1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. Section Mechanical Materials and Methods. 2. Section Motors. 3. Section HVAC Insulation. 4. Section Hydronic Piping. 5. Section Duct Insulation for external insulation of air terminals. 6. Section15900 HVAC Instrumentation and Controls" for control devices installed on air terminals. 7. Section Sequence of Operations. 8. Section Testing, Adjusting and Balancing. 1.2 SUMMARY A. This Section includes the following: 1. UCP control variable-air-volume, hot water reheat terminal boxes 2. UCP control variable-air-volume terminal boxes 1.3 REFERENCES A. ARI 410 (Air-Conditioning and Refrigeration Institute) - Forced-Circulation Air-Cooling and Air-Heating Coils. B. SMACNA (Sheet Metal Air Conditioning Contractors National Association) - HVAC Duct Construction Standards, Metal and Flexible. 1.4 SUBMITTALS A. Product Data: Include rated capacities; shipping, installed, and operating weights; furnished specialties; and accessories for each model indicated. Include a schedule showing drawing designation, room location, number furnished, model number, size, and accessories furnished. B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loadings, required clearances, method of field assembly, components, and location and size of each field connection. 1. Wiring Diagrams: Detail wiring for power, signal, and control systems and differentiate between manufacturer-installed and field-installed wiring. C. Coordination Drawings: Reflected ceiling plans drawn to scale and coordinating air outlets with other items installed in ceilings. D. Maintenance Data: List of parts for each type of air terminal and troubleshooting maintenance guide to include in the maintenance manuals. Page 1 of 5
2 1.5 CLOSEOUT SUBMITTALS A. Project Record Documents: Record actual locations of components and locations of access doors in radiation cabinets required for access to valves. B. Operation and Maintenance Data: Submit manufacturer s descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listings. 1.6 QUALITY CONTROL A. Product Options: Drawings and schedules indicate requirements of air terminals and are based on specific systems indicated. Other manufacturers' systems with equal performance characteristics may be considered. Refer to Section "Substitutions." B. All air terminal boxes shall be rated in accordance with ARI Standard 880 and shall comply with the ARI Certified Ratings Program. C. All air terminal boxes shall bear the ARI Seal. D. All air terminal equipment insulation materials shall meet the requirements of NFPA 90A. E. Listing and Labeling: Provide electrically operated air terminals specified in this Section that are listed and labeled. 1. The Terms "Listed" and "Labeled": As defined in NFPA 70, Article Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing Laboratory" as defined in OSHA Regulation F. NFPA Compliance: Install air terminals according to NFPA 90A, "Standard for the Installation of Air Conditioning and Ventilating Systems." G. Comply with NFPA 70 for electrical components and installation. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering air terminals that may be incorporated into the Work include, but are not limited to, the following: B. Manufacturers: Subject to compliance with requirements, provide air terminals by one of the following: 1. York International. 2. Titus. 3. Kruegar 2.2 AIR TERMINAL BOXES - GENERAL A. All air terminal boxes shall be selected to provide pressure drops less than or equal to those listed on the drawings when operating at the scheduled air flow rates. Page 2 of 5
3 B. All air terminal boxes shall be selected to generate less noise than the values listed on the drawings when operating at air flow rates scheduled on the drawings and a total pressure drop of 1.5 inches w.g. (not including reheat coil). C. All reheat coils shall be selected to transfer at least the amount of heat scheduled when operated at the air and water flow rates listed with the entering air and water temperatures listed. D. The terminal boxes shall be suitable for maintaining minimum flow with inlet static pressure of up to 3 inches w.g. E. Provide engineering data prepared by the Terminal Box Manufacturer including minimum and maximum air flow rates, pressure drop, heat transfer and noise generation for each unit. All engineering