1 ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018

2 AMERICAN SOCIETY OF HIGHWAY ENGINEERS National Project of the Year Award OFFICIAL ENTRY FORM AWARD CATEGORY (Check One): Under $20 Million Over $20 Million SPONSORING REGION (Check One): Northeast Mid-Atlantic Southeast Great Lakes North Central South Central Northwest Rocky Mountain Southwest CONTACT INFORMATION FOR SPONSORING REGION: Primary Contact Name: ASHE Region Position: Phone (Office): Phone (Mobile): Address: Secondary Contact Name: ASHE Region Position: Phone (Office): Phone (Mobile): Address: PROJECT INFORMATION (From Section Entry): ENTERING AGENCY/COMPANY S NAME: PROJECT NAME: PROJECT LOCATION: CITY: CONSTRUCTION COST: PROJECT COMPLETION DATE: TYPE: COUNTY: BUDGETED CONSTRUCTION COST: PROJECT OWNER: STREET ADDRESS: CITY: STATE: ZIP: PHONE: FAX: CONTACT PERSON: ADDRESS: PROJECT DESIGN FIRM: STREET ADDRESS: CITY: STATE: ZIP: PHONE: FAX: CONTACT PERSON: ADDRESS: PRIME CONTRACTOR: STREET ADDRESS: CITY: STATE: ZIP: PHONE: FAX: CONTACT PERSON: ADDRESS: Entry Form Completed By: Date:

3 Project Description: CDR Maguire Inc. (CDR-M) was retained by PennDOT District 12-0 to design the SR 0136-G10 Bridge Replacement in Eighty Four, Washington County, PA. CDR-M provided project design engineering, environmental permitting, railroad and utility coordination, public/community outreach, and construction consultation services. Subconsultants included American Geotechnical & Environmental Services for Geotechnical Design, ARROW Land Solutions for Right-of-Way Acquisition, and Monaloh Basin Engineers for Survey. This project replaced a 70-year-old structurally deficient 4-span bridge. The replacement structure is a 2-span continuous, 206-foot-long steel multi-girder bridge supported on integral abutments and a pier which carries three lanes of SR 0136 over Little Chartiers Creek and the B&O (CSX) Railroad. The bridge was raised 2 feet to meet current vertical clearance requirements over the railroad. Because of high traffic volumes and lengthy detour, the bridge was designed and constructed using Accelerated Bridge Construction (ABC) methods resulting in a detour duration of just 24 days. Complexity: If this bridge was constructed using conventional methods, it would have been of nominal complexity for a 2-span steel plate girder bridge. However, the use of ABC introduced several complexities that needed addressed to ensure a successful project: Deflections: The girder camber and deck deflection during precasting needed to be considered to ensure that the field splices could be assembled at the site. Field Splices: Access to the tops of the girders for assembly of the field splices needed to be provided. Precise Fabrication: Grouted splice couplers used to connect the various precast elements provided very little fabrication tolerance for fitment. Foundations: Working adjacent to the existing pier and abutment foundations while avoiding interference with existing piles or compromising the integrity of the existing pier was critical. Site Restrictions: The site boundaries were very tight, limiting the room to work without exceeding environmental permit constraints. Crane Sizing: Heavy pick weights with long reaches over a creek and a railroad required a large crane. The contractor used a 650-ton Manitowoc VPC crawler crane located near the pier which enabled him to erect the entire bridge with a single crane. New Application of Existing Techniques / Originality / Innovation: The SR 0136-G10 Bridge Project is the first 2-span continuous bridge replacement constructed using ABC in Pennsylvania. ASTM A709-Grade 50W Weathering Steel Plate girders were paired up and a lightweight composite precast concrete bridge deck was cast onto them to form Prefabricated Bridge Units (PBUs). SR 0136-G10 ABC Bridge Replacement Page 1 of 3

