1 SystemVision 2015 Contractor s Guide COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION

2 INTRODUCTION HISTORY North Carolina Housing Finance Agency Thanks to the NC Housing Finance Agency (NCHFA), Advanced Energy s partner in SystemVision, through which funding is available to select non-profit organizations to help defray the costs often associated with building highperformance homes. These nonprofits must become a Self Help or Community Home Loan Pool Member with NCHFA. For more information on how to become a member and reserve funds, contact Josh Burton, Sonia Joyner, or Donna Coleman at NCHFA at (919) About Advanced Energy Advanced Energy, a non-profit out of Raleigh, is committed to ensuring that every home in the nation is healthy, safe, durable, comfortable, energy efficient and environmentally responsible. Our staff of building science experts provides training and consultation services to a variety of clients in the building industry. SystemVision Home Status Builders and raters can view the status of their homes at SystemVision Guarantee Advanced Energy guarantees the heating and cooling energy consumption, and the comfort of the original homeowner for two years. The heating and cooling usage is calculated after a full year of occupancy by estimating the base load usage (e.g., TVs, appliances, water heating, lights, etc.) and subtracting the base load from the total energy used. If the home uses more energy for heating and cooling than the guarantee, Advanced Energy will reimburse the homeowner and initiate a diagnostic process to address the cause. The SystemVision guarantee gives the homeowner certain responsibilities. These responsibilities are laid out on the guarantee information sheet (see Resources), as well Questions regarding the guarantee can be submitted to systemvision@advancedenergy.org. SystemVision Guarantee Example kwh Total Annual Heating & Cooling Electricity Usage= 3842 kwh Total Annual Heating= 2691 kwh Total Annual Cooling= 1151 kwh Heating & Cooling JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Base Load Since 2001, SystemVision has been certifying new homes in North Carolina, guaranteeing their heating and cooling bills, and ensuring that the homes meet a high standard for comfort, durability, health, safety, energy efficiency and environmental responsibility. As of July 2015, SystemVision has guaranteed over 4,300 homes! COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 2

3 INTRODUCTION PROCESS Pre-Construction 1. NCHFA Loan Pool Application and Three-Party Contract 2. NCHFA Funding Reservation Request 3. Minimum of 3 weeks before starting to build, submit new floor plans, PRIF (see Resources) and HVAC load calc to systemvision@advancedenergy.org 4. Complete New Builder Orientation before first home 5. Begin Home Construction 6. Framing Check Submit completed Framing Checklist to rater and request inspection, if needed 7. Insulation Check Submit completed Insulation Checklist to rater and request inspection 8. Final Check Submit completed Final Checklist to rater and request inspection Submit AHRI Certificate and load calc to rater 9a. If someone other than Advanced Energy is your rater: Send completed checklists and inspection requests to the appropriate Follow agreed upon process for scheduling 9b. If Advanced Energy is your rater: Send completed checklists and inspection requests to svinspections@advancedenergy.org Contact Advanced Energy at least three business days before intended inspection date Advanced Energy will contact you within 24 hours Post-Construction 10. Sign up homeowner with ResiSpeak (see Resources) 11. Advanced Energy issues SystemVision Guarantee ed to loan pool member 12. Homeowner education on SystemVision guarantee 13. Advanced Energy issues invoice ed to loan pool member $1,050 per house for up to three inspections Re-inspections charged at $50 for fourth inspection, $150 per hour for additional re-inspections, not to exceed $ NCHFA Releases Funds to loan pool member COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 3

4 INTRODUCTION PROGRAM STANDARDS 1. Air Tightness 1.1. Tightness shall be less than or equal to 0.20 CFM50 per square foot of conditioned envelope area. 2. Moisture Management 2.1. Finished grade shall be sloped away from foundation walls or slab Slabs: Vapor retarder with 100% coverage, and overlapped seams, shall be installed under the slab Crawl Spaces: Shall be closed and have the following components: A sump pump or drain to daylight with a backflow preventer shall be located at the low point of the crawlspace All air leakage paths from the home to the crawlspace, and from the crawlspace to outside shall be air sealed Vapor Barrier Walls - vapor barrier shall be sealed, mechanically fastened, and run up walls to within 3 of mudsill Floors - vapor barrier shall be sealed at all seams, penetrations and to wall vapor barrier Drying Mechanism - A stand-alone dehumidifier or supply register with backflow preventer that provides 1 CFM/30SF of floor area Crawl spaces during construction shall have at least one of the following: (1) crawl space vents or (2) a vapor retarder covering the ground. 3. Framing and Insulation 3.1. Roof framing shall allow for 10" of vertical space from exterior of top-plate to roof sheathing Insulation shall be installed to manufacturer s specifications, with no gaps, voids, compression or wind intrusion. Insulation and the air barrier shall be installed in physical contact with each other Attic accesses shall be insulated to a minimum of R-30. This will require an insulated, air sealed and weather stripped box to be constructed for attic pull-down stairs Insulation levels shall, at minimum, equal those in the following table or meet the 2015 IECC Total UA alternative. CLIMATE ZONE CRAWLSPACE WALLS SLAB WALLS CEILING FLOORS 4. Heating, Air Conditioning, Zone 3 NA R-19 or R cont. R-38 R-19 R-5 cont. and Ventilation Zone 4 R-10 R-19 or R cont. R-49 R-19 R-10 cont Equipment Minimums Zone 5 R-10 R-21 or R cont. R-49 R-30 R-15 cont Furnaces/AC - 90% efficient, 14 SEER Heat Pumps - 14 SEER, 8.2 hspf 4.2. All duct connections shall be sealed with a UL listed bucket mastic product Duct leakage, measured in cubic feet per minute at 25 Pascals, shall not exceed 3% of the conditioned square footage Mechanical systems shall be sized to within 6,000 Btuh (or closest available size) of the whole home ACCA Manual J total load. ACCA Manual J room-by-room load calculations, including all inputs, shall be submitted for each plan to verify sizing. Physical copy of the load calculation with the AHRI certificate shall be attached to AHU unit or submitted to the rater prior to the final inspection Heat pumps shall have an outdoor thermostat installed to prevent supplementary heater operation when the heat pump is capable of meeting the load. The lockout shall be set to 35 F. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 4

5 INTRODUCTION PROGRAM STANDARDS 4.6. The measured airflow for each room shall be within ± 20% or 25 CFM of the ACCA Manual J calculation. This will require supply dampers to be installed for bedrooms and bathrooms Total system airflow shall be set between CFM per ton in cooling, or set to total system airflow as specified by the manufacturer Whole House Ventilation: There shall be a filtered whole-house mechanical fresh air ventilation system that is capable of meeting the current version of ASHRAE 62.2 that complies with one of the following options: Option 1: Identify Supply Ventilation - Air handler cannot have a PSC motor. System shall be designed to operate intermittently and automatically based on a timer (e.g., air cycler) and to restrict outdoor air intake when not in use (e.g., motorized damper). Ventilation at a minimum shall occur 10% of every 24 hours. Option 2: Balanced Ventilation 4.9. Spot Ventilation: All ventilation ducts shall terminate beyond the exterior skin of the building All bathrooms shall have a fan vented to the outside that exhausts 50 CFM intermittently (requires a min. fan rating of 70 CFM) All kitchens shall have a fan vented to the outside that exhausts 100 CFM (requires a min. fan rating of 120 CFM) All ventilation ducts, excluding kitchen exhaust ducts, shall be insulated. 5. Pressure Balancing 5.1. All rooms within the conditioned space, except baths and laundry, shall not exceed ± 3 Pascals pressure differential with respect to the main body when interior doors are closed and the air handler is operating. Returns, transfer grilles or jump ducts shall be used to balance each room in addition to door undercuts. 6. Plumbing 6.1. Electric water heaters shall have an energy factor (EF) of at least Gas water heaters shall have an EF of at least From the water heater, the first three feet of hot and cold pipes shall be insulated to R Toilets shall be 1.3 GPF or less (including dual-flush models). Showerheads shall be 2.25 GPM or less. Kitchen faucets shall be 2.2 GPM or less. Bath faucets shall be 1.5 GPM or less. 7. Appliances & Lighting 7.1. Dishwashers and refrigerators, if provided by the builder, shall be ENERGY STAR rated Home shall not have any incandescent lights. 8. Combustion Safety 8.1. Any combustion appliance inside the conditioned space, other than gas ranges and wood fireplaces, shall be direct vent or power-vented. Vent-free gas logs are not allowed One hard-wired carbon monoxide (CO) detector shall be installed per 1,000 sq. feet of living space in homes that have any combustion appliance within the conditioned space, or which have an attached garage (minimum one per floor). COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 5

