Forsyth County Procurement

Size: px
Start display at page:

Download "Forsyth County Procurement"

Transcription

1 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director August 21, 2017 ADDENDUM # 3 BID NO For: Construction of the Newton Pumping Station and Sanitary Sewer This addendum supersedes and supplements all portions of the bidding documents and becomes part of the contract documents for the above-referenced project. Where any original item is amended, voided, or superseded hereby, the provision of such item not so specifically amended, voided, or superseded shall remain in effect. Where any item called for in the specifications or indicated on the drawings that is not specifically supplemented, amended, voided, or superseded hereby, the original requirements shall remain in effect. Following are questions received and responses (in italics): 1. What type of paving should be used to replace pump station driveway? The paving should be replaced with 8-inch GDOT GAB compacted to 100% Standard Proctor (ASTM D698) (AASHTO T-99) with tack coat and 2 inches of GDOT SuperPave 9.5 mm per Forsyth County Department of Water and Sewer Standards Specifications. 2. May a substitute channel grinder be approved as an or equal prior to bidding? Regarding the channel grinder in Section , the contractor should bid the job using the JWC Channel Monster specified. If the successful low bidder wants to substitute equipment, then the contractor should submit a cost reduction change order in accordance with the contract documents for the substitute equipment after the contract is awarded. The Vogelsang Grinder is not an approved equal. 514 West Maple Street, Suite 104 Cumming, Georgia (770) forsythco.com

2 3. May a substitute submersible pump be approved as an or equal prior to bidding? Regarding the submersible pump in Section , the contractor should be bid the job using the four manufacturers specified. Additional pump manufacturers are not approved. If the successful low bidder wants to substitute pumps and equipment, then the contractor should submit a cost reduction change order in accordance with the contract documents after the contract is awarded. The Grundfos Pump is not an approved equal. 4. Do DIP fittings have to be zinc coated like the DIP? The DIP fittings should be coated as specified. All fittings shall have a cement-mortar lining with an asphaltic seal coat and an asphaltic coating on the exterior. Fittings may be furnished with a 6-mil minimum nominal thickness fusion bonded epoxy coating conforming to ANSI/AWWA C550 and C116/A21.16 in lieu of bituminous coating. Protecto 401 coating is also acceptable. 5. What specific models of the air vacuum release valves Section Air/Vacuum Valves for Wastewater Service should be used for bidding this project? The two approved air vacuum release valves are the H-tec model 986 with 4-inch flange and the ARI model D-020 with 4-inch flange. Both valves may be provided with an isolation valve supplied by the AVRV valve manufacturer or the AWWA gate valve shown on the construction details. Both valves should provide the stainless steel type body. Both valves should be adapted to the 12 Flange x 8 Flange Tee by the contractor. 6. Are diesel driven pumps acceptable? Diesel driven pumps will not be accepted as standby power because the standby diesel electric generator set provides back up electrical power for more than the pumps. 7. When do questions need to be submitted? The period for written questions to be submitted to Forsyth County Procurement will end August 24, 2019 at 4:00 PM.

3 8. Which set of engineering plans should be used? The Engineering Plans have been extensively revised. The project should be bid using the plans dated and showing Addendum #3 in the revision box. The revised plans are available on the Forsyth County Procurement web site as part of this Addendum #3. All earlier versions of the Hayes James plans are now void. 9. Can you verify if there will be an addendum release with Grundfos listed as an approved manufacturer? Grundfos is not an approved manufacturer. 10. Second, I have looked through all the plans and specifications and cannot find a hatch size listed for the well. Is there a size you have designed already, or are you leaving this to the pump manufacturer to recommend? The pump manufacturer is to provide the hatch for the wet well that is compatible with the manufacturer s pumps with the pump installed on the manufacturer s recommended spacing between the pumps. The supplied hatch should provide acceptable clearance between the hatch frame and the edge of the pump while the pump is still on the slide rails. 11. May a Vent-Tech Are Vacuum Release Valve be approved as an or equal prior to bidding? Vent-Tech is not an approved manufacturer of air vacuum release valves for this project. 12. Are there any technical issues regarding the pumps that I should be aware of? Read the revised plans and specs as issued. 13. Have any of the pump suppliers said anything to you regarding the size requirement for the wet well access hatch? The pump manufacturer is to provide the hatch for the wet well that is compatible with the manufacturer s pumps with the pump installed on the manufacturer s recommended spacing between the pumps. The supplied hatch should provide acceptable clearance between the hatch frame and the edge of the pump while the pump is still on the slide rails. 14. Will the hatch sitting on top of an 8 diameter wet well allow the pumps to pass through easily? The wet well raiser section is 10 feet inside diameter, see Sheet C-22. The wet well base section is 12 feet inside diameter.