data shall be ARI certified. F. All terminal boxes shall be provided for rooms with Direct Digital Control operators shall be provided with velocity sensing tubes for the primary air flows and with dampers. The BDDC Manufacturer is required to make arrangements with the Terminal Box Manufacturer for installation of controls and operators. Refer to Section "HVAC Instrumentation and Controls" for further requirements. H. The terminal boxes where scheduled shall be provided without insulation lining and shall be externally insulated or shall be provided with lining which is factory covered with a tedlar vinyl material to prevent erosion. I. The box casing shall be fabricated of 22-gauge minimum zinc coated sheet steel. The casing of the box shall be lined with 1-inch glass fiber conforming to NFPA-90A except as otherwise noted. The terminal box shall be provided with round primary air inlet connection and rectangular discharge suitable for flange type connection. J. The primary air control valve shall be internally mounted and shall consist of a single piece, flat oval damper valve providing shutoff to full open travel not exceeding 60 degrees. The damper valve shall be constructed of minimum 22-gauge zinc-coated steel. The damper valve shall be capable of sealing the primary inlet to limit leakage to 2% at 3 inches w.g. inlet static pressure. The damper shaft shall be continuous across the centerline of the damper valve (two piece, or end pivot shafts are not acceptable). The damper shaft shall pivot on lubrication free nylon bushings. The damper shaft shall extend outside the box casing and shall be driven by the actuator. K. Pitot tube type airflow sensing tubes of the automatic averaging type shall be provided in each box inlet. The same sensing tube shall also be used as balancing taps for field adjustment of the maximum and minimum primary air volumes. The balancing taps shall be used in conjunction with a flow chart on each box to permit readjustment of maximum and minimum primary air volumes if job conditions dictate. D. Discharge sound levels shall not exceed the NC value scheduled. Radiated sound levels shall not exceed the NC values scheduled. E. Where shown on the drawings, provide "Octopus" plenums with round outlets and individual balancing dampers where multiple outlets are employed. Page 3 of 5
4 2.4 UCP CONTROL VARIABLE-AIR-VOLUME, HOT WATER REHEAT TERMINAL BOXES A. Provide UCP controlled Variable-Air-Volume (VAV) terminal boxes with reheat for the room usage. B. Hot Water Reheat Coils shall be constructed of aluminum fins on 1/2-inch copper tubing mounted on the box. Refer to "Air Coils" Section, for further coil requirements. Refer to the reheat terminal schedule for capacity and performance requirements. C. VAV reheat boxes with UCP controls shall have controls provided by the BDDC Manufacturer. The BDDC Manufacturer shall coordinate field mounting the controls with the Terminal Box Manufacturer. The Terminal Box Manufacturer shall provide factory mounted brackets for field mounting the controls on the VAV Reheat boxes at the job site. Coordinate VAV reheat box controls with Section "HVAC Instrumentation and Controls. 2.7 UCP CONTROL VARIABLE-AIR-VOLUME TERMINAL BOXES A. Provide UCP controlled Variable-Air-Volume (VAV) terminal boxes for the rooms specified in the "Air Terminal Boxes - General" article in this Section. B. VAV boxes with UCP controls shall have controls provided by the BDDC Manufacturer. The BDDC Manufacturer shall coordinate field mounting the controls with the Terminal Box Manufacturer. The Terminal Box Manufacturer shall provide factory mounted brackets for field mounting the controls on the VAV boxes at the job site. Coordinate VAV box controls with Section "HVAC Instrumentation and Controls". 2.8 SOURCE QUALITY CONTROL A. Testing Requirements: Test and rate air terminals according to ARI 880, "Industry Standard for Air Terminals." B. Identification: Label each air terminal with plan number, nominal airflow, maximum and minimum factory-set airflows, coil type, and ARI certification seal. PART 3 - EXECUTION 3.1 INSTALLATION A. Install air terminals level and plumb, according to manufacturer's written instructions, rough-in drawings, original design, and referenced standards; and maintain sufficient clearance for normal service and maintenance. B. Connect ductwork to air terminals according to Division 15 ductwork Sections. 3.2 CONNECTIONS A. Install piping adjacent to air terminals to allow service and maintenance. Page 4 of 5
