Building Excellence IV Capital Levy Projects Under Construction

Save this PDF as:
 WORD  PNG  TXT  JPG

Size: px
Start display at page:

Download "Building Excellence IV Capital Levy Projects Under Construction"

Transcription

1 Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary School 26 Hazel Wolf K-8 at Pinehurst 39 Olympic Hills Elementary School 52 Seattle New World School at TT Minor 60 New Thornton Creek Building 72 April 22, 2016

2 Building Excellence IV Capital Levy Arbor Heights Elementary School Site: Playfield irrigation installation ongoing, concrete loading dock walls placed, gabion basket installation ongoing, site fence installation in-progress. South Building: Exterior mineral wool insulation, siding hardware, and fiber-cement board siding installation ongoing. Interior Light fixture installation ongoing on first and second floor. Interior painting ongoing at third floor. Casework and acoustical ceiling grid installation ongoing at second floor. Ceramic tile floor and wall tile installation ongoing at second floor. HVAC, plumbing, and electrical installation ongoing at second and first floor mechanical rooms and first floor boiler room. North Building: Exterior Air-barrier and siding hardware installation ongoing. Interior Gypsum wall board (GWB) tape/mud ongoing at gymnasium, library, admin, and second and third floor. Mechanical, plumbing and electrical rough-in ongoing at second and third floor ceilings.

3 Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015

4 Arbor Heights Elementary School Aerial View from the South February 29, 2016

5 Arbor Heights Elementary School Site Looking North East April 19, 2016

6 Arbor Heights Elementary School South Building West Elevation April 19, 2016

7 Arbor Heights Elementary School South Building South and East Elevations April 19, 2016

8 Arbor Heights Elementary School South Building Second Floor Art/Idea Lab April 19, 2016

9 Arbor Heights Elementary School South Building Open Learning Area April 19, 2016

10 Arbor Heights Elementary School North Building North East Elevation April 19, 2016

11 Arbor Heights Elementary School North Building Library April 19, 2016

12 Arbor Heights Elementary School North Building Commons April 19, 2016

13 Arbor Heights Elementary School North Building Gymnasium April 19, 2016

14 Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School Site: Monitoring temporary erosion sedimentation control (TESC) measures. ES: Exterior - Exterior framing and sheathing ongoing. Windows have started to arrive, stored on site. Roofing started. All the skylights have been installed. Interior - Slab-on-grade poured at stage; building is poured out. Interior metal stud framing and mechanical, electrical and plumbing (MEP) wall rough-in ongoing. Mechanical penthouse framing and steel beam installation ongoing. MS: Slab-on-grade poured at Commons. Mechanical penthouse framing started. Canopy framing started. Structural steel/decking installation ongoing. All slab-on-metal-deck pours completed. Gym repairs ongoing: all bolts replaced, bent column replaced.

15 Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan

16 Cascadia Elementary School & Robert Eagle Staff Middle School Zone Map Middle School Elementary School

17 Cascadia Elementary School & Robert Eagle Staff Middle School Aerial View from the South March 30, 2016

18 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Exterior Framing, North Side, Looking West April 12, 2016

19 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Roofing Installation, Looking North West April 12, 2016

20 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Zone 4 Exterior Sheathing, Looking South East April 12, 2016

21 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Slab-on-Grade at Stage, Looking South April 12, 2016

22 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Zones 2 and 3, South Side, Looking North April 12, 2016

23 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Zone 4 Decking, Looking North April 12, 2016

24 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Zone 4 Slab-on-Grade Vapor Barrier, Looking South April 12, 2016

25 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Formwork for Mechanical Penthouses, Looking West April 12, 2016

26 Building Excellence IV Capital Levy Genesee Hill Elementary School Site: Completed street improvement along SW Dakota St; continued to form and pour sidewalks north side of Area 1; completed clear and grub area east of Area 1; began installing handrails and guardrails at site stairs; completed storm water connections at Genesee St; installing topsoil and fertilizer in preparation of sod at lower parking lot. Area 1: Exterior - Completed application of water repellant graffiti-resistant coating on CMU veneer. Interior - Completed installation of AV, CATV, and intercom trim; continued air and hydronic balancing. Area 2: Interior - Completed carpet installation at level 1and began same task at level 2; began installing stair treads at stair #4. Continued installation of drop ceiling tile. Completed start-up of the mechanical air handlers; Continued wire termination at the main fire alarm panel and continued testing of fire alarm system; continued installation of AV, CATV, and intercom trim; Area 3: Interior - Continued installation of stage flooring; continued electrical rough-in to kitchen equipment; Area 4: Interior - Gym flooring installed, first coat of sealer applied, stripping complete.

