Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016

Size: px
Start display at page:

Download "Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016"

Transcription

1 Method Statement BLOCK WORK Civil Works 6/26/2016 The purpose of this Work Method Statement for Block Works (Concrete Masonry Units) is to outline and describe in detail the procedure such as setting and lay-out plan on actual location, erection of scaffolding, mixing of cement mortar, mounting/laying of blocks and all other related activity. Inform all concerned supervisor including workers the value and importance of this activity prior to implementation. This activity should be performed with strict compliance and implementation of Safety Requirements & Procedure and project specifications to complete the work both for exterior and interior masonry walls.

2 TABLE OF CONTENTS 1. BLOCK WORK DRAWING AND DETAILS 2. STACKING BLOCKS 3. SCAFFOLD AND CLEAN WORKING AREA 4. LIFTING, SHIFTING & STORING 5. SCOPE 6. TOOLS EQUIPMENT PLANT 7. STARTING THE BLOCK WORK 8. BLOCK LAYING ALIGNMENT JOINTING 9. STRIKING JOINTS 10. CURING 11. TOOL BOX TALK ON

3 BLOCK WORK DRAWINGS AND DETAILS Detailed layout of the building showing room dimensions, thickness of walls at various locations in the building Details of openings (with sizes) to be provided in the walls for doors, windows, ventilators, exhaust fan openings & other openings Details of door, window, ventilator frames and their fixing means like holdfasts, anchor bolts etc and their levels Details of cross walls to ensure proper bond in main walls Location details of concealed items such as electrical conduits, telephone conduits, conduits for TV Antenna wires and cables Location details of items such as water supply pipes with details of inlet, outlet and crossings of service lines, sanitary pipes with details of inlet, outlet and crossings of service lines, openings or holes for positioning of water closet p / s traps, openings required for air conditioning ducts, pipe sleeves to be left in walls for other service pipes STACKING BLOCKS Blocks shall be stacked properly near the place of work (too large a quantity must not be stacked near the work area thereby causing safety hazard) Height of the stack should be one meter if stacks are non-interlocking arrangement, and if interlocking arrangement not more than 10 block height.

4 SCAFFOLD & CLEAN WORKING AREA Scaffolding should be braced adequately Scaffolding should be checked for the load carrying capacity and ensure no overloading. Working space should be clear from rubbish, waste mortar etc. so that easy access is ensured Use only narrow and podium scaffold only for block works with safe platform LIFTING, SHIFTING & STORING Unloading, Lifting, shifting of materials manual/mechanical transporting of blocks etc. have to be carried out by workers who are properly trained. Otherwise this may leads to serious injuries to workers since blocks are heavy Dry mix and cement should be kept in a dry location. Do stack the blocks on a proper platform & clean surface. Do stack blocks at just convenient location for immediate use. Do not over rule safety aspects to achieve timely completion

5 SCOPE This work procedure enumerates the scope of masonry work to be executed in the project as specified in the approved drawings and at places when instructed by the Engineer-in-charge. TOOLS, EQUIPMENT & PLANT Standard tools that listed below should keep available at site, those are: Electric drill & Masonry bits Measuring tape Trowels Mechanical mixer Laser levels Mixing Tray Scaffold Podium Spirit level 3 Bucket Scaffold Narrow Mason (club)hammer Wire brushes 3 Meter aluminium straight edge Mason Square Chisels Wheel barrow Line tread Mason brick hammer