4 Three PBUs were connected using bolted field splices between the positive and negative moment regions to create two 103-foot-long continuous spans. This eliminated the need for a link slab or transverse joint at the pier. Four sets of PBUs formed the full bridge width. To access the field splices for bolting, a 4-foot gap was provided in the deck. Precast concrete infill panels were used to fill these gaps. Ultra High-Performance Concrete (UHPC), with a compressive strength of approximately 21 ksi, was used in the longitudinal and transverse closure pours to connect the PBUs and infill panels. Precast concrete approach slabs were used and connected using UHPC. An epoxy overlay was then applied over the superstructure. The superstructure is supported on integral abutments and a 3-column pier. The integral abutments, wingwalls, cheekwalls, and backwalls utilized precast concrete for quick assembly at the site. The abutment caps were formed with 30 diameter sleeves to accommodate the piles that were driven prior to assembly. These sleeves were then grouted, and the rest of the elements connected to the abutment cap using grouted splice couplers. The pier foundation was cast-in-place under the existing bridge prior to demolition. The proximity of the new pier foundation to the existing pier created some concerns. A layer of claystone required the bottom of the new pier foundation to be approximately 16 feet below the foundation of the existing pier. Opening a large excavation this deep adjacent to the existing pier while under live traffic would negatively affect the integrity of the existing pier. Extensive shoring was considered. However, limited work space between the creek, the existing pier, and the railroad proved to be prohibitive. As a solution, a series of 60 diameter drilled caissons with steel shells were constructed in a tight pattern. This allowed for the foundation bearing loads to be transferred to bedrock without opening a large, unsupported excavation next to the existing pier. Once the caissons were completed, the cast-in-place spread footing and pier shaft section were poured with the top of shaft set at one foot above the 100-year flood elevation. Once the existing bridge was closed and demolished, the pier was completed using precast concrete columns, cap, and beam seats. Similar to the integral abutments, the pier elements are connected together using grouted slice couplers. Social/Economic Considerations and Safety: The use of ABC on this project provided significant benefits. While ABC typically averages about 20% higher cost than conventional construction, this cost is more than offset by the savings in road user costs. The Road User Liquidated Damages for this project amounted to $50,000 per day based on the traffic volume and detour length. Assuming this project would require 6 months of detour for conventional construction, versus 1 month for ABC, there is a savings of 5 months or approximately 150 days. This amounts to $7.5M. Alternatively, with an ADT of approximately 5,000 vehicles per day traveling a 13 mile detour route, this amounts to an extra 65,000 miles per day or 9.75 million miles over the 5 months extra construction duration. With a 20 mpg average and gasoline cost at $2.50 per gallon, the use of ABC on this project saved the traveling public $1.22M in fuel costs alone. This cost does not even account for wear and tear on the vehicles or lost time it takes to travel the extra 13 miles every day. The project also provided direct benefits by way of improvements in the function of the transportation system locally. The new bridge allowed for the lengthening of the center left turn lane at the signalized intersection with SR east of the bridge. It also raised the vertical clearance over the railroad to meet current SR 0136-G10 ABC Bridge Replacement Page 2 of 3