6 FRAMING CHECKLIST Builder/Developer: Site Super: Framer Company: HVAC Contractor: Phone: Phone: Phone: House Address: City/State/Zip: Plan Name: Framing Checklist Requesting Field Inspection by Rater? Yes: No: YES NO N/A Q/A SLAB CRAWL FOUNDATION A vapor retarder with 100% coverage and overlapped seams is installed under all slabs. Slabs built in Climate Zones 4 and 5 are insulated to at least R-10. (vertical slab edge insulation) Crawl spaces are graded to a low point and have a sump pump or drain to daylight roughed in. Crawl spaces have at least one of the following during the framing inspection: Crawl space vents that will be sealed when construction is complete. A vapor retarder covering the ground. FRAMING Roof framing allows for 10" of vertical space from the exterior edge of the top plate to roof sheathing. Attic platforms are raised to a height that allows for the installation of the same insulation R-value used elsewhere in the attic. 7. If continuous rigid insulation is not used, all exterior wall studs are Transfer grills, jumper ducts, or individual room returns are roughed in. AIR SEALING Sill seal and/or caulk has been used to air seal bottom plates of exterior to the subfloor. All penetrations and cracks in the building shell are air sealed with foam, mastic or caulk. This includes, but is not limited to: holes for MEP, bands between floors, beam pockets, bottom plate to sheathing, top plate to sheathing. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 6

7 FRAMING CHECKLIST YES NO N/A Q/A 11. Rigid air barrier is installed and air sealed at all chases, behind all tubs and showers, and on the attic side of all knee walls. OTHER 12. All recessed lights are insulation contact (IC) rated and airtight All bath fans are rated to exhaust at least 70 CFM and point in the direction of the termination location. Request AHRI Certificate and ACCA Manual J room-by-room load calculation and confirm mechanical systems will be sized to within 6,000 Btuh (or closest available size) of whole home total load. Comments and Corrective Work Order Items: BUILDER CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 7

8 INSULATION CHECKLIST Builder/Developer: Site Super: Phone: House Address: City/State/Zip: Rater: Insulation contractor: Plan Name: Phone: Phone: YES NO N/A Q/A Insulation levels meet or exceed those in the following table: CLIMATE ZONE WALLS CEILING FLOORS CRAWLSPACE WALLS Zone 3 R-19 or R cont. R-38 R-19 R-5 cont. Zone 4 R-19 or R cont. R-49 R-19 R-10 cont. Zone 5 R-21 or R cont. R-49 R-30 R-15 cont. or have documentation that envelope meets 2015 IECC total UA Alternative. Insulation is installed to manufacturer s specifications, with no gaps, voids, compression, misalignment, or wind intrusion. All insulated walls (including knee walls, walls behind tubs, walls under stairs, and framed walls in crawl spaces) are framed with six rigid, air-tight sides. Wind baffles are installed along the perimeter of attic insulation, including vaulted and cathedral ceilings, and allow at least 8 in. of insulation to be installed over top plate. Sill seal is installed on the vertical face of all interior and exterior wall top plates. Exception: builder may use caulk, foam, or mastic to seal top plates to drywall from the attic side after drywall is installed. Windows and doors have backer-rod, caulk, or foam between the frame and rough opening. UL listed bucket mastic has been used to seal all connections (flex, collars, plenums, boots, and boxes) in the duct system (total duct leakage must be less then 3%). 8. Metal seams have been sealed with bucket mastic. 9. Rigid metal splicing collars have been used at all flex duct splices and have been sealed with bucket mastic. 10. Fresh air ventilation is filtered. The filter will be easily accessible. 11. Dampers have been installed in all supply ducts and bedroom return ducts. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 8

9 INSULATION CHECKLIST YES NO N/A Q/A 12. Ventilation ducts do not have turns or bends greater than Ventilation ducts terminate beyond the exterior skin of the home. 14. All ventilation ducts, excluding kitchen exhaust ducts, are insulated. 15. Transfer grills, jumper ducts, or individual room returns are installed for pressure balancing in all bedrooms. Comments and Corrective Work Order Items: BUILDER CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 9

10 INSULATION INFORMATION SHEET: NC CLIMATE ZONES Insulation is installed to meet SystemVision R-value Requirements a. CLIMATE ZONE CEILING FRAME WALL FLOOR CRAWL SPACE WALL SLAB Zone 3 R-38 R-19 or R-15+3 R-19 R-5 N/A Zone 4 R-49 R-19 or R-15+3 R-19 R-10 R-10 Zone 5 R-49 R-21 or R-15+5 b R-30 c R-15 R-10 Winston-Salem Greensboro Durham Asheville Statesville Asheboro Raleigh Wilson Greenville Charlotte New Bern a. R-Values are minimums. b. R-13+R-5 means R-13 cavity insulation plus R-5 insulated sheathing. If structural sheathing covers 25 percent or less of the exterior, insulated sheathing is not required where structural sheathing is used. If structural sheathing covers more than 25 percent of the exterior, structural sheathing shall be supplemented with insulation sheathing of at least R-2. c. Sufficient insulation to fill the cavity, R-19 minimum. Wilmington COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 10

11 INSULATION TECH TIPS Insulation is installed to fill the cavity between conditioned and unconditioned space without gaps, voids, misalignments or compression. INCORRECT CORRECT INCORRECT CORRECT INCORRECT CORRECT COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 11

12 INSULATION INFORMATION SHEETS: WIND BAFFLE INSTALLTION 1" min. 1" min. 8" minimum of insulation Air sealing at seams & joints, typical INCORRECT CORRECT COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 12

13 FINAL CHECKLIST Builder/Developer: Site Super: Phone: House Address: City/State/Zip: Rater: Plan Name: Phone: YES NO N/A Q/A All penetrations in ceiling drywall (for lighting, ceiling fans, bath fans, etc.) are sealed with caulk or foam. Attic hatches are weather stripped and have at least R-30 insulation attached. This will require an insulated, air sealed and weather stripped box to be constructed for attic pull-down stairs. Electric water heaters have an energy factor (EF) of at least Gas water heaters have an EF of at least The first three feet of hot and cold pipes from the water heater are insulated to at least R-4. Plumbing fixtures do not exceed the maximum flow rates listed in the following table: 5. FIXTURE TOILETS (dual-flush models) SHOWER- HEADS KITCHEN FAUCETS BATHROOM FAUCETS Flow Rate 1.3 GPF (1.1 & 1.6 GPF) 2.25 GPM 2.2 GPM 1.5 GPM 6. Dishwashers and refrigerators, if provided by the builder, are ENERGY STAR rated. 7. No incandescent lights have been installed in the home. 8. All kitchens have a fan vented to the outside and exhaust 100 CFM. 9. All baths have fans vented to outside and exhaust 50 CFM. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 13

14 FINAL CHECKLIST YES NO N/A Q/A CRAWL GAS Crawl space foundation A sump pump or drain to daylight with a backflow preventer is located at the low point of the crawl space. All penetrations in crawl space walls are sealed with caulk or foam. Vapor barrier is sealed, mechanically fastened to walls (not taped), and extends up all walls and piers to within 3" of the mudsill or floor joist. Vapor barrier completely covers the ground and is sealed to the wall vapor barrier and also at all seams and penetrations. There is either a standalone dehumidifier or a supply register with a backflow preventer that provides at least 1 CFM per 30 ft 2 of floor area The crawl space access door is weather stripped and insulated to the same value as the crawl space wall. AHRI and load calculation are submitted to rater or are attached to air handing unit. HVAC checklist has been reviewed with HVAC contractor or completed by HVAC contractor. Combustion devices or an attached garage: All combustion devices inside the conditioned space, other than gas ranges and wood fireplaces, are direct vent or power-vented. One hard-wired carbon monoxide (CO) detector is installed per 1,000 ft 2 of living space, with a minimum of one per floor Caulk or mastic has been used to seal all supply boots, return boxes, and bath fans to their rough openings. Heat pumps have an outdoor thermostat installed that prevents auxiliary heater operation when temperature is above 35 F. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 14

