1 WATERFRONT PLACE IMPLEMENTATION STRATEGY Prepared for Port of Everett TEAM Reid Middleton BST Associates RMC Architects MARINA PHASING AND COSTS This section Prepared by: Reid Middleton September 2014 This section of the report is part of the Port of Everett Waterfront Place Implementation Strategy. It is important to bear in mind that it is but one part of a larger document.

2 Chapter 4 Marina Phasing and Costs PHASING PLAN... 2 SLIP COUNT SUMMARY BY PHASE OVERWATER COVERAGE SUMMARY BY PHASE CONSTRUCTION COSTS FIGURES FIGURE 4-1. MARINA PHASE FIGURE 4-2. LANDING WHARF AND FISHING FLOAT FIGURE 4-3. MARINA PHASE FIGURE 4-4. MARINA PHASE FIGURE 4-5. MARINA PHASE FIGURE 4-6. MARINA PHASE FIGURE 4-7. MARINA PHASE FIGURE 4-8. PREFERRED ALTERNATIVE TABLES TABLE 4-1. SLIP SIZE. NORTH, CENTRAL, AND SOUTH BASINS TABLE 4-2. SUMMARY OF OVERWATER COVERAGE CHANGES BY PHASE TABLE 4-3. OPINION OF PROBABLE COSTS MARINA TABLE 4-4. OPINION OF PROBABLE COSTS WHARFS AND FISHING FLOAT Chapter 4 1

3 Chapter 4 Marina Phasing and Costs PHASING PLAN The following describes the phases for marina redevelopment for the preferred alternative for the master plan. A variety of factors were discussed with stakeholders and staff to determine the preferred phasing plan for the Marina redevelopment. In general, a five- year period was discussed as the potential time frame for each phase; and the plan was separated into six phases. A separate action to develop a linear float and wharf expansion to support commercial fishing and provide other flexible use for vessels was added to the master planning process as part of the Waterfront Place development of the Fishermen s Harbor area. This facility is not assigned to a specific phase in the phasing plan but can be done independently depending on upland development timing and funding availability. The actual timing for each phase may also vary depending on available funding, permitting, and design time frames, and other factors. The proposed phases for the project and the fishing float are shown in Figures 4-1 to 4-7 and are describe below. Information such as a detailed slip mix changes, overwater coverage, and a discussion of what is included in the costs are shown following the descriptions of the phases. Additional information such as more detail for the cost estimates is shown in the appendix. PHASE ONE Phase 1 includes replacement of Central Marina Docks I through P in the eastern section of the Central Marina with new Central Marina Docks I through L. The new docks will provide moorage for boathouses, permanent moorage tenants, commercial moorage such as fishing vessels and yacht brokers, and guest moorage. Additional public inwater amenities such as activity floats and public pedestrian access on the floating dock will be provided in this area. A new gangway and gatehouse will be installed to access the south side of the new L Dock. The total cost including construction, planning, design, permitting, and contingencies for the inwater infrastructure for this Phase is $10,800,000. All the existing boathouses in this area will be relocated to the new Docks I and J. Side tie and open slips will be provided on the new Docks K and L. All new floats, piling, utilities, and appurtenances will be provided. The new dock laterals will tie into the newer headwalks floats along the 14 th Street Bulkhead. The Phase 1 work will modify the overall slip mix of the marina by reducing the number of slips under forty feet and increasing the number of slips 40 feet or longer. These longer slips are intended to be used by a combination of permanent moorage, guest moorage, and commercial moorage for fishing vessels and yacht brokers. The total number of slips in all three marinas will change from approximately 2,091 slips before construction to 2,038 slips after construction with an approximate reduction in moorage of 468 linear feet. Further detailed information on the slip mix changes is included in a later part of this section of the report. The total overwater coverage in the marina will be reduced by approximately 10,000 square feet after the work for Phase 1 is complete. The eastern section of the Central Marina was selected as the first phase for a variety of factors. A driving factor was the old age and poor condition of the docks in this area. These docks are the oldest dock facilities in the entire marina and consist of open slips and boathouse moorage. The docks are primarily concrete floats with a few timber float sections. The docks are anchored with a combination of steel and timber piling. The utility system in this area is relatively old and includes overhead electrical Chapter 4 2

4 services to the boathouses. The majority of the docks are oriented in the east west direction in this area, with a few shorter docks oriented north south. The existing configuration has an inefficient zigzagged- shaped channel that leads to the marine railway and haulout pier in the northeastern corner of the area. The marine railway and haulout pier are being removed as part of the environmental cleanup and reconstruction of the bulkhead in the area. The proposed reconfiguration for Phase 1 eliminates the nonlinear channel through the area and aligns the main dock laterals in the north south direction similar to the majority of the other docks in the South, Central, and North Marinas. The proposed reconfiguration replaces the current configuration of 9 smaller dock laterals with 9 fairways running both east west and north south with four new main dock laterals with three fairways oriented north and south. This creates a more efficient layout and improves operations for moorage tenants leaving and entering their slips. The eastern section of the Central Marina was also selected as the first phase because of the environmental cleanup activities and bulkhead replacement that is currently underway in this area. The cleanup is associated with the previous use of the area as a marine haulout and shipyard site. The cleanup actions include removal of the existing marine railway, removal of contaminated sediments in the marina basin, and replacement of portions of the adjacent bulkhead. Removal of contaminated soils will require some temporary removal of the docks within the area. Many of the permanent moorage tenants in the open slips have been relocated to other areas within the marina leaving many of the open slips in the area unoccupied. This provides an opportunity to perform the dock reconfiguration in this area with minimal impact to open slip tenants. Minimal boathouse relocations will be required for the cleanup action. The proposed marina reconfiguration for Phase 1 provides moorage space for all the existing boathouses on the new I and J Docks. Some temporary relocation of boathouses will be required during the construction of Phase 1 to allow for construction sequencing of dock demolition and new dock construction. A significant factor in selecting the eastern section of the Central Marina as the first phase is its proximity to the early action area for the upland redevelopment plan for Waterfront Place. This area is in the Fishermen s Harbor area of the plan which is slated for the first upland redevelopment into a mixed use and residential area at Waterfront Place. In addition to residential and mixed uses, a hotel is also proposed for the first phase of upland development adjacent to the Phase 1 new docks. The proposed replacement of in- water docks includes provisions for pedestrian access along the waterfront, down to the water on the new guest moorage L Dock and potential for yacht broker and other shared usage on the new K Dock. The proposed plan also includes activity floats at the south end of the new L Dock that can be used by the public and tenants to gather down at water level. The upland features in this eastern area include a wide public walkway and various public spaces including a public overlook and art feature in the location of the existing haulout pier. Other potential improvements that are being planned as part of the upland work include incorporation of art work and water features and activities that draw people down to the water. Potential ideas that enhance the connection between the public and the water include the option of creating a remote controlled radio operated small boat area or course in the north section of the dock area between Central Marina Docks K and L near the public overlook. The inner slip area adjacent to the headwalk dock near the 14 th Street Bulkhead could be separated off with a rope buoy line and used for a remote controlled boat course or Chapter 4 3

5 for other activities such as dinghy storage or use that encourage public interaction and enhances the experience and draw of the public with and to the water. The proposed open fifty and seventy foot slips in this area are designed to provide flexibility in the uses of these open slips. They can be used as guest slips for single vessels per slip or similar to other transient moorage facility such as Point Hudson in Port Townsend, the seventy foot slips can be rented out to visiting yacht clubs for multiple rafting of four or six vessels between two seventy foot fingers. Other marinas have also rented out the seventy foot slips to yacht brokers who keep multiple vessels within the slips. These large slips and side ties on the new Dock K can also be used for fishing vessels. Because of the poor condition of the docks, the environmental cleanup occurring in the area, and the focus of the first phase of upland development for Waterfront Place in the area, the eastern section of the Central Marina, Docks I through L were selected as the preferred first phase for the marina master plan. Work to implement the first phase is already underway. The federal and state environmental permit documents have been received for the inwater work associated with Phase 1. The design and preparation of construction documents for the first phase of new dock inwater work is currently underway with construction planned for The construction for the inwater environmental cleanup and replacement of a section of bulkhead in the area is also currently underway. Chapter 4 4