5 criteria. Because it was designed to current standards, the bridge is safer due to details such as current barrier details and protective fencing over the railroad. Aesthetics and Sustainable Features: While the project did not warrant any special aesthetic details, a sustainable design that minimized future maintenance was prioritized. Integral abutments and a continuous span design resulted in a jointless superstructure. High quality precast concrete elements and UHPC closure pours ensure a long service life while weathering steel for the girders and cross frames eliminates the need for painting or other coatings. And finally, the girder lines are arranged in a manner that considers future re-decking schemes that minimize impacts to traffic. Meeting and Exceeding /Owner Needs: As described above, the use of ABC increased the project cost over conventional construction. The bids were about 24% higher than the engineer s estimate. The total budgeted cost was $7.1M while the project actual cost was $8.8M. Several factors are believed to have contributed to the increased cost. The project was in competition with PennDOT s ongoing P3 Rapid Bridge Replacement project for materials procurement and fabrication. Additionally, because the amount of time between the project letting and the required start date was short, a premium was paid to meet the aggressive schedule. Also, the unlimited $50,000 per day disincentive cost may have lead the contractor to build in costs to offset the risk of running over schedule. PennDOT has not done many ABC projects, resulting in minimal item price history to adequately predict costs. As more projects are constructed using ABC, it is anticipated that costs will lower and become more predictable due to increased comfort and competition between contractors, suppliers, and fabricators. Dedication to teamwork, communication, and coordination by all parties ultimately resulted in a successful project. Clear contract documents and details and timely reviews allowed the contractor and his fabricators to quickly develop shop drawings to advance procurement of materials and fabrication to meet the aggressive schedule. Detailed reviews, attention to detail, and tight tolerances during fabrication ensured proper fitment of the elements in the field, avoiding delays. Because of everyone s efforts, the project was completed on September 30, 2016 in just 24 days of detour duration 4 days ahead of the scheduled deadline of October 4, Summary: The SR 0136-G10 Bridge Replacement Project is a significant project for a variety of reasons. It was the first 2-span continuous bridge replacement designed and built using ABC methods in Pennsylvania. The use of ABC introduced unique challenges including critical detailing to ensure fit, integral abutment and pier foundation design to accommodate the existing structure, and crane sizing to construct the project. The entire team, from the owner (PennDOT), the consultant (CDR Maguire), and the contractor (Brayman Construction) were committed to the success of the project. This resulted in the project being completed ahead of an already very aggressive schedule. Therefore, CDR Maguire believes this project is worthy of recognition. SR 0136-G10 ABC Bridge Replacement Page 3 of 3

6 Photo 1: Longitudinal Reinforcing at Girder Field Splice SR 0136-G10 ABC Bridge Replacement Page 1 of 5

7 Photo 2: Cast-In-Place Pier Shaft Section Construction under Existing Bridge SR 0136-G10 ABC Bridge Replacement Page 2 of 5

8 Photo 3: Erected Precast Pier Columns and Bent with Adjacent Temporary Towers SR 0136-G10 ABC Bridge Replacement Page 3 of 5

9 Photo 4: Span 2 Deck Module Erection with Erected Negative Moment Region SR 0136-G10 ABC Bridge Replacement Page 4 of 5

10 Photo 5: Filler Panel and Transverse Closure Pours Over Field Splice SR 0136-G10 ABC Bridge Replacement Page 5 of 5

11

12

13

14

15

16 STATEMENT OF COMMITMENT: CDR Maguire Inc. commits that at least one representative of the project team will attend the awards luncheon. SR 0136-G10 ABC Bridge Replacement Page 1 of 1

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction 2018 Virginia Concrete Conference March 2, 2018 Bardia Emami, PE Outline Projects

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights

More information

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be

More information

Presented by: Taya Retterer BRG Webinar July 30, 2012

Presented by: Taya Retterer BRG Webinar July 30, 2012 Presented by: Taya Retterer BRG Webinar July 30, 2012 PHASED CONSTRUCTION RECOMMENDATIONS FOR BRIDGES Will be posted to the TxDOT Website http://www.dot.state.tx.us/business/contractors_consultants/bridge/default.htm

More information

The Pennsylvania Rapid Bridge Replacement Project

The Pennsylvania Rapid Bridge Replacement Project 1 The rebuilding of 558 structurally deficient bridges in the Commonwealth of Pennsylvania over a 3+ year span April 2017 Charles Zugell The Plenary Walsh Keystone Partners believe engaging local community

More information

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

PHASING CONSIDERATIONS FOR BRIDGES

PHASING CONSIDERATIONS FOR BRIDGES PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada

More information

SOUTH MEDFORD INTERCHANGE BRIDGES

SOUTH MEDFORD INTERCHANGE BRIDGES Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is

