1 Developing the Standard Operating Procedures of BIM Collaboration Management for General Contractor Hui-Hsuan Yang 1 and Yu-Cheng Lin 2 1) PhD Student, Department of Civil Engineering, National Taipei University of Technology, Taipei, Taiwan. a @gmail.com 2) Professor, Department of Civil Engineering, National Taipei University of Technology, Taipei, Taiwan. yclin@ntut.edu.tw Abstract: To improve communication and coordination between all stakeholders, general contractors utilize Building Information Modeling (BIM) technology during the construction phase. Furthermore, the major work of BIM model development is often using the way of collaborative work. The information and correctness of BIM model development is very important for BIM project. Without the effective and suitable management approach, it is easy to cause rework and mistakes regarding to the collaboration development of BIM models. Those problems include rework, schedule delay, and low quality of BIM model development. In order to enhance the effectiveness and qualities of BIM Model development, this study develops the frameworks and standard operating procedures of BIM collaboration management special for general contractor (GC). Furthermore, the proposed frameworks and standard operating procedures are applied to a building project case in Taiwan to verify its efficacy and demonstrate its effectiveness of the collaboration development of BIM models. Finally, this paper summaries the limitations, difficulties, suggestion for further practical implementation. Keywords: BIM, building information modeling, collaboration management, general contractor, standard operating procedures 1. INTRODUCTION In recent years, general contractors apply Building Information Modeling (BIM) technology in the construction engineering to improve communication and coordination between all stakeholders. General contractor (GC) needs to develop and revise BIM model during the construction phase. Therefore, the primary task of using of BIM technology is BIM model development that is often use the way of collaborative work. The information and correctness of BIM model is very important for BIM project, without the effective and suitable management approach, it is easy to cause rework and mistakes by the collaboration development of BIM model. Those problems include rework, schedule delay, and low quality of BIM model development. In the past, General contractor (also often rely on clash detection software or model checking software to check the problems of BIM model after BIM model development is finished, this time, the BIM model may have some serious problems, and affect subsequent work and on-site construction progress. Therefore, to make the BIM modeling work smoothly and reducing the problems of model, GC should to plan the standard operating procedures before the BIM model development, to enhance the effectiveness and quality of BIM Model development. Because each BIM project s size and degree of application are different, the development of standards and specifications, necessary manpower, and collaborative modeling approach to each model will be different. Therefore, this paper will develop BIM modeling CM approach, and standard operating procedures for BIM models development. The purposes of this study are as follows: 1.To develop a collaboration management standard operating procedures for BIM models for general contractors, and to ensure possibility of management of checks on the model that will ensure accuracy and quality. 2. To discuss the benefits of the BIM collaboration management system in a real case study. 2. LITERATURE REVIEW In recent years, BIM has increasingly been used in the construction industry and international construction projects and, as many of the files in a project require synchronous execution, the importance of collaboration work has increased. Shelbourn et al. (2007) pointed out collaborative working is a creative process undertaken by two or more individuals, sharing their collective skills, expertise, understanding and knowledge (information) in an atmosphere of openness, honesty, trust and mutual respect, to jointly deliver the best solution that meets their common goal. Established collaboration practices in the construction industry are document centric and are challenged by the introduction of BIM. Document management collaboration systems have significantly improved document collaboration practices in recent years; however, their capabilities for model collaboration are limited and do not support the complex requirements of BIM collaboration (Shafiq et al., 2013). Zada et al. (2014) identified that 1 585

2 changes and modifications are inevitable, even in the contemporary BIM approach in the building design process, and developing a collaborative BIM platform is essential to keep track of the changes and ensure that designers have an up-to-date version of the BIM model. Munkley et al. (2014) pointed out that much of the research on BIM technologies and processes has focused on BIM file-based collaboration in recent years and proposed a low cost IT platform to execute BIM model-based collaboration. Kassem et al. (2014) proposed protocols for BIM collaborative design that can be utilized at the project level by an entire supply chain of lead architects, engineering consultants, clients, and contractors to increase the efficiency and consistency of information flow and BIM deliverables. Das et al. (2014) presented a distributed cloud-based BIM framework that was designed to support collaboration and information sharing among project participants. Chen et al. (2014) proposed a system to enable Internet-based modeling collaboration among teams from multiple disciplines for the development of BIM. The achievements of BIM technology attained in virtual design and construction are obvious. However, as a technology designed to apply to the whole life cycle of building, current technology application of BIM cannot support all the workflow of the life cycle (Tian and Xue, 2014). Wu and Xu (2014) proposed a collaborative framework of BIM information from the perspective of supply chain management. Tian and Xue (2014) summarized the barriers in the process of building an information collaborative application on site and discusses how to solve the barriers. According to above literature reviews, most existing literature focuses on development of collaboration systems in the AEC industry. However, less research focuses on BIM CM in the development of BIM models. The GC has to ensure the quality and accuracy of BIM models before exchanging information or executing their application with project stakeholders. Therefore, this paper proposes a CM approach for BIM model development for GCs and researches a collaboration work rule and management mechanism of BIM modeling to enhance the effectiveness of collaborative BIM model development. 3. THE STANDARD OPERATING PROCEDURES OF BIM COLLABORATION MANAGEMENT With the development of BIM technology, GC began using BIM technology in the construction phase. To take full advantage of collaboration method to execute BIM modeling work to achieve the effect of reduced operating time. In the absence of BIM-related rule operating guidelines and standard operating procedures, likely to cause conflict between the work, rework and so on, thus increasing the work time. Besides, use of BIM technology in the project, the correctness of BIM model is the necessary and important. If BIM model is incorrect that will affect subsequent application (for example: unable to output shop drawing, unable to review constructability). Therefore, GC need to execute model check and authority management to ensure the quality and accuracy of the BIM model in BIM collaboration modeling process. The work framework of BIM collaboration modeling is using on the same model by several BIM engineers. In the BIM modeling process often encounter naming rule of BIM models elements are different to result in difficulty to obtain information, the set of origin coordinate are different to cause some problems when integrating BIM model, BIM model and file do not have set rights management, anyone can modify, so they cannot ensure the correctness of the information and documents of BIM model. Furthermore, when encounter some problems in the BIM modeling process, they can only submit RFI (Request for Information) documents and communicate and discuss in the routine meeting, that will spend a lot of time. So how to ensure the correctness of the information of BIM model and the immediacy of Information transfer is a thorny question. To alleviate the current problem, and to enhance the effectiveness of BIM, this paper, using the concept of collaboration, proposes a collaboration management framework for BIM model development. Although use of BIM technology among general contractors has become increasingly popular, but collaboration function in BIM software are only in the technical aspects, but there is no way to set the rules of collaboration, and this deficiency leads to difficulty in having multiple parties work together on the same BIM model. A BIM model is typically modified based on the outcome of meetings to discuss it, or on RFI documents, and timely modification must still be managed manually. The process of developing a BIM model is highly complex, as the architectural, structural, mechanical, and electrical drawing information are all using on the same model by several BIM engineers. This mass collaboration has manual operation risks, and if there is no complete process with which to manage everything, it can be difficult to reap the benefits of BIM collaboration. Using BIM technology, the general contractor must implement the BIM collaboration management framework, thus acting upon its integration and synchronization functions. This section proposes the framework of the proposed BIM collaboration management mechanisms for GC, the framework mainly divided into three stages: initial phase, model development phase, model checking phase. According to three stages of BIM model development collaboration management framework, this study will develop collaboration workflow of each stages. To ensure the BIM model can be developed quickly with good quality for GC, this study will execute the plan of initial phase before developing the BIM model that will affect the whole operation. The standard operating 2 586

