SECTION BITUMINOUS CONCRETE PAVING AND ATHLETIC SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

Size: px
Start display at page:

Download "SECTION BITUMINOUS CONCRETE PAVING AND ATHLETIC SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION."

Transcription

1 SECTION PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting a bid for the work of this SECTION SCOPE OF WORK A. Provide all labor, materials, equipment, services and transportation required to complete bituminous concrete pedestrian paving and athletic surfacing work as shown on the Drawings and as specified herein or both RELATED WORK A. The following Related Work to be performed under the designated Sections: 1.04 REFERENCES 1. Pavement base courses: EARTHWORK - SECTION Lines and Grading: FINISH GRADING - SECTION Vehicular bituminous paving: SECTION FLEXIBLE PAVING 4. SITE CONCRETE SECTION MISCELLANEOUS SITE IMPROVEMENTS - SECTION FENCING - SECTION SOIL PREPARATION - SECTION PLANTING - SECTION LAWNS - SECTION A. Unless otherwise specified, bituminous concrete material and workmanship shall comply with the applicable provisions of the latest edition Standard Specifications For Highways and Bridges, Department of Public Works of the Commonwealth of Massachusetts for the items noted herein. This document shall be referred to as The Standard Specifications

2 1.05 SUBMITTALS A. Submit the following in accordance with the provisions of SECTION SUBMITTALS. B. Product Data: Manufacturer's current catalogue cuts and specifications and suppliers material certificates for the following: 1. Bituminous concrete items Pedestrian Paving: a. Binder course. b. Surface course. c. Tack coat. 2. Bituminous concrete items Basketball Courts: a. Binder course. b. Surface course. c. Tack coat. 3. Athletic surfacing items: a. Surface preparations 1) Plexipave Court Patch Binder. 2) Acrylic Resurfacer (1) coat. 3) Fortified Plexipave (3) coats. 4) Plexicolor line paint (2) coats 5) Color chips for each color. C. Shop Drawings: Minimum 3/8 scale plan drawing of the area of Athletic Surface installation showing the location, dimensions and relationships of the Athletic Surfacing QUALIFICATIONS/SPECIAL REQUIREMENTS A. The athletic surfacing materials shall be one manufacturer's materials only. B. The Contractor shall have at least 3 years experience installing athletic surfacing materials. C. The manufacturer's representative shall be engaged by the Contractor at his expense to inspect and monitor the applications of the following athletic surfacing items: 1. Court patch binder. 2. Acrylic resurfacer. 3. Fortified plexipave

3 1.07 JOB CONDITIONS A. Weather limitations 1.08 GUARANTEE 1. Athletic surfacing systems weather limitations are as specified by the manufacturer. A. Paving, Color Surfacing and Painted Lines 1.09 DEFINITIONS 1. All paving, color surfacing and painted lines shall be guaranteed for a period of one year from final acceptance, against cracking, peeling, checking or other defect. The Contractor will repair, recoat or otherwise make satisfactory, any failed paving, color surfacing or painted lines at no cost to the Owner, except for the cracks noted below. A. References to Landscape Architect shall mean Architect or the Architects designated representative

4 PART 2 MATERIALS 2.01 DENSE GRADED CRUSHED STONE A. Refer to SECTION EARTHWORK BITUMINOUS CONCRETE MATERIALS A. Bituminous Concrete Pedestrian Pavement and Basketball Court Pavement shall be laid in two courses of depths after rolling, as shown on the Drawings. 1. Bituminous Concrete Paving Pedestrian: a. Binder Course shall conform to Section M3 of the Standard Specifications. b. Top Course shall conform to the requirements for Dense Mix as specified in Section M3 of the Standard Specifications. c. Tack coat shall be AC-5, AC-10 or AC-20 paving asphalt cement, applied at a rate of 1/20 gallon per square yard or as otherwise indicated. 2. Bituminous Concrete Paving Basketball Courts: a. Binder Course: Percent By Weight Passing Square Opening Sieve Percentage Passing / / # # # # A.C. (% of mix)