4 15. We estimate that each pump will weigh about 2,200 lbs each. There is no crane or hoisting equipment specified? The Forsyth County maintenance crews are equipped with a boom truck to lift the pumps from the wet well for maintenance. 16. Does the County have the equipment to safely remove the pumps when necessary or will a permanent device be added? See answer to Question It was not clear regarding an access hatch for the valve pit and so I was not going to quote this item. Where was that item shown? The valve pit does not have a top; therefore, no hatch is needed. See Sheet S-4. The meter vault is 9ft x 9ft inside dimensions with a 4ft x 4ft hatch with safety grate. 18. Was a safety grate required for the valve pit access hatch if there is a hatch requirement? No. 19. The chains are specified as 316L SS. I did not see a SS type specified for the guide rails. Is type 304 OK or do you want 316? The chains to hoist the pumps and channel grinder should be 316L stainless steel. The guide rails should also be 316L SS. 20. Can Fusible PVC be used by HDD to cross the creeks in lieu of jack and bore? No. 21. Can Fusible PVC be used in lieu of DIP to downsize the jack and bores? No. 22. Are there plan revisions? Yes. To eliminate confusion, a complete set of revised plans is included in this Addendum #3. The bid set of plans is therefore those plans showing Addendum #3 in the revision box and dated Plan sheets that have changed are Cover, C-0, C-1, C-2, C-7, C-9, C-10, C-11, C-12, C-15, C-16, C-16.1, C-17, C-22, C-32, C-33, S-1, S-2, E-5, E-8, & E-10.

5 23. How will the bids be compared considering the alternatives? The bids will be compared on the basis bid using the Flygt Pumps. If one of the alternative pumps has a better price than the Flygt pumps the alternative pump will be used in the actual contract as a substitute for line item Specification section M. 17. a. (Top of Page 21 of 33) states in the second sentence: Inside the control panel there will be a main breaker. This conflicts with Drawings E-2 (One-Line Diagram) and E-7 (Schematic Wiring Diagrams) that show the circuit breaker in Switchboard PS. Which is correct? Do we need an additional circuit breaker, a main disconnect, or nothing in the control panel? EDEC: Since Pump control panel will be located next to the switchboard, main breaker is not required in the pump control panel. 25. In addition, Drawing E-2 Note 5.S. lists several spares requirements that conflict with the requirements of M. 26. The drawing simply states fuses while the specification states 10% for each type and the drawing adds a pump basic pump repair kit which is not noted in the specification. What are the required spares to be provided? EDEC: Spare parts shall include the parts listed in Note 5.S on Drawing E-2. For any additional spare parts and quantities requirements refer to spec Please verify we are to use domestic construction materials per Section A of the specifications. Please use domestic materials whenever possible. 27. Please verify contractor is to pay all costs associated with bringing power to the pump station site per Note 1 on Sheet E-2. Yes 28. Sheet C-19 names both Ross and APCO surge relief valves but the specs only name Ross in Section Please confirm APCO valves are acceptable. The Ross Valve is preferred but the very similar APCO valve is acceptable. 29. In what manner are the antiflotation collars attached to the composite wet well and composite grinder manhole? See the details on sheet c- 21 amd c-22. The means and methods are up to the contractor. The anti-flotation collars may be attached to the wet well prior to placement in the excavation. 30. On drawing E-5, in the lower left corner of the Electrical Room, there is a rectangular area shown that is not clear. A panelboard and an LCP are shown mounted to one side of this rectangle, as though a wall is present for them to be mounted on, but we are not sure. Could you clarify what this rectangular area is, and where panelboard LP-1 and LCP-HP-AC are to be mounted? The rectangular simply denotes the portion of the room the wet well air units are to be located within. The high pressure air compressor has been eliminated. The control unit for the wetwell air units are to be connected to panel LP-1 for power. On off controls for the wet well air unit should be located next to the units on an electrical rack.