3 procedures of the initial phase is shown in Fig.1. In this process, first of all, execution of a BIM project is confirmed after the project goals and contracts have been established. Then, the project starts, and the work process is planned by the BIM manager. This process includes the establishment of the BIM team, discussions with BIM engineers, assignment of work, setting permission for each staff engineer, and scheduling of regular meetings to track the schedule. Then, all project participants will hold a meeting to discuss the requirement and schedule of model after obtain the drawing, and setting BIM model operating rules, then according model requirement to plan work item and assign, decide the time required to complete the model, upload the BIM model file to the server, and implement the basic environment settings. Figure 1. SOP for the initial phase for the BIM CM implementation BIM engineers will link the server BIM model and execute BIM modeling when finished the initial phase. There may encounter problems of drawings and modeling in the model development phase, so this paper plans the process of model development phase (see Fig.2). During this process, the BIM model is updated synchronously to the server model according to the BIM model operating rules. At this stage, the BIM manager needs to determine whether should modify the BIM model should be modified based on the updated project information or not. A voluntary inspection confirms the correctness of BIM model in the BIM modeling process. If there have any questions, RFI document will be presented, and via discuss at the meeting to clarify the model issues, so that BIM model development can proceed smoothly. Because the BIM model is the basis of its subsequent applications, so the model must have a good quality management. Therefore, this paper will discuss the model check phase, and develop the model check mechanism. The mechanism mainly divided into three stages: The first stage is to check the original BIM model in the server that is essential for BIM collaboration. Furthermore, BIM model checking engineer checks the basic environment setting of the server BIM model, and so on. Ensure the correctness of the server BIM model to avoid the error of BIM model development. The second stage is model voluntary inspection that is BIM engineer checks the BIM model by their own develop, to confirm the quality of the BIM model, this stage can reducing the check time after completion of all models, and to avoid a lot of mistakes cumulative to the final inspection stage to cause behind schedule. This paper is also set model checking reference items for model voluntary 3 587

4 inspection. The third stage is the final model check for ensuring the constructability and practical application requirements of BIM models. Through model checking mechanism of three stages to check the problem of BIM model. To make the problem must be solved as soon as possible, this paper develops the management process of the problem of BIM model (see Fig.3). When a problem is found, the BIM engineer must first determine the problem whether is BIM model development error or did not follow the rules to develop BIM model, if the problem is described in the above, then then the BIM engineer needs to fill out the form with a description of the problem of the BIM model and submitted to a responsible BIM engineer. BIM engineers will respond and modify the model based on questions raised by the table. When modify is done, then to reply via fill out the table. If the problem is not described in the above, then project participants will discuss the problem with RFI documents. Until to confirm all BIM model are correct. Figure 2. SOP for the BIM model development phase for the BIM CM implementation 4 588

5 4. CASE STUDY Figure 3. SOP for BIM model checking management for the BIM CM implementation The chosen MRT station in Taiwan involves the engineering construction of four underground floors. The scope of the BIM model development is the floor of underground platform. The station will use the BIM CM proposed in this paper as a management method of BIM model development. In this case study, Autodesk Revit 2014 is used as the BIM modeling software. All BIM models is developed based on proposed framework and approaches in the study. The BIM model development is divided into three parts (see Fig.4), and sequentially to execute the initial phase, model development phase and model check phase, to confirm BIM model can be applied to construction site. Figure 4. The framework of BIM model development in the case study 5 589

6 During the initial phase, BIM Team references the initial phase that is proposed from this research to execute the initial phase of BIM model of this station. BIM managers to evaluate the station before to execute three stages of BIM model development, and confirm the dispatch five BIM engineers to develop the BIM model, one BIM model checking engineer to check model (see Table 1). Because this BIM project will be applied to the operation maintenance phase, there will discuss requirements of operation maintenance and constructability with owner and site engineers. This BIM project objectives are to develop the station model that contains structure, part of the decoration, and equipment. It was decided that one BIM central model file to execute collaboration modeling in this case, there will set workset based on the number of engineer in the central model. To avoid BIM central model have any problem, only BIM manager has the authority of new add and backup of this BIM model, BIM engineers not have. After confirming this BIM project assessment and setting, BIM manager gets 2D drawing, project participants via a meeting to discuss and confirm the requirement of BIM model, then setting BIM model operating rules. According to the assessment, the station will develop one BIM central model file to develop the model. The way of BIM model development is importing 2D CAD files. According to the requirements of the BIM model, the proficiency of the BIM engineer uses BIM software and available time for BIM model development. This case study involved one senior BIM engineer and four junior BIM engineers. The BIM model development work took 42 days. BIM manager will develop BIM central model file to the server, the model as the base model of BIM model development. Then, ensure the correctness of 2D drawing, and 2D drawing information whether clear. Due to each BIM engineers need the information of 2D drawing are different, so BIM engineers are responsible to finish their 2D drawing. BIM manager will set up shared parameter files based on the requirements of the owners, the construction site and modeling. The way of this BIM model development is cooperated by five BIM engineers, if the model needs to modify that must modify by the responsible engineer to maintain the model quality and enhance the accuracy of the model. When the main process is complete, BIM team executes subsequent work based on BIM models operating rules (including the development of baseline and the basic elements of BIM model), to develop the BIM central basic model. During the initial model development phase, BIM manager assigns BIM model work to each BIM engineer via concept of collaboration. BIM team will reference the procedure of the development phase of the BIM collaboration management Implementation that is proposed from this research to develop the BIM model. BIM team will discuss BIM model and tracking model status via periodic meetings. BIM team also use the online communication software and unscheduled meeting to execute real time discussion, to solve the problem as soon as possible to continue the work. BIM engineer will check the BIM model by their own develop, to confirm the correctness of the BIM model in the process of BIM model development. Further, in order to keep abreast of the progress and status of BIM models development, BIM engineers must fill out the online daily work schedules, the content is the work item of finished and unfinished, and so on. BIM manager will review the progress of each engineer's work via daily work schedules to deploy work at any time that can make the BIM model can progress smoothly. During the model check phase, the BIM model is the basis of the construction and operation maintenance phase use, so BIM team has to execute model checking very well. BIM team must self-management in the process of BIM model development, and they will reference the mechanisms of model checking that is proposed from this research to execute BIM model check. This BIM mode check is divided into three stages, the first stage is before the BIM model development, BIM model checking engineer will check the BIM central basis model that is output from the initial phase. ; The second stage is model voluntary inspection that is BIM engineer will check the BIM model by their own develop, to confirm the quality of the BIM model, its check item will reference the model voluntary inspection table that is proposed by this research. After the structure/construction phase is finished, BIM engineer will check the model structure/architecture, decoration/refined decoration elements, including its location, size and height, and checking the missing /repeat element, then confirm whether there is fill in the parameters. Due to this station have the requirement of some of equipment and its parameters, this case study designed the main focus of the check to incorporate the model for operation and maintenance usage. BIM engineer will check the model equipment elements, including its quantity, item and location, and checking the level of detail whether is meets the needs of the owners. Finally, check the pre-build equipment parameters fields are complete. ; The third stage is that the BIM model checking engineer also use the staged way for BIM model check implementation. When BIM engineer is finished the voluntary inspection of each model phase, BIM model checking engineer will check the models that is develop by all BIM engineer. After the completion of a three-stage model checking, BIM model checking engineer performs these checks to ensure that the BIM model complies with the constructability and practical application requirements, and ensures the correctness of the BIM model. For any problems found during the three-stage model checking mechanism, BIM team references the management process of BIM model problems proposed in this research to execute the management process. When BIM model checking engineer finds a model problem, after judge, to determine the problem is BIM model development error, then BIM model checking engineer will fill out the table of BIM model problems, and submit to BIM engineer. BIM engineers will respond and modify the model based on questions raised by the table

