1 Update on FCPS Construction/Renovation Projects

2 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (12): $162, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 88.4% Revised Completion Date per GC: No Change

3 Squires Elementary -- Renovation Rendering of Final Façade

4 Squires Elementary -- Renovation Work Completed to Date: Exterior block masonry completed (Phase 3). Roof system has been started and is 85% complete (Phase 3). Tile in the Lower Level restrooms is complete (Phase 3) Bar joists and decking completed at the kitchen addition (Phase 3). Acoustical spray in the Kitchen completed. (Phase 3) Current Work Effort (June): Brick to complete (Phase 3). Kitchen Hood, Walk-in Cooler/Freezers to install (Phase 3). Roof System to complete (Phase 3). Gym Equipment installation to start and complete (Phase 3). Start site demo (Phase 3).

5 Squires Elementary -- Renovation Kitchen Addition Roof System Interior CMU at Stage Gym Ramp Removal

6 Squires Elementary -- Renovation Stage Slab Poured Café Acoustical Spray Kitchen Quarry Tile Main Restroom

7 Garrett Morgan Elementary Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (11): $117, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 95.21% Revised Completion Date per GC: No Change

8 Garrett Morgan Elementary Rendering of Final Façade

9 Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up. Complete interior storefronts and glass. Install blinds & shades. Install stage equipment. Install remaining asphalt. Current Work Effort (June): Complete with final grading. Install seed, sod, and plants. Complete pre-school fencing & dumpster. Complete asphalt. Complete punch list.

10 Garrett Morgan Elementary Media Center Café Entry Bench Entry Mural

11 Garrett Morgan Elementary Kitchen Art Room High Windows Media Ctr. Exterior Street View

12 Coventry Oak Elementary Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (10): $49, Scheduled Contract Completion Date: July 2016 % of Contract Completed: 92.0% Revised Completion Date per GC: No Change

13 Coventry Oak Elementary Rendering of Final Façade

14 Coventry Oak Elementary Work Completed to Date: Classroom and office casework installation completed. Steel canopies and interior detail work nearly completed. Interior soffit framing and drywall installation and painting continued. Interior finishes (painting, terrazzo marker boards / tack boards & ceilings) ongoing. Gym floor installed and painted and bleachers are installed. Mechanical, plumbing & electrical continues. Plumbing & light fixture installation ongoing. Current Work Effort (June): Mechanical, plumbing will complete, electrical will continue. Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete. Final grading, asphalt, CMU and brick masonry, exterior doors and metal roof. Brick masonry will complete. Landscaping installation will complete.

15 Coventry Oak Elementary Car Loop Computer Lab Entrance Corridor

16 Coventry Oak Elementary Front Lobby Café Finishes Rear Lobby SE Elevation

17 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (9): $156, Scheduled Contract Completion Date: July 2017 % of Contract Completed: 44.91% Revised Completion Date per GC: No Change

18 New High at Winchester Road Schematic Rendering of Final Façade

19 New High at Winchester Road Work Completed to Date: Storm sewer, sanitary sewer and fire service continued. Grading at the parking lot on the west side and at the football field and tennis courts began. Brick was completed in Area B and began in Areas A, D, E1 & E2. Work on miscellaneous non-loadbearing walls continued throughout the building. Steel roof joists and deck were completed in Area E2 and steel columns and beams were set in the Main Lobby. Metal stud walls and parapets at the cafeteria were completed and metal stud framing in Area B continued. Drywall began in Area C. Roofing dry-ins were completed in Area A and Area E2, and began in Area E1. Air barrier application continued. Metal panels continued in Area C & E4. Type X storefront was installed. Electrical wall rough-ins continued in all areas. Overhead conduits, cable tray work, & panel tub mounting continued. Temporary power and lighting continued. Electrical work completed under west parking lot. Site lighting underground conduits began. Mechanical insulation, ductwork, plumbing and HVAC rough-ins will continue. Roof leaders and overflow in Main Gym were completed.

20 New High at Winchester Road Current Work Effort (June): Site utilities installation will continue. Grading will be near complete at the west and south parking lots, dense grade to begin. Foundations will be completed at the Bathrooms / Concessions. Concrete slab preparation will continue in the Auditorium and begin in the Cafeteria. Bearing walls will be completed in the Auditorium and Fieldhouse. Brick will continue in Area A. Steel joist/deck will be completed in Area E1. Roofing Dry-ins will move to Area D. Metal Panels will be completed in Area C & move to Area E4. Windows will begin installation in Area C. Air Barrier will continue as required. Electrical wall rough-ins will continue in all areas. Overhead conduits, & panel tub mounting will continue. Cable tray work in Area E1 will be completed. Temporary power and lighting will continue as required. Ductwork rough-ins will be completed on 2 nd floor of Area B and mechanical insulation will continue. Area A plumbing rough-ins will continue on the 2 nd floor. Plumbing, HVAC, mechanical room hydronic piping and mechanical insulation will continue in Areas E3 & E4. Main Gym duct installation will be completed.