More information

Accelerated Bridge Construction (ABC) National Status

Accelerated Bridge Construction (ABC) National Status Accelerated Bridge Construction (ABC) National Status by Mary Lou Ralls, P.E., Ralls Newman, LLC 88 th Annual Transportation Short Course Texas A&M University College Station, Texas Session: Construction

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc. Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing

More information

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction Gregory A. Banks, Myles Parrish, Charles W. Spry WSDOT ABC Workshop April 2015 Project Overview Location Located in Renton, WA PROJECT

More information

Accelerated and Innovative Bridge Construction In Washington State

Accelerated and Innovative Bridge Construction In Washington State Accelerated and Innovative Bridge Construction In Washington State Bijan Khaleghi Bijan.Khaleghi@WSDOT.WA.Gov Washington State Department of Transportation Bridge and Structures Office Olympia Washington

More information

Boeing North Bridge in Washington State

Boeing North Bridge in Washington State Boeing North Bridge in Washington State Gregory A. Banks ABC-UTC Webinar May 2015 Project Overview -Location Located in Renton, WA PROJECT SITE RENTON 2 Project Overview Site Layout Lake Washington Existing

More information

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal FEHRL Long Life Bridges SQUARE (Brussels) Thursday June 10, 2010 Objective RAPID RENEWAL Bridge Systems WHAT IS THE BIG IDEA? Manufactured Bridges

More information

I-94/I-69 Interchange Bridge Construction

I-94/I-69 Interchange Bridge Construction I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) , PLACEMENT OF PRECAST PRESTRESSED CONCRETE GIRDER BRIDGE SPANS WITH SELF PROPELLED MODULAR TRANSPORTERS PIONEER CROSSING DESIGN/BUILD PROJECT, AMERICAN FORK, UT Steve Haines, P.E., Parsons, (303) 831-8100,

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C Accelerated Design-Build Replacement of SEPTA s Crum Creek Viaduct Jeffrey D. Knueppel, P.E. General Manager Robert L. Lund, Jr., P.E. Assistant General Manager EM&C Key Presentation Take-Aways NEED TO

More information

Accelerated Bridge Construction in USA

Accelerated Bridge Construction in USA Accelerated Bridge Construction in USA Abstract Rush hour traffic is a common daily occurrence in the USA. Highway and bridge construction further aggravates the situation. The Federal Highway Administration

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

PRECAST CONCRETE GIRDER ERECTION

PRECAST CONCRETE GIRDER ERECTION 7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

Ministry of Forests & Range

Ministry of Forests & Range Ministry of Forests & Range DRAWING SCHEDULE DRAWING No. / MODEL TYPE STD-EC-040-01 STD-EC-040-02 STD-EC-040-03 STD-EC-040-04 STD-EC-040-05 STD-EC-040-06 STD-EC-040-07 STD-EC-040-08 DESCRIPTION REV. DATE

More information

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change

More information

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa 2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price

More information

ABC Techniques for Rapid Bridge Replacement. Bala Sivakumar HNTB Corporation. Purdue Road School 2017

ABC Techniques for Rapid Bridge Replacement. Bala Sivakumar HNTB Corporation. Purdue Road School 2017 ABC Techniques for Rapid Bridge Replacement Bala Sivakumar 03.08.2017 HNTB Corporation Purdue Road School 2017 Outline Introduction to ABC ABC Technologies Precast Decks SHRP2 ABC Toolkit Implementing

More information

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi

More information

7 Bridges in 74 Days. NC 12 Detour

7 Bridges in 74 Days. NC 12 Detour 7 Bridges in 74 Days (Or Less) NC 12 Detour Ocracoke NC 12 Bridges Ocracoke NC 12 Bridges Existing 7 bridges built in 1950's Timber structures w/ ACP Clear width 22.5 ft. 36 to 152 ft. long Limited redirective