5 b. Top Course: Percent By Weight Passing Square Opening Sieve Percentage Passing 1/ / # # # # A.C. (% of mix) ATHLETIC SURFACING ITEMS shall be the PLEXIPAVE SYSTEM as manufactured by California Products Corporation, Cambridge, Massachusetts or The NESCO LATEX-ITE SYSTEM distributed by New England Sealcoating Co., Inc. Hingham, or Equal. The Plexipave Athletic Surfacing Items for application over a bituminous concrete surface are listed below: A. Plexipave Court Patch Binder shall be used to correct any minor surface deficiencies in the Bituminous Concrete Surface. B. Plexipatch. C. Acrylic Resurfacer. D. Fortified Plexipave a. Plexipave Color Base. b. Plexichrome. E. Plexicolor Line Paint (2) coats per each line: White

6 PART 3 EXECUTION 3.01 INSTALLATION OF BITUMINOUS CONCRETE PAVING FOR PEDESTRIAN PAVING AND BASKETBALL COURTS: A. Installation procedures for bituminous concrete pavements shall comply with Standard Specifications, Section 420. B. Installation of bituminous concrete paving shall be as shown on the Drawings and specified herein. C. Align bituminous concrete walks and patches as shown on the Drawings. 1. Obtain landscape architect's approval layout of all walks before work is done. Make adjustments as required in the layout to ensure smooth continuous curves and straight lines and transitions. D. Subgrade preparation and installation of Gravel Base Course shall be found in SECTION EARTHWORK, of these specifications. E. Make any corrections necessary to subbase course (minor cuts and fills) furnished and installed under SECTION EARTHWORK, to bring to the sections and elevations shown on the Drawings. F. Remove loose material from compacted gravel base surface immediately before installing bituminous concrete. Proof roll prepared gravel base surface to check for unstable areas requiring additional compaction. Do not begin paving work until deficient gravel base areas have been properly compacted as specified. G. Construct Bituminous Concrete Paving in accordance with the Standard Specifications Sections 420 and 460. H. No bituminous material shall be applied when the temperature is below 32 F. I. No vehicular traffic of any kind shall be allowed to pass over the newly finished surface until it has had time to set. Twenty-four hours will be considered sufficient time for the pavement to set in most cases, but this period may be extended by the Engineer as required by weather or other reasons. J. The Contractor shall ensure that positive drainage occurs on all walks, patches and court surfaces. All areas of finished paving on which water stands or which are found excessively uneven shall be promptly brought to the correct grade and line. There shall be no deviation from true surface planes represented by the grade elevations shown on the Drawings

7 K. Pavement Edges: The Contractor shall construct a neat tamped edge as shown on the Drawings at all proposed pavement edges not abutting vertical faces of adjacent structures or pavements. New paving shall be well blended into adjoining existing paving and thoroughly rolled to present continuous uniform surface without perceptible arises or depressions at the jointure. L. The bituminous pavement shall cure for fourteen days prior to applying the Color Surfacing or Line Paint. M. Do any repair or patching to pavements outside the project site damaged by the work of the Contract. N. All cuts in existing pavement shall be "saw cut" TACK COAT A. Apply to contact surfaces of existing or previously constructed asphalt or portland cement concrete and surfaces abutting or projecting into bituminous concrete pavement. Distribute at a rate of 0.30 to 0.35 gallons per square yard of surface or greater to provide complete coverage. 1. Apply tack coat to vertical surface of all saw cut existing bituminous concrete. B. Allow to dry or until at proper condition to receive paving APPLICATION OF ATHLETIC SURFACING AND LINES A. Athletic surfacing and lines shall be applied in strict conformance with the manufacturer's specifications and requirements and as specified herein. B. Bituminous Paving Surface Preparation: Preparation for areas requiring athletic surfacing shall be cleaned before installation of each of these items as follows: 1. All dirt, sand, dust and other loose debris materials and grease, oils and other foreign materials shall be cleaned from the paved areas to be covered by sweeping with brooms and pressure washing with water and or other methods as applicable. 2. Prior to the application of surfacing materials, the entire surface shall be checked and all minor depressions or irregularities located. 3. The surface shall then be flooded and any depressions covering a nickel shall be located and corrected as follows: a. The Court Patch Binder shall be applied over all these depressions according to the manufacturer's instructions

