe Express - Ideal for pipeline installations in environmentally sensitive areas. Herrenknecht AG. Dr. Gerhard Lang Business Development Manager UT Division Founded in 1977 Conversion to Herrenknecht

More information

1 of 1 04/09/ :41

1 of 1 04/09/ :41 1 of 1 04/09/2008 06:41 Buried Shipping Containers http://web.archive.org/web/20031124215255/www.cont 1 of 5 04/09/2008 06:41 DO IT YOURSELF...Partial Burial Example FIND A SITE AND EXCAVATE FOR A PARTIAL

More information

Cost Estimating Framework

Cost Estimating Framework Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach

More information

2 3 4 Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling

More information

IEEE 18-May Intake. Tunnel. Outlet

IEEE 18-May Intake. Tunnel. Outlet IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

Innovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines

Innovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines Innovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines GHD Energy & Resources Brendan Henry Manager, Tunnels and Underground Spaces Safety Commitment Safety

More information

Tunneling Machines of Today and Tomorrow

Tunneling Machines of Today and Tomorrow Tunneling Machines of Today and Tomorrow T. N. WILLIAMSON, Jacobs Associates, San Francisco Current tunneling machines are competitive in making circular bores in rock as strong as 25,000 psi compressive

More information