6 31. On drawing E-5, under the plan view of the Electrical Room, Note 1 says to Relocate HVAC Unit. Please clarify this note, as it is our understanding that both the building and the HVAC unit are to be furnished new for this project. Provide a new HVAC unit on the south wall of the building instead of the east side of the building. The HVAC thermostat and controls should be located according to the building code. 32. What s the difference between the two affidavits highlighted above? Does one of them refer to the subcontractor s affidavit? Or did I misinterpret this? The Subcontractor s Affidavit is separate from the Bidder s Affidavit (Bidder s Acknowledgement). The Contractor Affidavit is for e-verify purposes. 33. Geotechnical Report attached. NOTE: If you are a current planholder, Revised Plans will be sent electronically under separate cover via WeTransfer. Please contact our office if you do not receive. End Addendum #3

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

Forsyth County Procurement

Forsyth County Procurement August 1, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 Bid 17-72-3340 For: Providing all materials, equipment and labor for the Jot em Down Road Water Tank

More information

Forsyth County Procurement

Forsyth County Procurement July 7, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 BID 17-63-3150 For: Providing all labor, materials and equipment for the construction of the Brookwood

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

TITLE: Construction Services for the US-1 South Re-Pump and Booster Pump Station Project

TITLE: Construction Services for the US-1 South Re-Pump and Booster Pump Station Project Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 June 06, 2018 ADDENDUM NUMBER: One (1) TITLE: Construction Services for the US-1 South

More information

ADDENDUM NO. 5. Except as hereinafter specified, the work shall be in accordance with the drawings and specifications.

ADDENDUM NO. 5. Except as hereinafter specified, the work shall be in accordance with the drawings and specifications. ADDENDUM NO. 5 ITB-CD-CME-16-10 Southern Well Field Expansion: Equip 5 Wells and New Raw Water Main Phase 2 ISSUE DATE: August 22, 2016 DUE DATE: August 25, 2016 @ 2:00 p.m. SUBJECT: Addendum No. 5 INTENT:

More information

ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. PS 061 SEVEN SPRINGS WASTEWATER TREATMENT FACILITY IMPROVEMENTS PASCO COUNTY,

More information

OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC Robyn M. Courtright, CPPO, Procurement Director

OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC Robyn M. Courtright, CPPO, Procurement Director OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC 29691 Robyn M. Courtright, CPPO, Procurement Director Tronda Spearman, CPPB, Assistant Procurement Director Telephone: 864-638-4141

More information

C o u n t y o f F a i r f a x, V i r g i n i a

C o u n t y o f F a i r f a x, V i r g i n i a 001961 Page 2 C o u n t y o f F a i r f a x, V i r g i n i a A D D E N D U M DATE: August 2, 2016 ADDENDUM NO. 4 TO: REFERENCE: FOR: DUE DATE/TIME: ALL PROSPECTIVE BIDDERS Government Center Generator System

More information

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications

More information

Addendum No. 2 is hereby issued to revise the Procurement Schedule, clarify Bid Bond Requirements,

Addendum No. 2 is hereby issued to revise the Procurement Schedule, clarify Bid Bond Requirements, ITB 2018-02 ADDENDUM NO. 2 Addendum No. 2 to ITB 2018-02 MEDART LIFT STATION BYPASS Issued February 15, 2018 SECTION 2.0 SCHEDULE OF EVENTS See dates added in RED below Failure to comply with this or any

More information

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL Page 312 VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS-12-01 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the IL ROUTE

More information

Response: The due date for receipt of proposals has been extended. Please see Amendment

Response: The due date for receipt of proposals has been extended. Please see Amendment 1) Question: Bid Date Due to the complexity, size, and prebid legwork required on a project of this scope, we request that the bid date be extended 45-60days. We appreciate your consideration of this request.

More information

General Water Bid Items Item No.