7 When modify is done, then to reply through fill out the table of BIM model problems (reply) (see table 2). BIM manager also confirmed the problem of the model modification via this reply table. In this case, all the model problems will get effective management via this management process. Table 1. The initial assessment table using in the case study Table 2. The request and respond forms for BIM model problems This case through the set of standard operating procedures for BIM models development that can according to these standard operating procedures to develop BIM model fast, if any inconsistencies were found among the standards of any involved parties, it was necessary to ask questions and resolve these differences. This mutual enlightenment led to a reduction in time necessary to complete the project. BIM engineers can check 2D drawings, if there is a problem and propose solutions as soon as possible at the process of BIM models development. The main benefits based on case study are summarized as following: (1) BIM models development will reduce naming the element which does not match the actual content of the 2D drawing based on proposed initial phase plan. (2) BIM team can enhance the efficiency of BIM models development using the proposed standard operating procedures of BIM models development. (3) Multi-stage model checking mechanism that can effectively reduce the problem of BIM cumulative to the final inspection stage to cause the situation of behind schedule. The following facing problems and difficulties are based on case study: (1) Because there is no suitable the updating and backup mechanism during the BIM models development, so that when BIM central model was deleted, BIM manager has to spend time to search for the latest BIM model file of BIM engineers, set it as a new BIM central model files, thereby affecting the progress of the work. (2) Although there are plans for the work range of BIM engineers, but did not set up authority of the work area, led to the work range of BIM engineer are influence each other during the BIM models development. (3) Some of BIM engineers lack the experience in construction site, the station BIM model has a lot of not comply with the application of the construction site, which led BIM model checking engineer needs to spend a lot of time to check model, resulting in the efficiency of collaborative BIM model development will decrease. The following recommendations are based on user feedback: (1) To develop the updating and backup mechanism for collaborative BIM model development. (2) To strict set the authority of work area when planning and assigning of work. (3) To enhance the experience of BIM engineers before the BIM model development, more experienced BIM engineers should explain that BIM model development does not always comply with the construction site. 5. CONCLUSIONS Use of BIM technology by the general contractor as a more efficient means of BIM models creation requires 7 591

8 collaboration among all members of a BIM team. If the approach does not have a complete management method, it is likely to require rework and have reduced overall operational efficiency. Therefore, the application of BIM work integrated with the BIM collaboration management mechanisms during the construction phase is discussed in this work. This study develops the novel BIM CM approach for all project participants as BIM CM mechanisms. As evidenced by a case study, there are several advantages to BIM collaboration management, including the following: 1. Through the set of standard operating procedures for BIM models development, BIM Team can develop BIM model with the same procedures, that can keeping the quality of model but also reducing time of check model of BIM model checking engineer, enhancing the efficiency of collaboration BIM modelling. 2. Three stages of the BIM model check mechanism can prevent the accumulation of problems with the BIM model leading to bigger problems, and training BIM engineer in professional abilities, enhancing the correctness and quality of BIM model. 3. Despite BIM model has a lot of project information, but also needs document and table to assist communication meeting and the process of check BIM model, those document and meeting records can track and record common problems of BIM collaboration work, and feedback to next BIM project. 4. Advanced planning of the BIM model environment settings in the server model is required to meet the project s model file framework. If the project needs more than two model files to execute the work, the server model can be split into multiple models for special purpose. The recommendations made as a result of the research findings are as follows: 1.Establish collaborative platform of BIM project, so that all BIM engineers and project stakeholders can coordinate communication through this platform to enhance BIM collaboration efficiency. 2. Currently, through human method to check models have limitations, this paper recommended to use the model check software assisted BIM model check work to shorten the working time of model check and maximize quality management of model. 3. Fill out table need to spend a long time, this paper recommended systematize the process of BIM modeling for filling out the table more quickly. 4. Because the requirements of the BIM model application for each project are different, this study suggests setting different model check mechanisms according to the model requirements with the appropriate level of detail to avoid wasting time performing unnecessary checks. ACKNOWLEDGMENTS The authors would like to acknowledge the National Science Council, Taiwan, for financially supporting this work and express our appreciation to the experts and engineers of the involved case study for providing useful data, valuable information, and helpful comments. REFERENCES Chen, H.M., Hou, C.C. (2014). Asynchronous online collaboration in BIM generation using hybrid client-server and P2P network. Automation in Construction, Vol.45, Das, M., Cheng, J., and Shiv Kumar, S. (2014). BIMCloud: A Distributed Cloud-Based Social BIM Framework for Project Collaboration. Computing in Civil and Building Engineering (2014), pp Kassem, M., Iqbal, N., Kelly, G., Lockley, S., Dawood, N. (2014). Building information modelling: protocols for collaborative design processes. Journal of Information Technology in Construction, ITcon Vol.19, Munkley, J., Kassem, M. and Dawood, N. (2014). Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study. Computing in Civil and Building Engineering (2014), pp Shafiq, M., Matthews, J, Lockley, S. (2013). A study of BIM collaboration requirements and available features in existing model collaboration systems. Journal of Information Technology in Construction, ITcon Vol.18, Shelbourn, M., Bouchlaghem, N.M., Anumba, C., Carrillo, P. (2007). Planning and implementation of effective collaboration in construction projects. Construction Innovation, 7 (4), Tian, Q. and Xue, X. (2014). Information Barriers in BIM Collaborative Application on Site. ICCREM 2014, Kunming, P.R. China, pp Wu, Y. and Xu, N., (2014). BIM Information Collaborative Framework Based on Supply Chain Management. ICCREM 2014, Kunming, P.R. China, pp Zada, A., Tizani, W., and Oti, A. (2014). Building Information Modelling (BIM) Versioning for Collaborative Design. Computing in Civil and Building Engineering (2014), pp

