Update on FCPS Construction/Renovation Projects. June 2016
|
|
- Madlyn Theodora Hines
- 5 years ago
- Views:
Transcription
1 Update on FCPS Construction/Renovation Projects
2 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (12): $162, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 88.4% Revised Completion Date per GC: No Change
3 Squires Elementary -- Renovation Rendering of Final Façade
4 Squires Elementary -- Renovation Work Completed to Date: Exterior block masonry completed (Phase 3). Roof system has been started and is 85% complete (Phase 3). Tile in the Lower Level restrooms is complete (Phase 3) Bar joists and decking completed at the kitchen addition (Phase 3). Acoustical spray in the Kitchen completed. (Phase 3) Current Work Effort (June): Brick to complete (Phase 3). Kitchen Hood, Walk-in Cooler/Freezers to install (Phase 3). Roof System to complete (Phase 3). Gym Equipment installation to start and complete (Phase 3). Start site demo (Phase 3).
5 Squires Elementary -- Renovation Kitchen Addition Roof System Interior CMU at Stage Gym Ramp Removal
6 Squires Elementary -- Renovation Stage Slab Poured Café Acoustical Spray Kitchen Quarry Tile Main Restroom
7 Garrett Morgan Elementary Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (11): $117, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 95.21% Revised Completion Date per GC: No Change
8 Garrett Morgan Elementary Rendering of Final Façade
9 Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up. Complete interior storefronts and glass. Install blinds & shades. Install stage equipment. Install remaining asphalt. Current Work Effort (June): Complete with final grading. Install seed, sod, and plants. Complete pre-school fencing & dumpster. Complete asphalt. Complete punch list.
10 Garrett Morgan Elementary Media Center Café Entry Bench Entry Mural
11 Garrett Morgan Elementary Kitchen Art Room High Windows Media Ctr. Exterior Street View
12 Coventry Oak Elementary Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (10): $49, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 92.0% Revised Completion Date per GC: No Change
13 Coventry Oak Elementary Rendering of Final Façade
14 Coventry Oak Elementary Work Completed to Date: Classroom and office casework installation completed. Steel canopies and interior detail work nearly completed. Interior soffit framing and drywall installation and painting continued. Interior finishes (painting, terrazzo marker boards / tack boards & ceilings) ongoing. Gym floor installed and painted and bleachers are installed. Mechanical, plumbing & electrical continues. Plumbing & light fixture installation ongoing. Current Work Effort (June): Mechanical, plumbing will complete, electrical will continue. Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete. Final grading, asphalt, CMU and brick masonry, exterior doors and metal roof. Brick masonry will complete. Landscaping installation will complete.
15 Coventry Oak Elementary Car Loop Computer Lab Entrance Corridor
16 Coventry Oak Elementary Front Lobby Café Finishes Rear Lobby SE Elevation
17 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (9): $156, Scheduled Contract Completion Date: July 2017 % of Contract Completed: 44.91% Revised Completion Date per GC: No Change
18 New High at Winchester Road Schematic Rendering of Final Façade
19 New High at Winchester Road Work Completed to Date: Storm sewer, sanitary sewer and fire service continued. Grading at the parking lot on the west side and at the football field and tennis courts began. Brick was completed in Area B and began in Areas A, D, E1 & E2. Work on miscellaneous non-loadbearing walls continued throughout the building. Steel roof joists and deck were completed in Area E2 and steel columns and beams were set in the Main Lobby. Metal stud walls and parapets at the cafeteria were completed and metal stud framing in Area B continued. Drywall began in Area C. Roofing dry-ins were completed in Area A and Area E2, and began in Area E1. Air barrier application continued. Metal panels continued in Area C & E4. Type X storefront was installed. Electrical wall rough-ins continued in all areas. Overhead conduits, cable tray work, & panel tub mounting continued. Temporary power and lighting continued. Electrical work completed under west parking lot. Site lighting underground conduits began. Mechanical insulation, ductwork, plumbing and HVAC rough-ins will continue. Roof leaders and overflow in Main Gym were completed.
20 New High at Winchester Road Current Work Effort (June): Site utilities installation will continue. Grading will be near complete at the west and south parking lots, dense grade to begin. Foundations will be completed at the Bathrooms / Concessions. Concrete slab preparation will continue in the Auditorium and begin in the Cafeteria. Bearing walls will be completed in the Auditorium and Fieldhouse. Brick will continue in Area A. Steel joist/deck will be completed in Area E1. Roofing Dry-ins will move to Area D. Metal Panels will be completed in Area C & move to Area E4. Windows will begin installation in Area C. Air Barrier will continue as required. Electrical wall rough-ins will continue in all areas. Overhead conduits, & panel tub mounting will continue. Cable tray work in Area E1 will be completed. Temporary power and lighting will continue as required. Ductwork rough-ins will be completed on 2 nd floor of Area B and mechanical insulation will continue. Area A plumbing rough-ins will continue on the 2 nd floor. Plumbing, HVAC, mechanical room hydronic piping and mechanical insulation will continue in Areas E3 & E4. Main Gym duct installation will be completed.
21 New High at Winchester Road Area C Storefront Area C Gypsum Wallboard Area C Block Filler Auditorium Loadbearing CMU
22 New High at Winchester Road Areas E1 & D Roofs Areas E2 & E3 Brick West Parking Grading Field House & Football Bleachers
Update on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. August 2016
Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationUpdate on FCPS Construction/Renovation Projects. September 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationNew Ringgold Middle School. Project Slideshow August 26, 2017
New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More informationDOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.