6 Figure 4-1. Marina Phase 1. Chapter 4 5

7 SOUTH MARINA NORTH WHARF, LANDING WHARF, AND FISHING FLOAT As part of the overall upland and inwater planning process for Waterfront Place, an opportunity was identified for enhancing opportunities for fishermen and the commercial fishing aspects of the waterfront within the Fishermen s Harbor District of Waterfront Place. This opportunity includes the repair and expansion of the Landing Wharf, repair to the South Marina North Wharf, and installation of a new 400 foot long linear float along the South Marina North Wharf to serve commercial fishermen (see Figure 4-2). The intent of this facility is to provide access for fishing vessel moorage and activities as well as flexible side tie moorage for other vessels such as small tourism or specialty vessels to support community events and activities in the area. There are currently approximately 8 Seiners moored in the marina as well as other smaller commercial fishing vessels including long liners, crabbers, and gillnetters. The Seiners are approximately 50 feet in length. Approximately six to seven Seiners could tie up along the 400 foot linear float adjacent to the South Marina North Wharf. The Landing Wharf can be used for active loading or unloading of the vessels. If permanent stern tie moorage is desired at the Landing Wharf then an additional float along the face of the wharf may be desired to provide moorage along the Landing Wharf. Additional loading and unloading could occur in the North Marina at the haulout pier with the addition of a crane to the pier structure. The commercial fishing vessels could also be placed on the linear side tie or slips on K Dock for moorage. The South Marina North Wharf is the large timber pier structure at the southern edge of the Fishermen s Harbor section of the uplands. This wharf will serve as a waterfront walkway. This wharf is in generally good condition but does require some repairs. The existing Landing Wharf located adjacent to this structure is a timber structure that is in generally good condition but also requires general repairs. A separate analysis of the repair options for these two wharf structures is being conducted. The expansion of the wharf and new fishing vessel float was not included in the permitting for the Phase 1 work. Permitting and design work for these repairs, the wharf expansion and fishing float have not been started. The repairs to the existing wharfs, expansion of the Landing Wharf, and installation of the fishing float can be done independently from the other phases of the marina reconfiguration. The timing of the work will depend on the timing of the upland improvements in the area and funding availability for the projects. The costs for the wharf repairs will depend on the selected repair method and may vary depending on the timing and packaging of the construction work. A preliminary planning level estimated cost including soft costs for the repair of the South Marina North Wharf, repair and expansion of the existing Landing Wharf, and installation of the fishing float facility is $4,200,000. This cost may vary depending on which repair options and decking options are selected for the wharf structures and do not include costs for railings, signage, and other upland features that may incorporated as part of the waterfront walkway. Chapter 4 6

8 Figure 4-2. Landing Wharf and Fishing Float Chapter 4 7

9 PHASE TWO Phase 2 includes repair of the covered moorage docks on South Marina Docks I through O and extension of South Marina Docks J, K, L and M. Repairs will include additional floatation, upgraded utilities, waler replacements, and repaired and renovated covered moorage structures. The renovated docks will continue to provide covered moorage as no removal of covered moorage is planned. The dock expansion will consist of new floats, piling, utilities, and appurtenances. The new slips on the dock extensions will be open permanent moorage slips. A new gangway and gatehouse will be installed. The Seine Pier will be removed as part of this phase. The total cost including construction, permitting, design, and contingencies for this Phase is $14,000,000. The Phase 2 work will modify the overall slip mix of the marina by adding slips in the 30 foot to 40 foot range. The total number of slips in all three marinas will increase by 83 slips with a change from approximately 2,031 slips before construction to 2,114 slips after construction and an approximate increase in moorage of 2,840 linear feet. The total overwater coverage in the marina will be increased by approximately 4,400 square feet for the work for Phase 2. This area was selected as Phase 2 for a variety of reasons. Renovation of the covered moorage and upgrade of the utilities on these docks was an identified priority in the 2009 Recapitalization Plan. A benefit of this option is that with the demolition of the Seine Pier, there is space to expand J through M Docks in the South Marina. This will generate additional linear footage of moorage and new revenue in the Marina. This ability to add moorage was seen as a benefit over replacing other sections of the marina and was a reason for selecting renovation and expansion of these docks as Phase 2. The Seine Pier is a large timber- pile supported fixed pier structure in this area designated as Dock Q in the Central Marina on the phasing plans. The Seine Pier is currently gated off and access is no longer provided to the pier because of its poor condition. Linear moorage floats located along each side of the Seine Pier are still utilized for moorage. The Seine Pier is scheduled for removal as part of Phase 2 of the project to provide both space for expansion of the South Marina docks in that area and to provide a reduction in overwater coverage as mitigation for the expansion of overwater coverage for the extensions of Docks J, K, L, and M in the South Marina as part of Phase 2. This area was also selected as a second phase, because the concrete docks are in generally good condition with the concrete portions having a significant remaining life cycle of approximately thirty years. Because the docks are under cover and their decks are not subject to the same exposure to weather as the docks on the open slips they are in better condition that open slip docks of the same age. However, the docks have lost freeboard over time and the wood waler structural components of the dock systems are subject to immersion in the salt water increasing their rate of deterioration. By adding additional floatation and replacing the waler and thru- rod systems on these docks, the life cycle of the docks can be extended another thirty years without complete replacement of the dock system. Repair and replacement of the roof structures will also extend the life of the overall dock system by another thirty years. Improvements (such as repair and replacement of the roof structures, raising the freeboard, and new electrical utility services) are predicted to increase the occupancy of the covered moorage facilities. Given the current lower occupancy rates in these covered moorages, including less than 40 percent occupancy on K and L Docks, there is a high potential to increase the occupancy in these docks with improvements to the float, covered roof, and utility systems. Chapter 4 8

10 Figure 4-3. Marina Phase 2. Chapter 4 9

11 PHASE THREE Phase 3 includes replacement of the South and Central Marina breakwaters, replacement of a bulkhead adjacent to the former conference center, and replacement of the Fuel Dock and Central Marina Dock A with a new linear fuel dock. The breakwaters are critical to maintaining safe operations within the Marina. Replacement within 10 to 15 years for these structures will ensure that the Marina is protected from waves and currents from the river channel. The total cost including construction, planning, design, and contingencies for this Phase is $12,500,000. The costs are based on replacing the existing piling and concrete floats with new steel piling and monolithic post- tensioned concrete floating breakwaters. The existing structures are nearing the end of their design lives and will need to be replaced. There is the potential to obtain grant funding for guest moorage portions of the breakwater as part of the replacement. Since the majority of these structures are used for guest moorage, they will not impact the overall permanent slip mix for the facility. There is potential to add some additional permanent slips on the breakwater in the Central Marina if grant funds are not used for its replacement. Reconfiguration of the fuel dock is included in Phase 3 but may also be moved into Phase 4, depending on timing and funding availability. Straightening of the fuel dock and moving it slightly away from the river channel will allow for better operations and circulation of vessels around this important facility. This has been identified as a priority in past planning work as well. The costs for the fuel pier relocation are included in Phase 3. In order to install a straight fuel float with space for larger fingers on the breakwater, the Central Marina A Dock would be removed as part of this phase. The Phase 3 work including a new fuel dock and the removal of Central Marina Dock A will modify the overall slip mix of the marina by reducing the number of slips by 66, from approximately 2,114 slips before construction to 2,048 slips after construction and an approximate decrease in moorage of 3,197 linear feet. Chapter 4 10