General Water Bid Items Item No. BID PROPOSAL PROPOSAL OF, a corporation organized and existing under the laws of the State of, a partnership consisting of, an individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6 SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO. 18-4501 SOLICITATION NO. CO-00198 ADDENDUM 6 (September 10, 2018) To Respondent of Record: This addendum, applicable to work referenced

More information

PERMANENT PAVEMENT REPAIR NO SCALE

PERMANENT PAVEMENT REPAIR NO SCALE SAWCUT EXISTING PAVEMENT 2" BITUMINOUS CONCRETE SURFACE COURSE, CLASS 2 (MIN) CLEAN EDGE PRIOR TO PAVING AND PAINT WITH LIQUID BITUMEN. INSTALL SEALANT OVER JOINT UPON COMPLETION 2" BITUMINOUS CONCRETE

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

CHAPTER 8 WATER SUPPLY SYSTEM

CHAPTER 8 WATER SUPPLY SYSTEM CHAPTER 8 WATER SUPPLY SYSTEM 8-1 INTRODUCTION These improvement standards shall govern the engineering design of all domestic water systems intended for operation and maintenance by the County of Sutter

More information

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details Changes for the 2017 TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details The following changes are made to the existing standards and details to clarify or improve existing information.

More information

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

EXHIBIT E SCHEDULE OF UNIT PRICES

EXHIBIT E SCHEDULE OF UNIT PRICES SCHEDULE OF UNIT PRICES TO ACCOMPANY THE BID OF (Bidder/Contractor) ON CALL UTILITY SERVICES AND MISCELLANEOUS CONSTRUCTION FOR SEWER AND WATER LINES SOLICITATION NO.: IFB SA1703 Any bidder who enters

More information

DUCTILE IRON PIPE AND FITTINGS

DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239)

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239) STANDARD DETAILS Revised January 2018 Bonita Springs Utilities, Inc. 11900 East Terry Street Bonita Springs, FL 34135 (239) 992-0711 DETAIL SHEET INDEX WATER DETAILS W-1 CONSTRUCTION JUMPER ASSEMBLY W-2

More information

CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE,

CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE, CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE FOR THE CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS RQ# 41677 BIDS DUE ON: May 1, 2018, at 2:00 p.m. ADDENDUM NUMBER 1, April 25, 2018, Page

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer complete in place and the material therein,

More information

B. Fiberglass for construction in back lot easements placed on cast-in-place base.

B. Fiberglass for construction in back lot easements placed on cast-in-place base. Section 02083 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fiberglass manholes for unpaved areas placed on top of a precast base to form a manhole. B. Fiberglass for construction in back lot easements

More information

November 19, REVISED Bid Opening Date: December 4, 2018

November 19, REVISED Bid Opening Date: December 4, 2018 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y19-709-CH / ADDENDUM # 3 WESTERN REGIONAL WATER SUPPLY FACILITY IMPROVEMENTS PHASE 3B REVISED Bid Opening Date: December 4, 2018 This addendum is hereby

More information

SECTION PACKAGED, SUBMERSIBLE SEWERAGE PUMP UNITS

SECTION PACKAGED, SUBMERSIBLE SEWERAGE PUMP UNITS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 22 13 33 PACKAGED, SUBMERSIBLE SEWERAGE PUMP UNITS SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 GENERAL 1.01 SUMMARY This Section includes ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

SEMINOLE TRIBE OF FLORIDA PURCHASING DEPARTMENT RFB MABEL T FRANK WAY ROADWAY CONSTRUCTION BIG CYPRESS INDIAN RESERVATION

SEMINOLE TRIBE OF FLORIDA PURCHASING DEPARTMENT RFB MABEL T FRANK WAY ROADWAY CONSTRUCTION BIG CYPRESS INDIAN RESERVATION SEMINOLE TRIBE OF FLORIDA PURCHASING DEPARTMENT RFB MABEL T FRANK WAY ROADWAY CONSTRUCTION BIG CYPRESS INDIAN RESERVATION 6300 STIRLING ROAD HOLLYWOOD, FLORIDA 33024 ADDENDUM NUMBER THREE June 12, 2015

More information

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PUBLIC WORKS DEPARTMENT GENERAL NOTES PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard

More information

CECIL COUNTY, MARYLAND. ADDENDUM #2 Bid ; Marley Road Sewer Extension

CECIL COUNTY, MARYLAND. ADDENDUM #2 Bid ; Marley Road Sewer Extension Office of the County Executive Alan J. McCarthy County Executive Department of Finance Purchasing Division Ken Jackson Purchasing/Fleet/Leasing Mgr. Alfred C. Wein, Jr. Purchasing Office Director of Administration

More information

MUSC Psychiatric Hospital CRI Air-Cooled Chiller Replacement Project

MUSC Psychiatric Hospital CRI Air-Cooled Chiller Replacement Project MUSC Psychiatric Hospital CRI Air-Cooled Chiller Replacement Project H51-9832-FW-A ADDENDUM NO. 01 The following items shall take precedence over the drawings and specifications for the above named project

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

THE CITY OF MT. PLEASANT, MICHIGAN

THE CITY OF MT. PLEASANT, MICHIGAN THE CITY OF MT. PLEASANT, MICHIGAN CITY HALL 320 W. Broadway 48858-2312 (989) 779-5300 (989) 773-4691 fax PUBLIC SAFETY 804 E. High 48858-3595 (989) 779-5100 (989) 773-4020 fax PUBLIC WORKS 1303 N. Franklin

More information

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 February 27, 2014 ITB NO. 14-33 WAKEFIELD PUMPING STATION UPGRADE ADDENDUM NUMBER

More information

ARTICLE 29 SANITARY SEWER FORCE MAINS

ARTICLE 29 SANITARY SEWER FORCE MAINS SANITARY SEWER FORCE MAINS Index 29.01 GENERAL 29.02 DESIGN CRITERIA 29.03 MATERIALS 29.04 VALVES 29.05 INSTALLATION 29.06 IDENTIFICATION 29.07 HYDROSTATIC TESTING BACK TO TABLE OF CONTENTS Section 29.01

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335

TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335 TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335 BIDS TO BE RECEIVED UNTIL 1:00 P.M., LOCAL TIME, WEDNESDAY, OCTOBER 28, 2015, AT THE OFFICE OF THE CITY CLERK LOCATED AT

More information

SECTION 2100 WATER MAIN

SECTION 2100 WATER MAIN SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous

More information

San Antonio Water System Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

San Antonio Water System Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer manholes, complete in place and the materials

More information

University of Delaware

University of Delaware University Contact: Energy & Engineering Group (302) 831-1744 SECTION 03 45 00_PRECAST CONCRETE STRUCTURES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the contract, including

More information

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply: SECTION 400 SANITARY SEWER SYSTEM The design of sanitary sewers shall be in conformance with the applicable sections of the State of Washington, Department of Ecology manual, Criteria for Sewage Works

More information

NOTICE TO BIDDERS FOR THE

NOTICE TO BIDDERS FOR THE NOTICE TO BIDDERS FOR THE STRUCTURAL REPAIRS, APPLICATION OF 150 MIL THICK POLYURETHANE FOR INTERNAL LINING OF RESERVOIR 4A, REMOVAL AND REPLACEMENT OF A 7.5 HP PUMP, PIPES, FITTINGS, ELECTRICAL CONDUITS,

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

SAN ANTONIO WATER SYSTEM 2013 REHABILITATION WORK ORDER CONSTRUCTION CONTRACT 4 SAWS Job No SAWS Solicitation No.

SAN ANTONIO WATER SYSTEM 2013 REHABILITATION WORK ORDER CONSTRUCTION CONTRACT 4 SAWS Job No SAWS Solicitation No. SAN ANTONIO WATER SYSTEM 2013 REHABILITATION WORK ORDER CONSTRUCTION CONTRACT 4 SAWS SAWS To Bidder of Record: ADDENDUM NO. 2 August 15, 2013 This addendum, applicable to work referenced above, is an amendment

More information

ADDENDUM NO. 3. Please make note of the following clarifications:

ADDENDUM NO. 3. Please make note of the following clarifications: Purchasing Division ADDENDUM NO. 3 DATE: March 6, 2019 FROM: City of Grand Junction Purchasing Division TO: All Offerors RE: Raw Water Irrigation Supply and Waterline Replacement IFB-4611-19-DH Offerors