5 B. Hot-Water Piping: In addition to requirements in Section 15181, Hydronic Piping, connect heating coils to supply with shutoff valve, strainer, control valve, and union or flange; and to return with balancing valve and union or flange. C. Electrical: Comply with applicable requirements in Division 16 Sections. D. Ground equipment. 1. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. Where manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. 3.3 FIELD QUALITY CONTROL A. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. 3.4 CLEANING A. After completing system installation, including outlet fittings and devices, inspect exposed finish. Remove burrs, dirt, and construction debris, and repair damaged finishes. 3.5 COMMISSIONING A. Verify that installation of each air terminal is according to the Contract Documents. B. Check that inlet duct connections are as recommended by air terminal manufacturer to achieve proper performance. C. Check that controls and control enclosure are accessible. D. Verify that control connections are complete. E. Check that nameplate and identification tag are visible. F. Verify that controls respond to inputs as specified. 3.6 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel as specified below: 1. Train Owner's maintenance personnel on procedures and schedules related to startup and shutdown, troubleshooting, servicing, and preventive maintenance. 2. Review data in the maintenance manuals. Refer to Section "Contract Closeout." 3. Review data in the maintenance manuals. Refer to Section "Operation and Maintenance Data." 4. Schedule training with Owner, with at least 7 days' advance notice. END OF SECTION Page 5 of 5
Price Fan Powered Terminal Units
Price Fan Powered Terminal Units Division 23 Heating, Ventilating, and Air Conditioning Section 23 3600 Air Terminal Units The following specification is for a defined application. Price would be pleased
More information1.02 Related Sections A. Section Heating, Ventilation and Air Conditioning (HVAC). C. Section Pneumatic and Electric Control HVAC.
PART 1: GENERAL 1.01 Section Includes A. Dual duct terminal units. B. Variable volume regulators. C. Integral damper motor operators. D. Integral controls. 1.02 Related Sections A. Section 23 00 00 Heating,
More informationPIKES PEAK PARKING RESTORATION TABLE OF CONTENTS
23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters
More informationSECTION CONVECTORS
SECTION 23 82 33 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationCapital Projects Group Air Terminal Units Specification
Capital Projects Group Air Terminal Units Specification Specification 23 36 00 Revision 0 Date: August 2018 Air Terminal Units Specification Specification 23 36 00 Publication Date: August 2018 COPYRIGHT
More informationGUC LNG Facility Phase IIB Expansion 6/20/14 INSTRUMENTATION SPECIFICATION. A. This Section includes instrumentation for process piping systems.
INSTRUMENTATION SPECIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationSECTION AIR COILS
SECTION 23 82 16 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationPrice High Performance Horizontal Fan Coil Units
Price High Performance Horizontal Fan Coil Units Division 23 Heating, Ventilating, and Air Conditioning Section 23 82 19 Fan Coil Units The following specification is for a defined application. Price would
More informationSECTION AIR-TO-AIR ENERGY RECOVERY EQUIPMENT
SECTION 23 72 00 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationPrice Active & Passive Beams Division 23 Heating, Ventilating, and Air Conditioning Section Chilled Beams Section Induction Units
Price Active & Passive Beams Division 23 Heating, Ventilating, and Air Conditioning Section 23 82 14 Chilled Beams Section 23 82 26 Induction Units The following specification is for a defined application.
More informationSECTION AIR DUCT CLEANING
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationSECTION DUCTS PART 1 GENERAL 1.01 SUMMARY
1 1 1 1 1 1 1 1 0 1 0 1 SECTION 1 DUCTS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Duct Materials.. Insulated flexible ducts.. Single wall spiral round ducts.. Ductwork fabrication.. Duct cleaning.