8 b. The finished patching surface shall not vary more than 1/8 inch in 10 feet measured in any direction and shall blend smoothly with adjacent unpatched areas. C. Surface Course Preparation: Apply (1) application of Acrylic Resurfacer per manufacturerʼs specifications. D. Fortified Plexipave: Apply (3) coats as per manufacturerʼs specifications. E. Plexicolor Line Paint: Apply (2) coats as per manufacturerʼs specifications. END OF SECTION

Stanford University Facilities Design Guidelines SECTION STONE FINES PAVING. American Society for Testing and Materials.

Stanford University Facilities Design Guidelines SECTION STONE FINES PAVING. American Society for Testing and Materials. SECTION 32 15 40 STONE FINES PAVING PART 1 GENERAL 1.1 RELATED WORK Section 32 11 00: Base Courses 1.2 QUALITY ASSURANCE A. Applicable Standards: Any reference shall mean the current or latest editions

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING SECTION 02500 ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS a) Drawings and general provisions of the Contract, including the General and Supplementary General Conditions and Division 00 & 01 specification

More information

Stanford University Facilities Design Guidelines SECTION ASPHALT UNIT PAVING. A. ASTM C-33 Standard Specification for Concrete Aggregates.

Stanford University Facilities Design Guidelines SECTION ASPHALT UNIT PAVING. A. ASTM C-33 Standard Specification for Concrete Aggregates. SECTION 32 14 23 ASPHALT UNIT PAVING PART 1 GENERAL 1.1 DESCRIPTION Work Included: All labor, materials, appliances, tools, equipment, facilities, transportation, and services for and incidental to performing

More information

SECTION BITUMINOUS CONCRETE PAVEMENT

SECTION BITUMINOUS CONCRETE PAVEMENT SECTION 321216 BITUMINOUS CONCRETE PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Chapter 5: Designs for Recreational Uses 5-1 Asphalt Pavements for Non-Vehicular Use 5-1 Table 5-1: Thickness Design Chart: Bikeways, Paths, Trails

Chapter 5: Designs for Recreational Uses 5-1 Asphalt Pavements for Non-Vehicular Use 5-1 Table 5-1: Thickness Design Chart: Bikeways, Paths, Trails 5-1 Asphalt Pavements for Non-Vehicular Use 5-1 Table 5-1: Thickness Design Chart: Bikeways, Paths, Trails and Walkways 5-3 Table 5-2: Thickness Design Chart: Playgrounds 5-4 Tennis Courts 5-5 Table 5-3:

More information

ASPHALTIC CONCRETE PAVING SECTION

ASPHALTIC CONCRETE PAVING SECTION SECTION 31 50 00 PART 1: GENERAL 1-01 SECTION INCLUDES: A. Asphaltic concrete paving. B. Seal Coat. 1-02 RELATED SECTIONS: A. Division 31 Earthwork B. Section 31 60 00 Aggregate Base Course. C. Section

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING PART 1 - GENERAL 1.1 DESCRIPTION SECTION 32 12 16 ASPHALT PAVING SPEC WRITER NOTE: Delete or add information between // ---- // and any other items applicable to project. Any item added to the text shall

More information

SECTION ASPHALT PAVING AND SURFACING

SECTION ASPHALT PAVING AND SURFACING SECTION 02500 ASPHALT PAVING AND SURFACING PART 1 - GENERAL 1.01 WORK INCLUDED A. Traffic control as required to divert vehicular and pedestrian traffic around construction. B. Spreading and compacting

More information

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL This section covers the restoration of roadways and sidewalks, in whole or in part, with bituminous concrete paving. WITHIN 4 DAYS OF BACKFILLING IN AREAS