DOCUMENT 00 43 36B EXPANDED SUBCONTRACTORS LISTING TO: CLARK COUNTY SCHOOL DISTRICT hereinafter called "Owner" FROM: ~AU;)"''"-' Oeve\,(;p,-...e,.,,... IA... t. ~o~ t>.m..e>u,i-j (Print Company Name) Pe-Mo1..,,,-t,:;>.tJ
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationSECTION ALTERNATES
SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationAGILITAS Property Development
Hartmann Commons offered by For Infomation and Leasing Mr. Seth T. McDowell 1614 16th Avenue South Nashville, Tennessee 37212 Voice 615-327-8788 Fax 615-327-8789 Hartmann Commons Agilitas Property Development
More informationPRESENTATION JANUARY 24, 2017
4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction
More informationHeritage High School
Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery
More informationAPPLICATION AND CERTIFICATE FOR PAYMENT
AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in
More informationCEFPI Monthly Meeting
CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationFACILITY COMPONENTS - MIDDLE SCHOOL
SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls
More informationEvansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data
Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School
More informationCapital Projects Progress Report. January Presented by
Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428
More informationNAAHB Workgroup Index General Ledger Account
NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationEASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923
INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More informationMichael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School
A D D E N D U M # 1 DATE: TO: FROM: PROJECT: All Bidders Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School CBI JOB NO.: 11063 The following items shall modify
More informationMARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD
MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE
More informationPROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls
More informationBoard Work Session Feasibility Study. January 9, 2017
Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking
More informationSTRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC
CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking
More information2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities
More informationBuilding Systems and Design Elements included in SliDeRulE
Building Systems and Design Elements included in SliDeRulE No. System Subsystem Design Element 1.1.1 Foundation Deep Foundation Steel H-pile 1.1.2 Foundation Deep Foundation Steel pipe pile 1.1.3 Foundation
More information6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After
Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationTABLE OF CONTENTS. (Δ = Rev 06/08)
TABLE OF CONTENTS (Δ = Rev 06/08) INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-9 Record Drawings B-10 Variance Procedure B-11 Surface Water Procedures (New Section)
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More informationDrexel Hill Middle School
150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationDarlington Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Cain Elementary School Observed By: Creed/Carter Principal: Grade
More informationRB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)
STANDARD SPECIFICATIONS FOR 505 EWING STREET PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad * Steel insulated with embossed panels with
More informationTABLE OF CONTENTS. (Δ = Rev 11/15) Update #7
TABLE OF CONTENTS ( = Rev 11/15) Update #7 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes (New) B-9 Record Drawings B-10 Variance Procedure
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMaterial Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5
Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00
More informationTABLE OF CONTENTS. (Δ = Rev 04/17) Update #8
TABLE OF CONTENTS ( = Rev 04/17) Update #8 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes B-9 As-Builts and Record Drawings B-10 Variance
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationCivic Center Renovation News
Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented
More informationMinneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C
2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More informationDelco Activity Center Site Summary
1 Site Summary Address 4601 Pecan Brook Austin, TX 78724 Number of Permanent Campus Facilities 1 Original Year of Construction 2003 Total Campus Building Area (combined) 60,294 SF Introduction The is located
More informationFOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156
FOR SALE 8800 Miller Dr (SW 56 Street) Miami, FL 33156 Completely 12,820 SF 1.87 Acres Presented exclusively by Dimitri Kiosseff of Brown Harris Stevens BHSMiami.com NEW YORK CITY THE HAMPTONS PALM BEA
More informationOwen County School District
Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationRB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)
STANDARD SPECIFICATIONS FOR 309 EWING STREET PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad * Steel insulated with embossed panels with
More informationBIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D
HOSKINS ARCHITECTURE, LLC 1827 1 ST AVENUE NORTH, SUITE 104 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 3 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS
More informationMarch 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT
March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationDelta Gamma Sorority Renovation Budget Scope 3/7/2018
Delta Gamma Sorority Renovation Budget Scope 3/7/2018 PROJECT: Barbara Cerni Delta Gamma Sorority Tallahassee, Fla. This scope is based on the 50% Construction Documents drawn by BKJ Architecture dated
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More informationTODAY S DATE: January 24th, 2019
TODAY S DATE: January 24th, 2019 Top Left: View of metal panels and louvers on the South elevation. Top Right: Interior storefront glass is getting installed on the atrium side of 1st floor labs. Bottom
More informationPROCUREMENT AND CONTRACTING DOCUMENTS GROUP
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders
More informationHunter s Point South Project
January 2013 Update Hunter s Point South Project New York City Economic Development Corporation The City of New York continues work on the Hunter s Point South project, a waterfront development on a 30-acre
More informationRB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)
STANDARD SPECIFICATIONS FOR 28 HILLSIDE ROAD PRINCETON, NJ 08540 EXTERIOR Garage Doors: * Two 8 X7 steel insulated, tan door * Two garage openers, 1 keypad * Steel insulated with embossed panels with windows
More informationFleet Elementary School
Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project
More informationRB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)
STANDARD SPECIFICATIONS FOR 73 LEAVITT LANE PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad. * Steel insulated with embossed panels with
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationLincoln Akerman School Hampton Falls, NH
Lincoln Akerman School for Proposed Gym Addition September 29, 2016 The following list of items is intended to assist you in understanding any assumptions that have been made in the preparation of the
More informationPROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More information