CASE STUDY: Captain Cook Drive, NSW Ecoflex E Wall & E Pave Systems Project No: EAJ00264
|
|
- Alison Christina Washington
- 5 years ago
- Views:
Transcription
1 CASE STUDY: Captain Cook Drive, NSW Project No: EAJ Kalaroo Road, Redhead NSW Australia.
2 TABLE OF CONTENTS TITLE PAGE# Project Background 03 Project Specification & Design Design Drawings. 05 Engineers Certification Construction Photographs Company Information 19 Lic No: EF-2003 AELA Approved Product The recycled rubber technology employed by Ecoflex has been assessed by the Australian Environmental Labeling Association and has been awarded a Good Environmental Choice Licence by the Australian Ecolabel Program. The technology was assessed against the voluntary environmen tal labeling standard for Recycled Rubber Products: AELA-Recycled Rubber Details: Page 2
3 PROJECT BACKGROUND A report was released in October 2006 by Sutherland Shire Consulting Services to Sutherland Shire Council for the proposed road widening of Captain Cook Drive between Woolooware Rd and Elouera Rd at Woolooware, NSW. It offered four Construction Methodologies for consideration, these were Lime Cement Columns, Geogrid Reinforcement with Gabion Embankment Edge, Preloading and Ecoflex. The pros and cons of each method were detailed to Council in the report and in summary were; Lime Cement Columns- Extremely expensive with settlement practically eliminated. Geogrid Reinforcement- Expect significant overall settlement would require Gabion basket embankment edge into the tidal waters. Pre-loading- Not acceptable due to possible environmental impact for many months. Ecoflex- Advantage over the other systems include reduced road footprint, eliminates batter into mangroves or gabion into tidal salt water. The Report states that some ongoing pavement deformation will occur due to the due to the poor subgrade and its variable nature. The Council in February 2012 engaged CSG Engineering to incorporate Ecoflex Systems into their road design. Ford Civil Contracting were the successful tenderer. Site works commenced in November 2012, Ecoflex Civil Contractors supplied Ford Civil with trained supervisors to coordinate, train and supervise the placement of the Ecoflex systems to the engineers specifications. Sustainability must be high on the Council agenda as this road construction consists almost entirely of recycled materials these include recycled tyres for Ecoflex E Pave subbase and E Wall embankment retaining, recycled concrete aggregate for Ecoflex unit infill, recycled Asphalt for backfill, recycled concrete for roadbase. The recycled concrete and recycled asphalt were both available locally and suitable for the engineering design, to use quarried rock on this project would have involved trucking rock from quarries over 80 km away, this would have imposed a huge unnecessary cost to the project and added a significant Carbon Cost due to transport alone. Page 3
4 PROJECT SPECIFICATION & DESIGN Project Name: Client:: Ecoflex System: Contractor:: Project Purpose: Consulting Engineer: Captain Cook Drive Widening for Sutherland Shire Council Ford Civil Contracting Pty Ltd E Wall & E Pave Ecoflex Civil Constructions Pty Ltd Widen existing road by extending it 8 metres into the mangrove tidal region The widened road will include a pedestrian path and a cycle lane. CSG Engineering Pty Ltd The project involved construction of an Ecoflex retaining wall along the embankment edge Ecoflex pavement was then placed in varying layers to the engineering design from the E Wall to the excavated edge of the existing road which remained in service during the construction process. Ford Civil engaged ECC supervisors to work with the site manager to assist with installation procedures, delivery schedules and staff training, with the aim of keeping the project running efficiently in the trying conditions presented. The conditions encountered included varying retaining wall subbase conditions along the length of the project, tidal flows covering the work areas to depths of 200 to 400 mm along with limited access conditions of busy Captain Cook Drive. The varying conditions created varying rates of settlement as was described in the preliminary Geotechnical Report, the settlement required additional Ecoflex units to be installed to maintain finished road height. The settlement did not cause any structural deterioration to the E Wall or E Pave structures according to subsequent engineering inspection. Following the installation of the Ecoflex systems which used recycled concrete aggregate as the infill material Ford Civil placed and compacted the recycled asphalt infill followed by the placement and compaction of the recycled concrete road base. This project has utilised nearly 17,000 recycled truck tyres (Approx 85,000 EPU s) manufactured into Ecoflex Units now embedded into this permanent infrastructure project. Page 4