More informationPrice Flat Faced Displacement Diffusers
Price Flat Faced Displacement Diffusers Division 23 Heating, Ventilating, and Air Conditioning Section 23 37 13 Diffusers, Registers, and Grilles PART 1 GENERAL 1.01 Section includes: A. Flat Faced Displacement
More informationSECTION HVAC AIR CLEANING DEVICES
SECTION 23 40 00 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationSECTION FUEL-FIRED UNIT HEATERS
SECTION 23 55 33 PART 1 - GENERAL 1.1 DESCRIPTION A. This Section includes gas-fired unit heaters. SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable
More informationACBC Floor Mounted Active Beam
Floor Mounted Active Beam The Price Floor Mounted Active Beam,, is designed for occupant comfort. It provides high cooling and heating capacities while simultaneously supplying ventilation air from a DOAS
More informationA. This Section includes the following sump pumps and accessories, inside the building, for building storm drainage systems:
SECTION 221429 - SUMP PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationPrice Single Duct Terminal Units
Price Single Duct Terminal Units Division 23 Heating, Ventilating, and Air Conditioning Section 23 36 00 Air Terminal Units The following specification is for a defined application. Price would be pleased
More informationSECTION LOW-VOLTAGE TRANSFORMERS
PART 1 GENERAL 1.1 DESCRIPTION SECTION 26 22 00 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between // // if not applicable to project. Also, delete any other item or paragraph not
More informationA. This Section includes ceiling- and wall-mounted diffusers, registers, grilles and louvers.
SECTION 23 37 13 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationA. Operation and Maintenance Data: For pumps and controls, to include in operation and maintenance manuals.
Page 221429-1 SECTION 221429 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More information1 29SEP03 ALL General update with miscellaneous changes in entire document.
REVISION RECORD SECTION 16461 Dry-Type Transformers (600 V and Less) REV DATE PAGE PARA NO. DESCRIPTION APPROVED BY 28SEP01 ALL Initial issue. 1 29SEP03 ALL General update with miscellaneous changes in
More informationB. Wiring Diagrams: For power, signal, and control wiring.
Page 221429-1 SECTION 221429 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION ROTARY SCREW WATER CHILLERS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationACBC Floor Mounted Active Beam
Floor Mounted Active Beam The Price Floor Mounted Active Beam,, is designed for occupant comfort. It provides high cooling and heating capacities while simultaneously supplying ventilation air from a DOAS
More informationArchitect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 23 81 00 DECENTRALIZED HVAC EQUIPMENT A. The other Contract Documents complement the requirements of this section. The General requirements apply to the work
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 102239 - FOLDING PANEL PARTITIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION AIR DISTRIBUTION
SECTION 15880 AIR DISTRIBUTION PART 1 GENERAL 1.1 SUMMARY A. This section describes minimum requirements, products and methods of execution relating to the project air distribution systems. PART 2 PRODUCTS
More informationNV series. Induction VAV air volume control terminals
NV series Induction VAV Table of contents Description Page Type designation 1 Technical data - General 2 - Specification 3 - Installation instruction 3 overview / dimensions 4-5 Sound data NVOAOOB 6-7
More informationB. Shop Drawings: For air terminal units. Include plans, elevations, sections, details, and attachments to other work.
SECTION 233600 - PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Fan-powered air terminal units. 2. Shutoff, single-duct air terminal units. 1.2 PERFORMANCE REQUIREMENTS A. Structural Performance:
More informationB. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification
More informationA. Product Data: Identify thermal conductivity, thickness, and jackets (both factory and field applied, if any), for each type of product indicated.