More information

Stabilizer Solutions, Inc. All Rights Reserved. Page 1 of 5

Stabilizer Solutions, Inc. All Rights Reserved. Page 1 of 5 SECTION 32 11 00 STABILIZER FOR STABILIZED AGGREGATE PAVEMENT: FIRELANES, DRIVEWAYS AND PARKING LOTS Stabilizer Solutions, Inc. 33 South 28 th Street Phoenix, AZ 85034 USA toll free 800.336.2468 p 602.225.5900

More information

Chapter 6 Designs for Recreational Uses

Chapter 6 Designs for Recreational Uses Designs for Recreational Use 6-1 Chapter 6 Designs for Recreational Uses ASPHALT PAVEMENTS FOR NON- VEHICULAR USE In addition to highways, streets, and parking lots that carry autos and trucks, many other

More information

KU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT

KU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT PERMEABLE BITUMINOUS PAVEMENT PART 1: GENERAL 1.01. RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including Special Requirements General Conditions and Division 1 Specifications Sections,

More information

HARD COURT/RUNNING TRACK CONSTRUCTION. A. Section Includes: Tennis courts, basketball/volleyball courts, and running tracks.

HARD COURT/RUNNING TRACK CONSTRUCTION. A. Section Includes: Tennis courts, basketball/volleyball courts, and running tracks. PART 1 GENERAL 1.01 SUMMARY SECTION 02545 HARD COURT/RUNNING TRACK CONSTRUCTION A. Section Includes: Tennis courts, basketball/volleyball courts, and running tracks. B. Related Sections: 1. 02200 - Earthwork.

More information

1. Concrete pavers, with ungrouted joints, over sand base. a. Large precast sections in random mix with smaller concrete pavers

1. Concrete pavers, with ungrouted joints, over sand base. a. Large precast sections in random mix with smaller concrete pavers SECTION 32 14 00 - PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specifications Sections, apply

More information

SECTION SITE CONCRETE

SECTION SITE CONCRETE SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of

More information

A. Testing Laboratory Services: Section B. Excavation, Site Fill and Rough Grading: Section Sub-Base Course Material (If requested).

A. Testing Laboratory Services: Section B. Excavation, Site Fill and Rough Grading: Section Sub-Base Course Material (If requested). SECTION 02500 - PART 1 - GENERAL 1.01 RELATED WORK SPECIFIED ELSEWHERE A. Testing Laboratory Services: Section 01411. B. Excavation, Site Fill and Rough Grading: Section 02200. C. Concrete: Section 03310.

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

SECTION CONCRETE PAVING

SECTION CONCRETE PAVING PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials

More information

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL 13686.00 CONCRETE WALKS AND CURBS 033015-1 1.1 RELATED DOCUMENTS: SECTION 033015 CONCRETE WALKS AND CURBS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 321610 - CURBING PART 1 - GENERAL 1.1 DESCRIPTION A. This Section specifies requirements for furnishing and installing all types of curbing including the following: granite curb, concrete and bituminous

More information

ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING

ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING AFTER NOVEMBER 1, 2008 ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous

More information

Addendum No. 3 page 1

Addendum No. 3 page 1 Addendum No. 3 page 1 Project: 2018 Physical Education Facilities North Harrison Middle School Ramsey, Indiana Proj. No: 1518.03 Date: December 12, 2017 This addendum is a part of the bid documents. Acknowledge

More information

1.01 Work Included This work includes furnishing and installing a synthetic all-weather running track surface.

1.01 Work Included This work includes furnishing and installing a synthetic all-weather running track surface. PRODUCT SPECIFICATIONS FOR (13MM) LATEX MAT SYSTEM PART 1 Scope of work 1.01 Work Included This work includes furnishing and installing a synthetic all-weather running track surface. 1.02 Description of

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 00252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous

More information

CITY OF FARGO SPECIFICATIONS ASPHALT LEVELING COURSE

CITY OF FARGO SPECIFICATIONS ASPHALT LEVELING COURSE ASPHALT LEVELING COURSE PART 1 DESCRIPTION OF WORK The work to be done under these Specifications and the accompanying plans consist of furnishing all labor, material, accessories, and plant necessary

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING SECTION 321216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Hot-mix asphalt paving. 1.2 PRE-INSTALLATION MEETINGS A. Pre-installation Conference: Conduct conference at Project site.