27 Genesee Hill Elementary School Site Plan

28 Genesee Hill Elementary School Aerial View from the East

29 Genesee Hill Elementary School Site Installing Topsoil and Fertilizer in Preparation of Sod at Lower Parking

30 Genesee Hill Elementary School Site Form Curbing at North Parking Lot Ongoing

31 Genesee Hill Elementary School Site Installation of Storm Drain and Catch Basin Southeast of Area 1 Ongoing

32 Genesee Hill Elementary School South Play Area Began Installing Play Equipment

33 Genesee Hill Elementary School Area 1, Level 1 Installing Light Fixtures

34 Genesee Hill Elementary School Area 2, Level 1 Installation of Casework at Reception Ongoing

35 Genesee Hill Elementary School Area 2, Level 1 Installing Stair Treads at Stair No. 4

36 Genesee Hill Elementary School Area 2, Level 2 Completed Carpet at Library

37 Genesee Hill Elementary School Area 3 Installation of Stage Flooring Ongoing

38 Genesee Hill Elementary School Area 4 Completed Striping of Gym Floor

39 Building Excellence IV Capital Levy Hazel Wolf K-8 at Pinehurst Site: General site clean up and monitoring TESC measures. Electrical vault pad prepared for transformer set/install. Grading of loading dock area access continues. Side sewer connection lines completed on 117th avenue - 12th side sewer connection lines ongoing. Off-site sidewalks and curbing efforts continue. Building A: A1 Exterior - Top deck water proofing continues. Interior - GWB taping ongoing at Library and Art classroom. Area A2 Exterior - Storefront window install at end of building stair wells completed. Interior - GWB hanging complete at end of building stairs, main stairs ongoing. Painting continues first floor. Ceiling grid installation ongoing on the first, second and third floors. Elevator installation work continues. Millwork/cabinetry ongoing on second floor and plumbing fixtures delivered. Area A3 Exterior -Water proof membrane install ongoing, concrete stairs form work ongoing. Exterior masonry work completed. Interior MEP ongoing. Building B: Exterior - Placement of exterior concrete slab on grade pending weather. Roofing completed. Exterior sheeting completed with air barrier nearly complete. Interior - Band/choir room metal stud framing completed. MEP ongoing. Building C: Exterior - Air Barrier complete. Final retaining wall section rebar placed and concrete poured. Interior - Soffit framing ongoing. GWB started at soffits and walls. MEP at ceiling soffits ongoing.

40 Hazel Wolf K-8 at Pinehurst Site Plan

41 Hazel Wolf K-8 at Pinehurst Aerial View from the East April 16, 2016

42 Hazel Wolf K-8 at Pinehurst Area A1 Exterior Siding Looking South April 15, 2016

43 Hazel Wolf K-8 at Pinehurst Area A1 Siding Looking North April 13, 2016

44 Hazel Wolf K-8 at Pinehurst Area A1 Freezer Installed April 14, 2016

45 Hazel Wolf K-8 at Pinehurst Area A2, A3 Exteriors Looking North West April 13, 2016

46 Hazel Wolf K-8 at Pinehurst Area A2 Second Floor Millwork Installed April 12, 2016

47 Hazel Wolf K-8 at Pinehurst Area A2 Second Floor Restroom Tile April 12, 2016

48 Hazel Wolf K-8 at Pinehurst Area C Exterior of Before/After School Care Area Looking South East April 13, 2016

49 Hazel Wolf K-8 at Pinehurst Area C Exterior Block Looking North East April 10, 2016

50 Hazel Wolf K-8 at Pinehurst Area C Gypsum Wall Board (GWB) Installed in Gym April 9, 2016

51 Hazel Wolf K-8 at Pinehurst Area C Exterior Gymnasium Doors April 13, 2016

52 Building Excellence IV Capital Levy Olympic Hills Elementary School Site: TESC measures ongoing; ended use of baker tanks for sediment. Building: Continued steel column erection and structural wall framing in Area A and B. Prep for last slab-on-grade pour in Area C. Continue forming, pouring, backfilling footings and stem walls in Area D. Underground MEP installation in Area C and D.