SECTION 23 07 13 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-23 82 19.00 40 (May 2017) ------------------------------ Preparing Activity: NASA Superseding UFGS-23 82 19 (May 2014) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationSECTION AIR OUTLETS AND INLETS
PART 1 - GENERAL 1.1 DESCRIPTION A. Roof Curbs SECTION 23 37 00 AIR OUTLETS AND INLETS SPEC WRITER NOTE: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph
More informationSECTION COOLING TOWER
PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue
More informationSECTION [ ] COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 08332 [08 33 13] COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Metal Counter
More informationSECTION ENCLOSED BUS ASSEMBLIES
SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationCentral Station Air Handler Specification
Central Station Air Handler Specification PART 1: GENERAL 1.01 WORK INCLUDED (Model CS 3 ) Mechanical Specification A. Provide complete air handling unit(s) suitable for indoor installation. Contractor
More informationSECTION EXHAUST FANS PART 1 GENERAL
SECTION 15800 EXHAUST FANS PART 1 GENERAL 1.01 DESCRIPTION A. The Contractor shall furnish all labor, materials, accessories and all incidentals required to install wet well and control building ventilation
More informationSECTION BUSWAYS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and
More informationSECTION HYDRONIC PIPING
PART 1 GENERAL 1.1 REFERENCES SECTION 23 21 13 HYDRONIC PIPING A. ANSI/ASME SEC 9: Welding and Brazing Qualifications B. ANSI/ASME B16.3: Malleable Iron Threaded Fittings Class 150 and 300 C. ANSI/ASME
More informationSECTION ENCLOSED BUS ASSEMBLIES
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the
More informationFundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619
AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,
More informationDesign and Construction Standards SECTION HYDRONIC PIPING
SECTION 15510 HYDRONIC PIPING PART 1 GENERAL 1.1 REFERENCES A. ANSI/ASME SEC 9: Welding and Brazing Qualifications. B. ANSI/ASME B16.3: Malleable Iron Threaded Fittings Class 150 and 300. C. ANSI/ASME
More informationYORK PASSIVE CHILLED BEAMS ENGINEERING GUIDE
YORK PASSIVE CHILLED BEAMS ENGINEERING GUIDE Contents YORK Passive Chilled Beams 3 CB-PBE-YK / CB-PBR-YK Performance Data 5 CB-PBE-YK Dimensions 7 CB-PBR-YK Dimensions 8 Specifications 9 2 YORK Passive
More informationYORK BULKHEAD MOUNTED CHILLED BEAMS ENGINEERING GUIDE
YORK BULKHEAD MOUNTED CHILLED BEAMS ENGINEERING GUIDE Contents YORK Bulkhead Active Chilled Beams 3 CB-ABB-YK / CB-ABC-YK Performance Data 5 CB-ABB-YK Dimensions 10 CB-ABC-YK Dimensions 11 Specifications
More informationSECTION HYDRONIC PIPING
PART 1 GENERAL 1.1 REFERENCES SECTION 15510 HYDRONIC PIPING A. ANSI/ASME SEC 9: Welding and Brazing Qualifications. B. ANSI/ASME B16.3: Malleable Iron Threaded Fittings Class 150 and 300. C. ANSI/ASME
More informationA. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva:
SECTION 16461 - LOW-VOLTAGE TRANSFORMERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationGUIDE SPECIFICATION: DUCT LINER
GUIDE SPECIFICATION: DUCT LINER This specification guide includes thermal & acoustical insulation for ductwork and air handling systems. This section is based on the format recommended by MICA (Midwest
More informationA. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.
SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary
More informationPrice Egg Crate Grille
Price Egg Crate Grille Division 23 Heating, Ventilating, and Air Conditioning Section 23 37 13 Diffusers, Registers, and Grilles The following specification is for a defined application. Price would be
More informationSECTION HVAC PUMPS. A. Provide centrifugal HVAC pumps, called for in drawing schedule, and as needed for a complete and proper installation.
PART 1 - GENERAL 1.01 DESCRIPTION OF WORK SECTION 15540 HVAC PUMPS A. Provide centrifugal HVAC pumps, called for in drawing schedule, and as needed for a complete and proper installation. B. Provide variable
More informationA. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationSECTION HYDRONIC PIPING
PART 1 GENERAL 1.1 REFERENCES SECTION 23 21 13 HYDRONIC PIPING A. ASME BPVC Section IX - Welding and Brazing Qualifications B. ASME B16.3 - Malleable Iron Threaded Fittings Classes 150 and 300 C. ASME
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationA. Section includes busway and fittings including plug-in units.
SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:
More informationSECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT
SECTION 23 05 12 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between // // if not applicable to project. Also delete
More informationPROJ. NO SECTION HVAC DUCT INSULATION
SECTION 23 07 13 HVAC DUCT INSULATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION DOOR HARDWARE
SECTION 087100 -DOOR HARDWARE PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More information2. Water Pressure Booster Systems. 3. Duplex Pedestal Type Sump Pumps.
PART 1: GENERAL 1.01 Purpose: A. The design guidelines contained herein includes the requirements for pumps utilized for plumbing systems at Texas State University. It is the intention of this document
More informationDESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED
DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON- APPLICABILITY (NA). 1. HEATING SYSTEMS: A. GENERAL
More informationSECTION OVERHEAD COILING FIRE DOORS MODEL 662 OVERHEAD COILING COUNTER FIRE DOORS WITH INTEGRAL FRAME
SECTION 08331 OVERHEAD COILING FIRE DOORS MODEL 662 OVERHEAD COILING COUNTER FIRE DOORS WITH INTEGRAL FRAME Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES
More informationSECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and
More informationA. The work consists of furnishing a Chiller Noise Reduction System as listed in the specifications.
SECTION 32 31 14 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply
More informationA. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:
SECTION 16050 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: General requirements for providing basic electrical materials and methods. B. Related Work Specified in Other Sections Includes: 1. Certain
More informationNVR / NVS / NVF / NVA
NVR / / NVF / NV Product Overview Models Rectangular Roof Stack Unit Square Roof Stack Unit Facade Mounted Natural Vent Wall Mounted Transfer Unit NVR NVF NV The Price natural ventilation system operates
More informationSECTION ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED
SECTION 08350 ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationSECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System
SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF WELDED SYSTEM PART 1 GENERAL 1.1 SECTION
More informationC. Samples: For each exposed product and for each color and texture specified, <Insert dimensions> in size.
SECTION 08 12 16 - ALUMINUM DOOR FRAMES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationD. Provide UL-approved assemblies for pipes and ducts passing through fire-rated floors, walls, or partitions as required.
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-11 70 00 (May 2011) ------------------------------ Preparing Activity: NAVFAC Superseding UFGS-11 70 00 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationDesign & Construction Standards, Revised January
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationEssex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationT-Series SPLIT SYSTEM UNITS TSA R-410A - 60 HZ
REFRIGERANT CONDENSERS Guide Specifications T-Series SPLIT SYSTEM UNITS TSA R-410A - 60 HZ September 5, 2012 Note: This Specification is for Allied Commercial T-Series 6- to 20-ton, outdoor air conditioner
More informationUniversity of Delaware
SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality
More informationPRODUCT SPECIFICATION GUIDE MODEL EQB BELT DRIVEN MIXED FLOW INLINE FAN FACILITY SERVICES SUBGROUP: DIVISION 23 SECTION
P.O. Box 410 Schofield, WI 54476 Phone: 715.359.6171 www.greenheck.com PRODUCT SPECIFICATION GUIDE MODEL EQB BELT DRIVEN MIXED FLOW INLINE FAN FACILITY SERVICES SUBGROUP: DIVISION 23 SECTION 23 34 23 *********
More informationSECTION DUCT ACCESSORIES. A. Types of ductwork accessories required for this project include the following:
SECTION 15910 PART I - GENERAL 1.01 WORK INCLUDED A. Types of ductwork accessories required for this project include the following: 1. Turning Vanes 2. Duct Hardware 3. Duct Access Doors 4. Flexible Connections
More informationThe motor shall be high-starting torque, ball bearing, rated at 460 V, 3 phase
MODEL 41 ELECTRIC FOUR FOLD DOORS Guide Specification Template INSTRUCTIONS FOR USE EPD has provided this PDF guide template to assist in your development of an accurate document for use in specifying
More informationCopyright 2004 and 2005 by The American Institute of Architects (AIA)
Page 232500-1 Copyright 2004 and 2005 by The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA Modified by MSU Physical
More informationSECTION HEAT TRACING FOR PLUMBING PIPING
SECTION 22 05 33 HEAT TRACING FOR PLUMBING PIPING PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph not
More informationThe factory assembled air handler shall conform to the requirements outlined ASHRAE 90.1.