15 FINAL CHECKLIST Airtightness and Pressurization Ventilation Flows House Airtightness: CFM50 Kitchen: CFM Duct Airtightness: CFM25 Bath 1: CFM Pressure Balanced: Bath 2: CFM Window Structure: Bath 3: CFM U-Value: Outside Air Flow: CFM SHGC Vaule: Mechanicals and Appliances AHU/Indoor Coil Make: AHU Model #: Make: Model: Location: Efficiency: Water Heater EF Make: Model: AC/Outdoor Coil Location: R-Value: Ductwork Outdoor thermostat setting (this applies to heat pump systems only) This house has no incandescent light bulbs. If provided by the builder, the dishwasher and refrigerator are ENERGY STAR appliances. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 15

16 FINAL CHECKLIST Comments and Corrective Work Order Items: BUILDER CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 16

17 FINAL CRAWL SPACE All Penetrations in Floor Air Sealed 3" Termite Inspection Gap All Penetrations in Wall Air Sealed Floor liner overlaps wall liner and is sealed HVAC Unit Supply Air at 1 CFM/30 SF or Dehumidifer Weather- Stripped Door Sealed Wall/Floor Liner Sump or Drain to Daylight COMPONENT Floor Liner Wall Liner Sump Pump/Drain to Daylight Supply Air/Dehumidifier Air/Pest Sealing Insulation DESCRIPTION/PURPOSE The floor liner is a sealed vapor retarder that covers 100% of the crawl space floor. The floor liner retards moisture from the crawl space floor from entering the crawl space. The floor liner overlaps wall liner and is sealed. The wall liner runs from under the floor liner up the masonry walls to 3" below the mudsill where it is mechanically fastened and sealed to the wall. The wall liner retards moisture from the masonry walls from entering the crawl space. The sump pump/drain is located at the low point of the crawl space. The purpose of the sump pump/drain is to: 1. help rid water from under the floor liner 2. remove water that may accidentally accumulate on top of the floor liner from bulk water issues. The drying mechanism maintains an appropriate level of humidity (typically below 70% RH) in the crawl space to prevent moisture related problems. All holes in the crawl space walls, band joists, and floor system above the crawl space are sealed with an appropriate sealant. Sealing is done to isolate the crawl space from the outside and conditioned space. In addition to isolating the space the sealing also can effectively limit the intrusion of pests into crawl space. The insulation for the closed crawl space can be located on the crawl space walls or in the floor system above the crawl space. When the crawl space walls are insulated there must be 3" of exposed masonry below the mudsill and the band joists of the crawl space must be insulated. The insulation helps complete the thermal envelope of the home and retard heat transfer into or out of the structure. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 17

18 HVAC: DESIGN CHECKLIST HVAC Contactor: HVAC Contact: Phone: House Address: City/State/Zip: Rater: Plan Name: Phone: YES NO N/A Q/A DESIGN HVAC equipment meets or exceeds the following minimum efficiencies: Heat pumps: 14 SEER, 8.2 HSPF. Furnaces with A/C: 90% efficient, 14 SEER. An ACCA Manual J room-by-room load calculation, including all inputs, is submitted to Advanced Energy systemvision@advancedenergy.org prior to installation. Mechanical systems are sized to within 6,000 Btuh (or closest available size) of the whole home ACCA Manual J total load. Note: If multiple systems are to be installed, minisplits will be necessary. A filtered whole-house mechanical fresh air ventilation system capable of meeting the current version of ASHRAE 62.2 is installed that complies with one of the following options: OPTION 1: Supply Ventilation - Air handler cannot have a PSC motor. System shall be designed to operate intermittently and automatically based on a timer (e.g., air cycler) and to restrict outdoor air intake when not in use (e.g., motorized damper). Ventilation at a minimum shall occur 10% of every 24 hours. OPTION 2: Balanced Ventilation HVAC CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 18

19 HVAC: ROUGH-IN CHECKLIST HVAC Contactor: HVAC Contact: Phone: House Address: City/State/Zip: Rater: Plan Name: Phone: YES NO N/A Q/A ROUGH-IN 1. UL listed bucket mastic has been used to seal all connections (flex, collars, plenums, boots, and boxes) in the duct system (total duct leakage must be less then 3%). 2. Metal seams have been sealed with bucket mastic. 3. Rigid metal splicing collars have been used at all flex duct splices and have been sealed with bucket mastic. 4. Fresh air ventilation is filtered. The filter will be easily accessible. 5. Dampers have been installed in all supply ducts and bedroom return ducts. 6. Ventilation ducts do not have turns or bends greater than Ventilation ducts terminate beyond the exterior skin of the home. 8. All ventilation ducts, excluding kitchen exhaust ducts, are insulated. 9. Transfer grills, jumper ducts, or individual room returns are installed for pressure balancing in all bedrooms. HVAC CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 19

20 HVAC: FINAL CHECKLIST HVAC Contactor: HVAC Contact: Phone: House Address: City/State/Zip: Rater: Plan Name: Phone: FINAL Caulk or mastic has been used to seal all supply boots, return boxes, and bath fans to their rough openings. Heat pumps have an outdoor thermostat installed that prevents auxiliary heater operation when temperature is above 35 F. Total system airflow is set between CFM per ton of cooling capacity, or set to total system airflow as specified by the manufacturer. Airflow for each room is within 20% or 25 CFM of the ACCA Manual J calculation. Physical copy of the room-by-room ACCA Manual J and matching AHRI certificate is attached to AHU or submitted to builder before the final inspection. YES NO N/A Q/A HVAC CERTIFICATION Name: Company: Signature: Date: RATER CERTIFICATION Name: Company: Signature: Date: COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 20

21 HVAC STANDARDS + SPECIFICATIONS: Equipment Sizing and Selection Heat pumps and air conditioners, if used, must be sized according to ACCA Manual J and be installed within a ½ ton of that size. A room-by-room Manual J load calculation must be completed for each floor plan (not for each house). Please indicate on the Plan Review Input Form (PRIF) who will be responsible for the load calculation - either the HVAC contractor or Advanced Energy. HVAC contractors should refer to the Load Calculation Input Form in this section and the appendices for a list of required reports and inputs. If you elect Advanced Energy to complete this load calculation, the fee is $0.15 per square foot. Heat pumps and air conditioners shall have a minimum seasonal energy efficiency ratio (SEER) rating of 14 and a heating season performance factor (HSPF) of at least 8.2. Furnaces shall be 90% efficient and their cooling systems shall have a minimum SEER rating of 13. Air Distribution All joints in the air distribution system shall be sealed with bucket duct mastic and fiberglass mesh. Total duct leakage measured in CFM at 25 Pascals (with reference to the outside) shall be less than 3% of the conditioned floor area (i.e., if the house has 1,000 sq. ft. of conditioned space, there shall be no more than 30 CFM of duct leakage when tested). Tested airflow must be within ± 20% or 25 CFM of the designed airflow in each room. The HVAC contractor is responsible for balancing the system at start-up. Mechanical Equipment Installation Heat pumps must include an outdoor thermostat connected to lock out the heat strips above 35 F. Inert gas (nitrogen) shall be used during any brazing and soldering of refrigerant lines. Condensation drain shall be installed to meet local codes and manufacturer s specifications. Airflow volume across the indoor coil and heat exchanger shall meet manufacturer s specifications of CFM. Indoor and outdoor units must be matched according to the AHRI Directory or the manufacturer s listing. Correct charge must be installed per manufacturer s specifications. Bucket Mastic must be used to seal ducts Load Calculations Template If you would like a WrightSoft SystemVision template for your climate zone, please systemvision@advancedenergy.org to request one. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 21