A Framework for Collaboration Management of BIM Model Creation in Architectural Projects

A Framework for Collaboration Management of BIM Model Creation in Architectural Projects A Framework for Collaboration Management of BIM Model Creation in Architectural Projects Yu-Cheng Lin* 1 and Hui-Hsuan Yang 2 1 Professor, Department of Civil Engineering, National Taipei University of

More information

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study 89 Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3

More information

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE

More information

Applications of Building Information Modeling (BIM) in Knowledge Sharing and Management in Construction

Applications of Building Information Modeling (BIM) in Knowledge Sharing and Management in Construction Applications of Building Information Modeling (BIM) in Sharing and Management in Construction Shu-Hui Jan, Shih-Ping Ho, Hui-Ping Tserng Abstract Construction knowledge can be referred to and reused among

More information

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM Page 1 of 5 The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM By Rick Oehmcke, S.E. Not that many years ago, few structural engineers

More information

The Impact of BIM and VDC on Company Business Processes

The Impact of BIM and VDC on Company Business Processes By Terry D. Bennett, LS LPF MRICS LEED AP Senior Industry Manager, Civil Engineering and Heavy Construction Autodesk, Inc. Paper prepared for presentation at the Geometric Design Lessons Learned: Case

More information

THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS

THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS Chung-Wei Feng 1 *, Osama Mustaklem 1, and Yi-Jao Chen 2 1 Department of Civil Engineering, National Cheng Kung University, Tainan,

More information

STUDY ON BIM-BASED STRUCTURAL WORKING DRAWING DESIGN SYSTEM

STUDY ON BIM-BASED STRUCTURAL WORKING DRAWING DESIGN SYSTEM STUD O BIM-BASED STRUCTURAL WORKIG DRAWIG DESIG SSTEM ong Wang, PhD, PMP, wangyong_tj@126.com Beijing Urban Construction Group Co. Ltd., Beijing, China Department of Civil Engineering, Tsinghua University,

More information

Title. Author(s)WENG-FONG CHEUNG; YU-CHENG LIN. Issue Date Doc URL. Type. Note. File Information

Title. Author(s)WENG-FONG CHEUNG; YU-CHENG LIN. Issue Date Doc URL. Type. Note. File Information Title THE DEVELOPMENT OF WEB-BASED INTEGRATING MANAGEMENT CONSTRUCTION LAB Author(s)WENG-FONG CHEUNG; YU-CHENG LIN Issue Date 2013-09-11 Doc URL http://hdl.handle.net/2115/54213 Type proceedings Note The

More information

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER PROJECT NAME BIM EXECUTION PLAN PROJECT INFORMATION CLIENT PROJECT NAME PROJECT NUMBER XX XXXXX XX XXXXX XXXXXXXXXXXXXXXXXXXXXXXXX DATE XXXXXXXX 2016 PROJECT LOCATION & ADDRESS XXXXX, XXXXX. INTRODUCTION...

More information

BIM for Building Water Supply and Drainage Design Rong Yang, Wenwu Song

BIM for Building Water Supply and Drainage Design Rong Yang, Wenwu Song International Conference on Automation, Mechanical Control and Computational Engineering (AMCCE 2015) BIM for Building Water Supply and Drainage Design Rong Yang, Wenwu Song School of Energy and Power

More information

Autodesk MEP Engineering Solutions. Engineer for energy efficiency.

Autodesk MEP Engineering Solutions. Engineer for energy efficiency. Autodesk MEP Engineering Solutions Engineer for energy efficiency. Deliver Sustainable Building Systems More Quickly and Economically Autodesk MEP Engineering Solutions help MEP engineers, designers, and

More information

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM WHAT S INSIDE: 1 BENEFITS Keep constructability top-of-mind Improve project margins Make better

More information

October 17-19, 2016 ATLANTA, GEORGIA. Coordination. Closing the Loop Between Design and Construction

October 17-19, 2016 ATLANTA, GEORGIA. Coordination. Closing the Loop Between Design and Construction October 17-19, 2016 ATLANTA, GEORGIA Coordination Closing the Loop Between Design and Construction COORDINATION Closing the Loop Between Design and Construction October 19, 2016 COORDINATION October 19,

More information

Application of BIM on Documenting Construction Defects

Application of BIM on Documenting Construction Defects Application of BIM on Documenting Construction Defects Ying-Mei Cheng Abstract This study aims to establish a system prototype using Autodesk Revit API to code the add-ins which display 3D elements with

More information

CHAPTER 7 Building Information Modeling

CHAPTER 7 Building Information Modeling CHAPTER 7 Building Information Modeling Dr Nabil Elsawalhi Associate Professor of Construction Management 1 Information and Communication Technology/ Building Information Modeling New approaches to construction

More information

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia

BIM FOR SURVEYORS. Survey Economics State of recovery. Tracking Wildlife With a total station. Measuring a Meridian Time in 1700s Philadelphia JUNE 2017 BIM FOR SURVEYORS Survey Economics State of recovery Tracking Wildlife With a total station Measuring a Meridian Time in 1700s Philadelphia A NEW MODEL FOR SURVEYORS As BIM moves into more projects

More information

BIM Event. Martin Huggins Senior R&D Consultant University of Wolverhampton. Black Country Constructing Excellence Club

BIM Event. Martin Huggins Senior R&D Consultant University of Wolverhampton. Black Country Constructing Excellence Club Black Country Constructing Excellence Club BIM Event Martin Huggins Senior R&D Consultant University of Wolverhampton Why Needed? 30% of construction is rework 60% of labour effort is wasted 10% loss due