More information

SECTION PLAYGROUND SAFETY SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION PLAYGROUND SAFETY SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 321810 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION ASPHALT CONCRETE

SECTION ASPHALT CONCRETE SECTION 02740 ASPHALT CONCRETE PART 1. GENERAL 1.01 SECTION INCLUDES A. Work includes but is not limited to the following: 1.02 RELATED SECTIONS 1. Provide all material, labor, and equipment to prepare

More information

BITUMEN-SET PRECAST CONCRETE PAVING SLABS

BITUMEN-SET PRECAST CONCRETE PAVING SLABS SECTION 32 14 13.16 BITUMEN-SET PRECAST CONCRETE PAVING SLABS (1995 MasterFormat Section 02784) NOTE: This guide specification is the U.S. for concrete paving slabs adhered with a neoprene mastic to a

More information

CONCRETE TILE PAVERS

CONCRETE TILE PAVERS Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the

More information

KU Medical Center 2018 PAVEMENT RESTORATION PROJECT Project No May 4, 2018

KU Medical Center 2018 PAVEMENT RESTORATION PROJECT Project No May 4, 2018 SECTION 321216 - ASPHALT PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Requirements of the Contract apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Cold milling of existing

More information

Specification for Asphalt Paving for the Los Angeles Department of Water & Power DS Street Improvement

Specification for Asphalt Paving for the Los Angeles Department of Water & Power DS Street Improvement Specification for Asphalt Paving for the Los Angeles Department of Water & Power DS-144 - Street Improvement PART 1 - GENERAL 1.01 DESCRIPTION A. This Section includes specifications for providing asphaltic

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 12 16 ASPHALT CONCRETE PAVING PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for placing a hot laid plant mix asphalt surface course upon either an asphalt stabilized

More information

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section 02670-1 of 6 SECTION 02670 CURB, COMBINATION CURB AND GUTTER, AND 02670.01 GENERAL A. Description This work shall include, but not necessarily be limited to, the construction of concrete curb, concrete

More information

BID NO VOLUME II. Date Due: May 7, 2018 at 10:30am

BID NO VOLUME II. Date Due: May 7, 2018 at 10:30am BID NO. 1804 Hardscape Repair At Multiple Sites Summer 2018 VOLUME II Date Due: May 7, 2018 at 10:30am BID NO. 1804 Hardscape Repair At Multiple Sites Summer 2018 - Page 1 TABLE OF CONTENTS - VOL-2 VOLUME

More information

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS STANDARD SPECIFICATIONS SECTION 02950 PAVEMENT REQUIREMENTS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for removing, replacing and providing new paving for roads, driveways, parking

More information

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements... SECTION 02530 CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Inspection And Tests... 1 1.04 Quality Assurance...

More information

Allen & Sherriff Architects, Inc Yonge Street, S202, Richmond Hill, Ontario L4C 5K9 Tel: Fax: File Ref.

Allen & Sherriff Architects, Inc Yonge Street, S202, Richmond Hill, Ontario L4C 5K9 Tel: Fax: File Ref. Allen & Sherriff Architects, Inc. 10350 Yonge Street, S202, Richmond Hill, Ontario L4C 5K9 Tel: 905-884-1117 Fax: 905-884-4970 File Ref. 4166 Tender No.: T18-21 St. Theresa C.S. Child Care Expansion Durham

More information

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating

More information

SECTION 503 TEMPORARY PAVEMENT RESTORATION

SECTION 503 TEMPORARY PAVEMENT RESTORATION SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

City of Toronto-St. Clair Reservoir Waterproofing and Building Envelope Rehabilitation 15ECS-MI-01WA / TCN Page 1 of 10

City of Toronto-St. Clair Reservoir Waterproofing and Building Envelope Rehabilitation 15ECS-MI-01WA / TCN Page 1 of 10 15ECS-MI-01WA / TCN 324-2015 Page 1 of 10 1 General 1.1 DESCRIPTION.1 This section specifies the requirements for tennis court construction including the supply and installation of additional compacted

More information

SECTION UNIT PAVERS

SECTION UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Concrete pavers. 2. Detectable warning pavers. 3. Warning stripe pavers. 1.2 SUBMITTALS A. Product Data: For the following: 1. Pavers.