12 Figure 4-4. Marina Phase 3. Chapter 4 11

13 PHASE FOUR The fourth phase is to replace the remaining docks in the Central Marina. Phase 4 includes the replacement of six dock laterals (Central Marina Docks B through G) with five new docks laterals (Central Marina Docks B through F). The replacement will include open slips and the potential for boathouses, covered moorage and floating homes. The new docks will provide moorage for permanent tenants. The docks will be connected to the existing headwalk floats along the 14 th Street bulkhead and will utilize the existing 14 th Street gatehouse. The total cost including construction, planning, design, and contingencies for this Phase is $15,800,000. The Phase 4 work will modify the overall slip mix of the marina by reducing the number of slips under forty feet and increasing the number of slips 40 feet or longer. The lengths for the boathouse and floating home site range from 40 feet to 50 feet long. The total number of slips in all three marinas will change from approximately 2,048 slips before construction to 1,926 slips after construction with an approximate reduction in moorage of 316 linear feet. The amount of overwater coverage in the marina will depend on if the slips are replaced with open slips, boathouses, or floating homes. If the slips were all replaced with open slips, then the total overwater coverage in the marina will be reduced by approximately 35,100 square feet for Phase 4 work. These docks were selected for this phase for a variety of reasons. The G Dock Port- owned boathouses are in poorer condition and have a low occupancy rate. Replacement of these with a new boathouse, individual boathouses, or floating homes is expected to increase the occupancy and revenue generated from this dock. This area also has a significant number of small slips and seasonal lower occupancy rates, particularly on the existing B Dock. Reconfiguring these docks will still provide a significant number of smaller 30- foot slips and opportunities for some larger 38- foot slips and additional boathouses or floating homes. Since this phase is approximately twenty years out, the market may change prior to its implementation. Prior to implementation of this phase it is recommended that the Port review the market for smaller vessels and determine if the proposed selected mix for the slip diversity is still valid or if a different slip mix diversity should be implemented in this area. The west portion of the Central Marina was also selected as Phase 4 because of its proximity to the upland area proposed for redevelopment. The adjacent upland area is proposed for mixed use, commercial, and residential redevelopment. As residential and other uses are developed in this area, renovation of the in- water elements can be done concurrently to provide coordinated redevelopment in this area. Following completion of this phase, all docks in the Central Marina will have been replaced. Chapter 4 12

14 Figure 4-5. Marina Phase 4. Chapter 4 13

15 PHASE FIVE The fifth phase is to replace the South Marina Docks G and H with one new dock lateral G. The replacement will include all open slips and will provide moorage for permanent tenants. The docks will be connected to the existing headwalk float. This phase will replace existing 26 foot slips which have low off season occupancy rates with new 42 foot and 46 foot slips that are more likely occupied year around. The total cost including construction, planning, design, and contingencies for this Phase is $3,200,000. The total number of slips in all three marinas will be reduced by 130 slips, from approximately 1,926 slips before construction to 1,796 slips after construction with an approximate reduction in moorage of 2,262 linear feet. The total overwater coverage in the marina will be reduced by approximately 8,700 square feet for Phase 5 work. The proposed modification eliminates Dock H and replaces the two dock laterals with one new lateral with larger slips. The replacement of G and H Docks in the South Marina was selected for Phase 5, since these docks are in generally poorer condition than the other docks in the west section of the South Marina. Assuming an average implementation of five years per phase, Phase 5 would be implemented approximately twenty years from now. The demand for smaller versus larger slip sizes may change over time. Replacing these docks during Phase 5 provides the opportunity to determine at this later date whether the two docks should be replaced with one dock with larger slips or two docks with smaller slips. It is recommended that a review be completed prior to replacing the two smaller docks to determine the best replacement based on occupancy and demand at that time. Chapter 4 14

16 Figure 4-6. Marina Phase 5. Chapter 4 15

17 PHASE SIX Replacing Docks A through F in the western portion of the South Marina is proposed for Phase 6. The proposed modification replaces the six dock laterals with five new laterals with larger slips. New gatehouses and gangways would also be installed as part of the project. The entire South Marina will be renovated once these slips are replaced. The total cost including construction, planning, design, and contingencies for this Phase is $19,300,000. The total number of slips in all three marinas will be reduced by 154 slips, from approximately 1,796 slips before construction to 1,642 slips after construction with an approximate reduction in moorage of 2,886 linear feet. The total overwater coverage in the marina will be reduced by approximately 7,200 square feet for Phase 5 work. The replacement of these docks was selected as the last phase because these docks are in generally good condition and have been renovated and repaired over the years, with new piling, waler replacements, and deck repairs. If each of the earlier phases takes approximately five years, it will be 25 years before these docks are replaced. The docks will likely need complete replacement at that time. Keeping these docks as the last to be replaced will also allow the Port to reassess the moorage market at the time and determine if the six dock laterals should be replaced with the proposed larger slip mix or if six similar slip size laterals should be reinstalled. It is recommended that a review be completed prior to replacing the docks to determine the best replacement based on occupancy and demand at that time. Chapter 4 16

18 Figure 4-7. Marina Phase 6. Chapter 4 17

19 PHASE SUMMARY Once Phase 6 is completed the 30 year time frame for this master planning process will be completed. All docks will have been either entirely replaced or renovated prior to or within the time frame of the plan within the South, Central, and North Marinas. The overall facility will have been modified from a 2,091 inwater slip marina to a 1,642 inwater slip marina. The slip mix diversity will shift from a mix of 43% of inwater slips under 30 feet and 43% of slips in the 30 to 49 foot range to the majority of slips (75%) in the 30 to 49 foot range. Overall linear footage of moorage will decrease by 5,657 from approximately 74,915 to 69,258 linear feet. However with the majority of the inwater slips 30 feet and longer, the marinas will more likely be occupied year around without the highly seasonal fluctuations that occur in the under 30 foot slips. The recommendation in the master plan is to do a review of the moorage market prior to Phases 4, 5, and 6. This information can be utilized to implement the proposed layout or refine the slip mixes for each of these phases. Additional dry stack storage, trailerable ramp facility improvements, and other upland storage opportunities may likely be implemented within this 30 year period that accommodate trailerable vessels 30 feet and under, resulting in a continued shift in demand for inwater moorage to boats over 30 feet. However economic factors or other drivers may shift the demand back to smaller vessels. The master plan provides a preferred sequence of phasing for the marina development but allows for readjustment of specific dock layouts in each phase to respond to market changes. Chapter 4 18

20 Figure 4-8. Preferred Alternative Chapter 4 19

21 Slip Count Summary by Phase Table 4-1 provides a summary of the number of slips by type (open, covered, boathouse), the percentage by size, the percentages less than a certain size, and the total linear feet of moorage by slip size for the existing conditions and following each of the phases of implementation of the master plan. Table 4-1. Slip Size. North, Central, and South Basins. Existing Configuration Slip Size Open Covered Boathouse Total Percentage Total Percent Less Total LF of Moorage Based on average length of slip < or = % 4.3% 1, % 43.0% 21, % 72.9% 21, % 86.1% 12, % 93.8% 8, % 97.7% 5,265 > or = % 100.0% 3,675 TOTAL ,915 Chapter 4 20

22 After Phase 1 Slip Size Open Covered Boathouse Total Percentage Total Percent Less Total LF of Moorage Based on average length of slip < or = % 3.9% 1, % 41.8% 20, % 69.1% 19, % 84.9% 14, % 93.7% 9, % 97.1% 4,420 > or = % 100.0% 4,500 TOTAL ,447 Chapter 4 21

23 After Phase 2 Slip Size Open Covered Boathouse Total Percentage Total Percent Less Total LF of Moorage Based on average length of slip < or = % 3.7% 1, % 40.3% 20, % 69.4% 21, % 85.4% 15, % 93.9% 9, % 97.2% 4,420 > or = % 100.0% 4,500 TOTAL ,287 Chapter 4 22

24 After Phase 3 Note: Central Marina A Dock Removed Total LF of Moorage Based on average length of slip Slip Size Open Covered Boathouse Total Percentage Total Percent Less < or = % 2.4% % 39.9% 20, % 68.8% 19, % 85.1% 15, % 93.8% 9, % 97.1% 4,420 > or = % 100.0% 4,500 TOTAL ,090 Chapter 4 23

25 After Phase 4 Note some of the slips could be boathouses or floating homes Total LF of Moorage Based on average length of slip Slip Size Open Covered Boathouse Total Percentage Total Percent Less < or = % 0.3% % 26.6% 13, % 65.6% 26, % 83.3% 15, % 93.7% 11, % 97.0% 4,160 > or = % 100.0% 4,350 TOTAL ,406 Chapter 4 24

26 After Phase 5 Note some of the slips could be boathouses or floating homes Total LF of Moorage Based on average length of slip Slip Size Open Covered Boathouse Total Percentage Total Percent Less < or = % 0.2% % 17.9% 8, % 59.8% 26, % 82.3% 18, % 93.2% 10, % 96.8% 4,160 > or = % 100.0% 4,350 TOTAL ,144 Chapter 4 25