More information

Electronic document management offers many advantages

Electronic document management offers many advantages Electronic document management offers many advantages Improves engineering productivity Fast Forward: Database-centric electrical computer-aided engineering (E-CAE) enhances productivity. In using E-CAE

More information

Windows Server 2003 migration: Your three-phase action plan to reach the finish line

Windows Server 2003 migration: Your three-phase action plan to reach the finish line WHITE PAPER Windows Server 2003 migration: Your three-phase action plan to reach the finish line Table of contents Executive summary...2 Windows Server 2003 and the big migration question...3 If only migration

More information

BEST PRACTICE COLLABORATION

BEST PRACTICE COLLABORATION WHITE PAPER BEST PRACTICE COLLABORATION Executive Summary The architecture, engineering and construction (AEC) industry was once almost synonymous with inefficiency and conflict, and was generally regarded

More information

Enhance Construction Visual As-Built Schedule Management Using BIM Technology

Enhance Construction Visual As-Built Schedule Management Using BIM Technology Enhance Construction Visual As-Built Schedule Management Using BIM Technology Shu-Hui Jan, Hui-Ping Tserng, Shih-Ping Ho Abstract Construction project control attempts to obtain real-time as-built schedule

More information

The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study

The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study Creative Construction Conference 2015 The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study Miranda Griffin, Scott W. Kramer, Ph.D.* 118 M. Miller Gorrie Center, Auburn

More information

The ProjectWise Advantage

The ProjectWise Advantage 2014 Bentley Systems, Incorporated The ProjectWise Advantage October 15, 2013 Eddie Anderson Global Practice Leader - ProjectWise Email Eddie.Anderson@Bentley.com LinkedIn - linkedin.com/in/eddiejanderson

More information

A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1

A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1 A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1 Yi-Wen Chen & Shang-Hsien Hsieh Department of Civil Engineering, National Taiwan University, Taipei, Taiwan ABSTRACT: Since the

More information

Discussion on the Application of BIM Technology in the Assembly Building

Discussion on the Application of BIM Technology in the Assembly Building Discussion on the Application of BIM Technology in the Assembly Building Abstract Yuanyuan Duan a, Hongyong Liu School of Southwest Petroleum University, Chengdu 610500, China a 1127900583@163.com With

More information

Autodesk BIM solutions for construction. Get started >

Autodesk BIM solutions for construction. Get started > Autodesk BIM solutions for construction Get started > Introduction Today s successful construction firms are adopting new practices that help them improve all areas of their business and create a competitive

More information

Analysis and design on airport safety information management system

Analysis and design on airport safety information management system Analysis and design on airport system Lin Yan School of Air Transportation, Shanghai University of Engineering Science, China Abstract. Airport system is the foundation of implementing safety operation,

More information

POSITION DESCRIPTION June 16, 2017

POSITION DESCRIPTION June 16, 2017 POSITION DESCRIPTION June 16, 2017 Common Name: Classification: Team / Section: Bureau / Division: ROOFING / BUILDING ENVELOPE PROJECT MANAGER ENGINEERING SPECIALIST MANAGEMENT Project Delivery Services

More information

Potential and Benefits of Building Information Modeling (BIM) During Pre-Construction, Construction and Post Construction Stage

Potential and Benefits of Building Information Modeling (BIM) During Pre-Construction, Construction and Post Construction Stage ANALELE UNIVERSITĂŢII EFTIMIE MURGU REŞIŢA ANUL XXIV, NR. 1, 2017, ISSN 1453-7397 Potential and Benefits of Building Information Modeling (BIM) During Pre-Construction, Construction and Post Construction

More information

Telstra. Telstra maximised their real estate utilisation, streamlined their move process and saved millions.

Telstra. Telstra maximised their real estate utilisation, streamlined their move process and saved millions. CASE STUDY Telstra Telstra maximised their real estate utilisation, streamlined their move process and saved millions. 51 commercial sites 448,000 sqm 39,000 staff 25 cities 7 states 1 platform Increased

More information

A Framework of BIM-Based Bridge Health Monitoring System

A Framework of BIM-Based Bridge Health Monitoring System International Conference on Civil, Transportation and Environment (ICCTE 2016) A Framework of BIM-Based Bridge Health Monitoring System Siqi Wang1, a, Jinsheng Du1, b and Jianyong Song2, c 1 School of

More information

Construction coordination

Construction coordination SBS5322 Basics of Building Information Modelling http://ibse.hk/sbs5322/ Construction coordination Ir. Dr. Sam C. M. Hui Faculty of Science and Technology E-mail: cmhui@vtc.edu.hk Jan 2018 Contents Construction

More information

Features to meet any requirement

Features to meet any requirement Storage and Retrieval Find any document instantly Store all of your electronic and scanned documentation in a secure, electronic repository that is accessible anywhere and at any time. Documents can be

More information

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES Mohamed Marzouk, Associate Professor, mm_marzouk@yahoo.com Mohamed Hisham, Graduate Student, mohamed1984_h@hotmail.com Construction

More information

This document describes the overall software development process of microcontroller software during all phases of the Company Name product life cycle.

This document describes the overall software development process of microcontroller software during all phases of the Company Name product life cycle. Maturity Process Owner Check Release Description Valid Name / Department Name / Department Name / Department Detailed procedure for software development Title: Software Development Procedure Purpose: This

More information

Application of BIM Based on Security in the Process of Engineering Construction

Application of BIM Based on Security in the Process of Engineering Construction Application of BIM Based on Security in the Process of Engineering Construction Weidong Wu, Chuxuan Ren, Yuhong Wang School of Civil Engineering and Architecture, SWPU, China Abstract In recent years,

More information

An innovative, smart, BIM-enabled product specification tool which streamlines collaboration and information sharing

An innovative, smart, BIM-enabled product specification tool which streamlines collaboration and information sharing The global leader in door opening solutions An innovative, smart, BIM-enabled product specification tool which streamlines collaboration and information sharing Openings Studio Introducing ASSA ABLOY s

More information

6 BIM FAILURES. The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak!

6 BIM FAILURES. The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak! 6 BIM FAILURES The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak! To meet the owner s performance requirements and complete the project

More information

Discussion Paper on the Validation of Pharmacovigilance Software provided via SaaS

Discussion Paper on the Validation of Pharmacovigilance Software provided via SaaS Discussion Paper on the Validation of Pharmacovigilance Software provided via SaaS June 2012 K Edmonds Page 1 of 10 Page 2 of 10 Contents 1. Introduction... 4 2. Quality Statement ISO 9001:2015... 4 3.