22 HVAC STANDARDS + SPECIFICATIONS: Ventilation and Moisture Management Bathroom: Each bathroom must have an exhaust fan that exhausts a minimum of 50 CFM directly to the outside. This is the measured flow as installed, not the rated flow. Kitchen: Each kitchen must have a range hood or exhaust fan that exhausts a minimum of 100 CFM directly to outside. This is the measured flow as installed, not the rated flow. The kitchen exhaust must be hard ducted to the outside with a back-draft damper installed. Recirculating range hoods are not acceptable. Typically the 120 CFM models will be adequate to provide 100 CFM of flow. The quieter the hood, the better; homeowners will often not use them if they are too noisy. Outside Air: There must be a mechanical fresh air ventilation system that Is capable of meeting ASHRAE 62.2: Supply ventilation or balanced ventilation are the only allowable mechanical fresh air systems. Ventilation systems must operate a minimum of 10% of every 24 hours. If supply ventilation is used the system must have a mechanical damper, a filter that is accessible, and an aircycler. Outside air intakes must be installed at least 18 in. above finished grade or 12 in. above the roof deck. They must also be at least 10 ft. from plumbing vents, chimneys, combustion appliance vents, dryer vent terminations and exhaust fan terminations. All ventilation ducts in unconditioned spaces must be insulated. Closed Crawl Spaces Closed crawl spaces shall have a strategy for humidity control. One approved method is to deliver supply air (1 CFM per 30 sq. ft. of crawl space floor area). The HVAC contractor should coordinate with the builder about the drying strategy. When supply air is used as a drying strategy, the supply duct shall have both a backflow damper and a manual damper. The backflow damper is installed to prevent entry of crawl space air into the supply system when the system is not operating. The manual damper is installed to adjust the amount of airflow into the crawl space. Pressure Balancing and Return Air Paths No pressure with a magnitude greater than 3.0 Pascals with reference to the main body may exist in any bedroom. Some form of pressure relief in addition to ¾ in. door undercuts is required between each bedroom and the main body of the house. Examples of pressure relief strategies include dedicated returns, jump-over ducts and transfer grilles. Combustion Safety Any gas appliance, other than gas ranges, located inside of the conditioned space must be direct or power-vented. One hard-wired carbon monoxide (CO) detector shall be installed per 1,000 sq. ft. of living space (minimum 1 per floor) in houses that have any combustion appliance within the conditioned space or an attached garage. The following are strongly recommended: Ducts should not touch any exterior walls. All flexible ductwork should not be compressed more than the thickness of the insulation. All flexible ductwork should be supported at least every 4 ft. and have no bends greater than 90 degrees. Tools for ASHRAE 62.2 RiteVent App (Free on Apple Store) RED Tool redcalcfree/tools/ashrae COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 22

23 HVAC CRITICAL DETAIL: BATH EXHAUST FAN ORIENTATION Orient the fan outlet so the duct will have the shortest and straightest route to the outside of the building. Bath Exhaust Fan: Introduction Each bathroom that has an exhaust fan must exhaust a minimum of 20 CFM continuously or 50 CFM intermittently directly to the outside. DAMPER Bath fans must have backdraft damper to keep outside air from entering the bathroom. Remove shipping tape from the damper and ensure it swings freely. SEALING Caulk all of the holes between the drywall and the fan housing unit as well as all holes in the housing unit. RATING Ensure that your bath fan will pull a minimum of 50 CFM once it is installed. Install a fan rated for 70 CFM. COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 23

24 HVAC CRITICAL DETAIL: PRESSURE BALANCING TRANSFER GRILLE Small pressure differentials between the interior and exterior of a house, or between spaces within the house, can have a significant impact on human health and safety and on the durability of the building. For all rooms within the conditioned space except baths and laundry include properly sized returns, transfer grilles, or jump ducts. TRANSFER GRILLE Check the chart below for the size transfer grille needed, depending on the air supplied to the room or suite in question. If there is more than one supply in the room or suite in question, remember to add all of the supply flows and size the transfer grille on that total. Always go up a size in transfer grille if you find that the chart leaves you between regular sizes. Sizing chart for transfer grilles: JUMPER DUCT Room/Suite supply air flow (CFM) Net free area required (in2) Area required after door undercut (in2) Transfer grille height required for listed width in inches Jump Duct Diameter Required (in) 10" 12" 14" Assuming ¾" door undercut and net free area as 0.75 of total grille area. JUMPER DUCT COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 24

25 HVAC CRITICAL DETAIL: BOOT DUCT SEALING MASTIC BOOT INSTALL ZIP TIE INSTALL LINER MASTIC CONNECTION Duct Sealing Requirements: All joints in the air distribution system shall be sealed with bucket duct mastic and fiberglass mesh. Total duct leakage measured in CFM at 25 Pascals (with reference to the outside) shall be less than 3 percent of the conditioned floor area (i.e., if the house has 1,000 sq. ft. of conditioned space, there shall be no more than 30 CFM of duct leakage when tested). INSULATE BOOT SEAL SEAMS SEAL TO SUBFLOOR SEAL TO DRYWALL COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED CONTRACTOR S GUIDE VERSION PAGE 25

26 HVAC CRITICAL DETAIL: PLENUM DUCT SEALING MASTIC PLENUM INSTALL ZIP TIE MASTIC COLLAR MASTIC CONNECTION Duct Sealing Requirements: All joints in the air distribution system shall be sealed with bucket duct mastic and fiberglass mesh. Total duct leakage measured in CFM at 25 Pascals (with reference to the outside) shall be less than 3 percent of the conditioned floor area (i.e., if the house has 1,000 sq. ft. of conditioned space, there shall be no more than 30 CFM of duct leakage when tested). INSULATE COLLAR SEAL SEAMS MASTIC PLENUM TO AHU USE BUCKET MASTIC COPYRIGHT 2016 COPYRIGHT ADVANCED 2016 ENERGY. ADVANCED ALL ENERGY. RIGHTS RESERVED ALL RIGHTS VERSION RESERVED CONTRACTOR S PAGE 26 GUIDE VERSION PAGE 26

27 NOTES COPYRIGHT 2016 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 27

28 RESOURCES You can find resources to support your work in the SystemVision New Construction Program Some of the support materials on our site include: Program Standards SystemVision Process New Builder Orientation Checklist Plan and Load Review Input Form (PRIF) How-To Guide for Scheduling Inspections Framing, Insulation, and Final Checklists Homeowner Guarantee ResiSpeak Instructions (SV energy bill data collection tool) High-Bill Inquiry Instructions Training Videos Technical Tip Information Sheets Frequently Asked Questions (FAQs) Marketing Materials If you would like to make a request for additional online resources, the SystemVision team at systemvision@advancedenergy.org Advanced Energy Capability Drive, Ste Raleigh, NC THE MATERIAL CONTAINED IN THIS DOCUMENT IS PREPARED BY ADVANCED ENERGY, A NONPROFIT CORPORATION. NEITHER ADVANCED ENERGY, ITS MEMBER ORGANIZATIONS, THE ACKNOWLEDGED INDIVIDUALS, NOR ANY PERSON ACTING ON BEHALF OF THEM: (A) MAKES ANY WARRANTY, EXPRESSED OR IMPLIED, WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, OR PROCESS DISCLOSED IN THIS PUBLICATION THAT SUCH USE MAY NOT INFRINGE PRIVATELY OWNED RIGHTS; OR (B) ASSUMES ANY LIABILITY WITH RESPECT TO THE USE OF, OR FOR DIRECT OR CONSEQUENTIAL DAMAGES RESULTING FROM THE USE OF, ANY INFORMATION, APPARATUS, METHOD, OR PROCESS DISCLOSED IN THIS PUBLICATION; OR (C) HAS ANY LIABILITY FOR ANY DAMAGES THAT RESULT FROM ANY NEGLIGENT ACT OR OMISSION INVOLVED IN THE PREPARATION OF THE MATERIAL. ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR USE IS SPECIFICALLY EXCLUDED.