5 DESIGN DRAWINGS Typical Section Page 5
6 ENGINEER S CERTIFICATION Page 6
7 Preparation Clearing Page 7
8 Clearing Page 8
9 E Wall Footing Page 9
10 Footing Page 10
11 Tidal Conditions Page 11
12 Ecoflex Wall and Subbase with Backfill Page 12
13 Works Progress Page 13
14 E Pave Subbase Recycled Concrete Infill Page 14
15 Works Progressing Page 15
16 Works Progressing Page 16
17 Works Progressing Page 17
18 Works Continue at High Tide Page 18
19 Recycled Asphalt Backfill Placement Page 19
20 Placing Road Base Page 20
21 Tarred and Armco Installed Page 21
22 Armco Installation Page 22
23 COMPANY INFORMATION HEAD OFFICE: Newcastle 66 Kalaroo Road Redhead NSW 2290, Australia Telephone: Facsimile: mail@ecoflex.com.au Website: PATENTS International Patents cover the works and intellectual property shown in this document. All rights reserved. No part of the works and/or intellectual property may be reproduced or utilised in any form or by means, without prior written consent of ECOFLEX AUSTRALIA PTY LTD. Page 23
CASE STUDY: Tarro, NSW Ecoflex E-Bridge System Project No: EAJ00079
Project No: EAJ00079 20 Kalaroo Road, Redhead NSW Australia. TABLE OF CONTENTS TITLE PAGE# Project Background 03 Project Specification & Design... 04 Design Drawings. 05 Engineers Certification... 06 Construction
More informationCASE STUDY: Waste Management Centre, Eastern Creek, NSW E-Rosion Control System Project# EAJ00063 Completed: 03/11/04
Waste Management Centre, Eastern Creek, NSW E-Rosion Control System Project# EAJ00063 Completed: 03/11/04 TABLE OF CONTENTS TITLE PAGE# Project Background 03 Project Specification & Design... 04-06 Design
More informationSelect Subgrade Material, Compacted
314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.
More informationVillawood Properties Pty Ltd Lakeview Estate - Stage 2
ORIGINAL DRAWINGS (These are the originals only if this text is RED) Pty Ltd Not Yet Approved by Council TATALIA LANE MILGATE LANE INDEX MURRAY RIVER MURRAY RIVER TWENTY FOUR LANE HOLIDAY COTTAGES RICH
More informationTable of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15
Table of Contents Chapter 1 : Introduction 1 1-1 Overview of Japan 1 1-1-1 Topography 1 1-1-2 Climate 1 1-1-3 Population 3 1-1-4 Economy 3 1-2 History and current status of roads in Japan 5 1-2-1 Road
More informationAustStab Construction Tip
AustStab Construction Tip Version No.8A January 2006 Pavement crossblending prior to stabilisation Introduction The performance of insitu and plant-mix stabilisation methods relies on many factors, with
More informationDESIGN CONSIDERATIONS FOR NSWS NATURAL STONE RETAINING AND FREE-STANDING WALL SYSTEMS
DESIGN CONSIDERATIONS FOR NSWS NATURAL STONE RETAINING AND FREE-STANDING WALL SYSTEMS Natural Stone Wall Solutions, Inc (NSWS ) 2352 Main Street, Suite 103 Concord, MA 01742 (978) 461-1777 Concept and
More informationManagement of Design and Construction for Civil Works under EPC contract in one Oversea Wind Farm Project
ORIGINAL ARTICLE Management of Design and Construction for Civil Works under EPC contract in one Oversea Wind Farm Project Wu Zheng Power China Chengdu Engineering Corporation LTD, Chengdu 610072 Abstract:
More informationengineered by application
engineered by application REINFORCED EARTH WALLS Conjola Mountain NSW Retaining Solutions Design Construct Pty Ltd (Retaining Solutions) is a privately owned and operated Australian company. The company
More informationConstruction Specification for General Excavation
Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03
More informationVersion 1 July Ash Management Strategy
Version 1 July 2012 Ash Management Strategy Table of Contents 1. Introduction... 3 2. Regulatory Issues... 3 3. Traditional Ash Markets... 4 4. New Ash Markets and New Technology... 5 5. Ash Management
More informationSECTION CONTROLLED LOW STRENGTH MATERIAL
SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including
More informationCity Circle Recycling pty. ltd Construction & Demolition Waste Recycling Jones Rd Brooklyn
City Circle Recycling pty. ltd Construction & Demolition Waste Recycling Jones Rd Brooklyn BCRG 11/11/2015 Introduction Who am I? Who are City Circle? What will I be talking about tonight? Overview City
More informationKurnell Terminal Demolition Project
Kurnell Terminal Demolition Project Traffic Management Plan CALTEX REFINERIES (NSW) PTY LTD September 2015 Page 1 Page 2 1 Introduction... 5 1.1 Legislative and Other Requirements... 6 2 Objectives...