More information

Building Best-of-Breed File Collaboration Infrastructure for Concurrent Design

Building Best-of-Breed File Collaboration Infrastructure for Concurrent Design Building Best-of-Breed File Collaboration Infrastructure for Concurrent Design Contents Introduction......................................... 1 Concurrent Design Challenges................................

More information

Research on the Application of BIM in Sewage Treatment Project

Research on the Application of BIM in Sewage Treatment Project 5th International Conference on Sustainable Energy and Environment Engineering (ICSEEE 2016) Research on the Application of BIM in Sewage Treatment Project Jiayuan Wang, Xiaohan Han, Miao Qun*, Fengjiao

More information

VMware Network Virtualization Deploy Service

VMware Network Virtualization Deploy Service DATA SHEET VMware Network Virtualization Deploy Service AT-A-GLANCE The primary objective of this service is a rapid installation, configuration, and high-level validation (deployment) of a reference design

More information

White Paper Microsoft SharePoint for Engineering Document Management and Control

White Paper Microsoft SharePoint for Engineering Document Management and Control www.cadac.com White Paper Microsoft SharePoint for Engineering Document Management and Control Microsoft SharePoint is a powerful platform for document management and project collaboration. Many project-driven

More information

BUILDING INFORMATION MODELING (BIM) THE WHOLE TRUTH 10:30am 12:00pm. Presenter: Rod Yeoh, Principal, Omicron Architecture Engineering Construction

BUILDING INFORMATION MODELING (BIM) THE WHOLE TRUTH 10:30am 12:00pm. Presenter: Rod Yeoh, Principal, Omicron Architecture Engineering Construction BUILDING INFORMATION MODELING (BIM) THE WHOLE TRUTH 10:30am 12:00pm Presenter: Rod Yeoh, Principal, Omicron Architecture Engineering Construction Omicron AEC + Architecture, Engineering, & Construction

More information

Is the art and science of precision measurement and navigation in and on construction sites.

Is the art and science of precision measurement and navigation in and on construction sites. THEOMETRICS Is the art and science of precision measurement and navigation in and on construction sites. There is little benefit from Innovations without Implementation. Technology drives business only

More information

Best Practices for Creating an Open Source Policy. Why Do You Need an Open Source Software Policy? The Process of Writing an Open Source Policy

Best Practices for Creating an Open Source Policy. Why Do You Need an Open Source Software Policy? The Process of Writing an Open Source Policy Current Articles RSS Feed 866-399-6736 Best Practices for Creating an Open Source Policy Posted by Stormy Peters on Wed, Feb 25, 2009 Most companies using open source software know they need an open source

More information

QUICK FACTS. Supporting an International Infrastructure Organization with its Legacy Oracle ERP Environment

QUICK FACTS. Supporting an International Infrastructure Organization with its Legacy Oracle ERP Environment [ Professional Services, Enterprise Applications and Middleware Services ] TEKSYSTEMS GLOBAL SERVICES CUSTOMER SUCCESS STORIES Client Profile Industry: Asset and property management Revenue: More than

More information

Automated Building Code Checking Related Activities in Korea

Automated Building Code Checking Related Activities in Korea Automated Building Code Checking Related Activities in Korea Inhan Kim Professor, Kyung Hee University Chief Vice-Chairman, buildingsmart Korea http://buildingsmart.or.kr Contents 2 1. Seumter Status 2.

More information

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer PROJECT NAME By signature below, this Execution Plan is herewith adopted and incorporated into the Agreement, dated, for Professional Design Services between and Duke University. Duke University Architect

More information

International Research Journal of Engineering and Technology (IRJET) e-issn: Volume: 03 Issue: 01 Jan p-issn:

International Research Journal of Engineering and Technology (IRJET) e-issn: Volume: 03 Issue: 01 Jan p-issn: Contribution Of Building Information Modeling (BIM) To Solve Problems In Architecture, Engineering and Construction (AEC) Industry and Addressing Barriers to Implementation of BIM Vinay Kushwaha Assistant

More information

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Abstract Considering the significant amount of material wasted in the construction

More information

Design & Detailing, or why every structural steel project is not profitable

Design & Detailing, or why every structural steel project is not profitable How to maximize the benefits of 3D models throughout Intelligent Steel Fabrication PART 1 Design & Detailing, or why every structural steel project is not profitable Contents Background: Model behavior

More information

Owner has determined that this project is a Major Capital Renovation project as that term is defined herein.

Owner has determined that this project is a Major Capital Renovation project as that term is defined herein. BUILDING INFORMATION MODELING REQUIREMENTS Owner has determined that this project is a Major Capital Renovation project as that term is defined herein. PART 1 GENERAL 1.1. RELATED DOCUMENTS 1.1.1. Attention

More information

STREAMLINING PRODUCT DOCUMENTATION ACROSS THE MANUFACTURING ENTERPRISE WITH 3DVIA COMPOSER

STREAMLINING PRODUCT DOCUMENTATION ACROSS THE MANUFACTURING ENTERPRISE WITH 3DVIA COMPOSER W H I T E P A P E R STREAMLINING PRODUCT DOCUMENTATION ACROSS THE MANUFACTURING ENTERPRISE WITH 3DVIA COMPOSER Overview For many years, manufacturers simply had to accept more time delays and greater costs

More information

Research on Intelligent Logistics Development Model Based on Internet of Things and Cloud Computing in Big Data Age

Research on Intelligent Logistics Development Model Based on Internet of Things and Cloud Computing in Big Data Age Research on Intelligent Logistics Development Model Based on Internet of Things and Cloud Computing in Big Data Age Tao Zhang 1, Xiaoxia Wu 2 1 Hebei Professional College of Political Science and Law;

More information

Authentic BIM Collaboration using a Private Cloud and Virtual Workstations

Authentic BIM Collaboration using a Private Cloud and Virtual Workstations Authentic BIM Collaboration using a Private Cloud and Virtual Workstations Edward Lick STV Incorporated Christopher Bradt STV Incorporated Matthew Dierolf STV Incorporated CM5549 This lecture will illustrate

More information

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED IN LEADERSHIP AND MANAGEMENT The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering

More information

Promoting better business outcomes through the use of BIM and digital technologies.