27 After Phase 6 Note some of the slips could be boathouses or floating homes Total LF of Moorage Based on average length of slip Slip Size Open Covered Boathouse Total Percentage Total Percent Less < or = % 0.1% % 5.5% 2, % 52.8% 27, % 80.4% 20, % 93.2% 11, % 96.8% 3,770 > or = % 100.0% 3,975 TOTAL ,258 Chapter 4 26

28 Overwater Coverage Summary by Phase The replacement of in- water facilities will require full permitting of the proposed improvements from federal, state, and local agencies. One important factor to the regulatory agencies in their review and approval for in- water improvements is the amount of overwater coverage. Project impacts to the environment should be avoided as much as feasible, minimized, and mitigated if they cannot be avoided. In general, regulators responsible for reviewing project impacts to the environment will review projects to see whether there is a net reduction or no net change in overwater coverage. Table 4-2 provides a summary of the overwater coverage by phases for the preferred plan. The increase shown in Phase 3 is based on slightly wider breakwaters. If breakwaters of the same width as existing are proposed, there would be zero increase in the overwater coverage for Phase 3. The amount of overwater coverage for Phase 4 is highly dependent on what type of use occurs on the new Central Marina Docks E and F. If the existing port- owned boathouse structure is replaced with open moorage and all other slips in this phase are open slips then there will be a large reduction in overwater coverage of 35,000 square feet. New boathouses or floating homes in this area could change that from a large decrease in overwater coverage to a net increase in overwater coverage of 20,000 square feet or more. Table 4-2. Summary of Overwater Coverage Changes by Phase. Phase Approx. Overwater Coverage Change for Phase (SF) Total Change (SF) Phase 1-10,000-10,000 Phase 2 +4,400-5,600 Phase 3 +14,000 +8,400 Phase 4-35,100 to +20,000-26,700 to +28,400 (depending on open slips versus boathouse or floating homes) Phase 5-8,700-35,400 to +19,700 Phase 6-7,200-42,600 to +12,500 Chapter 4 27

29 Construction Costs An Opinion of Probable Construction Costs was developed for each of the phases. The construction costs were based on the dock layout in the master plan. The basic construction costs and the total costs including soft costs such as engineering and permitting are shown in Table 4-3. For the financial analysis, the soft costs were added to these costs for a full financial analysis. The construction costs are in 2014 dollars and include a 15% Contractor Overhead and Profit and a 20% contingency. For planning purposes the soft costs including engineering, permitting, and sales tax are estimated to be 35% of the construction cost. The actual soft costs may vary depending on timing, changing permit requirements, whether each phase is issued as one or more construction bid packages, and other factors that may influence these costs over time. The costs are based on steel piling, modular concrete dock system (wood waler and thru- rods), and full utilities including electrical service, potable and fire water. Telecommunications wiring and cable systems are not included in the costs. Costs are not included for dredging or upland modifications other than the wharf repairs are included with the fishing float estimate. Detailed cost estimates are included in the appendix for the first phase work, Seine Pier demolition, and the fishing pier work. The cost estimate for the work associated with repair and upgrades to the covered moorage for Phase 2 were obtained from the Marina Recapitalization Plan from 2009, which is in the appendix, with the costs escalated to The costs for Phases 3 through 6 are planning level estimates based on an average per slip cost for the slips sizes installed for each of the phases. Table 4-3. Opinion of Probable Costs Marinas. Phase Construction Cost Total Cost W/ Soft Costs Phase 1 $8,000,000 $10,800,000 Phase 2 $10,349,000 $14,000,000 Phase 3 $9,230,000 $12,500,000 Phase 4 $11,700,000 $15,800,000 Phase 5 $2,400,000 $3,200,000 Phase 6 $14,300,000 $19,300,000 Total $56,000,000 $75,600,000 Chapter 4 28

30 The following is a summary of the costs for the repair to the North Marina Wharf, Landing Wharf repairs and extension, and installation of a new gangway and fishing float. The actual costs may vary depending on the repair options selected for the wharfs and the selection of decking and finishing for the wharf structures. These estimates include the 15% Contractor overhead and profit and a 20% contingency. The estimates do not include railings, signage, or other upland site features that may be installed as part of the waterfront walkway system. A detailed estimate for this work is included in the appendix. Table 4-4. Opinion of Probable Costs Wharfs and Fishing Float. Project Construction Cost Total Cost W/ Soft Costs Repair Wharfs, Extend Wharf, & Fishing Float $3,100,000 $4,200,000 \h:\doc\24wf\2013\012 port of Everett master plan phase ii\reports\poe marina master plan\chapter 4 marina phasing and costs.docx\smk Chapter 4 29

Current Trends in Marina Planning and Design

Current Trends in Marina Planning and Design ASSOCIATION OF PACIFIC PORTS 101 st Annual Conference, July 2014 Current Trends in Marina Planning and Design, PE, LEED AP, Reid Middleton Outline Introduction Market & Demand Planning Environmental Design

More information

LOCATION: At 12 Port of Everett locations in Port Gardner at Everett, Washington.

LOCATION: At 12 Port of Everett locations in Port Gardner at Everett, Washington. US Army Corps of Engineers Seattle District Joint Public Notice Application for a Department of the Army Permit and a Washington Department of Ecology Water Quality Certification and/or Coastal Zone Management

More information

Panama City Marina City of Panama City, Florida

Panama City Marina City of Panama City, Florida Panama City Marina City of Panama City, Florida MARINA BULKHEAD ASSESSMENT October 3, 2011 Prepared For: Prepared By: 543 Harbor Boulevard, Suite 204 Destin, Florida 32541 DRAFT - 12/19/2011 Panama City

More information

Revitalization Plan and EIR Board of Supervisors Hearing January 31, 2006

Revitalization Plan and EIR Board of Supervisors Hearing January 31, 2006 Dana Point Harbor Revitalization Plan and EIR Board of Supervisors Hearing January 31, 2006 Existing Conditions 2 3 4 Dana Point Harbor Drive Golden Lantern Proposed Commercial Core Plan (PA 1 & 2) 5 Environmental

More information

County of Orange. Dana Point Marinas Workshop No. 5. Marina Planning. Meeting No. 6. January 30, 2007 CASH &

County of Orange. Dana Point Marinas Workshop No. 5. Marina Planning. Meeting No. 6. January 30, 2007 CASH & County of Orange Dana Point Marinas Workshop No. 5 Marina Planning Meeting No. 6 January 30, 2007 CASH & Dana Point Marinas Project Considerations Age & Dock Condition Existing Boater Feedback Design Criteria

More information

MEMORANDUM. From: Moffatt & Nichol. Date: April 3, Subj: Wharf J-10 Evaluation of Structure for EIR Document. M&N File No:

MEMORANDUM. From: Moffatt & Nichol. Date: April 3, Subj: Wharf J-10 Evaluation of Structure for EIR Document. M&N File No: 2001 North Main St, Ste 360, Walnut Creek, CA 94596 Ph: 925-944-5411 ; Fax: 925-944-4732 MEMORANDUM To: Ed Byrne From: Moffatt & Nichol Date: April 3, 2006 Subj: Wharf J-10 Evaluation of Structure for

More information

Exhibit B Shoreline Checklist & Statement of Exemption Form for Ensuring Consistency with SMP Policies and Regulations and No Net Loss Policy

Exhibit B Shoreline Checklist & Statement of Exemption Form for Ensuring Consistency with SMP Policies and Regulations and No Net Loss Policy CLALLAM COUNTY Department of Community Development 223 East 4th Street, Suite 5 Port Angeles Washington 98362 360-417-2420 Exhibit B Shoreline Checklist & Statement of Exemption Form for Ensuring Consistency

More information

Waterfront Lands Analysis By: BST Associates For: City of Tacoma

Waterfront Lands Analysis By: BST Associates For: City of Tacoma Waterfront Lands Analysis 2008 By: BST Associates For: City of Tacoma 1 Purpose Is sufficient land available to meet the most critical needs of water-dependent uses? Recreational boating Power, sail, and

More information

DRAFT. Point Hudson. Marina Breakwater Rehabilitation Task 1 Design Refinement. Port of Port Townsend. August 30, 2017