More informationSustainable Pavement Design in Christchurch Southern Motorway
Sustainable Pavement Design in Christchurch Southern Motorway Dr Bryan Pidwerbesky General Manager Technical Fulton Hogan Ltd, PO Box 39185, Christchurch 8545, New Zealand Tel: +64 3 357 0615 email: bryan.pidwerbesky@fultonhogan.com
More informationDana N. Humphrey, Ph.D., P.E. Consulting Engineer
Dana N. Humphrey, Ph.D., P.E. Consulting Engineer November 19, 2004 Mr. Garry Callinan Ecoflex Australia Pty Ltd 32-34 Annie Street Wickham NSW 2293 Australia RE: Technical review of E Wall, E Pave, and
More informationCHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH
CHAPTER 2 201 ROADS 201.1 General This section is to assist the designer in determining what is needed for the design of roads in public rights-of-way. For these standards, the terms used are: Restricted
More informationTasman Retaining Wall
Tasman Retaining Wall EVALUATION AND INSTALLATION GUIDE Landscaping Tasman Retaining Wall Evaluation and Installation Guide This installation guide demonstrates the basics on how to construct: A. Tasman
More informationB512 - GABIONS - OPSS 512
B512 - - OPSS 512 512.1 GENERAL Gabions are contained rectangular units made of steel wire mesh and filled with stone. The double twisted wire mesh is galvanized and PVC (polyvinyl chloride) coated. Gabions
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationGeotechnical Level 1 Supervision Report Donald Road, Redland Bay.
TG30027-43 Geotechnical Level 1 Supervision Report 58-98 Donald Road, Redland Bay. Frostdale Civil Contractors TOTAL GEOTECHNICS Adelaide, Ballarat, Brisbane, Hallam, Hoppers Crossing, Traralgon, Warrnambool
More informationMarrangaroo Quarry. Product Brochure E D I T I O N
Marrangaroo Quarry Product Brochure 2 0 1 0 E D I T I O N Page 2 MARRANGAROO QUARRY Page 3 Table of Contents M A R R A N G A R O O Q U A R R Y Overview Page 4 Delivery Service Page 4 Technical Service
More informationMarrangaroo Quarry. Product Brochure 2010 EDITION
Marrangaroo Quarry Product Brochure 2010 EDITION Page 2 MARRANGAROO QUARRY Page 3 Table of Contents MARRANGAROO QUARRY Overview Page 4 Delivery Service Page 4 Technical Service Page 4 Fine Aggregates Page
More informationGeoTechTools Your Decision Making Solution
GeoTechTools Your Decision Making Solution Silas Nichols, P.E. Principal Geotechnical Engineer U.S. Federal Highway Administration Washington, DC www.geotechtools.org Did you know That up to half of all
More informationST. TAMMANY PARISH COUNCIL ORDINANCE
ST. TAMMANY PARISH COUNCIL ORDINANCE ORDINANCE CALENDAR NO: 5563 COUNCIL SPONSOR: DEAN/BRISTER INTRODUCED BY: MR. BELLISARIO ORDINANCE COUNCIL SERIES NO: PROVIDED BY: DEVELOPMENT SECONDED BY: MR. STEFANCIK
More informationINVITATION TO TENDER ITT / PS VANCOUVER LANDFILL FRONT ENTRANCE REDESIGN - PRELOAD QUESTIONS AND ANSWERS NO.1
FINANCIAL SERVICES GROUP Supply Management INVITATION TO TENDER ITT / PS20161054 ISSUED ON OCTOBER 13, 2016 Schedule A - Item 3.01 references MMCD Section 03 40 01 Measurement and Payment Clause 1.4.3.
More informationERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007
ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007 Sheet 1 of 7 GENERAL The Kansas Department of Transportation STANDARD SPECIFICATIONS FOR STATE ROAD AND
More informationAppendix 15 Estimated costs of dams
Appendix 15 Estimated costs of dams September 2014 Brown Hill Keswick Creek Stormwater Management Plan Part B Report Earth Dam Site 1 BROWN HILL CREEK DAM COST ESTIMATE FOR EARTH DAM ( OPTION 1) AT SITE
More information2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationFoundations, Excavation & Shoring Specialists
Foundations, Excavation & Shoring Specialists July 8, 017 Reference: 17-7 McElhanney Consulting Services Ltd. Suite 00 Central City Tower 10 10 nd Avenue Surrey, BC VT X Via email: mflorendo@mcelhanney.com
More informationFox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS
Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # 2016-04 PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION 100 GENERAL... 1 SECTION 200 MATERIALS... 1 CONSTRUCTION METHODS... 1 SECTION
More informationBELMURO WALL SYSTEM INSTALLATION GUIDE
BELMURO WALL SYSTEM INSTALLATION GUIDE TABLE OF CONTENTS TABLE OF CONTENTS... 1 SYSTEM DESCRIPTION... 2 DRY STACK SYSTEM: INSTALLATION GUIDE... 5 GEOGRID WALL SYSTEM: INSTALLATION GUIDE... 9 MASONRY WALL
More informationINDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6
03005_Jan31_2018.pdf Page 1 of 6 INDEX Page 03005-1 DESCRIPTION 2 03005-2 MATERIALS 2 03005-3 APPROVAL FOR BASE COURSE 3 03005-4 CONSTRUCTION 3 03005-5 MEASUREMENT 6 03005-6 PAYMENT 6 03005_Jan31_2018.pdf
More informationGEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT
PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES
More informationTasman. Retaining Wall System. Available From. Choose the original Tasman block. Beware of imitations!
Available From Tasman Retaining Wall System Choose the original Tasman block. Beware of imitations! Prestige & Quality Near Vertical Walls Do It Yourself No Concrete Footings Flexible 90 Corners, Steps,
More informationMaterials and Surfacing - Organization and Functions
Materials and Surfacing - Organization and Functions Organization & Functions Page 1 Materials and Surfacing. Organization: Chief Materials and Surfacing Engineer 1. Materials 2. Pavement Design 3. Surfacing
More informationINDEX Warrant for Reclaiming Asphalt Pavement - Partial Depth Warrant for Reclaiming Asphalt Pavement - Full Depth
399-2 - INDEX 399-2.1 GENERAL 399-2.1.1 Tender Items 399-2.1.2 Traffic Warrant 399-2.1.3 Reference Publication 399-2.1.4 Warrant for Reclaiming Asphalt Pavement - Partial Depth 399-2.1.5 Warrant for Reclaiming
More informationSECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS
SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction
More informationUSER S VIEW POINT: WHY WE USED THESE PRODUCTS
GEOSYNTHETICS & STEEL MESHES FOR LONGER LASTING ROADS SCI HQ, London Thursday, 12 May 2011 USER S VIEW POINT: WHY WE USED THESE PRODUCTS John Howe Lincs Laboratory Highways & Transportation www.lincolnshire.gov.uk/lincslab
More informationArlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL )
MINIMUM RATE 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to
More informationArlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL )
1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to top of fill starting
More informationInstallation Guide Trade Waste Products
Installation Guide Trade Waste Products Given the large range of trade waste products, there are various standard installation instructions for our products. All trade waste products are delivered to site
More informationAN INNOVATIVE APPROACH TO SMALL BRIDGE REHABILITATION. Peter Marchant ITS Pipetech Pty Ltd, NSW Australia
AN INNOVATIVE APPROACH TO SMALL BRIDGE REHABILITATION Peter Marchant ITS Pipetech Pty Ltd, NSW Australia Introduction Summary Since first construction our principle infrastructure we are witnessing Increasing
More informationSCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B
SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B SCHEDULE 3-1 DETAILED CONSTRUCTION PLAN Part B Narrative: Work Area B We will carry out the excavation for Work Area B as per Company s
More informationSECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS
SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 353 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS TABLE OF CONTENTS 353.01 SCOPE 353.02 REFERENCES 353.03 DEFINITIONS
More informationSustainable Use of All Quarry Materials K E V I N V A U G H A N V U L C A N M A T E R I A L S C O M P A N Y
Sustainable Use of All Quarry Materials K E V I N V A U G H A N V U L C A N M A T E R I A L S C O M P A N Y Aggregate Types Quarries produce three basic products Clean/Coarse Aggregate Fine Aggregate/Screenings
More informationAppendix A General Conditions to Utility Cut Permanent Restoration
Appendix A General Conditions to Utility Cut Permanent Restoration Abilities and Experience Appendix A General Conditions to Utility Cut Permanent Restoration All Contractors retained by the utility must
More informationFirst field trial commences in USA of Australia s super strength carbon enriched concrete additive
ACN 109 200 900 AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT 23 February 2015 First field trial commences in USA of Australia s super strength carbon enriched concrete additive Eden Energy Ltd ( Eden )
More informationCold In-Place Recycling with Expanded Asphalt B-335 COLD IN-PLACE RECYCLING WITH EXPANDED ASPHALT OPSS 335
B-335 COLD IN-PLACE RECYCLING WITH EXPANDED ASPHALT OPSS 335 335.1 GENERAL Use of Cold In-Place Recycled Expanded Asphalt Mix (CIREAM) is recommended by the Regional Geotechnical Section on a work-project
More informationCan sustainability win you more work? 10th April 2013
Can sustainability win you more work? 10th April 2013 Tony Suckling Technical Director Balfour Beatty Ground Engineering Contents Introduction Balfour Beatty Sustainability Agenda BBGE examples Case studies
More informationCompany Profile 1300 SHOTCRETE
1300 SHOTCRETE Company Profile RIX Specialist Contracting can tailor solutions to meet even the most demanding project requirements. From initial consultation right through to completion, the team at RIX
More informationCITY OF KANSAS CITY, MISSOURI
KCMO Supplement April 2000 Document No. 000079 CITY OF KANSAS CITY, MISSOURI SUPPLEMENT TO APWA STANDARD SPECIFICATIONS AND DESIGN CRITERIA SECTION 2600 This is the Kansas City, Missouri Supplement to
More informationCONTRACT NO. : MTK11/2017 REHABILITATION OF MSAULI ASBESTOS MINE SCHEDULE OF QUANTITIES SECTION 1: PRELIMINARY AND GENERAL
SECTION 1: PRELIMINARY AND GENERAL SECTION 1: PRELIMINARY & GENERAL 1.1 1200A FIXED CHARGE AND VALUE RELATED ITEMS 8.3.1 CONTRACTUAL REQUIREMENTS 1.1.1 Surety or bank guarantee Sum 1 1.1.2 Common Law Liability
More informationNICK JOSCELYNE CONTRACTS MANAGER
Thompsons of Prudhoe Ltd NICK JOSCELYNE CONTRACTS MANAGER Telephone: 01661 832 422 Mobile: 07919 491 726 EMail: info@thompsonsofprudhoe.com Year of birth: 1957 Nationality: British QUALIFICATIONS & TRAINING
More informationTasman and Norfolk Retaining Wall
Tasman and Norfolk Retaining Wall Evaluation and Installation Guide BAINES We deliver Sydney s Best! Order online: bcsands.com.au Call: (02) 8543 3400 Taren Point & Mascot Tasman and Norfolk are registered
More informationSECTION XXXXX STONE COLUMNS PART 1 - GENERAL
SECTION XXXXX STONE COLUMNS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division 01
More informationGrading Requirements City of Red Bluff Table of Contents. Introduction and Scope...1. Permit Exempt Work...1. Permit Application Submittals...
Table of Contents General Notes Introduction and Scope...1 Permit Exempt Work...1 Permit Application Submittals...2 Other Procedural Requirements...3 Exhibit A - Grading Plans...4 Exhibit B - Milestones
More informationKlohn Crippen Berger Ltd Virtual Way Vancouver BC V5M 4X6 CANADA t f
Klohn Crippen Berger Ltd. 500-2955 Virtual Way Vancouver BC V5M 4X6 CANADA 604.669.3800 t 604.669.3835 f www.klohn.com TABLE OF CONTENTS 1 INTRODUCTION... 1 2 BACKGROUND... 2 3 PAVEMENT DESIGN AND RECOMMENDATIONS...