More information

SECTION BITUMINOUS CONCRETE PAVING

SECTION BITUMINOUS CONCRETE PAVING PART 1 GENERAL 1.1 SECTION INCLUDES: SECTION 02400 BITUMINOUS CONCRETE PAVING A. The intent of this specification section is to provide requirements for materials, equipment, and methods for constructing

More information

SECTION ASPHALTIC CONCRETE PAVING

SECTION ASPHALTIC CONCRETE PAVING SECTION 02742 ASPHALTIC CONCRETE PAVING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Prepare pavement sub-grade as described in Contract Documents to receive pavement base and paving. 2.

More information

SECTION PAVING SLABS ON AN AGGREGATE BASE

SECTION PAVING SLABS ON AN AGGREGATE BASE SECTION 32 14 13.16 PAVING SLABS ON AN AGGREGATE BASE (1995 MasterFormat Section 02784) NOTE: This guide specification for the U.S. is for paving slabs on a sand bed over a compacted aggregate base for

More information

SECTION PAVING SLABS ON AN AGGREGATE BASE

SECTION PAVING SLABS ON AN AGGREGATE BASE SECTION 32 14 13.16 PAVING SLABS ON AN AGGREGATE BASE (1995 MasterFormat Section 02784) NOTE: This guide specification for the U.S. is for paving slabs on a sand bed over a compacted aggregate base for

More information

CUT, RE SECTION VI. (Sub-section 290) Cut, Removal, and Replacement of Paved Surfaces. 1. Description Bituminous Pavements thru 290-2

CUT, RE SECTION VI. (Sub-section 290) Cut, Removal, and Replacement of Paved Surfaces. 1. Description Bituminous Pavements thru 290-2 CUT, RE SECTION VI (Sub-section 290) Cut, Removal, and Replacement of Paved Surfaces Article Page 1. Description 290-1 2. Bituminous Pavements 290-1 thru 290-2 3. Concrete Pavements 290-3 thru 290-4 4.

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 WORK INVOLVED A. Provide all labor, materials and equipment as required for all excavation, grading, providing borrow materials, hauling, placing and compacting

More information

SECTION PAINTED PAVEMENT MARKINGS. A. Section Includes: Painted traffic striping and symbols on pavements and curbs.

SECTION PAINTED PAVEMENT MARKINGS. A. Section Includes: Painted traffic striping and symbols on pavements and curbs. SECTION 02763 PAINTED PAVEMENT MARKINGS PART 1 - GENERA 1.1 SUMMARY A. Section Includes: Painted traffic striping and symbols on pavements and curbs. B. Related Documents: The Conditions of the Contract

More information

CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING

CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING Guide Specification CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING COORDINATE WITH DRAWINGS: Show location and extent of stabilized aggregate surfacing. Show details required at adjoining

More information

*************************************************************************************************************************

************************************************************************************************************************* SECTION 02545 HARD COURT & RUNNING TRACK CONSTRUCTION ************************************************************************************************************************* SPECIFIER: CSI MasterFormat

More information

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required

More information

A. Florida Department of Transportation (DOT) "Standard Specifications for Road and Bridge Construction" 1991 Edition.

A. Florida Department of Transportation (DOT) Standard Specifications for Road and Bridge Construction 1991 Edition. SECTION 02510 - BITUMINOUS PAVING PART 1 - GENERAL 1.1 REFERENCE A. Florida Department of Transportation (DOT) "Standard Specifications for Road and Bridge Construction" 1991 Edition. 1.2 STANDARD OF WORK