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over

More information

A Closer Look Inspection Service 2015 IECC Residential DFW area handout

A Closer Look Inspection Service 2015 IECC Residential DFW area handout 103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

Standards for Jackson EMC s Right Choice Program Revised: June 2011

Standards for Jackson EMC s Right Choice Program Revised: June 2011 Standards for Jackson EMC s Right Choice Program Revised: June 2011 All homes in the program must meet the requirements of the Georgia Energy Code, which is the International Energy Conservation Code (IECC)

More information

Town of Farragut RESIDENTIAL CONSTRUCTION ENERGY EFFICIENCY. LAST UPDATE: July 03, 2014

Town of Farragut RESIDENTIAL CONSTRUCTION ENERGY EFFICIENCY. LAST UPDATE: July 03, 2014 Town of Farragut RESIDENTIAL CONSTRUCTION ENERGY EFFICIENCY LAST UPDATE: July 03, 2014 TABLE OF CONTENTS Front Cover Sheet Page 1 Table of Contents Page 2 Applying for a Gas/Mechanical Permit Page 2 Important

More information

Table Air Barrier and Insulation Inspection Component Criteria

Table Air Barrier and Insulation Inspection Component Criteria Table 40.4. Air Barrier and Insulation Inspection Component Criteria NUMBER COMPONENT CRITERIA Air barrier and thermal barrier Exterior thermal envelope insulation for framed walls is installed in substantial

More information

Success with 2009 IECC in Arkansas Tech Tips for Builders HVAC INSTALLATION

Success with 2009 IECC in Arkansas Tech Tips for Builders HVAC INSTALLATION Success with 2009 IECC in Arkansas Tech Tips for Builders TECH TIPS: 1. Seal all duct work to drywall and/or subfloor and all HVAC penetrations in the building envelope with foam, caulk or mastic. Use

More information

Town/City: State: Zip: Town/City: State: Zip: Phone: Cell: Phone: Cell:

Town/City: State: Zip: Town/City: State: Zip: Phone: Cell: Phone: Cell: Town of Durham, N.H. Residential Energy Code Application for 2012 IECC Code for Certification of Compliance for New Construction, Additions and/or Renovations (EC-1A Form) Minimum Provisions Effective

More information

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016 CHEBOYGAN COUNTY DEPARTMENT OF BUILDING SAFETY 870 South Main Street P.O. Box 70 Cheboygan, Michigan 49721 Phone: (231) 627-8813 Fax: (231) 627-8454 www.cheboygancounty.net 2015 MICHIGAN UNIFORM ENERGY

More information

Charter Township of Washington

Charter Township of Washington Charter Township of Washington Building Department 57900 V an Dyke Washington, MI. 48094 Phone:(586) 786-0010 Ext. 211 Fax: 586-752-6463 2015 Michigan Residential Code Energy Worksheet for New Single-family

More information

Boulder City NV Prepared by (Print Name) Signature Date

Boulder City NV Prepared by (Print Name) Signature Date City of Boulder City Community Development Department Building & Safety Division 401 California Avenue Boulder City, NV 89005-2600 702-293-9282 (Main Line) 702-293-9392 (Fax) 2009 International Energy

More information

SUSTAINABLE ENERGY ANALYTICS

SUSTAINABLE ENERGY ANALYTICS SUSTAINABLE ENERGY ANALYTICS Mandatory Requirements Mandatory Documents Duct Test Report 403.3.3 Must be from a certified HERS Rater or BPI Agent Fresh Air Ventilation Documentation 403.6 Must be from

More information

General Contractor: Company Name: Location of Proposed Structure: Tax Map #: Lot #:

General Contractor: Company Name: Location of Proposed Structure: Tax Map #: Lot #: New Hampshire Residential Energy Code Application Town of Sutton for Certification of Compliance for New Construction, Additions and/or Renovations to be submitted with completed building permit (EC-1

More information

2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building

2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building 2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building Building Department 52700 Van Dyke, Shelby Township, MI 48316 Phone (586) 731-5969 Fax (586) 803-2099 building@shelbytwp.org

More information

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders insulation Copyright 2014 Advanced Energy. All Rights Reserved TEch Tips: 1. Install insulation to meet the 2012

More information

2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building

2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building 2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building Building Department 52700 Van Dyke, Shelby Township, MI 48316 Phone (586) 731-5969 Fax (586) 803-2099 building@shelbytwp.org

More information

Hardin County Planning and Development Commission

Hardin County Planning and Development Commission Location by Climate Zone: Hardin County (per Table N1101.2), and the entire state of Kentucky is located in Climate Zone 4, the HDD is 4000 to 4999. Building Requirements; Building Thermal Envelope The

More information

A.ENVELOPE AIR SEALING

A.ENVELOPE AIR SEALING (Page 1 of 4) Note: The Energy Efficiency Standards Section 110.7 requires that all joints, penetrations and other openings in the building envelope that are potential sources of air leakage shall be caulked,

More information

Success with 2009 IECC in Georgia: Tech Tips for Builders. Insulation. Copyright 2014 Advanced Energy. All Rights Reserved

Success with 2009 IECC in Georgia: Tech Tips for Builders. Insulation. Copyright 2014 Advanced Energy. All Rights Reserved Success with 2009 IECC in Georgia: Tech Tips for Builders Copyright 2014 Advanced Energy. All Rights Reserved 1. For vented attics, install wind baffles on top of all exterior walls, leaving room for at

More information

Air Sealing for 5 ACH 50

Air Sealing for 5 ACH 50 November 13th, 2018 Christopher Hine Air Sealing for 5 ACH 50 www.phrc.psu.edu Provider # 60114115 PPP ID: 1562 November 13th, 2018 Christopher Hine Air Sealing for 5 ACH 50 www.phrc.psu.edu Provider #

More information

Presented by: Stephen Carr Regional Building Science Manager (386)

Presented by: Stephen Carr Regional Building Science Manager (386) Presented by: Stephen Carr Regional Building Science Manager (386) 846-9155 stephen.carr@topbuild.com Understanding the Energy Code 2015 IECC CZ 1 CZ 2 CZ 3 CZ 4 CZ 5 CZ 6 CZ 7&8 Ceiling 30 38 38 49 49

More information

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process NC Energy Code Requirements ENERGY STAR and NC Energy Code in Alignment RESNET Standards HERS Index A scoring

More information

PREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and

PREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and PREP + INSULATION HOME ENERGY UPGRADES What every contractor needs to know. Copyright 2012 Advanced Energy. All Rights Reserved 103 HOME ENERGY UPGRADES Prep + Insulation Contents Air sealing is a challenging

More information

THE GEORGIA ENERGY CODE: 2009 IECC + AMENDMENTS

THE GEORGIA ENERGY CODE: 2009 IECC + AMENDMENTS THE GEORGIA ENERGY CODE: 2009 IECC + AMENDMENTS For the Georgia Association of Home Inspectors Bourke Reeve ABOUT SOUTHFACE 1 EARTHCRAFT Regional Green Building Program HISTORY OF ENERGY CODES MEC 1992,

More information

FIELD COPY ATTACHMENT

FIELD COPY ATTACHMENT FIELD COPY ATTACHMENT The released plans for the project must be on site and available to the inspectors at all times. No inspection will be done without the released field plans. If you have any questions,

More information

2009 IECC with St Louis Amendments. Fenestration U-factor Skylight U-factor Glazed fenestration SHGC NR 0.

2009 IECC with St Louis Amendments. Fenestration U-factor Skylight U-factor Glazed fenestration SHGC NR 0. Comparison Between Residential 2009 IECC with St Louis amendments, the 2015 IECC, and 2015 IECC w/ Building Codes Review Committee (BCRC) proposals: Climate Zone 4 Note: This document does not contain

More information

Project Type: New Home Addition Alteration (Describe)

Project Type: New Home Addition Alteration (Describe) MICHIGAN ENERGY CODE WORKSHEET City of Mt. Pleasant - Building Safety Department 320 W. Broadway Street, Mt. Pleasant, MI 48858 (989) 779-5347 www.mt-pleasant.org Effective September 20, 2017, all NEW

More information

2015 Michigan Residential Code Energy Worksheet for Single-family Additions, Alterations, Renovations and Repairs

2015 Michigan Residential Code Energy Worksheet for Single-family Additions, Alterations, Renovations and Repairs 2015 Michigan Residential Code Energy Worksheet for Single-family Additions, Alterations, Renovations and Repairs Building Department 52700 Van Dyke, Shelby Township, MI 48316 Phone (586) 731-5969 Fax

More information

IRC 2012 Key Changes

IRC 2012 Key Changes IRC 2012 Key Changes Overview of changes between the 2009 and 2012 IRC A Webinar Provided by The Pennsylvania Housing Research Center November 4, 2011 Presented by Mike Turns; Associate Director, PHRC

More information

Town/City: State: Zip: Town/City: State: Zip: Phone: Cell: Phone: Cell:

Town/City: State: Zip: Town/City: State: Zip: Phone: Cell: Phone: Cell: New Hampshire Residential Energy Code Application for Certification of Compliance for New Construction, Additions and/or Renovations (EC-1 Form) Minimum Provisions Effective Date: April 1, 2010 Owner/Owner

More information

INSULATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings

INSULATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings SUCCESS WITH 2012 IECC DELAWARE Recommended Practices for Optimized Energy Savings for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION 2015.1.0 DELAWARE For vented attics,

More information

Work Order (Bid Form) Upper East Tennessee Human Development Agency, Inc.