21 New High at Winchester Road Area C Storefront Area C Gypsum Wallboard Area C Block Filler Auditorium Loadbearing CMU

22 New High at Winchester Road Areas E1 & D Roofs Areas E2 & E3 Brick West Parking Grading Field House & Football Bleachers

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. August 2016 Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening. DOCUMENT 00 43 36B EXPANDED SUBCONTRACTORS LISTING TO: CLARK COUNTY SCHOOL DISTRICT hereinafter called "Owner" FROM: ~AU;)"''"-' Oeve\,(;p,-...e,.,,... IA... t. ~o~ t>.m..e>u,i-j (Print Company Name) Pe-Mo1..,,,-t,:;>.tJ

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012 Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

AGILITAS Property Development

AGILITAS Property Development Hartmann Commons offered by For Infomation and Leasing Mr. Seth T. McDowell 1614 16th Avenue South Nashville, Tennessee 37212 Voice 615-327-8788 Fax 615-327-8789 Hartmann Commons Agilitas Property Development

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

Capital Projects Progress Report. January Presented by

Capital Projects Progress Report. January Presented by Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428

More information

NAAHB Workgroup Index General Ledger Account

NAAHB Workgroup Index General Ledger Account NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As

More information

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School A D D E N D U M # 1 DATE: TO: FROM: PROJECT: All Bidders Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School CBI JOB NO.: 11063 The following items shall modify

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE

More information

PROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

Building Systems and Design Elements included in SliDeRulE

Building Systems and Design Elements included in SliDeRulE Building Systems and Design Elements included in SliDeRulE No. System Subsystem Design Element 1.1.1 Foundation Deep Foundation Steel H-pile 1.1.2 Foundation Deep Foundation Steel pipe pile 1.1.3 Foundation

More information

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication

More information

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

TABLE OF CONTENTS. (Δ = Rev 06/08)

TABLE OF CONTENTS. (Δ = Rev 06/08) TABLE OF CONTENTS (Δ = Rev 06/08) INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-9 Record Drawings B-10 Variance Procedure B-11 Surface Water Procedures (New Section)

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As

More information

Drexel Hill Middle School

Drexel Hill Middle School 150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

LLANO ISD SCHOOL BOARD MEETING. January 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016 LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Cain Elementary School Observed By: Creed/Carter Principal: Grade

More information

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609) STANDARD SPECIFICATIONS FOR 505 EWING STREET PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad * Steel insulated with embossed panels with

More information

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7 TABLE OF CONTENTS ( = Rev 11/15) Update #7 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes (New) B-9 Record Drawings B-10 Variance Procedure

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8 TABLE OF CONTENTS ( = Rev 04/17) Update #8 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes B-9 As-Builts and Record Drawings B-10 Variance

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

Civic Center Renovation News

Civic Center Renovation News Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

Delco Activity Center Site Summary

Delco Activity Center Site Summary 1 Site Summary Address 4601 Pecan Brook Austin, TX 78724 Number of Permanent Campus Facilities 1 Original Year of Construction 2003 Total Campus Building Area (combined) 60,294 SF Introduction The is located

More information

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156 FOR SALE 8800 Miller Dr (SW 56 Street) Miami, FL 33156 Completely 12,820 SF 1.87 Acres Presented exclusively by Dimitri Kiosseff of Brown Harris Stevens BHSMiami.com NEW YORK CITY THE HAMPTONS PALM BEA

More information

Owen County School District

Owen County School District Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical

More information

City of Westerville Guide to Commercial Inspections

City of Westerville Guide to Commercial Inspections City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing

More information

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609) STANDARD SPECIFICATIONS FOR 309 EWING STREET PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad * Steel insulated with embossed panels with

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS ARCHITECTURE, LLC 1827 1 ST AVENUE NORTH, SUITE 104 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 3 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS

More information

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

Delta Gamma Sorority Renovation Budget Scope 3/7/2018

Delta Gamma Sorority Renovation Budget Scope 3/7/2018 Delta Gamma Sorority Renovation Budget Scope 3/7/2018 PROJECT: Barbara Cerni Delta Gamma Sorority Tallahassee, Fla. This scope is based on the 50% Construction Documents drawn by BKJ Architecture dated

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

TODAY S DATE: January 24th, 2019

TODAY S DATE: January 24th, 2019 TODAY S DATE: January 24th, 2019 Top Left: View of metal panels and louvers on the South elevation. Top Right: Interior storefront glass is getting installed on the atrium side of 1st floor labs. Bottom

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

Hunter s Point South Project

Hunter s Point South Project January 2013 Update Hunter s Point South Project New York City Economic Development Corporation The City of New York continues work on the Hunter s Point South project, a waterfront development on a 30-acre

More information

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609) STANDARD SPECIFICATIONS FOR 28 HILLSIDE ROAD PRINCETON, NJ 08540 EXTERIOR Garage Doors: * Two 8 X7 steel insulated, tan door * Two garage openers, 1 keypad * Steel insulated with embossed panels with windows

More information

Fleet Elementary School

Fleet Elementary School Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project

More information

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609) STANDARD SPECIFICATIONS FOR 73 LEAVITT LANE PRINCETON, NEW JERSEY EXTERIOR Garage Doors: * One 16 x7 steel insulated, tan door. * Two garage openers, 1 keypad. * Steel insulated with embossed panels with

More information

Appendix J - Custom Uniformat for EDU Migration

Appendix J - Custom Uniformat for EDU Migration Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations

More information

Lincoln Akerman School Hampton Falls, NH

Lincoln Akerman School Hampton Falls, NH Lincoln Akerman School for Proposed Gym Addition September 29, 2016 The following list of items is intended to assist you in understanding any assumptions that have been made in the preparation of the

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information