Promoting better business outcomes through the use of BIM and digital technologies. Promoting better business outcomes through the use of BIM and digital technologies. Introduction The Role of the BIM Manager Agenda 18:00 Introduction + BIM update by Mike Turpin, Innovating Futures 18:10

More information

Streamlining Product Documentation across the Manufacturing Enterprise with 3DVIA Composer

Streamlining Product Documentation across the Manufacturing Enterprise with 3DVIA Composer white paper Streamlining Product Documentation across the Manufacturing Enterprise with 3DVIA Composer SUMMARY For many years, manufacturers simply had to accept more time delays and greater costs as they

More information

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM Mounir El Asmar, Ph.D., Assistant Professor, asmar@asu.edu School of Sustainable Engineering and the Built Environment,

More information

1.1 IT Requirement of Employer - MMRCL Digital Project management platform to be used for PMRCL

1.1 IT Requirement of Employer - MMRCL Digital Project management platform to be used for PMRCL 1.1 IT Requirement of Employer - MMRCL Digital Project management platform to be used for PMRCL 1.1.1 Employer s Enterprise wide IT system i.e. Digital Project Management Platform will be the working environment

More information

BIM Standard and Specifications for San Mateo County. Project Development Unit

BIM Standard and Specifications for San Mateo County. Project Development Unit BIM Standard and Specifications for San Mateo County Project Development Unit Table of Contents A. INTRODUCTION AND GENERAL REQUIREMENTS... 2 B. DEFINITIONS, TERMS, AND DESCRIPTIONS... 3 C. BIM KICK OFF

More information

COMPATIBILITY OF BIM BASED BOQ FOR SRI LANKAN CONSTRUCTION INDUSTRY

COMPATIBILITY OF BIM BASED BOQ FOR SRI LANKAN CONSTRUCTION INDUSTRY COMPATIBILITY OF BIM BASED BOQ FOR SRI LANKAN CONSTRUCTION INDUSTRY M.W. Thiwanka Sandaruwan 1 and H.S. Jayasena 2 1 Department of the Built Environment, Liverpool John Moores University, United Kingdom

More information

The SMART Visual Collaboration Solution

The SMART Visual Collaboration Solution Architecture, Engineering and Construction The SMART Visual Collaboration Solution With powerful software, featuring innovative unbound workspaces, and industry-leading interactive displays, you have everything

More information

Challenges and Obstacles of Adoption BIM Technology in the Construction Industry in Iraq

Challenges and Obstacles of Adoption BIM Technology in the Construction Industry in Iraq Challenges and Obstacles of Adoption BIM Technology in the Construction Industry in Iraq Hussein M. Hamada, Ahmad Tarmizi Haron, Zahrizan Zakaria Faculty of Civil Engineering and Earth Resources, University

More information

Riverbed SteelCentral

Riverbed SteelCentral Product Family Brochure Riverbed SteelCentral Managing Your Digital Experience Two-thirds of Enterprises are Investing in Digital Business Today is the era of digital business. Digital capabilities and

More information

Building Information Modeling to Facilities Information Management and Beyond

Building Information Modeling to Facilities Information Management and Beyond Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas

More information

Building Tomorrow Today: Spotlight on Autodesk Navisworks & BIM 360 Glue

Building Tomorrow Today: Spotlight on Autodesk Navisworks & BIM 360 Glue Building Tomorrow Today: Spotlight on Autodesk Navisworks & BIM 360 Glue Deepak Maini Technical Head Manufacturing Solutions Cadgroup Australia Join us on Twitter: #AU2014 Quick Introduction Technical

More information

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company?

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company? Organisation Type The first national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 67% of the industry sample possessed confidence in their skills

More information

BBK3253 Knowledge Management Prepared by Dr Khairul Anuar

BBK3253 Knowledge Management Prepared by Dr Khairul Anuar BBK3253 Knowledge Management Prepared by Dr Khairul Anuar L5: Supporting Knowledge Management through Technology www.notes638.wordpress.com Knowledge management systems (KMS) provide an important platform

More information

Managing Digital Experience with Riverbed SteelCentral

Managing Digital Experience with Riverbed SteelCentral Solution Brochure Managing Digital Experience with Riverbed SteelCentral Today is the era of digital business. Two-thirds of enterprises are investing in digital business. Digital capabilities and IT were

More information

Basic Model and Profit Channel of the Integrated Energy Services

Basic Model and Profit Channel of the Integrated Energy Services International Conference on Material Science, Energy and Environmental Engineering (MSEEE 2017) Basic Model and Profit Channel of the Integrated Energy Services Shiyu Meng1, a, Jinyue Dou1, Zhuhan Long1,

More information

The research of intelligent substation project management mode based on RFID

The research of intelligent substation project management mode based on RFID 2nd International Conference on Automation, Mechanical Control and Computational Engineering (AMCCE 207) The research of intelligent substation project mode based on RFID Chenglei Sun, 2, a, Ke Zhang,

More information

Using BIM to Automate Information Generation for Assembling Scaffolding -A Material Management Approach

Using BIM to Automate Information Generation for Assembling Scaffolding -A Material Management Approach Using BIM to Automate Information Generation for Assembling Scaffolding -A Material Management Approach C. W. Feng a and T. F. Hsu b Department of Civil Engineering, National Cheng Kung University, Taiwan

More information

FROM AUTOCAD TO ADVANCE STEEL 1 MOVE FROM 2D TO 3D WITH ADVANCE STEEL BASED ON AUTOCAD

FROM AUTOCAD TO ADVANCE STEEL 1 MOVE FROM 2D TO 3D WITH ADVANCE STEEL BASED ON AUTOCAD FROM AUTOCAD TO ADVANCE STEEL 1 MOVE FROM 2D TO 3D WITH ADVANCE STEEL BASED ON AUTOCAD FROM AUTOCAD TO ADVANCE STEEL 2 CONTENTS 1 2 3 LEVERAGE YOUR AUTOCAD INVESTMENT WITH DEDICATED TOOLS FOR STRUCTURAL

More information

DRY CREEK OFFICE / ARROW ELECTRONICS HQ

DRY CREEK OFFICE / ARROW ELECTRONICS HQ DRY CREEK OFFICE / ARROW ELECTRONICS HQ Category: 5 Best Building Project Specialty Contractor ($2M - $6M) Specialty Contractor: Weifield Group Contracting Project Name: Dry Creek Office / Arrow Electronics

More information

APPLICATION OF CLOUD COMPUTING AND INTERNET OF THINGS FOR INFRASTRUCTURE PROJECTS: A REVIEW OF LITERATURE

APPLICATION OF CLOUD COMPUTING AND INTERNET OF THINGS FOR INFRASTRUCTURE PROJECTS: A REVIEW OF LITERATURE APPLICATION OF CLOUD COMPUTING AND INTERNET OF THINGS FOR INFRASTRUCTURE PROJECTS: A REVIEW OF LITERATURE Dr. Debasis Sarkar, Harsh H. Patel Pandit Deendayal Petroleum University ABSTRACT This paper is