More information

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre 10.26.2016 HNTB Corporation Outline Overview of WV TPK Ghent NB Bridge Existing Conditions ABC Deck Replacement Alternatives

More information

Accelerated Bridge Construction Award

Accelerated Bridge Construction Award Accelerated Bridge Construction Award PBES SR 288 Main Street Bridge Project Wampum Borough, Pennsylvania This is a first for PADOT to incorporate an all precast project built in an accelerated manner

More information

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng. SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Construction Innovations / Sustainability

Construction Innovations / Sustainability Category: 2 Meeting the Challenge of a Difficult Job Specialty Contractor Contractor: Baker Concrete Construction, Inc. Project Name: Confluence Park Tower Project Overview Construction projects are never

More information

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... LECTURE 13 May 17, 2005 May 17, 2005 1 Where we have been Basics Allowable Stress Ultimate Strength Shear Camber

More information

ABRAHAM LINCOLN BRIDGE

ABRAHAM LINCOLN BRIDGE ABRAHAM LINCOLN BRIDGE PROJECT LOCATION: CONNECTING LOUISVILLE, KY WITH JEFFERSON, IN ACROSS THE OHIO RIVER. CATEGORY B: TRANSPORTATION PROJECT OWNER: KENTUCKY TRANSPORTATION CABINET COWI North America

More information

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION PRELIMINARY DESIGN SUBMISSION REPORT For U.S. Route 130 Over Raccoon Creek Bridge Township of Logan Gloucester County, New Jersey Prepared By: Structural

More information

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE Conference Center at the Maritime Institute Anne Arundel County, Maryland Thursday, April 28, 2016 Two bridges in Two Months - Accelerated

More information

Replacing the Aging US 52 Mississippi River Bridge

Replacing the Aging US 52 Mississippi River Bridge 2019 TRANSPORTATION & HIGHWAY ENGINEERING CONFERENCE F. Duncan, PE, G. Hasbrouck, PE and A. Dour, PE Replacing the Aging US 52 Mississippi River Bridge February 26, 2019 Project Overview US 52 / IL 64

More information

MODULAR STEEL SUPERSTRUCTURES FOR ACCELERATED BRIDGE CONSTRUCTION - IOWA DOT CASE STUDIES

MODULAR STEEL SUPERSTRUCTURES FOR ACCELERATED BRIDGE CONSTRUCTION - IOWA DOT CASE STUDIES MODULAR STEEL SUPERSTRUCTURES FOR ACCELERATED BRIDGE CONSTRUCTION - IOWA DOT CASE STUDIES NORM McDONALD CURTIS CARTER AHMAD ABU-HAWASH BIOGRAPHY Norm McDonald is the director of the Office of Bridges and

More information

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts Supplemental Technical Specification for Bi-Directional Static Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 2, 2015 1.0 GENERAL This work shall consist of furnishing all

More information

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts Supplemental Technical Specification for Bi-Directional Static Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (01/18) 1.0 GENERAL This work shall consist of furnishing all materials, equipment,

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation STANDARDIZED CONCRETE BRIDGES IN TEXAS John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation ABSTRACT Standardized concrete bridge plans are used extensively

More information

ACCELERATED BRIDGE CONSTRUCTION IN TEXAS. Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M.

ACCELERATED BRIDGE CONSTRUCTION IN TEXAS. Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M. ACCELERATED BRIDGE CONSTRUCTION IN TEXAS Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M. Holt, PE 5 ABSTRACT The Texas Department of Transportation (TxDOT)

More information

District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016

District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About

More information

Norfolk Southern s Online Rebuild of the Coosa River Bridge

Norfolk Southern s Online Rebuild of the Coosa River Bridge Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida 32202 Telephone:

More information

Final Estimates Level 2

Final Estimates Level 2 Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure

More information

Rapid Axial Load Testing of Drilled Shafts

Rapid Axial Load Testing of Drilled Shafts Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS

MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS SECTION 1 - MISCELLANEOUS STANDARDS 1.00.01 -.05 Table of Contents 1.11.01 Decimal Parts of a Foot and Inch 1.21.01 Factors

More information

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199)) 11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of

More information

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE Paul Gauvreau University of Toronto, Canada (formerly J. Muller International) Thomas E. Kelly, Jr. Earth Tech/J.

