SECTION EARTHWORK

Size: px
Start display at page:

Download "SECTION EARTHWORK"

Transcription

1 SECTION PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and perform all excavation, backfill, fill and grading required to complete the work as shown on the Drawings and as specified herein. The work shall include, but not necessarily be limited to; excavation and backfill for electrical manholes, handholes, conduits, cables, raceways and ducts; embankment and grading; disposal of waste and surplus materials; and all related work such as sheeting, bracing, and dewatering. B. All excavation, trenching and related sheeting, bracing, etc, shall conform to the requirements of the Florida "State Safety Act" (CS/SB 2626) which incorporates, by reference, OSHA's excavation safety standards, 29 CFR Subpart P. C. Excavation, backfill, and compaction for structures and piping are included in other sections as listed below RELATED WORK A. Dewatering and Drainage is included in Section and B. Rock and Boulder Excavation is included in Section C. Structural Excavation, Backfill and Compaction is included in Section D. Trenching, Bedding and Backfill for Pipe is included in Section and REFERENCE STANDARDS A. American Society for Testing and Materials (ASTM) 1. ASTM C33 - Specification for Concrete Aggregates. 2. ASTM Dl557- Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,00 ft-lbf/ft (2,700kN-m/m) 3. ASTM D1682- Standard Test Methods for Breaking Load and Elongation of Textile Fabrics. 4. ASTM D Standard Classification of Soils for Engineering Purposes. IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 1 of 6

2 5. ASTM D4751- Standard Test Method for Determining the Apparent Opening Size of a Geotextile. B. Where reference is made to one of the above standards, the revision in effect at the time of bid opening shall apply PROTECTION A. Sheeting and Bracing 1. Furnish, put in place and maintain such sheeting and bracing as may be required: by Federal, State and local safety requirements; to support the sides of excavations; to prevent any movement which could in any way diminish the width of the excavation below that necessary for proper construction; and to protect adjacent structures from undermining or other damage. Care shall be taken to prevent voids outside of the sheeting, but if voids are formed, they shall be immediately filled and rammed. Where soil cannot be properly compacted to fill a void, lean concrete shall be used as backfill. 2. In order to protect adjacent structures, installation or removal of sheeting by vibratory orhammering methods shall not be allowed. 3. Construct the sheeting outside the neat lines of the foundation, unless indicated otherwise, to the extent deemed desirable for the method of operation. Sheeting shall be plumb and securely braced and tied in position. Sheeting and bracing shall be adequate to withstand all pressures to which the structure or trench will be subjected. Any movement or bulging which may occur shall be corrected to provide the necessary clearances and dimensions. 4. Where sheeting and bracing is required to support the sides of excavations for structures, engage a professional Engineer, registered in the State of Florida to design the sheeting and bracing. The sheeting and bracing installed shall be in conformity with the design and certification of this shall be provided by the professional Engineer. Submit P.E. Certification Form contained in Section to show compliance with this requirement. 5. All sheeting and bracing not left in place shall be carefully removed in such manner as not to endanger the construction or other structures, utilities, or property. All voids left or caused by withdrawal of sheeting shall be immediately refilled with sand by ramming with tools especially adapted to that purpose, or otherwise as may be directed. 6. The right of the ENGINEER to order sheeting and bracing left in place shall not be construed as creating any obligation on his/her part to issue such orders and his/her failure to exercise his/her right to do so shall not relieve the CONTRACTOR from liability for damages to persons or property occurring from IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 2 of 6

3 or upon the work occasioned by negligence or otherwise, growing out of a failure on the part of the CONTRACTOR to leave in place sufficient sheeting and bracing to prevent any caving or moving of the ground. 7. No sheeting is to be withdrawn if driven below mid-diameter of any pipe and under no circumstances shall any sheeting be cut off at a level lower than 1-ft above the top of any pipe. B. Pumping and Drainage 1. At all times during construction provide and maintain proper equipment and facilities to remove all water entering excavations and keep such excavations dry so as to obtain a satisfactory undisturbed subgrade foundation condition until the fills, structures or pipes to be built thereon have been completed to such extent that they will not be floated or otherwise damaged by allowing water levels to return to natural levels. Engage a Geotechnical Engineer registered in the State of Florida to design the dewatering system in accordance with Section prior to commencing work. 2. Dewatering shall at all times be conducted in such a manner as to preserve the undisturbed bearing capacity of the subgrade soils at proposed bottom of excavation. Well or sump installations shall be constructed with proper sand filters to prevent drawing of finer grained soil from the surrounding ground. 3. Take all additional precautions to prevent uplift of any structure during construction. 4. Remove the dewatering equipment after the system is no longer required SOIL TESTING A. Previous to the general placement of the fill and during such placement, the ENGINEER may select areas within the limits of the fill for testing the degree of compaction obtained. Cooperate fully in obtaining the information desired. B. Payment for testing will be made by the OWNERCONTRACTOR as part of the project. If test results are unsatisfactory, all costs involved in correcting deficiencies in compacted materials to the satisfaction of the ENGINEER, will be borne by the CONTRACTOR.. PART 2 PRODUCTS 2.01 MATERIALS IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 3 of 6