More information

NOTICE TO BIDDERS FOR THE

NOTICE TO BIDDERS FOR THE NOTICE TO BIDDERS FOR THE STRUCTURAL REPAIR, APPLICATION OF 200 MIL THICK POLYURETHANE FOR INTERNAL LINING OF RESERVOIR 4A, REMOVAL AND REPLACEMENT OF AN EXISTING RETAINING WALL, A 7.5 HP PUMP, PIPES,

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

IFB # R Blythe Creek Grinder Pump Eliminations

IFB # R Blythe Creek Grinder Pump Eliminations IFB # 2019-015R Blythe Creek Grinder Pump Eliminations ADDENDUM No. 1 ISSUE DATE: October 10, 2018 *******************************************************************************************************************

More information

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016 To Respondent of Record: CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO-00082-RA Addendum 2 July 22 nd 2016 This addendum, applicable to work referenced above, is an amendment to the

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

Please acknowledge receipt of both Addendum No. 0 1 (issued

Please acknowledge receipt of both Addendum No. 0 1 (issued Bids for the construction of Water Supply Well PW-14 (), will be received by the City of Westerville, Ohio until the revised closing date and time indicated in this Addendum No. 02 and will be publicly

More information

Job Order Sewer Repair Services

Job Order Sewer Repair Services Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

Pump Station No. 1 and Storage Tank

Pump Station No. 1 and Storage Tank ADDENDUM NO. 3 Pump Station No. 1 and Storage Tank HMM Project No. 299802 CFWB Bid No. ITB 12-028 August 16, 2012 This addendum forms a part of the Contract Documents and modifies the original Project

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

Section C-111 ADVERTISEMENT FOR BIDS WINSTON-SALEM/FORSYTH COUNTY UTILITY COMMISSION IDOLS ROAD REGIONAL LIFT STATION

Section C-111 ADVERTISEMENT FOR BIDS WINSTON-SALEM/FORSYTH COUNTY UTILITY COMMISSION IDOLS ROAD REGIONAL LIFT STATION Section C-111 ADVERTISEMENT FOR BIDS WINSTON-SALEM/FORSYTH COUNTY UTILITY COMMISSION IDOLS ROAD REGIONAL LIFT STATION Pursuant to North Carolina General Statutes (NCGS) 143-128 and 143-129, sealed Bids

More information

CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1

CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1 Addendum No. 1 September 26, 2016 Page 1 of 8 CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1 This Addendum forms part of the original contract drawings and specifications

More information

EASTERN MUNICIPAL WATER DISTRICT August 1, 2014

EASTERN MUNICIPAL WATER DISTRICT August 1, 2014 EASTERN MUNICIPAL WATER DISTRICT August 1, 2014 ADDENDUM NO. 2 TO SPECIFICATION NO. 1235S Wine Country Infrastructure Project Loma Ventoso Lift Station This addendum to the specifications is for the purpose

More information

Failure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders.

Failure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders. Addendum #1 Project: Coteau Street & Utility Improvements Bid Date: 1:00 P.M., Local Time, March 20, 2017 Bid Location: Office of the City Administrator/Clerk, City of Lake Benton 106 S. Center Street

More information

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. SECTION 33 05 13 MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. B. Related Sections: 1. Section 03 20 00 - Concrete

More information

Index to Technical Specifications

Index to Technical Specifications Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

DIVISION 33 UTILITIES SECTION PACKAGED SEWAGE GRINDER PUMPING UNITS

DIVISION 33 UTILITIES SECTION PACKAGED SEWAGE GRINDER PUMPING UNITS DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: The work specified in this Section consists of providing an Environmental One grinder pump(s) unit with tank, internal piping and

More information

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES B-1 General Notes: SACWSD Standard Construction Drawing Notes 1. No work shall begin on any water or wastewater construction project until the construction

More information

SANITARY SEWER COLLECTION SYSTEM and March 12, 2015 RE-USE LINE

SANITARY SEWER COLLECTION SYSTEM and March 12, 2015 RE-USE LINE MATTHEWS INDUSTRIAL PARK Request For Bid No. FY15-0401 SANITARY SEWER COLLECTION SYSTEM and March 12, 2015 RE-USE LINE ADDENDUM #2 The following items shall take precedence over the drawings and specifications