More information

SECTION PORTLAND CEMENT CONCRETE

SECTION PORTLAND CEMENT CONCRETE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this

More information

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES AGGREGATE BASES PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, accessories, and equipment necessary

More information

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER BID # 14-47 REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER Board of Trustees Middlesex County College 2600 Woodbridge Avenue P.O. Box 3050 Edison, New Jersey

More information

SECTION RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL PART 2 - MATERIALS AND METHODS

SECTION RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL PART 2 - MATERIALS AND METHODS SECTION 01200 RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL 1.01 SCOPE This specification covers the work within the street right-of-way (property line) for the repair of that area which is disturbed during

More information

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating

More information

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

SECTION CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS

SECTION CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS SECTION 32 05 23 PART 1 - GENERAL 1.1 DESCRIPTION A. This section shall cover site work concrete constructed upon the prepared subgrade and in conformance with the lines, grades, thickness, and cross sections

More information

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint

More information

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or

More information

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007 Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION March 22, 2007 Description: This work consists of furnishing and applying asphalt rubber binder followed by an application of treated cover aggregate

More information

SECTION CONTROLLED LOW STRENGTH MATERIAL

SECTION CONTROLLED LOW STRENGTH MATERIAL SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PORTLAND CEMENT. Section PORTLAND CEMENT STABILIZED SUBGRADE

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PORTLAND CEMENT. Section PORTLAND CEMENT STABILIZED SUBGRADE PART 1 GENERAL 1.01 SUMMARY Section 02338 PORTLAND CEMENT This Section includes foundation course of Portland cement stabilized natural subgrade material. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1.

More information

SECTION RESILIENT TRACK SURFACING

SECTION RESILIENT TRACK SURFACING SECTION 32 2000 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

SECTION QUARRY TILE

SECTION QUARRY TILE SECTION 09 30 16 QUARRY TILE PART 1 GENERAL 1.1 SECTION REQUIREMENTS A. Provide all labor, materials and equipment required for the installation of quarry tile flooring as shown on drawings and schedules

More information

INDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

INDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6 03005_Jan31_2018.pdf Page 1 of 6 INDEX Page 03005-1 DESCRIPTION 2 03005-2 MATERIALS 2 03005-3 APPROVAL FOR BASE COURSE 3 03005-4 CONSTRUCTION 3 03005-5 MEASUREMENT 6 03005-6 PAYMENT 6 03005_Jan31_2018.pdf

More information

A. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the Drawings and specified herein.

A. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the Drawings and specified herein. PAGE 321216-1 SECTION 321216 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

A. Division 01 Specification Sections, Drawings, General Conditions, Supplementary General Conditions, and Special Conditions apply to this section.

A. Division 01 Specification Sections, Drawings, General Conditions, Supplementary General Conditions, and Special Conditions apply to this section. Note: This guide specification for U.S. applications is for concrete grid units placed on a sand bedding course over a compacted dense-graded aggregate base. The text allows an option of topsoil and grass

More information

SECTION CONCRETE GRID PAVEMENTS (1995 MasterFormat Section 02795)

SECTION CONCRETE GRID PAVEMENTS (1995 MasterFormat Section 02795) SECTION 32 14 13.19 CONCRETE GRID PAVEMENTS (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications is for concrete grid units placed on a sand bedding course over a compacted

More information

SECTION PAVING AND SURFACING

SECTION PAVING AND SURFACING SECTION 02500 - PAVING AND SURFACING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SECTION ASPHALT PAVEMENT

SECTION ASPHALT PAVEMENT SECTION 02510 ASPHALT PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of contract, including General Conditions and Division 1 Specification Sections, apply to this Section.