4 A. Select Common Soil and Structural Fill shall be as specified in Section B. Common soil shall be as specified in Section C. Crushed Stone 1. Crushed stone shall conform to Florida Department of Transportation Class 57 stone gradation. D. Screened Gravel 1. Screened gravel shall be used for pipe bedding as detailed and at other locations indicated on the Drawings. 2. Screened gravel shall consist of hard, durable, rounded or subangular particles of proper size and gradation and shall be free from sand, loam, clay, excess fines and deleterious materials. The gravel shall be graded within the following limits: Sieve Size 5/8-in 1/2-in 3/8-in No.10 Percent Finer by Weight to to 45 0 to 5 IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 4 of 6

5 PART 3 EXECUTION 3.01 BACKFILLING - COMMON FILL A. Common Fill may be used as trench backfill and fill against exterior walls of structures as indicated on the Drawings; as embankment fill; or in other areas as designated by the ENGINEER. Material conforming to the requirements of common fill shall be placed in layers having a maximum thickness of 2-ft measured before compaction. B. Common Fill shall be compacted to at least 95 percent of maximum density as determined by ASTM D1557, Method D. C. Materials placed in fill areas shall be deposited to the lines and grades shown on the Drawings making due allowance for settlement of the material and for the placing of loam thereon. D. The surfaces of filled areas shall be graded to smooth true lines, strictly conforming to grades indicated on the grading plan and no soft spots or uncompacted areas will be allowed in the work. E. No compacting shall be done when the material is too wet either from rain or from excess application of water. At such times, work shall be suspended until the previously placed and new materials have dried sufficiently to permit proper compaction DISPOSAL OF SURPLUS MATERIAL A. No excavated materials shall be removed from the site of the work or disposed of, except as specified by the ENGJNEER. Materials shall be neatly piled so as to inconvenience as little as possible the public and adjoining property OWNERS until used or otherwise disposed of as specified below. B. Suitable excavated material shall be used for fill embankments or backfill on the different parts of the work as required. C. Surplus fill shall become the property of the CONTRACTOR and shall be removed and disposed offsite DISPOSAL AND REPLACING OF ROCK A. Remove and dispose of all pieces of ledge and boulders which are not suitable for use in other parts of the work. Rock disposed of by hauling away to spoil areas is to be replaced by approved surplus IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 5 of 6

6 excavation obtained elsewhere on the work, insofar as it is available. Any deficiency in the backfill material shall be made up with acceptable material approved by the ENGINEER. B. Fragments of ledge and boulders smaller than 50 lb weight may be used in backfilling trenches unless in the opinion of the ENGJNEER the quantity is excessive, in which case he/she may order the removal and disposal of some of this rock. The small pieces of rock used as backfill shall not be placed in trenches until the pipe has at least 2-ft of earth over it. Place these pieces of stone in thin layers alternating them with earth to be sure that all voids between the stones are completely filled with earth to prevent the occurrence of voids and settlement which will result therefrom. C. Rock may be used in embankment fill only with the approval of the ENGJNEER GRADING A. Grading in preparation for placing of loam, planting areas, paved walks and drives and appurtenances shall be performed at all places that are indicated on the Drawings, to the lines, grades and elevations shown and otherwise as directed by the ENGINEER and shall be performed in such a manner that the requirements for formation of embankments can be followed. All material encountered, of whatever nature, within the limits indicated, shall be removed and disposed of as directed. During the process of grading, the subgrade shall be maintained in such condition that it will be well drained at all times. When directed, temporary drains and drainage ditches shall be installed to intercept or divert surface water which may affect the prosecution or condition of the work. B. If at the time of grading it is not possible to place any material in its final location, it shall be stockpiled in approved areas for later use. No extra payment will be made for the stockpiling or double handling of excavated material. C. The right is reserved to make minor adjustments or revisions in lines or grades if found necessary as the work progresses, in order to obtain satisfactory construction. D. Stones or rock fragments larger than 4-in in their greatest dimensions will not be permitted in the top 6-in of the finished subgrade of all fills. END OF SECTION IMMOKALEE ROAD CHLORAMINE BOOSTER STATION Page 6 of 6