More informationCHAPTER 3 CONSTRUCTION AND TESTING OF SUBGRADE
CHAPTER 3 CONSTRUCTION AND TESTING OF SUBGRADE WHAT IS SUBGRADE? SUBGRADE EMBANKMENT FOUNDATION The top surface of an embankment or cut section, shaped to conform to the typical section upon which the
More informationPlease ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender.
No. 1 Project: 47th Ave Road Reconstruction Owner: District of Chetwynd Date: March 5, 2019 Ref. No.: 1320.0095.01 This Addendum is issued prior to Tender Closing Date, in accordance with the Tender Documents
More informationTENSARTECH GREENSLOPE. earth retaining systems for slopes
TENSARTECH GREENSLOPE earth retaining systems for slopes Tensar Technology proven, practical solutions and the know-how to get them designed and built. Tensar Technology is widely adopted for Pavement
More informationCW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS
December 2012 CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard
More informationB. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.
SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.
More informationDIVISION 2100 SITEWORK
DIVISION 2100 SITEWORK SECTION 2120 STABILIZED SUBGRADE PART 1 - GENERAL 1.01 SCOPE This section covers the preparation of subgrade for pavement, sidewalks, recreational trails, and drive approaches. 1.02
More informationB441 - WATERMAINS - OPSS GENERAL
B441 - - OPSS 441 441.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.
More informationRECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 (VERSION 1.0)
RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 (VERSION 1.0) RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 A. GENERAL INFORMATION It is
More informationCONSTRUCTION SPECIFICATION FOR RUBBLIZING CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 361 NOVEMBER 2011 CONSTRUCTION SPECIFICATION FOR RUBBLIZING CONCRETE PAVEMENT AND CONCRETE BASE TABLE OF CONTENTS 361.01 SCOPE 361.02 REFERENCES 361.03
More informationMi l l er Pac i fic E N G I N E ERI NG GR O UP 504 Redwood B l vd. Suite 220 Novato, Ca l i f o rnia 94947
April 8, 2010 File: 739-17bltr.doc CSW/Stuber-Stroeh Engineering Group 45 Leveroni Court Novato, CA 94949 Mi l l er Pac i fic E N G I N E ERI NG GR O UP 504 Redwood B l vd. Suite 220 Novato, Ca l i f o
More informationTensar Geogrid Trench Repair Frequently Asked Questions
Tensar International Corporation 800-TENSAR-1 www.tensarcorp.com Tensar Geogrid Trench Repair Frequently Asked Questions Tensar geogrids are routinely excavated through in order to place guardrail posts,
More informationCONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02
More information21 July Anthony Yeates RATCH-Australia Corporation Limited Level 7, 111 Pacific Highway North Sydney NSW 2060
AECOM Australia Pty Ltd Level 21, 420 George Street Sydney NSW 2000 PO Box Q410 QVB Post Office NSW 1230 Australia www.aecom.com +61 2 8934 0000 tel +61 2 8934 0001 fax ABN 20 093 846 925 21 July 2015
More informationIndustrial waste treatments, oil conditioners, soil stabilisation and solution providers
stabilisation Industrial waste treatments, oil conditioners, soil stabilisation and roadway solution providers Cenin Ltd The Research Centre Parc Stormy Stormydown Bridgend Wales CF33 4RS Telephone: +44
More informationNOVEMBER 2016 GRANDWALL. retaining walls installation guide
NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining
More informationRETAINING WALL SYSTEMS SOUTH & NORTH QUEENSLAND
Keystone SOUTH & NORTH QUEENSLAND Contents Product Disclaimer Concrete Blocks, Bricks, Pavers and Retaining Wall products supplied by National Masonry are manufactured using raw materials that inherently
More informationThe design and construction of a 60m high reinforced soil retaining wall in the UAE
The design and construction of a 60m high reinforced soil retaining wall in the UAE Ir Chaido Doulala-Rigby (Yuli) MHKIE CEng FICE Chief Civil Engineer Outline 1. A few words about Tensar 2. Case Study
More informationSOIL STABILIZATION FOR PAVEMENTS ENGINEERING SOUNDBITES
page 1 / 6 page 2 / 6 soil stabilization for pavements pdf What is the Soil Stabilization Process? Proper design and testing is an important component of any stabilization project. Processes Soil Stabilization
More informationCrudine Ridge Wind Farm
Crudine Ridge Wind Farm CCC Presentation December 2017 Page 1 Agenda General Update Pre-construction Update Contracting Road Design Geotechnical study Management Plans Material Sourcing Timeline to construction
More informationSustainable Roadway Materials for the I-90 Project