More information

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses Replacement of the BNSF Approach Spans over the Mississippi River DAVID ROGOWSKI, P.E. AND JOSH CRAIN, Genesis Structures Inc., Kansas City, Missouri and DAN SIEVE AND KEVIN BECKER, Walsh Construction

More information

Application of Ultra High Performance Concrete in Expediting the Replacement and Rehabilitation of Highway Bridges

Application of Ultra High Performance Concrete in Expediting the Replacement and Rehabilitation of Highway Bridges Application of Ultra High Performance Concrete in Expediting the Replacement and Rehabilitation of Highway Bridges Abstract M. Ataur Rahman, P.Eng., Ph.D. and Tyler McQuaker, P.Eng. Ministry of Transportation

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS Quarterly Progress Report For the period ending August 31, 2018 Submitted by: PIs - Armin Mehrabi, Hesham Ali Graduate Students - Mohamadtaqi

More information

PUBLIC INFORMATION MEETING June 24, 2015

PUBLIC INFORMATION MEETING June 24, 2015 Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase

More information

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch Warwick Triangle Viaduct: Outbound INTRODUCTION The Warwick Triangle Precinct in Durban is one of the busiest trading and transport hubs in Africa. Major traffic conflict resulted from the movement of

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

Ellis Powell, PE NCDOT State Construction Engineer

Ellis Powell, PE NCDOT State Construction Engineer 7 Bridges in 74 Days (Or Less) Ellis Powell, PE NCDOT State Construction Engineer NC 12 Detour Ocracoke Island Former hangout of Blackbeard late 1600 s to early 1700 s National Seashore owned and controlled

More information

Appendix A. Sample Inspection Report

Appendix A. Sample Inspection Report Appendix A Sample Inspection Report This page intentionally left blank. PORT AUTHORITY OF ALLEGHENY COUNTY PITTSBURGH, PENNSYLVANIA REPORT ON THE INITIAL NBIS INSPECTION OF CHARTIERS CREEK BRIDGE BMS No.

More information

Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No MO MMO T C

Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No MO MMO T C 87-Hour Bridge Construction in Arizona ABC and ARC at the Speed of Commerce Mohave County (Topock), Arizona Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No. 0000

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS 1.0 DESCRIPTION This work shall consist of furnishing all materials and labor necessary for conducting an Osterberg Cell (O-cell)

More information

STRUCTURE SELECTION REPORT

STRUCTURE SELECTION REPORT STRUCTURE SELECTION REPORT Prepared for: City & County of Denver 201 West Colfax Avenue Denver, CO 80202 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse Way Suite 600 Centennial, CO 80111 June

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE G. Keith Donington, PE, Parsons Brinckerhoff, Manchester, NH Hany L. Riad, PhD, PE, Parsons Brinckerhoff, Boston, MA

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

New Development in Accelerated Bridge Design and Construction in WA

New Development in Accelerated Bridge Design and Construction in WA Delivery of Accelerated Bridge Construction WSDOT Workshop Wednesday April 1st, 2015 New Development in Accelerated Bridge Design and Construction in WA Washington State Department of Transportation Bridge

More information

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Scott Eshleman, P.E., S.E, CVS, Stanley Consultants Keith Sargent, P.E., Thomas Engineering Group, LLC February

More information

SO-DEEP, 9/2015 (703) VA. Group I-DL. Group I-DL

SO-DEEP, 9/2015 (703) VA. Group I-DL. Group I-DL LIMITED ACCESS HIGHWAY By Resolution of Commonwealth Transportation Board dated January 18, 2001 PROJECT MANAGER: SURVEYED BY, DATE: TIMOTHY HARTZELL, P.E. (703) 259-2749 (NOVA District) PRECISION MEASUREMENTS,