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to

More information

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING 32.1 GENERAL SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING This Section covers excavation, backfill, fill and grading associated with utility trench and structural construction. All such WORK

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL 13.01 GENERAL The work included in this section shall consist of furnishing all materials and equipment and performing all labor

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SPECIAL SPECIFICATION 4653 Polypropylene Pipe 2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered. SECTION 02200 PART 1 GENERAL 1.1 SECTION INCLUDES A. Subsoil and aggregate materials. B. Removal of subsoil and excavating all classes of material encountered. C. Handling, storage, transportation and

More information

DEWATERING AND DRAINAGE

DEWATERING AND DRAINAGE 2011 CDM Smith Inc. SECTION 02140 DEWATERING AND DRAINAGE PART 1 GENERAL 1.01 SCOPE OF WORK A. Design, furnish, install, operate, monitor, maintain and remove temporary dewatering systems as required to

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES AFTER MARCH 1, 2012 ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES 430.1 Description. This item shall govern for all excavation required for the construction of sewers, sewer structures, pipe culverts,

More information

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1 1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

The Six-Inch Layer Compaction Method

The Six-Inch Layer Compaction Method 1/7 1.0 PURPOSE This specification describes the minimum requirements for the backfilling of trenches or the construction of berms primarily for the installation of buried pipelines, cables, ducts and

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING Section Number Title 301 GENERAL 302 MATERIALS SPECIFICATIONS 303 CLEARING

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation. SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES 1 1 1 0 1 0 1 0 1 SECTION 1. STRUCTURAL EXCAVATION FOR STRUCTURES BASED ON DFD MASTER SPECIFICATION DATED /1/1 P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all

More information

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related

More information

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code. 1/6 1.0 PURPOSE This specification describes the minimum requirements for filling depressions and for backfilling excavations for structural footings, slabs, floors, buildings, trestles, and the like..

More information

SECTION 14 EMBANKMENT

SECTION 14 EMBANKMENT SECTION 14 EMBANKMENT 14.1 DESCRIPTION A. General: This work consists of constructing roadway embankments, including preparation of the areas upon which embankments are to be placed; the construction of

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations. Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet

More information

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.]

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.] 28-1 GENERAL SECTION 28 AGGREGATE BASE COURSE (FAA P-208) The Contractor shall perform all work required by the plans and specifications for construction of aggregate base course for, use under runway

More information

SECTION EXCAVATION, BACKFILLING AND COMPACTING

SECTION EXCAVATION, BACKFILLING AND COMPACTING PART 1 GENERAL 1.01 SCOPE Work of this Section shall include all labor, materials, equipment, plant and incidentals required to complete all excavation, backfilling and compacting as indicated on the Drawings

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

EXCAVATION & BACKFILL SPECIFICATION

EXCAVATION & BACKFILL SPECIFICATION REVISION DATE DESCRIPTION BY REVIEWER 0 12/14/2009 ISSUED FOR CONSTRUCTION MJS TDJ SECTION 1 EARTHWORK 1.1 GENERAL. This section covers general earthwork and includes preparation of the construction areas;

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 02222 - EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES PART 1 - GENERAL 1.01 SECTION INCLUDES A. Excavating trenches for the installation of utilities and stormwater detention facilities. B.

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL 804.1 DESCRIPTION: This section shall govern the excavation, trenching, and backfilling for water, sanitary sewer, and recycled water construction, unless

More information

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014 1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,

More information

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing. SECTION 02221 TRENCHING, BACKFILLING AND COMPACTION PART 1 GENERAL 1.01 WORK INCLUDED A. Excavation for piped utility material. B. Provide necessary sheeting, shoring and bracing. C. Prepare trench bottom

More information

SPECIAL SPECIFICATION 4xxx Thermoplastic Pipe

SPECIAL SPECIFICATION 4xxx Thermoplastic Pipe 2004 Specifications SPECIAL SPECIFICATION 4xxx Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm sewer mains,

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL 804.1 DESCRIPTION: This section shall govern the excavation, trenching, and backfilling for water, sanitary sewer, and recycle mains construction, unless

More information

REGIONAL CONSTRUCTION STANDARDS

REGIONAL CONSTRUCTION STANDARDS REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.5 (Full Committee Approved Proposed Revision 6.5 Storm Sewer Joint Wrap - Section 302 As Publication Update 6.5) March 27, 2018 Copyright

More information

SECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals.

SECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals. SECTION 312333 - TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 31 23 00 EXCAVATION AND BACKFILL, GENERAL PART 1 GENERAL... 2 1.1 Description... 2 1.2 Submittals... 2 1.3 Reference

More information

SECTION 303 CULVERTS

SECTION 303 CULVERTS 303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the

More information

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary

More information

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 1.0 EXCAVATION AND FILL 1.1 GENERAL.1 The excavation or fill shall be made to provide proper grade, lines and crosssection for the laying of

More information

SECTION GENERAL EXCAVATION

SECTION GENERAL EXCAVATION 02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SECTION 18 - EARTHWORK TABLE OF CONTENTS SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18.1 18-2 ROADWAY EXCAVATION... 18.1 18-2.01 General... 18.1 18-2.02 Unsuitable Roadway Excavation and Backfill... 18.1 18-2.03 Surplus

More information

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 31 23 33 TRENCHING AND BACKFILL PART 1 GENERAL... 3 1.1 Description... 3 A. Excavation for Utilities Includes... 3 B. Suitable Fill Material...

More information

County of Park PARK COUNTY WYOMING PRIVATE SOURCE GRAVEL POWELL AREA PRODUCE TO STOCKPILE REQUEST FOR QUOTE

County of Park PARK COUNTY WYOMING PRIVATE SOURCE GRAVEL POWELL AREA PRODUCE TO STOCKPILE REQUEST FOR QUOTE PUBLIC WORKS DEPARTMENT Brian J. Edwards, PE Park County Engineer Road & Bridge and Engineering 527-8520 or 754-8520 PARK COUNTY, WYOMING ORGANIZED 1911 ORIGINAL PARK COUNTY COURTHOUSE CODY, WYOMING COMPLETED

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS 1 PART ONE - GENERAL 1.1 COORDINATION SECTION 02466 DRILLED CONCRETE PIERS AND SHAFTS A. The General, Supplementary, and Special Conditions of these specifications shall all be considered as a part of

More information

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include

More information

1.2 REFERENCES.1 American Society for Testing and Materials International (ASTM)

1.2 REFERENCES.1 American Society for Testing and Materials International (ASTM) Pan Am Pool New Electrical Room Page 1 of 7 Part 1 General 1.1 SUMMARY.1 Related Sections:.1 Section 02 41 13 - Selective Site Demolition..2 Section 07 21 13 Board Insulation: perimeter foundation insulation

More information

SECTION UTILITY BACKFILL MATERIALS

SECTION UTILITY BACKFILL MATERIALS SECTION 31 23 23 UTILITY BACKFILL MATERIALS PART 1: GENERAL 1.01 SECTION INCLUDES A. Material Classifications B. : 1. Concrete sand 2. Gem sand 3. Pea gravel 4. Crushed stone 5. Crushed concrete 6. Bank

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

City of Thomasville Water, Sewer & Natural Gas Specifications SECTION TRENCH EXCAVATION AND BACKFILL

City of Thomasville Water, Sewer & Natural Gas Specifications SECTION TRENCH EXCAVATION AND BACKFILL SECTION 02225 TRENCH EXCAVATION AND BACKFILL PART 1 GENERAL 1.01 SCOPE A. The work under this Section consists of furnishing all labor, equipment and materials and performing all operations in connection

More information

SECTION FILL AND BACKFILL

SECTION FILL AND BACKFILL PART 1 GENERAL 1.1 SECTION INCLUDES A. Filling, backfilling, and compacting for building volume below grade, footings, slabs-on-grade, paving, site structures, and utilities within the building. B. Backfilling

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 312300 EXCAVATION AND FILL PART 1 - GENERAL 1.1 SUMMARY A. Excavate, backfill, compact, and grade the site to the elevations shown on the Drawings, as specified herein, and as needed to meet the

More information

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

A. Backfill: Soil material or controlled low-strength material used to fill an excavation. GSA Project No.: GS-P-03-14-AZ-5044 SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Preparing subgrades for walks. 2. Excavating and backfilling for structures. 3. Subbase

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 November 2015 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT TABLE OF CONTENTS D 422.01 D 422.02 D 422.03