DRAFT. Point Hudson. Marina Breakwater Rehabilitation Task 1 Design Refinement. Port of Port Townsend. August 30, 2017 DRAFT Point Hudson Marina Breakwater Rehabilitation Task 1 Design Refinement Port of Port Townsend August 30, 2017 Task 1 - Design Refinement Overview Contractor/ Supplier Outreach Information on cost

More information

Keeping Things Running

Keeping Things Running Keeping Things Running Preventative Maintenance Presentation for PCC Conference, Friday Harbor, April 2007 By: Lon A. White & Ray Majeski, Preventative Maintenance The act of fixing something before it

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION LSA ASSOCIATES, INC. OCTOBER 2009 DRAFT ENVIRONMENTAL IMPACT REPORT ALAMITOS BAY MARINA REHABILITATION PROJECT CITY OF LONG BEACH 3.0 PROJECT DESCRIPTION 3.1 PROJECT LOCATION AND SITE DESCRIPTION The Alamitos

More information

Specific Project Information Form For Construction of New or Modification of Existing Residential Overwater Structures

Specific Project Information Form For Construction of New or Modification of Existing Residential Overwater Structures Form For Construction of New or Modification of Existing Residential Overwater Structures and Drive Moorage Piling in Lake Washington, Lake Sammamish, the Sammamish River and Lake Union, Including the

More information

KROPF INDUSTRIAL Marine Commercial Docks

KROPF INDUSTRIAL Marine Commercial Docks KROPF INDUSTRIAL Marine Commercial Docks TABLE OF CONTENTS 1 Invest In Your Success 2 The Kropf Story 4 Kropf Steel Tube Docks 6 The Steel Tube Advantage 8 Aluminum Frame Docks 12 Decking 14 Gangways 16

More information

RE-ISSUED NOTICE OF PREPARATION SUBSEQUENT ENVIRONMENTAL IMPACT REPORT

RE-ISSUED NOTICE OF PREPARATION SUBSEQUENT ENVIRONMENTAL IMPACT REPORT RE-ISSUED NOTICE OF PREPARATION SUBSEQUENT ENVIRONMENTAL IMPACT REPORT Date: January 5, 2010 Subject: Re-Issue Notice of Intent to Prepare a Draft Subsequent Environmental Impact Report Project Title:

More information

Currituck County Pier, Dock & Bulkhead Handout

Currituck County Pier, Dock & Bulkhead Handout Currituck County Pier, Dock & Bulkhead Handout Definitions: ACCESSORY STRUCTURE. An accessory structure is any structure not roofed over and enclosed more than 50% of its perimeter walls, located on one-

More information

PREPARED FOR: NEW BEDFORD HARBOR DEVELOPMENT COMMISSION FLOATING DOCK CONDITION ASSESSMENT REPORT PORT OF NEW BEDFORD POPE S ISLAND MARINA

PREPARED FOR: NEW BEDFORD HARBOR DEVELOPMENT COMMISSION FLOATING DOCK CONDITION ASSESSMENT REPORT PORT OF NEW BEDFORD POPE S ISLAND MARINA PREPARED FOR: NEW BEDFORD HARBOR DEVELOPMENT COMMISSION FLOATING DOCK CONDITION ASSESSMENT REPORT PORT OF NEW BEDFORD POPE S ISLAND MARINA APRIL 14, 2014 Pope s Island Marina Floating Dock Condition Assessment

More information

SHO Recommendations June 16, Exhibit #11

SHO Recommendations June 16, Exhibit #11 ITEM SMP PROVISION TOPIC BILL FORMAT CHANGES [underline-additions; strikethrough-deletions] SHO - DISCUSSION/RATIONAL/PROPOSED CHANGES 25 25.06.020 (9) (a) [new] i. iv. Page 40. Shoreline Setback VEA Property

More information

The Port of Bellingham

The Port of Bellingham The Port of Bellingham Revitalizing Bellingham s Waterfront Mike Stoner, Environmental Director June 8, 2015 1 The Bellingham Bay Demonstration Pilot 2 100 Years of Industrial Use 3 4 Community Uncertainty

More information

I202. Central Wharves Precinct

I202. Central Wharves Precinct I202. Central Wharves Precinct I202.1. Precinct description The zoning of the land within the Central Wharves Precinct is the Business City Centre Zone and the underlying zoning of the part of the Central

More information

PENDER HARBOUR DOCK MANAGEMENT PLAN

PENDER HARBOUR DOCK MANAGEMENT PLAN PENDER HARBOUR DOCK MANAGEMENT PLAN 1.0 INTENT OF DOCK MANAGEMENT PLAN The Pender Harbour Dock Management Plan (the DMP) is an instrument of policy that provides guidance in relation to docks authorized

More information

PORT OF PORT TOWNSEND. Point Hudson Marina Breakwater Preliminary Design

PORT OF PORT TOWNSEND. Point Hudson Marina Breakwater Preliminary Design PORT OF PORT TOWNSEND Point Hudson Marina Breakwater Preliminary Design December 5, 2014 1 Outline Project Status (Scopes of Work, To-Do List from Conceptual Design) Existing Conditions Alternative Evaluation

More information

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012 The General Trade Knowledge examination will be administered in one session

More information

6.0 ALTERNATIVES TO THE PROPOSED PROJECT

6.0 ALTERNATIVES TO THE PROPOSED PROJECT 6.0 ALTERNATIVES TO THE PROPOSED PROJECT In accordance with California Environmental Quality Act (CEQA) Guidelines Section 15126.6, the following section describes a reasonable range of reasonable alternatives

More information

PRELIMINARY SHORELINE PROTECTION STUDY Parking Lot D to the JFK Library

PRELIMINARY SHORELINE PROTECTION STUDY Parking Lot D to the JFK Library PREPARED FOR: UNIVERSITY OF MASSACHUSETTS BOSTON PRELIMINARY SHORELINE PROTECTION STUDY Parking Lot D to the JFK Library UNIVERSITY OF MASSACHUSETTS Boston, Massachusetts PREPARED BY: PARE CORPORATION

More information

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. December 5, 2017

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. December 5, 2017 SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY December 5, 2017 The Members of the Woods Hole, Martha's Vineyard and Nantucket Steamship Authority ( SSA )

More information

HURON RIVER BOAT RAMP & PARKING LOT

HURON RIVER BOAT RAMP & PARKING LOT 2010 National Award as Best Large Boating Access Facility States Organization for Boating Access (SOBA) 2010 Quality Asphalt Paving Awards Flexible Pavements of Ohio AWARD WINNING PROJECT Location Huron,

More information

Marine 15. Planning & Infrastructure for Marina Development

Marine 15. Planning & Infrastructure for Marina Development Marine 15 Planning & Infrastructure for Marina Development Who is this Pompous American? Jesse Ellenz Vice President of Special Projects What Makes Him So Special? Nothing Not a PHD Not a Professor Not

More information

From the ADA and ABA Accessibility Guidelines for Buildings and Facilities

From the ADA and ABA Accessibility Guidelines for Buildings and Facilities From the ADA and ABA Accessibility Guidelines for Buildings and Facilities Published in the Federal Register on July 23, 2004 1003 Recreational Boating Facilities 1003.1 General. Recreational boating facilities

More information

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report SCCRTC- MP 19.43 San Lorenzo River Bridge Walkway Widening Feasibility Report May 19, 2016 INTRODUCTION Jacobs Engineering Group was selected to provide a feasibility report for the Santa Cruz County Regional

More information

HDB MARINE. Your Solution for Marina and Dock Design / Construction

HDB MARINE. Your Solution for Marina and Dock Design / Construction HDB MARINE Your Solution for Marina and Dock Design / Construction Commercial Marinas Recreational Marinas Resort Marinas Military Marine Dock Applications Custom Private Docks HDB will build your design

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice No.