PAGE 1 of 5 1.1. REFERENCE STANDARDS 1.1.1. The factory assembled air handler shall conform to the requirements outlined ASHRAE 90.1. 1.1.2. Unit shall be designed to conform to ASHRAE 15. 1.1.3. Unit
More informationFABRICOIL BASIC January 10, 2006
FABRICOIL BASIC January 10, 2006 General Notes: This guide specification document is provided by Raynor Door for use by design professionals in preparing project specification documents for FABRICOIL BASIC
More informationSECTION HVAC INSULATION
PART 1 GENERAL 1.1 SUMMARY SECTION 23 07 00 HVAC INSULATION A. Section Includes: 1. Ductwork insulation. 2. Duct liner. 3. Insulation jackets. 4. Equipment insulation 5. Piping system insulation. 6. Insulation
More informationSECTION PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS
SECTION 23 74 13 PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationSECTION LABORATORY FUME HOODS
PART 1 - GENERAL 1.1 DESCRIPTION: SECTION 11 53 13 LABORATORY FUME HOODS SPEC WRITER NOTE: Delete between // // if not applicable to project. Delete other items or paragraphs in the section that are not
More informationRAOUL WALLENBERG HIGH SCHOOL SECURITY COILING GRILLE SFUSD PROJECT NO SAN FRANCISCO UNIFIED SCHOOL DISTRICT SECTION 08330
SECTION 08330 PART 1 - GENERAL 1.1 SUMMARY A. Work Included: Provide all labor, materials, necessary equipment, services and included but limited to all related work to complete security coiling grille
More informationSECTION HEAT TRACING FOR PLUMBING PIPING
SECTION 22 05 33 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable in the section
More informationSECTION EZ-SLIDE 80 AND 180 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS
Page 1 of 6 SECTION 08 32 20 EZ-SLIDE 80 AND 180 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS PANEL PARTITIONS. SECTION INCLUDES OVERHEAD TRACK ASSEMBLY,
More informationSECTION PACKAGED, SUBMERSIBLE, DRAINAGE PUMP UNITS
SECTION 22 14 36 PACKAGED, SUBMERSIBLE, DRAINAGE PUMP UNITS PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph
More information2004 MASTER FORMAT SECTION Façade Panels
2004 MASTER FORMAT SECTION 07 44 00 Façade Panels Hunter Douglas Façades Aluminum Façade Systems PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-07 72 20 (August 2009) --------------------------- Preparing Activity: USACE Nontechnical Title Revision (August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationSECTION AIR FILTERS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationCONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist
CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist This checklist is a convenient reference to the 2012 Michigan Building Code. The checklist
More informationCounty of Yolo Development Services Building Inspection Division
County of Yolo Development Services Building Inspection Division 292 W. Beamer Street Woodland, CA. 95695 www.yolocounty.org (530) 666-8775 Mechanical Plan Review Comments Plan Review No. Owners Name Job
More informationFIRE STATION 55 June 14, 2010
SECTION 15250 MECHANICAL INSULATION PART 1 - GENERAL 1.01 DESCRIPTION A. Work Includes 1. Insulation of Domestic Water Piping. 2. Pipe Insulation of refrigerant piping. 3. Insulation of ductwork. 4. Aluminum
More informationTARRANT COUNTY PURCHASING DEPARTMENT
JACK BEACHAM, C.P.M., A.P.P. PURCHASING AGENT TARRANT COUNTY PURCHASING DEPARTMENT JANUARY 24, 2017 BID NO. 2017-064 ADDENDUM #1 ROB COX, C.P.M., A.P.P. ASSISTANT PURCHASING AGENT TARRANT COUNTY DICK ANDERSEN
More informationB. Provide equipment complying with this specification and manufactured by one of the following:
SECTION 230910 PAINT SPRAY BOOTH PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide Paint Spray Booth, Prep Booth and Paint Mix Room, and associated ventilation equipment, complying with the