More information

NC State University Design and Construction Guidelines Division 33 Utilities

NC State University Design and Construction Guidelines Division 33 Utilities 1.0 Purpose A. These guidelines provide methods and requirements to ensure that the connections, attachments, extensions, or other site utility modifications meet NC State standards. B. NC State is responsible

More information

ISSUE DATE JANUARY 1st, 2008 SECTION 5G FIBERGLASS PACKAGE LIFT STATION

ISSUE DATE JANUARY 1st, 2008 SECTION 5G FIBERGLASS PACKAGE LIFT STATION ISSUE DATE JANUARY 1st, 2008 SECTION 5G FIBERGLASS PACKAGE LIFT STATION FIBERGLASS PACKAGE LS SITE PLAN PAGE No. 111 NUMBER: FG-LS-SITE-PLN FIBERGLASS PACKAGE LS PIPING PLAN PAGE No. 112 NUMBER: FG-LS-PIPE-PLN

More information

HAIGHTS CREEK IRRIGATION COMPANY

HAIGHTS CREEK IRRIGATION COMPANY HAIGHTS CREEK IRRIGATION COMPANY DEVELOPMENT STANDARDS AND SPECIFICATIONS Adopted by the Haights Creek Irrigation Company Board June 11, 2015 (rev. 4/12/17) Haight s Creek Irrigation Company Adopted June

More information

KU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT

KU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT PERMEABLE BITUMINOUS PAVEMENT PART 1: GENERAL 1.01. RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including Special Requirements General Conditions and Division 1 Specifications Sections,

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION SECTION 22 11 16.13 CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION PART 1: GENERAL 1.01 SUMMARY A. This Section includes water-distribution backflow prevention products and installation specifications.

More information

16. Design of Pipeline Structures.

16. Design of Pipeline Structures. 16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.

More information

ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer complete in place and the material therein,

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

A New Municipal Building for Limerick Township

A New Municipal Building for Limerick Township A New Municipal Building for Limerick Township DOCUMENT 00 9001 - ADDENDUM NUMBER 01 December 9, 2016 Re: A New Municipal Building for Limerick Township From: Kelly Clough Bucher & Associates, Inc. 8 East

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 2 DATE: December 28, 2011 RE: RFP NUMBER: RFP TITLE: ITS Equipment Replacement in Broward County OPENING OF TECHNICAL PROPOSAL DATE: January 5, 2012 Notice

More information

The Metropolitan Sewer District of Greater Cincinnati

The Metropolitan Sewer District of Greater Cincinnati The Metropolitan Sewer District of Greater Cincinnati Dry Run Area Sewers, Phase 1 and Phase 2 Contract A, Project ID 10270000_10270005 Date Issued: 03/25/2010 ADDENDUM NO. 2 This addendum will only be

More information

QUESTIONS & ANSWERS ITB HELEN MCCALL PARK IMPROVEMENTS

QUESTIONS & ANSWERS ITB HELEN MCCALL PARK IMPROVEMENTS QUESTIONS & ANSWERS ITB 017-030 HELEN MCCALL PARK IMPROVEMENTS QUESTION: Site Lighting. The prints show that the existing site lighting structures are to be relocated on site. Is this the only site lighting

More information

of GENERAL. A. Description

of GENERAL. A. Description 02920-1 of 11 SECTION 02920: EARTH TUNNELING 02920.01 GENERAL A. Description Earth tunneling shall include, but not necessarily be limited to, constructing earth tunnels and furnishing and installing tunnel

More information

SARASOTA COUNTY GOVERNMENT PROCUREMENT 1660 Ringling Blvd., 3 rd Floor Sarasota, Florida Telephone Fax

SARASOTA COUNTY GOVERNMENT PROCUREMENT 1660 Ringling Blvd., 3 rd Floor Sarasota, Florida Telephone Fax SARASOTA COUNTY GOVERNMENT PROCUREMENT 1660 Ringling Blvd., 3 rd Floor Sarasota, Florida 34236 Telephone 941-861-5266 Fax 941-861-5129 ADDENDUM NO.1 BID # : #153025CS CCSWDC Leachate Lift Station Rehabilitation

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

DIVISION VI INDIVIDUAL GRINDER PUMP INSTALLATIONS

DIVISION VI INDIVIDUAL GRINDER PUMP INSTALLATIONS DIVISION VI INDIVIDUAL GRINDER PUMP INSTALLATIONS VI-1.000 DESCRIPTION 1.010 General A. Any extension of the Kitsap County sanitary sewer extension shall be completed in accordance with the applicable

More information

Port KC RFP NORTHLAND PARK BUILDING V

Port KC RFP NORTHLAND PARK BUILDING V Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?