THIS IS NOT A PAID ADVERTISEMENT. Public Notice No. THIS IS NOT A PAID ADVERTISEMENT 0BPublic Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. 1BCENAP-OP-R-2010-898-24 Application No. In Reply

More information

PORT MASTER PLAN AMENDMENT NO. 26 LA WATERFRONT LAND USE ADDITIONS, MINOR FILLS, AND NEW HARBORS

PORT MASTER PLAN AMENDMENT NO. 26 LA WATERFRONT LAND USE ADDITIONS, MINOR FILLS, AND NEW HARBORS PORT MASTER PLAN AMENDMENT NO. 26 LA WATERFRONT LAND USE ADDITIONS, MINOR FILLS, AND NEW HARBORS BACKGROUND The Port Master Plan for the Port of Los Angeles (Port) was certified by the California Coastal

More information

Fort Point Channel Watersheet Activation Plan. Marine Infrastructure Design and Costs. Vine Associates APPENDIX A

Fort Point Channel Watersheet Activation Plan. Marine Infrastructure Design and Costs. Vine Associates APPENDIX A Fort Point Channel Watersheet Activation Plan Marine Infrastructure Design and Costs APPENDIX A Fort Point Channel Watersheet Activation Plan Page 1 Marine Infrastructure Design and Costs CONTENTS A. GENERAL

More information

I213. Westhaven Tamaki Herenga Waka Precinct

I213. Westhaven Tamaki Herenga Waka Precinct I213. Westhaven Tamaki Herenga Waka Precinct I213.1. Precinct description The Westhaven Tamaki Herenga Waka Precinct is located at the western edge of the city centre and comprises the land and coastal

More information

SMALL HARBOR IMPROVEMENT PROJECTS PROGRAM (SHIPP) - MUNICIPAL

SMALL HARBOR IMPROVEMENT PROJECTS PROGRAM (SHIPP) - MUNICIPAL SMALL HARBOR IMPROVEMENT PROJECTS PROGRAM (SHIPP) - MUNICIPAL Connec=cut Port Local Matching CITY - TOWN PROJECT DESCRIPTION Project Total Authority Funding Funds Essex Update Harbor Management Plan $

More information

Shoreline Restoration Planning. Technical Review Committee December 17, 2008 City of Tacoma Shoreline Master Program Update

Shoreline Restoration Planning. Technical Review Committee December 17, 2008 City of Tacoma Shoreline Master Program Update Shoreline Restoration Planning Technical Review Committee December 17, 2008 City of Tacoma Shoreline Master Program Update What is the Shoreline Restoration Plan? Strategies and actions to meet the goals

More information

Wharf, Dock and Buoy Policy

Wharf, Dock and Buoy Policy DEV-250 Wharf, Dock and Buoy Policy Effective Date: June 12, 2018 Authorized By: Council Regular Meeting Replaces: August 28, 2012 April 12, 2011 1.1 Policy Statement The District of Peachland has entered

More information

HARBOR INFRASTRUCTURE INVENTORIES Oswego Harbor, New York

HARBOR INFRASTRUCTURE INVENTORIES Oswego Harbor, New York HARBOR INFRASTRUCTURE INVENTORIES Oswego Harbor, New York Harbor Location: Oswego Harbor is located on the southern shore of Lake Erie at the mouth of the Oswego River, about 32 miles Northwest of Syracuse,

More information

Installation: PURLoc 4.3 Linear Feet: 270 Sheet Lengths: 18 Soil Description: Sand/Clay Existing Wall: None Contractor: Albert Marine/ HiSix

Installation: PURLoc 4.3 Linear Feet: 270 Sheet Lengths: 18 Soil Description: Sand/Clay Existing Wall: None Contractor: Albert Marine/ HiSix Installation: PURLoc 4.3 Linear Feet: 270 Sheet Lengths: 18 Soil Description: Sand/Clay Existing Wall: None Contractor: Albert Marine/ HiSix New Jersey/Paramaribo Design Engineer: Design Build by Client

More information

Relevant Excerpts from Electoral Area C Official Community Plan Bylaw No. 725

Relevant Excerpts from Electoral Area C Official Community Plan Bylaw No. 725 Relevant Excerpts from Electoral Area C Official Community Plan Bylaw No. 725 (See Bylaw No. 725 for all policies) Section 2.3 Shoreline Environment Section 3.7 Foreshore Water Section 12.2 Foreshore and

More information

New Jersey Department of Environmental Protection

New Jersey Department of Environmental Protection New Jersey Department of Environmental Protection Assistant Commissioner Marilyn Lennon Land Use Management Division of Land Use Regulation Manager Virginia Kopkash September 16, 2013 Transformation of

More information

CITY OF VALDEZ ALASKA REQUEST FOR PROPOSALS

CITY OF VALDEZ ALASKA REQUEST FOR PROPOSALS CITY OF VALDEZ ALASKA REQUEST FOR PROPOSALS Project: Build, Own, and Operate a Fuel Dock and Related Infrastructure for the New Boat Harbor in Valdez, Alaska Issued: June 23, 2017 City of Valdez Port and

More information

Adjacent to Pearl Avenue, in the City of Burlington, Burlington County, New

Adjacent to Pearl Avenue, in the City of Burlington, Burlington County, New THIS IS NOT A PAID ADVERTISEMENT 0BPublic Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. 1BCENAP-OP-R-2014-0120 Application No. In Reply Refer

More information

SPORTSMAN S WORLD PROPERTY OWNERS ASSOCIATION APPLICATION FOR BUILDING PERMIT

SPORTSMAN S WORLD PROPERTY OWNERS ASSOCIATION APPLICATION FOR BUILDING PERMIT APPLICATION FOR BUILDING PERMIT Plans submitted for Section, Block or Tract, Lot ADDRESS Property owner s contact information: Name: Mailing address: City: _State: Zip: Cell: Other: E-mail: Contractor/builder

More information

Port Project & Priority List: 2010 and beyond

Port Project & Priority List: 2010 and beyond Port Project & Priority List: 2010 and beyond For all project and other listings, issues to be addressed include Need/reason for the project, Timeline, Scope, Potential Initial & Life-Cycle Costs, Financial

More information

Port Authority of Guam

Port Authority of Guam Port Authority of Guam An Inside Look at the Port Authority of Guam Presented to the: United Nations Economic & Social Commission for Asia and the Pacific High Level Meeting on Strengthening Inter- Island

More information

Lake Anna Shoreline Packet for Lake Structures Updated March 23, 2018

Lake Anna Shoreline Packet for Lake Structures Updated March 23, 2018 Lake Anna Shoreline Packet for Lake Structures Updated March 23, 2018 This packet is used for: - The construction of or addition to lake structures on the Lake Anna shoreline - Lake structure projects

More information

CENEX-HARVEST STATES DOCK Superior, Wisconsin

CENEX-HARVEST STATES DOCK Superior, Wisconsin Krech Ojard & Associates is a progressive firm offering professional material handling, logistics, transportation, and transshipment facility services. With outstanding client service and the ability to

More information

AGENDA PRE-BID CONFERENCE

AGENDA PRE-BID CONFERENCE ATTACHMENT NO. 1 TO ADDENDUM NO. 1 AGENDA PRE-BID CONFERENCE Date: December 13, 2016 Time: 1:00 P.M. Project: Boat Lifts at the Ocean Springs Harbor Contract: Boat Lifts at the Ocean Springs Harbor Location:

More information

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge WRBAC

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge WRBAC Portland - Milwaukie Light Rail Willamette River Bridge WRBAC 12.11.08 Vision Deliver a bridge that embodies the Portland aesthetic, is functional and affordable Aesthetic the right bridge for the context

More information

Ordinance No July 1, 2016

Ordinance No July 1, 2016 Sections: 2.13.010 Title. 2.13.020 Scope. 2.13.030 Tacoma Fire Code. 2.13.040 Existing installations. 2.13.050 Definitions. 2.13.060 Waterfront structures. 2.13.070 Dry boat storage. 2.13.080 Marinas.

More information

1. Is it possible that each site will become divided into its own project contract? The projects will not be divided into separate contracts.