Work Order (Bid Form) Upper East Tennessee Human Development Agency, Inc. Upper East Tennessee Human Development Agency, Inc. WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10214 CLIENT INFORMATION Address: Bluff City, TN 37618 AGENCY INFORMATION Agency:

More information

Plan Check & Field Inspection Guide

Plan Check & Field Inspection Guide Plan Check & Field Inspection Guide 1992 MEC, 1993 MEC, and 1995 MEC Inside This Guide Plan Check Field Inspection Plan Check Building plans and specifications must be submitted with each building application

More information

ENERGY STAR Qualified Homes National Program Requirements, Version 3.0

ENERGY STAR Qualified Homes National Program Requirements, Version 3.0 Qualifying Homes The following homes are eligible to earn the ENERGY STAR: Single-family homes; Units in multi-family buildings that are three stories or less; Units in multi-family buildings that are

More information

Indoor Air Quality and Mechanical Ventilation (Page 1 of 5)

Indoor Air Quality and Mechanical Ventilation (Page 1 of 5) Indoor Air Quality and Mechanical Ventilation (Page 1 of 5) Title 24, Part 6, Section 150.0(o) Ventilation for Indoor Air Quality. All dwelling units shall meet the requirements of ANSI/ASHRAE Standard62.2.

More information

Fenestration Components: Mechanical Summary. Water heater energy factor: Ef Fuel type: Gas Electric Other

Fenestration Components: Mechanical Summary. Water heater energy factor: Ef Fuel type: Gas Electric Other This information must be on the drawing documents not attached to plans. The following Compliance statements must be on the drawings: 2009 International Energy Conservation Code Statement of acknowledgement

More information

About Southface. Southface promotes sustainable homes, workplaces and communities through education, research, advocacy and technical assistance.

About Southface. Southface promotes sustainable homes, workplaces and communities through education, research, advocacy and technical assistance. About Southface Southface promotes sustainable homes, workplaces and communities through education, research, advocacy and technical assistance. 1 Photo: Jonathan Hillyer, 2009 2 Green Building Services

More information

Energy Provisions of the Residential Building Code IECC: Guide for Homeowners

Energy Provisions of the Residential Building Code IECC: Guide for Homeowners Energy Provisions of the Residential Building Code 2009 IECC: Guide for Homeowners Missouri Energy Code Guide If you are interested in buying a home or want to learn about the energy code and how to make

More information

A Rater s perspective from the field. Thomas H. Marston, February 21, 2007

A Rater s perspective from the field. Thomas H. Marston, February 21, 2007 A Rater s perspective from the field Thomas H. Marston, February 21, 2007 The checklist looks at the thermal envelope - the place where air sealing and insulation meet. Each of the items addresses a potential

More information

Work Order (Bid Form) Upper East Tennessee Human Development Agency

Work Order (Bid Form) Upper East Tennessee Human Development Agency Upper East Tennessee Human Development Agency WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10620 CLIENT INFORMATION Address: FALL BRANCH, TN 37656 AGENCY INFORMATION Agency:

More information

Residential Data Collection Checklist 2009 International Energy Conservation Code Climate Zone 2

Residential Data Collection Checklist 2009 International Energy Conservation Code Climate Zone 2 Residential Data Collection Checklist 2009 International Energy Conservation Code Climate Zone 2 Building Name & Address: Subdivision: Lot #: Conditioned Floor Area: ft 2 State: County: Jurisdiction: Building

More information

Michigan Energy Code Training and Implementation Program

Michigan Energy Code Training and Implementation Program Michigan Energy Code Training and Implementation Program 1.0 Hour Advanced Program Course Number 16201 Residential Energy Air Sealing School of Planning, Design & Construction Michigan State University

More information

Homes Across Nebraska Are Being Built to the Latest National Energy Standards Is Yours?

Homes Across Nebraska Are Being Built to the Latest National Energy Standards Is Yours? Homes Across Nebraska Are Being Built to the Latest National Energy Standards Is Yours? A home buyer s guide to the energy efficiency requirements of the 2012 International Energy Conservation Code Nebraska

More information

Measure 1 Seal Ducts Components Inspected

Measure 1 Seal Ducts Components Inspected WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 1000049 CLIENT INFORMATION Client ID: 1002275 AGENCY INFORMATION Agency: Upper East Tennessee Human Development Agency Address: 301 Louis

More information

THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012

THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012 THE CITY OF FAYETTEVILLE ADOPTED THE 2009 INTERNATIONAL ENERGY CONSERVATION CODE (IECC) ON JULY 17, 2012 Compliance with the code for new residential construction, additions, and substantial remodels will

More information

Initial House Assessments & Sealing Options:

Initial House Assessments & Sealing Options: Initial House Assessments & Sealing Options: July 2017 Dave Bohac, PE Center for Energy and Environment Ed VonThoma Building Knowledge Initial House Assessments and Sealing Options Contents Summary...

More information

Appendix RA Air Sealing and Insulation Key Points COMPONENT AIR BARRIER CRITERIA INSULATION INSTALLATION CRITERIA

Appendix RA Air Sealing and Insulation Key Points COMPONENT AIR BARRIER CRITERIA INSULATION INSTALLATION CRITERIA Air Sealing and Insulation Key Points COMPONENT AIR BARRIER CRITERIA INSULATION INSTALLATION CRITERIA 1 General requirements A continuous air barrier shall be installed in the building envelope. The exterior

More information

Project Name: Enforcement Agency: Permit Number:

Project Name: Enforcement Agency: Permit Number: Installation (Page 1 of 4) If more than one person has responsibility for installation of the items on this certificate, each person shall prepare and sign a certificate applicable to the portion of construction

More information

Work Order (Bid Form) Upper East Tennessee Human Development Agency

Work Order (Bid Form) Upper East Tennessee Human Development Agency Upper East Tennessee Human Development Agency WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10248 CLIENT INFORMATION Address: KINGSPORT, TN 37664 AGENCY INFORMATION Agency:

More information

SAN MIGUEL COUNTY & TOWN OF MOUNTAIN VILLAGE BUILDING DEPARTMENTS PRESCRIPTIVE ENERGY CODE & GREEN BUILDING STANDARD

SAN MIGUEL COUNTY & TOWN OF MOUNTAIN VILLAGE BUILDING DEPARTMENTS PRESCRIPTIVE ENERGY CODE & GREEN BUILDING STANDARD SAN MIGUEL COUNTY & TOWN OF MOUNTAIN VILLAGE BUILDING DEPARTMENTS PRESCRIPTIVE ENERGY CODE & GREEN BUILDING STANDARD The Prescriptive Energy Code & Green Building Standard requirements for San Miguel County

More information

Success with 2009 IECC: Tech Tips for Builders. Insulation. Copyright 2014 Advanced Energy. All Rights Reserved

Success with 2009 IECC: Tech Tips for Builders. Insulation. Copyright 2014 Advanced Energy. All Rights Reserved Success with 2009 IECC: Tech Tips for Builders Insulation Copyright 2014 Advanced Energy. All Rights Reserved Insulation 1. For vented attics, install wind baffles on top of all exterior walls, leaving

More information

currently referenced throughout the

currently referenced throughout the STANDARD WORK SPECIFICATIONS: HOME ENERGY UPGRADES FOR EXISTING MANUFACTURED HOMES Page 1 of 4 General Comments 1. The work specifications for manufactured housing should be the same as the specifications

More information

Homes. Plan Review Input Form. Office Use: P l an Rev iew Contro l Nu mb er

Homes. Plan Review Input Form. Office Use: P l an Rev iew Contro l Nu mb er Office Use: P l an Rev iew Contro l Nu mb er Homes Plan Review Input Form PLEASE SEND WITH HOUSE PLAN AND LOAD CALC. TO: Advanced Energy Corporation, Attention: Maria Mauceri 909 Capability Drive Suite