More information

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge ABC History in Colorado 1. Promote Using Prefabricated Bridge & CBC Members since Early 1990 (Partnership

More information

LRFD Bridge Design Manual Changes

LRFD Bridge Design Manual Changes LRFD Bridge Design Manual Changes Dave Dahlberg Bridge Design Manual & Policy Engineer May 17, 2017 Bridge Office mndot.gov/bridge Overview 1) Concrete mix designations 2) Reinforcing bar development and

More information

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,

More information

Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway.

Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway. Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway. ABSTRACT James Nasr, Senior Bridge Engineer, Cardno The Nan-Tien Pedestrian Bridge project

More information

I-74 over the Mississippi River

I-74 over the Mississippi River I-74 over the Mississippi River Design and Construction of Arch Foundations 104 th Transportation and Highway Engineering Conference Presented by: Andrew J. Keaschall, PE, SE, Alfred Benesch & Company

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR

More information

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure. Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE

More information

SPECIAL INSPECTION AND TESTING AGREEMENT

SPECIAL INSPECTION AND TESTING AGREEMENT COUNTY OF MENDOCINO DEPARTMENT OF PLANNING AND BUILDING SERVICES 860 NORTH BUSH STREET UKIAH CALIFORNIA 95482 120 WEST FIR STREET FT. BRAGG CALIFORNIA 95437 STEVE DUNNICLIFF, DIRECTOR PHONE: 707-234-6650

More information

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY ABSTRACT Jugesh Kapur, PE, SE 1 The seismic design and detailing of bridges made of precast prefabricated members

More information

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota AREMA 2008 Annual Conference LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota 55904 507-281-5188 Steve K. Jacobsen, PE 2 LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE

More information

Design of the IL 127 Kaskaskia River Bridge Illinois Transportation and Highway Engineering Conference February 24, 2015 University of Illinois at

Design of the IL 127 Kaskaskia River Bridge Illinois Transportation and Highway Engineering Conference February 24, 2015 University of Illinois at Design of the IL 127 Kaskaskia River Bridge February 24, 2015 University of Illinois at Urbana-Champaign Project Overview PTB 155, Item 58 Phase II Engineering Services IDOT District 8 Modjeski and Masters,

More information

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS Gregg Freeby, P.E., Leon Flournoy, P.E. & Sara Watts, E.I.T TxDOT Bridge Division Prefabricated Elements TxDOT s primary technique for

More information

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings

More information

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS 1.0 DESCRIPTION The Work shall consist of:.1 Transportation, unloading, erection and grouting of precast prestressed concrete

More information

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1 LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE Mark S. Mahan 1 Abstract The newly approved AASHTO Guide Specification for LRFD Seismic Bridge Design (referred to as LRFD Seismic Guide Spec), July 2007,

More information

BRIDGE INSPECTION REPORT

BRIDGE INSPECTION REPORT NC DEPARTMENT OF TRANSPORTATION ATTENTION DIVISION OF HIGHWAYS BRIDGE MANAGEMENT UNIT BRIDGE INSPECTION REPORT INSPECTION TYPE: Routine Inspection COUNTY IREDELL BRIDGE NUMBER 480596 INSPECTION CYCLE 2

More information

Lessons Learned Meeting Notes

Lessons Learned Meeting Notes EXTERNAL MEMORANDUM Lessons Learned Meeting Notes Distribution Date: April 24, 2017 Date of Meeting: April 19, 2017 Project: Sacramento Wash Crossing at Oatman Highway TRACS No. T0021 01D Federal Project

More information

Thesis Proposal. Matthew R Peyton

Thesis Proposal. Matthew R Peyton This Document is for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. S t r u c t u r a l O p t i o n P r o f e s s o r B e h r H o s p i t a l

More information