Sustainable Roadway Materials for the I-90 Project Jay Behnke, P.E. S.T.A.T.E. Testing L.L.C. FHWA Tollway National Open House, August 20, 2013 Tollway Building GREEN Waste reduction work zone Striving
More informationChapter 5: Designs for Recreational Uses 5-1 Asphalt Pavements for Non-Vehicular Use 5-1 Table 5-1: Thickness Design Chart: Bikeways, Paths, Trails
5-1 Asphalt Pavements for Non-Vehicular Use 5-1 Table 5-1: Thickness Design Chart: Bikeways, Paths, Trails and Walkways 5-3 Table 5-2: Thickness Design Chart: Playgrounds 5-4 Tennis Courts 5-5 Table 5-3:
More informationA REVIEW OF PATCHING AS A PAVEMENT MAINTENANCE TOOL
A REVIEW OF PATCHING AS A PAVEMENT MAINTENANCE TOOL Warren Smith, Stabilised Pavements Group of Companies, NSW, Australia ABSTRACT The aim of this paper is to try to analyse the effectiveness of patching
More informationContents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3
Contents Contents Before you begin v Introduction: Carrying out concreting to simple forms 1 Element 1: Planning and preparing 3 Section 1.1: Obtaining, confirming and applying work instructions and 4
More informationCONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR SUBBASE, BASE, SURFACE, SHOULDER, AND STOCKPILING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 314 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR SUBBASE, BASE, SURFACE, SHOULDER, AND STOCKPILING TABLE OF CONTENTS 314.01 SCOPE
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationearth retaining systems for slopes
TenSARTech greenslope earth retaining systems for slopes Independent Assessment and Approval Tensar offers a broad variety of cost effective and attractive alternatives for all types of construction Selected
More informationCONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 314 DECEMBER 1993 CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING 314.01 SCOPE 314.02 REFERENCES
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 353 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS TABLE OF CONTENTS 353.01 SCOPE 353.02 REFERENCES 353.03 DEFINITIONS
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 512 NOVEMBER 2008 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS TABLE OF CONTENTS 512.01 SCOPE 512.02 REFERENCES
More informationMOA Project # Golden View Drive Intersection & Safety Upgrades
Appropriate transitions can include extending the insulation beyond the roadway improvements, reducing the insulation thickness, or angling the insulation downward. Use of a frost tolerant section, an
More informationPort KC RFP NORTHLAND PARK BUILDING V
Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?
More information.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.
SECTION 31 22 00- GRADING 1.0 GENERAL.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.. 2 Excavate to exact line and grade as
More informationInstallation Guidelines
815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Guidelines Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles (optional),
More informationSECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT
SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating
More informationSECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.
SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction
More informationSECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL
SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division
More informationSPECIFICATIONS FOR STRUCTURAL EXCAVATION
SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition
More informationLong-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah
1 Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT Steven Bartlett, University of Utah Roadway Widening (I-15 Project) Salt Lake City Utah, USA 2002 Host of
More informationPublic Works Manual. Revised September Concrete & Asphalt
Public Works Manual Revised September 2015 Concrete & Asphalt Where it must cross domestic it must cross above and with a 1 minimum separation. Nonpotable water tape. 10.00 PORTLAND CEMENT CONCRETE 10.01
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 353 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS TABLE OF CONTENTS 353.01 SCOPE 353.02 REFERENCES 353.03 DEFINITIONS
More informationTENSARTECH TW1 WALL. earth retaining system for walls
TENSARTECH TW1 WALL earth retaining system for walls Tensar Technology proven, practical solutions and the know-how to get them designed and built. Tensar Technology is widely adopted for Pavement Optimisation
More information