More information

Encapsulated, Sealed & Closed Crawlspace Installation Manual

Encapsulated, Sealed & Closed Crawlspace Installation Manual YourCrawlSpace, Inc. 1007 Johnni4 Dodds Blvd. Mt. Pleasant, SC 29464 Toll Free: 877-44-CRAWL (27295) Local: (843) 593-1115 Encapsulated, Sealed & Closed Crawlspace Installation Manual Copyright 2017 Your

More information

REScheck Software Version Compliance Certificate

REScheck Software Version Compliance Certificate REScheck Software Version 4.3.1 Compliance Certificate Project Title: Chow Residence Renovation Energy Code: 2009 IECC Location: Boston, Massachusetts Construction Type: Single Family Project Type: Addition/Alteration

More information

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) PERMIT SUBMITTAL CHECKLIST: Signed and completed Building Permit application form. A separate Electrical permit is required from

More information

Is Yours? Homes Across Missouri are built to National Energy Efficiency Standards

Is Yours? Homes Across Missouri are built to National Energy Efficiency Standards Homes Across Missouri are built to National Energy Efficiency Standards Is Yours? A home buyers guide to the energy efficiency requirements of the St. Louis Building Code City of St. Louis Energy Code

More information

PICK YOUR POISON AND HOW TO GET THERE. Presented By Robby Schwarz

PICK YOUR POISON AND HOW TO GET THERE. Presented By Robby Schwarz PICK YOUR POISON AND HOW TO GET THERE Presented By Robby Schwarz Code Adoption Cycle 2012 International Energy Conservation code The code that got peoples attention Adoption and development are out of

More information

Is Yours? Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards

Is Yours? Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards Homes Across Missouri are Being Built to the Latest National Energy Efficiency Standards Is Yours? A home buyers guide to the energy efficiency requirements of the 2012 International Energy Conservation

More information

INFORMATIONAL HANDOUT FOR FINISHING A BASEMENT

INFORMATIONAL HANDOUT FOR FINISHING A BASEMENT 7100 147 th Street West Telephone (952) 953-2588 Apple Valley, MN 55124-9016 Fax (952) 953-2515 www.cityofapplevalley.org INFORMATIONAL HANDOUT FOR FINISHING A BASEMENT 1. Submit plan showing the proposed

More information

Compliance Certificate

Compliance Certificate REScheck Software Version 4.6.3 Compliance Certificate Project Energy Code: 2012 IECC Location: Frederick, Colorado Construction Type: Single-family Project Type: New Construction Conditioned Floor Area:

More information

Moisture Solution Becomes Efficiency Bonanza in Southeastern United States

Moisture Solution Becomes Efficiency Bonanza in Southeastern United States Moisture Solution Becomes Efficiency Bonanza in Southeastern United States Bruce Davis and Cyrus Dastur, Advanced Energy ABSTRACT This study compares the energy performance for space conditioning for a

More information

Major Texas Energy Code Changes (CZ3) TexEnergy Solutions August 30 th, 2016

Major Texas Energy Code Changes (CZ3) TexEnergy Solutions August 30 th, 2016 Major Texas Energy Code Changes (CZ3) TexEnergy Solutions August 30 th, 2016 Goals for today To give an overview of the Energy Code changes coming to Texas per Texas State Law. Will focus on IRC and Residential

More information

CERTIFICATE OF FIELD VERIFICATION & DIAGNOSTIC TESTING (Page 1 of 8)

CERTIFICATE OF FIELD VERIFICATION & DIAGNOSTIC TESTING (Page 1 of 8) CERTIFICATE OF FIELD VERIFICATION & DIAGNOSTIC TESTING (Page 1 of 8) Builder or Installer Name Builder or Installer Contact Telephone Plan/Permit (Additions or Alterations) Number Compliance Method (Prescriptive)

More information

Presented by: Stephen Carr Regional Building Science Manager (386)

Presented by: Stephen Carr Regional Building Science Manager (386) Presented by: Stephen Carr Regional Building Science Manager (386) 846-9155 stephen.carr@topbuild.com Understanding the Energy Code 2015 IECC CZ 1 CZ 2 CZ 3 CZ 4 CZ 5 CZ 6 CZ 7&8 Ceiling 30 38 38 49 49

More information

Explaining the Thermal Bypass Checklist. Ed Minch, Energy Services Group Kelly Parker, GWS

Explaining the Thermal Bypass Checklist. Ed Minch, Energy Services Group Kelly Parker, GWS Explaining the Thermal Bypass Checklist Ed Minch, Energy Services Group Kelly Parker, GWS ENERGY STAR Thermal Bypass Checklist WHY? ENERGY STAR is roughly doubling the number of houses verified each year,

More information

ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes. Thursday, February 24, 2011

ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes. Thursday, February 24, 2011 ENERGY STAR Homes version 3 Designing and Building to Meet the 2011 Changes Thursday, February 24, 2011 1 Efficiency Vermont is a Registered Provider with The American Institute of Architects Continuing

More information

Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4)

Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4) Quality Insulation Installation (QII) Insulation Installation (Page 1 of 4) A. QUALITY (QII) PREPARATION FOR INSULATION 01 Air barrier installation and preparation for insulation was done and verified

More information

New Construction Procurement Guidelines for the Pacific Northwest

New Construction Procurement Guidelines for the Pacific Northwest Northwest Portable Classroom Project New Construction Procurement Guidelines for the Pacific Northwest March 31, 2003 WSUCEEP03_063 Washington State University Extension Energy Program 925 Plum Street

More information

Prescriptive Checklist for the 2015 Washington State Energy Code

Prescriptive Checklist for the 2015 Washington State Energy Code Prescriptive Checklist for the 2015 Washington State Energy Code Chapter 51-11R WAC STATE BUILDING CODE ADOPTION AND AMENDMENT OF THE 2015 EDITION OF THE INTERNATIONAL ENERGY CONSERVATION CODE, RESIDENTIAL

More information

INSULATION. Success with 2015 IECC Northeast & Mid-Atlantic. Techtips for Builders & Trades

INSULATION. Success with 2015 IECC Northeast & Mid-Atlantic. Techtips for Builders & Trades Success with 2015 IECC Northeast & Mid-Atlantic Techtips for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED TEMPLATE 2015.1.0 PAGE 1 NORTHEAST For vented attics, install wind baffles

More information

Attic Access Hatch to have an area not less than 0.32m²/3.4ft² and no dimension less than 500mm with a min R-15 insulation value Crawlspace

Attic Access Hatch to have an area not less than 0.32m²/3.4ft² and no dimension less than 500mm with a min R-15 insulation value Crawlspace NOTABLE CODE REQUIREMENTS the following list represents important code requirements that shall be implemented into construction while still maintaining full compliance with all other requirements within

More information

APPLICATION FOR FINISHED BASEMENT PERMIT

APPLICATION FOR FINISHED BASEMENT PERMIT APPLICATION FOR FINISHED BASEMENT PERMIT REAL ESTATE TAX I.D. #: - - _ - _ 7607 W College Drive Ph: (708) 361-1804 Fax: (708) 923-7112 building@palosheights.org APPLICANTS: COMPLETE ALL ITEMS AND SUBMIT

More information

Chapter 14 - Air Sealing

Chapter 14 - Air Sealing Chapter 14 - Air Sealing Contents Chapter 14 - Air Sealing... 14-1 Pre-Mechanicals Activities... 14-3 Insulate Bathtub Enclosures... 14-3 Insulate Double Walls and Chases... 14-3 Pre-Inspection Checklist...