More information

SECTION TRENCH EXCAVATION AND BACKFILL

SECTION TRENCH EXCAVATION AND BACKFILL SECTION 02221 - TRENCH EXCAVATION AND BACKFILL CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Sections... 2 1.03 Reference Standards... 2 1.04 Quality Assurance... 2 1.05 Measurement

More information

SECTION EMBANKMENT

SECTION EMBANKMENT 02260-1 of 8 SECTION 02260 EMBANKMENT 02260.01 GENERAL A. Description 1. Embankment shall be formed of suitable material obtained from General, Structure, Borrow, Trench, and other excavations included

More information

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements. SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE

Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE 14-1 ROADWAY EXCAVATION AND BACKFILL In the Contract this item shall consist of excavating, removing, and satisfactory disposal of all material

More information

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 10 - TRENCHING AND BACKFILLING SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements

More information

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and

More information

SECTION TRENCHING, BACKFILL AND COMPACTION

SECTION TRENCHING, BACKFILL AND COMPACTION SECTION 312333 TRENCHING, BACKFILL AND COMPACTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. Native Backfill Material 2. Crushed Stone Bedding 3. Select Backfill Material 4. Shoring and Bracing

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 02210 - Site Grading C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 STRUCTURE PROTECTION... 2 1.03 JOB CONDITIONS... 3 PART 2 - PRODUCTS...

More information

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SECTION 18 - EARTHWORK TABLE OF CONTENTS SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL...18.1 18-2 ROADWAY EXCAVATION...18.1 18-2.01 General...18.1 18-2.02 Unsuitable Roadway Excavation and Backfill...18.1 18-2.03 Surplus

More information

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving. SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.

More information

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form Proposed Revision To: REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form General Provisions (Division 1) Technical Specifications (Divisions 2-8) Standard Details Change No. Hampton Roads Planning

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 313430- PART 1 GENERAL 1.1 WORK INCLUDED A. Provide all equipment, material, labor and supervision to design and install Engineered Aggregate Piers for the soil reinforcement. Design shall rely

More information

A. Work of this Section is affected by unit prices for earth moving specified in Section "Unit Prices."

A. Work of this Section is affected by unit prices for earth moving specified in Section Unit Prices. SECTION 312000 EARTH MOVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations. SPEC-1100 1/9 1.0 PURPOSE This specification describes the minimum requirements for general grading, excavation of earth, rock and solid slag, embankment construction, ditching, use of explosives, and

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications. SECTION 31 22 00- GRADING 1.0 GENERAL.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.. 2 Excavate to exact line and grade as

More information

SECTION 500 STRUCTURES

SECTION 500 STRUCTURES SECTION 500 STRUCTURES 500.1 GENERAL This section defines the various construction items that are associated with the completion of a concrete, steel, timber, or masonry unit structures, or a combination

More information

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS AFTER FEBRUARY 1, 2011 ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS 481.1 Description. This specification shall govern for the construction of monolithic, reinforced concrete box sewers of the size,

More information

ITEM I - EXCAVATION. Section VI - Technical Specifications Trenching and Excavation Regulations

ITEM I - EXCAVATION. Section VI - Technical Specifications Trenching and Excavation Regulations ITEM I - EXCAVATION 1.01 Trenching and Excavation Regulations The CONTRACTOR shall comply with OSHA trenching and excavation regulations as revised in "Subpart P" of Part 1926 in the Federal Register.

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

ITEM 750 ROCK FILTER DAMS

ITEM 750 ROCK FILTER DAMS AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 WORK INVOLVED A. Provide all labor, materials and equipment as required for all excavation, grading, providing borrow materials, hauling, placing and compacting

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 31 23 00 Trenching, Backfilling, and Compaction of Utilities 1. General A. The Contractor shall furnish all labor, materials, tools, equipment, and perform all

More information

EXCAVATION AND BACKF1LL

EXCAVATION AND BACKF1LL S E C T I O N 2 3 1 5 EXCAVATION AND BACKF1LL PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: Excavation, trenching, complete and continual dewatering of excavation, sheeting, bracing and shoring of

More information

TRENCH EXCAVATION AND BACKFILL

TRENCH EXCAVATION AND BACKFILL TRENCH EXCAVATION AND BACKFILL PART 1 - GENERAL 1.01 SECTION INCLUDES A. Trench Excavation for Pipe Systems B. Trench Foundation Stabilization C. Pipe Bedding and Backfill 1.02 DESCRIPTION OF WORK A. Excavate

More information