1. Is it possible that each site will become divided into its own project contract? The projects will not be divided into separate contracts. Ferry Landings Resilience Upgrades Project 6727 / Contract 67270001 Questions & Answers June 20, 2017 1. Is it possible that each site will become divided into its own project contract? The projects will

More information

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10 EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street

More information

Flotation Docking Systems INC

Flotation Docking Systems INC Flotation Docking Systems INC P.O. Box 178 Cedarville, MI 49719 P: 906-484-3422 F: 906-484-2335 E: info@flotationdocking.com W: www.flotationdocking.com Beauty strength is having, showing, or possessing

More information

PUBLIC NOTICE LOS ANGELES DISTRICT. APPLICATION FOR PERMIT Port of Los Angeles Berths : Wilmington Waterfront Promenade

PUBLIC NOTICE LOS ANGELES DISTRICT. APPLICATION FOR PERMIT Port of Los Angeles Berths : Wilmington Waterfront Promenade PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS LOS ANGELES DISTRICT BUILDING STRONG APPLICATION FOR PERMIT Port of Los Angeles Berths 182-186: Wilmington Waterfront Promenade Public Notice/Application No.:

More information

9 Conclusion. 9.1 Introduction

9 Conclusion. 9.1 Introduction 9 Conclusion 9.1 Introduction This final chapter presents a synthesis of the evaluation criteria leading to conclusions and recommendations. Also included is a summary of the current status of the Tappan

More information

Public Notice. In Reply Refer To: Corps File No. LRE S18 Date: October 1, 2018 Expires: October 19, 2018

Public Notice. In Reply Refer To: Corps File No. LRE S18 Date: October 1, 2018 Expires: October 19, 2018 US Army Corps of Engineers Detroit District Public Notice Applicant: Barrett Boat Works In Reply Refer To: Corps File No. LRE-1983-570234-S18 Date: October 1, 2018 Expires: October 19, 2018 Proposed marina

More information

PRESCRIPTIVE COMPLIANCE METHOD

PRESCRIPTIVE COMPLIANCE METHOD CHAPTER PRESCRIPTIVE COMPLIANCE METHOD 3 SECTION 301 GENERAL 301.2 Building materials. Building materials shall comply with the requirements of this section. 301.2.1 Existing materials. Materials already

More information

HARBOR INFRASTRUCTURE INVENTORIES Manitowoc Harbor, Wisconsin

HARBOR INFRASTRUCTURE INVENTORIES Manitowoc Harbor, Wisconsin HARBOR INFRASTRUCTURE INVENTORIES Manitowoc Harbor, Wisconsin Harbor Location: Manitowoc Harbor is on the west shore of Lake Michigan about 79 miles north of Milwaukee, Wisconsin. Authority: River & Harbor

More information

J O I N T P U B L I C N O T I C E

J O I N T P U B L I C N O T I C E J O I N T P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina 29403-5107 and THE S.C. DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL Water Quality

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 20, 2018

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 20, 2018 THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2018-0567-46 September 20, 2018 Application

More information

Construction Project Management: A Complete Introduction

Construction Project Management: A Complete Introduction Construction Project Management: A Complete Introduction by Alison Dykstra, AIA, CSI Slides are available for instructors who assign this book. They were developed using PowerPoint to assist instructors

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions Chelan County Shoreline Master Program Update July 2009 What is an SMP? Shoreline Master Programs (SMP) are a combination of rules and comprehensive planning that are prepared

More information

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011 FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN EB3679 February 2011 FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN Prepared for: The City of Westminster 511 Royal Avenue Westminster, BC V3L 1H9 Prepared

More information

CALCITE HARBOR Rogers, Michigan

CALCITE HARBOR Rogers, Michigan Krech Ojard s Marine Group provides services for the design and rehabilitation of marine facilities and waterfront infrastructure. Our certified, commercially-trained divers are also licensed, practicing

More information

ENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program. Structural Rehabilitation of Pier 68S

ENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program. Structural Rehabilitation of Pier 68S ENTRY FORM DVASE 2016 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings Buildings Buildings Buildings under $2M $2M-$10M $10M - $30M $30M - $100M Buildings Over

More information

Note to File on Changes to Environmental Impact Report

Note to File on Changes to Environmental Impact Report Note to File on Changes to Environmental Impact Report Addendum Date: March 20, 2012 Case No.: 2010.0493E State Clearinghouse No.: 2011022040 Project Title: 34th Americaʹs Cup & James R. Herman Cruise

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013846 CHARLESTON, CHARLESTON COUNTY, SOUTH CAROLINA CHARLESTON PORT ACCESS ROADWAY PROJECT (1) SITE - 1 - REPLACEMENT OF EXISTING US78/52 OVERHEAD

More information

ECOLOGY MAY 25, 2011 PUBLIC HEARING COMMENT SUMMARY MATRIX CITY OF BELLINGHAM SHORELINE MASTER PROGRAM

ECOLOGY MAY 25, 2011 PUBLIC HEARING COMMENT SUMMARY MATRIX CITY OF BELLINGHAM SHORELINE MASTER PROGRAM 1. Inventory Characterization Inventory is out-of-date and under reports fish, wildlife and habitat occurring in reaches. Update the inventory and establish the correct baseline for determining no-net-loss

More information

Bear Exhibit Fence Upgrades. The following modifications are hereby made part of the contract documents:

Bear Exhibit Fence Upgrades. The following modifications are hereby made part of the contract documents: ADDENDUM TO BID T2017-04 Metropolitan Park District Department of Planning, Design and Development 4702 South 19 th Street Tacoma WA 98405 Date Prepared: November 17, 2017 Bid Number: T2017-04 Addendum

More information

A Guide to Project Review

A Guide to Project Review A Guide to Project Review Updated March 2015 Vancouver Fraser Port Authority, doing business as Port Metro Vancouver, has prepared this guide to assist tenants, terminal operators, consulting firms and

More information

New Fire Boat Station 35, located at Pier 22.5 along The Embarcadero at Harrison Street.

New Fire Boat Station 35, located at Pier 22.5 along The Embarcadero at Harrison Street. Port of San Francisco Waterfront Design Advisory Committee Agenda Item No. 3 Meeting Date: Staff Report To: From: Re: Waterfront Design Advisory Committee: Laura Crescimano Marsha Maytum Kathrin Moore

More information

SHORELINE EROSION ARMOR RO BREAKWATER WAVE BARRIER WA DEFLECTORS SEDIMENTATION CURREN TIDES NUMERICAL MODELING CGWA

SHORELINE EROSION ARMOR RO BREAKWATER WAVE BARRIER WA DEFLECTORS SEDIMENTATION CURREN TIDES NUMERICAL MODELING CGWA SHORELINE EROSION ARMOR RO BREAKWATER WAVE BARRIER WA DEFLECTORS SEDIMENTATION CURREN TIDES NUMERICAL MODELING CGWA MIKE21 DRIVE STWAVE BOUS2D DOWN DELFT3D SEDTRA PLAXIS FIELD MEASUREMENTS BATHYMET PHYSICAL

More information

F3. Coastal Marina Zone

F3. Coastal Marina Zone F3. Coastal Marina Zone F3.1. Zone description The Coastal Marina Zone provides for the development and operation of various established marinas, including both land and water components. The zone covers

More information

2018 CAPITAL IMPROVEMENT

2018 CAPITAL IMPROVEMENT CAPITAL IMPROVEMENT Port Commission Workshop March 28, CAPITIAL PROJECT SUMMARY BOAT HAVEN MARINA & YARD Boat Haven Workyard Surface Project Estimate Confidence of Cost Estimate Capital Budget New Bond

More information

Table of Contents. List of Tables. 11. Advantages and Disadvantages

Table of Contents. List of Tables. 11. Advantages and Disadvantages Table of Contents 11. Advantages and Disadvantages... 11-1 page List of Tables... 11-1 11. Advantages and Disadvantages The overall advantages and disadvantages of the DMNP are articulated, summarized

More information

Florence County Government

Florence County Government Florence County Government Procurement Department April 29, 2016 ADDENDUM NO.1- CONSTRUCTION OF A BOARDWALK AND FISHING PIERS AT LAKE CITY PARK PROJECT (BID NO. 35-15/16) The following changes shall be

More information

PORT DOCK 5 CONCEPTUAL ALTERNATIVES ANALYSIS SUMMARY REPORT

PORT DOCK 5 CONCEPTUAL ALTERNATIVES ANALYSIS SUMMARY REPORT PORT DOCK 5 CONCEPTUAL ALTERNATIVES ANALYSIS SUMMARY REPORT For the Port Dock 5 Pier Approach Structural Renovation Design Project Newport, Oregon October 11, 2016 OBEC Consulting Engineers Corporate Office:

More information

Port of Long Beach Port Master Plan Overview December 22, 2008

Port of Long Beach Port Master Plan Overview December 22, 2008 Port of Long Beach Port Master Plan Overview December 22, 2008 PORT OF LONG BEACH PORT MASTER PLAN OVERVIEW INTRODUCTION In 1978 the California Coastal Commission certified the Port of Long Beach Port

More information

ARTICLE LAKE ERIE MARINA DISTRICT

ARTICLE LAKE ERIE MARINA DISTRICT Section 13.01 PURPOSE ARTICLE 13.00 LAKE ERIE MARINA DISTRICT A primary planning goal of Frenchtown Charter Township is to provide a balance and variety of land uses which are compatible to the community

More information

SOUTH BASIN FERRY TERMINAL DEVELOPMENT AND AGRICULTURE BUILDING RESTORATION FEASIBILITY STUDY

SOUTH BASIN FERRY TERMINAL DEVELOPMENT AND AGRICULTURE BUILDING RESTORATION FEASIBILITY STUDY SOUTH BASIN FERRY TERMINAL DEVELOPMENT AND AGRICULTURE BUILDING RESTORATION FEASIBILITY STUDY Prepared for the San Francisco Bay Area Water Transit Authority By ROMA Design Group FINAL REPORT September

More information

APC REPORT. TO: APC C Members File No: DP PL

APC REPORT. TO: APC C Members File No: DP PL APC REPORT TO: APC C Members File No: DP725-137 PL20180000028 FROM: Erica Hartling Development Services Assistant Date: March 16, 2018 SUBJECT: Electoral Area C: Development Permit 725-137 SHORT SUMMARY:

More information

Sewer Division of Public Works

Sewer Division of Public Works SEWER DIVISION OF PUBLIC WORKS The mission of the Sewer Division is to provide customers with high quality, cost effective, sanitary sewer services by collecting and treating all wastewater generated from

More information

KRISTOPHER J. KRZYSTON, CEI, CEM

KRISTOPHER J. KRZYSTON, CEI, CEM PERMITTING IN NEW JERSEY KRISTOPHER J. KRZYSTON, CEI, CEM Kristopher J. Krzyston Rutgers graduate 1994 B.S. Environmental Planning Certificate in G.I.S. Assistant Division Manager Environmental Science

More information

Pier 3 Upgrade Project

Pier 3 Upgrade Project AAPA Annual Convention & Expo November 2-4, 2015 Miami, FL Pier 3 Upgrade Project Stanley Ryter, PE, PMP Engineering Project Manager II Port of Tacoma Project Team Members Project Team Members Owner: Port

More information

REHABILITATION PACKAGE 4-a

REHABILITATION PACKAGE 4-a 4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.

More information

REPORT OF ROOF CONDITION STUDY. YOUR FACILITY Your Facilities Location. Date YOUR FACILITY S IDENTIFICATION. Prepared for Your Company

REPORT OF ROOF CONDITION STUDY. YOUR FACILITY Your Facilities Location. Date YOUR FACILITY S IDENTIFICATION. Prepared for Your Company REPORT OF ROOF CONDITION STUDY YOUR FACILITY Your Facilities Location YOUR FACILITY S IDENTIFICATION Date Prepared for Your Company 1114 Grindstone, Union, Kentucky 41091 (859) 657-6677 [Report Date] [Client]

More information

Exhibit #16. Additional SHO Recommendations June 13, 2011

Exhibit #16. Additional SHO Recommendations June 13, 2011 3 Critical Areas 25.01.070 Pages 7. Critical Areas Integration The Provisions of the Sammamish Critical Areas Ordinance codified in SMC 21A.50 exclusive of SMC 21A.50.050 (Complete exemptions), SMC 21A.50.060

More information

I. GENERAL INFORMATION

I. GENERAL INFORMATION STAFF REPORT DAROGA STATE PARK DOCKS & MOORAGE FLOATS REPLACEMENT TO: Douglas County Hearing Examiner FROM: Douglas County Land Services Staff RE:, SP-12-03 DATE: January 7,2013 I. GENERAL INFORMATION

More information

U.S. Army Corps of Engineers Regulatory Program Our Mission, Authority, Jurisdiction, and Permitting

U.S. Army Corps of Engineers Regulatory Program Our Mission, Authority, Jurisdiction, and Permitting U.S. Army Corps of Engineers Regulatory Program Our Mission, Authority, Jurisdiction, and Permitting Laban C. Lindley Team Leader Indianapolis Regulatory Office Louisville District January 9, 2018 US Army

More information

Step 1: Determine whether the action is located in a 100-year floodplain (or a 500-year floodplain for critical actions) or wetland.

Step 1: Determine whether the action is located in a 100-year floodplain (or a 500-year floodplain for critical actions) or wetland. EXECUTIVE ORDER 11988 FLOODPLAIN MANAGEMENT EXECUTIVE ORDER 11990 PROTECTION OF WETLANDS EIGHT-STEP PROCESS U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT COMMUNITY DEVELOPMENT BLOCK GRANT DISASTER RELIEF

More information

Dock Design Options. Engineered for Excellence DOCK DESIGN OPTIONS.

Dock Design Options. Engineered for Excellence DOCK DESIGN OPTIONS. Dock Design Options DOCK DESIGN OPTIONS Engineered for Excellence www.wahoodocks.com Design Options Overview Wahoo Docks custom builds more unique docks for more locations throughout the world than any

More information

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows:

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows: Segments 3, 4, 6 and 7 Pier Repairs Invitation for Bids (IFB) Project/Contract #C4962 Addendum # 1 November 30, 2018 To All Bidders: 1. Instructions to Bidders AIA Document A701, 1997 Section 5.3.1.3 of

More information

HISTORIC LANDMARK COMMISSION STAFF REPORT. TRACY AVIARY CONDOR EXHIBIT PLNHLC Liberty Park, 589 East 1300 South September 6, 2012.

HISTORIC LANDMARK COMMISSION STAFF REPORT. TRACY AVIARY CONDOR EXHIBIT PLNHLC Liberty Park, 589 East 1300 South September 6, 2012. HISTORIC LANDMARK COMMISSION STAFF REPORT TRACY AVIARY CONDOR EXHIBIT PLNHLC2012-00473 Liberty Park, 589 East 1300 South September 6, 2012 Planning and Zoning Division Department of Community and Economic

More information

Minimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS

Minimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS Minimum Standards for Construction of Aircraft Hangars ARTICLE 1. MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS Section 1. - Purpose Section 2. - Goals Section 3. General Provisions Section 4.

More information

DEPARTMENT OF PLANNING AND BUILDING STAFF REPORT TO CITY OF LAKE FOREST PARK HEARING EXAMINER

DEPARTMENT OF PLANNING AND BUILDING STAFF REPORT TO CITY OF LAKE FOREST PARK HEARING EXAMINER Exhibit 1.1 DEPARTMENT OF PLANNING AND BUILDING STAFF REPORT TO CITY OF LAKE FOREST PARK HEARING EXAMINER The following review by the City of Lake Forest Park Planning Department is based on information

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice No. CENAP-OP-R In Reply Refer to: REGULATORY BRANCH

THIS IS NOT A PAID ADVERTISEMENT. Public Notice No. CENAP-OP-R In Reply Refer to: REGULATORY BRANCH THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. CENAP-OP-R-2016-0160-24 Application No. In Reply Refer

More information

SWG Attachment A, Alternative Analysis Gulf Coast Ammonia, LLC 2/26/2018 Page 1 of 8

SWG Attachment A, Alternative Analysis Gulf Coast Ammonia, LLC 2/26/2018 Page 1 of 8 SWG-21-96 2/26/218 Page 1 of 8 The four criteria are: 1. Safety and navigability of incoming and outgoing vessel traffic with consideration to neighboring operations and infrastructure. 2. Federal, State,

More information

MARINA MAINTENANCE AND ANNUAL RESERVE PLANS ADOPTED:

MARINA MAINTENANCE AND ANNUAL RESERVE PLANS ADOPTED: MARINA MAINTENANCE AND ANNUAL RESERVE PLANS ADOPTED: 3-8-12 HARBOR POINTE MARINA FACILITY MAINTENANCE Maintenance is the cornerstone of facility safety and long-term survival. Maintenance monitoring shall

More information