More information

BSS 300 Embedded Synthetic Track Surfacing System System Specifications

BSS 300 Embedded Synthetic Track Surfacing System System Specifications BSS 300 Embedded Synthetic Track Surfacing System System Specifications G.3 - Bidder: FieldTurf USA, Inc. Part 1 General 1.1 Scope The synthetic surfacing contractor shall furnish all labor, materials,

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING SECTION 32 1216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Prepare pavement sub-grade as described in Contract Documents to receive pavement base and paving. 2. Furnish

More information

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines. SECTION 15.0 PIPE TRENCHES 15.01 Clearing and Grubbing The developer/contractor shall be responsible for the clearing and grubbing of the entire right-of-way. See Sections 13.01 and 14.01. Clearing and

More information

CITY OF SAN ANGELO ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

CITY OF SAN ANGELO ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) ITEM 275 CITY OF SAN ANGELO ITEM 275 275.1 DESCRIPTION. This Item shall govern for treating subgrade, new and/or existing base (with or without asphaltic concrete pavement (ACP)), or combinations as shown

More information

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

SKATE ON LAYKOLD Specification

SKATE ON LAYKOLD Specification Acrylic Sport & Recreational Surfaces SKATE ON LAYKOLD Specification PART 1 GENERAL 1.1 DESCRIPTION Scope: This guide specification covers the construction and installation for the SKATE ON LAYKOLD inline

More information

SECTION PAVING SLABS ON AN AGGREGATE BASE

SECTION PAVING SLABS ON AN AGGREGATE BASE Phone 905-655-3311 1-800-655-3430 Email brooklinsales@brooklin.com CAN-slabs on agg base.doc Phone 905-655-3311 1-800-655-3430 Email brooklinsales@brooklin.com SECTION 32 14 13.16 PAVING SLABS ON AN AGGREGATE

More information

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans. SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.

More information

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on

More information

STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS

STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS 16.01 GENERAL Specifications in this section shall apply to the construction of storm sewer systems including excavation, trenching, backfilling,

More information

CITY OF FARGO SPECIFICATIONS SEAL COATS

CITY OF FARGO SPECIFICATIONS SEAL COATS SEAL COATS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of furnishing all labor, material, accessories, and plant necessary

More information

BSS 300 Embedded Synthetic Track Surfacing System Specifications

BSS 300 Embedded Synthetic Track Surfacing System Specifications BSS 300 Embedded Synthetic Track Surfacing System Specifications Part 1 General 1.1 Scope The synthetic surfacing contractor shall furnish all labor, materials, equipment, supervision and services necessary

More information

SECTION CONCRETE GRID PAVEMENTS (Turfstone) (1995 MasterFormat Section 02795)

SECTION CONCRETE GRID PAVEMENTS (Turfstone) (1995 MasterFormat Section 02795) SECTION 32 14 13.19 CONCRETE GRID PAVEMENTS (Turfstone) (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications is for concrete grid units placed on a sand bedding course

More information

Draft Special Provision for. Asphalt Treated Permeable Base

Draft Special Provision for. Asphalt Treated Permeable Base Draft Special Provision for 1 0 1 0 1 Add the following new section: -0 ASPHALT TREATED PERMEABLE BASE (ATPB) (******) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course

More information

LITHOCRETE ARCHITECTURAL CONCRETE PAVING

LITHOCRETE ARCHITECTURAL CONCRETE PAVING LITHOCRETE ARCHITECTURAL CONCRETE PAVING PART 1 GENERAL 1.1 GENERAL CONDITIONS A. Requirements of "General Conditions of the Contract" and of Division 1, "General Requirements," apply to work in this Section

More information

PRODUCT SPECIFICATIONS FOR CONIPUR ISP AN IMPERMEABLE POLYURETHANE BASE MAT STRUCTURAL SPRAY SYSTEM

PRODUCT SPECIFICATIONS FOR CONIPUR ISP AN IMPERMEABLE POLYURETHANE BASE MAT STRUCTURAL SPRAY SYSTEM PRODUCT SPECIFICATIONS FOR CONIPUR ISP AN IMPERMEABLE POLYURETHANE BASE MAT STRUCTURAL SPRAY SYSTEM PART 1 General 1.01 Work Included This work includes furnishing and installing an IAAF certified synthetic

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information