More information

SECTION SUMMARY OF WORK STATE PROJECT NO.: DCF

SECTION SUMMARY OF WORK STATE PROJECT NO.: DCF PART 1 GENERAL 1.1 SUMMARY STATE PROJECT NO.: DCF 18040400 The project overall scope of work is a complete upgrade to the NEFSH Lift Station, Building # 27. Scope of work requires new sewage pump installation,

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

INVITATION TO BIDDERS. Solicitation No. CO-00157

INVITATION TO BIDDERS. Solicitation No. CO-00157 INVITATION TO BIDDERS Solicitation No. CO-00157 Sealed bids are requested by the San Antonio Water System for the construction of approximately 5,900 LF of 6 to 8-inch of water main and approximately 3,000LF

More information

CITY OF FARGO SPECIFICATIONS REMOVALS

CITY OF FARGO SPECIFICATIONS REMOVALS REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation

More information

ADDENDUM NO. 3. Project: GREENE COUNTY FSMF DOT BID PACKAGE #1

ADDENDUM NO. 3. Project: GREENE COUNTY FSMF DOT BID PACKAGE #1 ADDENDUM NO. 3 Project: GREENE COUNTY FSMF DOT-170005 BID PACKAGE #1 Index of Contents Addendum No. 3... 3 Pages Pre-Bid Meeting Agenda... 4 Pages Pre-Bid Meeting EDGE Requirements... 2 Pages Pre-Bid Meeting

More information

CITY OF FARGO SPECIFICATIONS REMOVALS

CITY OF FARGO SPECIFICATIONS REMOVALS REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation

More information

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS)

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) 00950 - Measurement & Payment Page 00950-1 00950 - MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) (Last revised 5/20/10) SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Base Course & Paving Curb & Gutter,

More information

Request for Proposal # Cane Creek Park Fiber Optic Cable Upfit

Request for Proposal # Cane Creek Park Fiber Optic Cable Upfit Request for Proposal # 2018-049 Cane Creek Park Fiber Optic Cable Upfit ADDENDUM NO. 1 ISSUE DATE: February 2, 2018 Bidders on this project are hereby notified that this Addendum shall be attached to and

More information

Effective Date: Revision #: 1. Section I: Castings and Aluminum Covers. Valve Boxes. Service Clean-out Box and Lid

Effective Date: Revision #: 1. Section I: Castings and Aluminum Covers. Valve Boxes. Service Clean-out Box and Lid Section I: Castings and Aluminum Covers I 1 I 2 I 3 I 4 Valve Boxes Service Clean-out Box and Lid Manhole Casting/ Standard Ring and Cover Access Covers/ Aluminum 1 I 1 VALVE BOXES: Valve boxes shall meet

More information

CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION

CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION ADDENDUM #4 DATE: 02/08/2016 PROJECT: CONTRACT No: 40604 BID DATE, TIME: 02/11/2016, 2:00PM NOTICE TO ALL CONTRACTORS

More information

All definitions are defined according to ANSI/AWWA C

All definitions are defined according to ANSI/AWWA C SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR REDUCED-WALL, RESILIENT-SEATED GATE AND TAPPING VALVES FOR WATER SUPPLY SERVICE 4 IN. THROUGH 48 IN. ANSI/AWWA C515-01 July 2017 1. SCOPE This product specification

More information

City of Wentzville. Standard Specifications and Construction Details Amendment List

City of Wentzville. Standard Specifications and Construction Details Amendment List Amendment No. 1 Standard Specifications and Construction Details Amendment List Date: September 21, 2009 Subject: SCD 700.23 - Residential Entrance Layout and drawing revised to more clearly show the location

More information