More information

Aras Accelerates Innovation at GETRAG FORD Transmissions

Aras Accelerates Innovation at GETRAG FORD Transmissions Aras Accelerates Innovation at GETRAG FORD Transmissions Aras is used as our PLM platform to not just automate, but to develop new business processes at GETRAG FORD Transmissions. The upshot is that because

More information

Director, Enterprise Technology JOB CLASS: Software Architect PAY GRADE: 39 EXEMPT STATUS: Exempt DATE: 05/27/2016

Director, Enterprise Technology JOB CLASS: Software Architect PAY GRADE: 39 EXEMPT STATUS: Exempt DATE: 05/27/2016 JOB DESCRIPTION: ENTERPRISE DATA ARCHITECT DEPARTMENT: Information Technology REPORTS TO: Director, Enterprise Technology JOB CLASS: Software Architect PAY GRADE: 39 EXEMPT STATUS: Exempt DATE: 05/27/2016

More information

Development of Financial Systems

Development of Financial Systems Subsection: Financial Systems Page: 1 of 5 Development of Financial Systems Objective Authority Applicability The objective is to outline the requirements for the development of financial systems. The

More information

VEIL of OPPORTUNITY AND/OR VEIL of CONFUSION. Presented by: Carmine Militano, P.Eng. Senior VP Business Development and Innovation December 10, 2014

VEIL of OPPORTUNITY AND/OR VEIL of CONFUSION. Presented by: Carmine Militano, P.Eng. Senior VP Business Development and Innovation December 10, 2014 VEIL of OPPORTUNITY AND/OR VEIL of CONFUSION Presented by: Carmine Militano, P.Eng. Senior VP Business Development and Innovation December 10, 2014 The A/E/C industry is being transformed through a number

More information

CONSTRUCTION SOFTWARE. E V O L V E D. CMiC Corporate Overview

CONSTRUCTION SOFTWARE. E V O L V E D. CMiC Corporate Overview CONSTRUCTION SOFTWARE. E V O L V E D CMiC Corporate Overview About Us The Competitive Difference CMiC Open Enterprise v10: Construction Software Evolved CMiC Corporate Overview The CMiC Team What CMiC

More information

Risk Mitigation in a Core Banking Conversion

Risk Mitigation in a Core Banking Conversion Risk Mitigation in a Core Banking Conversion Greg Meidt, chief information officer Chemical Bank Dick Smies, vice president IBS Conversion Services 1 800 822 6758 Introduction A core banking migration

More information

ctbuh.org/papers Reform Measures of Korea s High-rise Buildings Construction Period Title: Ki-In Kim, Senior Manager, HanmiParsons Co., Ltd.

ctbuh.org/papers Reform Measures of Korea s High-rise Buildings Construction Period Title: Ki-In Kim, Senior Manager, HanmiParsons Co., Ltd. ctbuh.org/papers Title: Author: Subject: Keywords: Reform Measures of Korea s High-rise Buildings Construction Period Ki-In Kim, Senior Manager, HanmiParsons Co., Ltd. Construction Construction Project

More information

20/02/2016. The BIM Hub. A trusted environment for BIM professionals. Why BIM? Why BIM? We need a more Sustainable Model of Building Procurement

20/02/2016. The BIM Hub. A trusted environment for BIM professionals. Why BIM? Why BIM? We need a more Sustainable Model of Building Procurement BENEFIT 20/02/2016 The BIM Hub A trusted environment for BIM professionals The I in BIM Why BIM? What is BIM? Benefits of BIM? BIM for Product Manufacturers thebimhub and Cadenas Why BIM? We need a more

More information

Executive Summary... 1 The Six Steps in Brief... 2 Pre-implementation Stage... 3 Design Stage... 4

Executive Summary... 1 The Six Steps in Brief... 2 Pre-implementation Stage... 3 Design Stage... 4 Executive Summary... 1 The Six Steps in Brief... 2 Pre-implementation Stage... 3 Design Stage... 4 Step 1: Discovery... 4 Step 2: Design... 6 Step 3: Proof of Concept... 8 Deployment Stage...10 Step 4:

More information

Autodesk Vault Family of Products. Manage your entire design.

Autodesk Vault Family of Products. Manage your entire design. Autodesk Vault Family of Products Manage your entire design. Stay In Control Imagine finding design data in seconds. Sharing digital prototyping information securely with team members across the world.

More information

Unit 3: Traditional Project Delivery Using IT Applications

Unit 3: Traditional Project Delivery Using IT Applications Unit 3: Traditional Project Delivery Using IT Applications 3.1 Construction Project Process Flow i. In a typical construction project, the major key to its success hinges on how well the project process

More information

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability

More information

BIM (Building Information Modelling) Joseph Kubin

BIM (Building Information Modelling) Joseph Kubin BIM (Building Information Modelling) Joseph Kubin Mühendislik BIM Building Information Modelling BIM, is a way of describing a collaboration design process using computer model data rather than separate

More information

Bringing Order out of Chaos

Bringing Order out of Chaos Bringing Order out of Chaos How architects can use simple Lean concepts to double the project team s productivity and maximize client satisfaction Susan Pratt Susan@PrattAandM.com AEC Labor Productivity

More information

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D

More information

INFRASTRUCTURE TECHNICIAN

INFRASTRUCTURE TECHNICIAN Group INFRASTRUCTURE TECHNICIAN LEVEL 3 APPRENTICESHIP WHAT IS IT? An Infrastructure Technician provides support to internal and external customers useing tools to problem solve and trouble shoot non-routine

More information

Meeting Management Solution

Meeting Management Solution Meeting Management Solution 707 17 th Street Suite 4000 Denver, CO 80202 Alex Chacon 800-274-5624 x703 Prepared For Sarasota Public Schools Date Updated 04-20-2018 Valid for 90 Days Executive Summary...

More information

Available online at ScienceDirect. Procedia Engineering 138 (2016 )

Available online at   ScienceDirect. Procedia Engineering 138 (2016 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 138 (2016 ) 413 420 SYMPHOS 2015, 3rd International Symposium on Innovation and Technology in the Phosphate Industry The Computerized

More information

AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM

AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM Introduction AIA 2009 BIM AWARDS Category B: Design/Delivery Process Innovation Using BIM Project: UNIVERSITY OF COLORADO - DENVER HEALTH SCIENCE CENTER RESEARCH COMPLEX II Owner s Statement Architect

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

Saurabh Gangwar 2018 Project Management Symposium

Saurabh Gangwar 2018 Project Management Symposium Name UMD Project Management Symposium May 10-11, 2018 Slide 1 FROM PEOPLE MANAGEMENT TO INFORMATION MANAGEMENT Impact of technology on project management in the design and construction industry Saurabh

More information