53 Olympic Hills Elementary School Site Plan

54 Olympic Hills Elementary School Aerial Photo

55 Olympic Hills Elementary School Zone Map

56 Olympic Hills Elementary School Zone A Structural Wall Framing, Looking Northeast April 13, 2016

57 Olympic Hills Elementary School Zone B Structural Steel Column Erection, Looking Southeast April 13, 2016

58 Olympic Hills Elementary School Zone C Preparation for Slab-on-Grade Concrete Pour, Looking South April 13, 2016

59 Olympic Hills Elementary School Zone D Exterior Stem Wall Rigid Insulation, Looking West April 13, 2016

60 Building Excellence IV Capital Levy Seattle World School at T.T. Minor Area A Administration Office, Student Services, Health Clinic and Library: Exterior - Administration addition roof panels complete and roofing material complete. Interior - GWB installation ongoing. Ready for paint this week. MEP work ongoing. Area B Multipurpose, Kitchen, Boiler Room: Exterior - Roofing material complete and installation of roof exhaust fans ongoing. Interior - ADA stage ramp in progress. GWB installation ongoing. MEP work ongoing. Air handling units set in place and mechanical installation ongoing. Area C Classrooms: Painting on going. Air handling units being set in place.

61 Seattle World School at T.T. Minor Site Plan Area C Area B Area A Area C Area B Area A

62 Seattle World School at T.T. Minor Site Seattle City Light Electrical Vault and Transformer Installation April 18, 2016

63 Seattle World School at T.T. Minor Site Seattle City Light Electrical Vault and Transformer Installation April 18, 2016

64 Seattle World School at T.T. Minor Area B Concrete Footing Waterproofing Installation In Progress April 18, 2016

65 Seattle World School at T.T. Minor Area A Front Entry Vestibule Concrete Footings and Stem Walls In Place April 18, 2016

66 Seattle World School at T.T. Minor Area B Roof Material Installation Complete and Exhaust Hoods Set April 18, 2016

67 Seattle World School at T.T. Minor Area A Mechanical Duct Installation to Air Handling Units April 18, 2016

68 Seattle World School at T.T. Minor Area B Weather Barrier Installation Ongoing April 18, 2016

69 Seattle World School at T.T. Minor Area B Skylight Well Framing April 18, 2016

70 Seattle World School at T.T. Minor Area B Fire Riser Room Framing Ongoing April 18, 2016

71 Seattle World School at T.T. Minor Area C Painting Ongoing April 18, 2016

72 Building Excellence IV Capital Levy New Thornton Creek Building Site: Monitoring TESC measures. Began installing fencing for playfield backstop. Building A: Exterior - Completed structural steel erection east end (Gym and Childcare). Ongoing metal stud framing and sheathing installation. Ongoing application of fluid applied air barrier. Ongoing roofing at northwest end of building. Completed roofing over Admin Area and Commons. Interior - Ongoing installation of metal stud framing, hollow metal frame doors and relites. Ongoing hanging of ductwork and installing louvers. Ongoing MEP rough-in. Building B: Exterior - Completed application of fluid applied air barrier. Began installing fiber cement panel support bracket and insulation. Masonry on north elevation ongoing. Window installation ongoing. Interior - Completed installation and taping of GWB on first and second floors. Began painting GWB on first floor. MEP rough-in at penthouse ongoing. Building C: Exterior - Completed installation of fiber cement panels. Interior - Ongoing painting of classrooms. Completed installing epoxy flooring in bathrooms. Ongoing installing casework in classrooms. Completed installing wood and hollow metal doors and hardware. Completed installation of lighting in hallway and classrooms. Ongoing trim of electrical devices. Off-site Improvements: Pouring concrete panels in NE 77 th St between 41 st Ave NE and 42 nd Ave NE. Began concrete curbs and ADA ramps at intersection of NE 77 th St. and 40 th Ave NE.

73 New Thornton Creek Building Key Plan Building C Building B Building A D

74 New Thornton Creek Building Aerial View from the North April 13, 2016

75 New Thornton Creek Building Building A Gym Mechanical Mezzanine

76 New Thornton Creek Building Building A Exterior Sheathing on Commons & Gym

77 New Thornton Creek Building Building A Roofing on Commons Roof

78 New Thornton Creek Building Building A Roofing on Gym Roof

79 New Thornton Creek Building Building B Gypsum Wall Board (GWB) Installed in Library

80 New Thornton Creek Building Building B Library Mechanical Mezzanine

81 New Thornton Creek Building Building B Supports for Fiber Cement Panels

82 New Thornton Creek Building Building C HVAC Ductwork & Equipment in Mechanical Room

83 New Thornton Creek Building Building C Glazing Installed in Classroom Relite Window