More information

Energy Star Qualified - New Homes

Energy Star Qualified - New Homes PDHonline Course G226 (6 PDH) Energy Star Qualified - New Homes Instructor: Jeffrey Havelin, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

REScheck Software Version Compliance Certificate

REScheck Software Version Compliance Certificate REScheck Software Version 4.3.0 Compliance Certificate Project Title: Breen Sample Residence Energy Code: 2006 IRC Location: Denver, Colorado Construction Type: Single Family Glazing Area Percentage: 14%

More information

HOUSING ENERGY- EFFICIENCY INSPECTION FIELD MANUAL

HOUSING ENERGY- EFFICIENCY INSPECTION FIELD MANUAL HOUSING ENERGY- EFFICIENCY INSPECTION FIELD MANUAL CONTENTS PREFACE.................................. 2 ACKNOWLEDGMENTS.........................2 DISCLAIMER................................ 2 REFERENCES...............................2

More information

Energy Efficiency Requirements 9.36

Energy Efficiency Requirements 9.36 The following information has been obtained from the HPO Illustrated Guide, Energy Efficiency Requirements for Houses in British Columbia, BCBC 9.36 & 9.32, Building Officials Association of British Columbia

More information

2015 IECC Air Sealing Multifamily For Code Compliance Funding for Energy Code Training

2015 IECC Air Sealing Multifamily For Code Compliance Funding for Energy Code Training 2015 IECC Air Sealing Multifamily For Code Compliance 2 Funding for Energy Code Training 1 Sponsor Also Recognize Resources Provided by Department of Energy: DOE Building America Program https://www.energycodes.gov/

More information

Success with Louisiana Energy Code. Techtips for Builders/Trades & Code Officials INSULATION

Success with Louisiana Energy Code. Techtips for Builders/Trades & Code Officials INSULATION Success with Louisiana Energy Code Techtips for Builders/Trades & Code Officials COPYRIGHT 2017 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION 2015.1.0 PAGE 1 For vented attics, install eave baffles on top

More information

RESIDENTIAL ENERGY CODE. The 2015 International Energy Conservation Code (IECC) as modified below.

RESIDENTIAL ENERGY CODE. The 2015 International Energy Conservation Code (IECC) as modified below. 305-2-4-.10 RESIDENTIAL ENERGY CODE. The 2015 International Energy Conservation Code (IECC) as modified below. (1) IECC CHAPTER 1 SCOPE AND ADMINISTRATION. (a) SECTION R101 SCOPE AND GENERAL REQUIREMENTS.

More information

2. Heat Transfer is quantified in British Thermal Units (BTU s)

2. Heat Transfer is quantified in British Thermal Units (BTU s) Basic Concepts 2. Heat Transfer is quantified in British Thermal Units (BTU s) 1 Btu is approximately equal to the energy in a single match. 3 INNOVATION & INTEGRATION: Transforming the Energy Efficiency

More information

Residential Requirements of the Texas Energy Code 2009 IRC Chap 11

Residential Requirements of the Texas Energy Code 2009 IRC Chap 11 BUILDING ENERGY CODES UNIVERSITY Residential Requirements of the Texas Energy Code 2009 IRC Chap 11 Ken Baker PNNL-SA-65859 The Family of I-Codes International Building Code International Mechanical Code

More information

Thermal Bypass Checklist: How We Got There?

Thermal Bypass Checklist: How We Got There? NORTH CAROLINA ENERGY STAR CONFERENCE NOVEMBER 16, 2007 Thermal Bypass Checklist: Lessons Learned Thermal Bypass Checklist: How We Got There? ENERGY STAR FOR HOMES OLD SPEC Tight Air Advanced d Efficient

More information

Performance Requirements and Options in the International Energy Conservation Code. Mike Turns, Senior Program Manager

Performance Requirements and Options in the International Energy Conservation Code. Mike Turns, Senior Program Manager Performance Requirements and Options in the International Energy Conservation Code Mike Turns, Senior Program Manager mturns@psdconsulting.com About PSD Programs Professional Services Software Design Implementation

More information

Questar ThermWise Duct Technical Specifications

Questar ThermWise Duct Technical Specifications Questar ThermWise Duct Technical Specifications 1. Introduction and Scope: This document sets forth the specifications for duct sealing and duct insulation in accordance to Questar ThermWise Weatherization

More information

Work Order (Bid Form) Upper East Tennessee Human Development Agency

Work Order (Bid Form) Upper East Tennessee Human Development Agency Upper East Tennessee Human Development Agency WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10329 CLIENT INFORMATION Address: ERWIN, TN 37692 AGENCY INFORMATION Agency: Upper

More information

Air Sealing, Infiltration & Ventilation

Air Sealing, Infiltration & Ventilation Providing effective energy strategies for buildings and communities Air Sealing, Infiltration & Ventilation 04.25.2018 12PM CDT Who we are Our goal: Reduce the energy footprint of Illinois. 2 SEDAC is

More information

Energy Provisions of the Kentucky Residential Code. Guide for Homeowners

Energy Provisions of the Kentucky Residential Code. Guide for Homeowners Energy Provisions of the Kentucky Residential Code Guide for Homeowners Kentucky Energy Code Guide If you are interested in buying a home or want to learn about the energy code and how to make your home

More information

2001 National Workshop on State Building Energy Codes July th, 2001 Burlington, Vermont

2001 National Workshop on State Building Energy Codes July th, 2001 Burlington, Vermont 2001 National Workshop on State Building Energy Codes July 16-19 th, 2001 Burlington, Vermont A Systems Engineering Approach to the Design of Energy and Resource Efficient Homes Presented By: Mark LaLiberte

More information

A Performance Based ENERGY STAR Homes Program: The Wisconsin ENERGY STAR Homes Perspective

A Performance Based ENERGY STAR Homes Program: The Wisconsin ENERGY STAR Homes Perspective A Performance Based ENERGY STAR Homes Program: The Wisconsin ENERGY STAR Homes Perspective Carter Dedolph, WECC Joseph Nagan, Home Building Technology Services ABSTRACT Over 13,000 certified homes during

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes 2014 British Columbia Building Code Changes A City of Prince George interpretation of the 2014 Building Code Changes for 9.32 & 9.36 The following changes reflect the most notable revisions and staff interpretations.

More information

Compliance Certificate

Compliance Certificate REScheck Software Version 4.6.2 Compliance Certificate Project Sample Energy Code: 2012 IECC Location: Coeur d'alene, Idaho Construction Type: Single-family Project Type: New Construction Conditioned Floor

More information

Energy Efficiency Programs

Energy Efficiency Programs Program Overviews Efficiency Programs Description Delivery Model Audit Requirement/ Multifamily - Existing Building Efficiency Alliant Services include free energy assessments, rebates for property owners

More information

A LOOK INTO THE 2015 IECC RESIDENTIAL PROVISIONS. Presented by: Shaunna Mozingo, Colorado Code Consulting

A LOOK INTO THE 2015 IECC RESIDENTIAL PROVISIONS. Presented by: Shaunna Mozingo, Colorado Code Consulting A LOOK INTO THE 2015 IECC RESIDENTIAL PROVISIONS Presented by: Shaunna Mozingo, Colorado Code Consulting WHAT CAN WE EXPECT TO SEE? Some consensus on enough is enough for now - No real roll backs, no real

More information

ENERGY STAR Qualified Homes, Version 3 (Rev. 03) Inspection Checklists For National Program Requirements

ENERGY STAR Qualified Homes, Version 3 (Rev. 03) Inspection Checklists For National Program Requirements Inspection Checklists For National Program Requirements As described in the ENERGY STAR Qualified Homes National Program Requirements, Version 3 (Rev. 03), one prerequisite for qualification is that a

More information

1. PREINSPECTION RESIDENTIAL ENERGY EFFICIENCY 7

1. PREINSPECTION RESIDENTIAL ENERGY EFFICIENCY 7 Chapter 4 Residential Energy Efficiency [Residential structures include R-3 buildings; R-2 and R-4 buildings three stories or less in height built to the International Building Code (see IBC classifications)]

More information

2012 IECC Residential with State Adopted Changes

2012 IECC Residential with State Adopted Changes 2012 IECC Residential with State Adopted Changes Salt Lake County Townships 385-468-6694 801-381-1449 bursenbach@slco.org bursenbach@yahoo.com BUILDING TALK 1 2 The Family of I-Codes International Building

More information

Residential Codes FAQs: 2015 International Energy Conservation Code (IECC) with MA Amendments & MA Stretch Energy Code

Residential Codes FAQs: 2015 International Energy Conservation Code (IECC) with MA Amendments & MA Stretch Energy Code Residential Codes FAQs: 2015 International Energy Conservation Code (IECC) with MA Amendments & MA Stretch Energy Code GENERAL 9 th EDITION Q: Which version of the energy code is in effect? A: On July

More information