6 STARTING THE BLOCK WORK Make sure all the materials are available at work area including dowel pin and other accessories Obtain access clearance from General Contractor Mark on the surface to establish the wall lines to attain proper layout of block work & maintain mark till the first course is fully laid. Obtain approval from General contractor on marking Scrub & clean with proper tool, the concrete or block work surface where new block work is to be done. Where usage of steel anchor or mesh etc, are specified for bonding block work with concrete, fix the anchors in position so that they are embedded properly in the courses. Before commencing block work, check reference points such as bench mark, lintel level, bed block level, cross beam level etc & be sure where to terminate the top most block course, after the same is studied in detail as stated above. Blocks should not be damp at the time of starting masonry. When much water is present on the blocks then mortar will become watery leading to a weak masonry. The blocks must be semi dry or skin wet. Mix quantity of mortar, which will be consumed in next 2 hours only. Mixing shall be done with proper measurements of ingredients. Mixing platform must be clean and protected from bonding to slab. Mixing of mortar shall be done in accordance with construction standard. (If more quantity is mixed and will not be consumed within the time, cement will start setting leading to weaker masonry). Add water to the dry mix of cement sand in required quantity. Neither wet cement nor wet sand is to be mixed. Bulk age of sand shall be considered while adding water to the dry mix. Prepare a scheme of scaffolding, draw a sketch and pass on the same to workers for execution. Ensure safety aspects such as stability, proper joints etc. Check and ensure availability of scaffolding materials, access ladder or staircases, working platforms etc. The maximum length of block wall without a break has to be limited to 6m. If wall is beyond this length vertical mullions have to be introduced. Where such mullions and

7 horizontal members are not given, please refer the case back to Architect / consultant for introduction of these members. BLOCK LAYING, ALIGNMENT AND JOINTING Carry out one row of block work with dry bond (i.e. without mortar, lay the blocks in position), the wall to establish the proper spacing of blocks. Lay mortar for full bed width and for a length of 3 blocks at a time, and to 12mm thickness. Lay one block at a time & gently press it on the mortar bed. Use a line thread from one end to end All block work shall be plumb, square and properly bonded. The joints shall not be broken. Excess mortar coming out on the edge (while pressing block in position in bed mortar) to be taken by trowel & buttered to the cross directional joint or head joint surface of the next block being laid. The thickness of courses shall be uniform with courses horizontal. Use straight edge & spirit levels on top of the blocks laid & check the top level. Make sure that the spirit level is in working condition & read the bubble carefully. Use laser tools for levelling if available. Lay the last closure block in the course, to close the bond and locate it to be near the centre of the wall normally. Butter both edges of closure block with mortar before lay. Repeat the above points for building more courses. After every two course of block work lay, check the verticality using plumb bob, sight down the wall. The whole block work to be built in uniform layers. For pointed masonry without plaster, smooth textured concrete block shall be used. The face of blocks work shall be kept clean at all times. Where block are to be used for load bearing walls, the uppermost layer of block masonry supporting slab or other structured members, shall be solid or treated as directed.

8 STRIKING JOINTS As soon as mortars in the joints have initially set, use a proper tool and strike the vertical joints first. The horizontal bed joints are to be raked next to a depth of 10 mm. After striking joints brush the wall surface head joint first & bed joints last to complete brushing. If, it is exposed block work without any plastering, the striking of joints should be 15mm in depth instead of 10mm Height of Construction No part of wall during construction shall raise more than one and ahalf meter above the general construction level.

9 CURING In hot & dry weather the mortar is likely to dry up before it has attained its final set in the block work. This leads to crumbling of mortar and resulting in weak block masonry. This shall be prevented, by keeping the new block work constantly wet, for at least seven days. Traditional floor screed basically consists of sand & cement mixed at a ratio of between 3 to 5 parts sand & 1 part cement. In the majority of cases 4 to 1 is quite sufficient.

10 TOOL BOX TALK ON: 1. Importance of PPE 2. Use and service of hand tools and electrical tools 3. Safe handling of power supply 4. Use of mechanical equipment and service 5. Housekeeping safety 6. Risk Assessment 7. MSDS (Material Safety Data Sheet) 8. Access clearance 9. Lifting, Shifting and Storing 10. Rest Area 11. Restriction of Mobile and Radio 12. Noise restriction 13. Cutting of materials that makes noise and dust 14. Approved shop drawing 15. Working at height 16. Use of scaffold

SECTION MORTAR

SECTION MORTAR PART l - SCOPE SECTION 04100 - MORTAR A. This Section includes all labor, materials, equipment, and related items required for the work of mortar as shown on the Drawings and specified herein. The work

More information

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated: SECTION 04220 CONCRETE UNIT MASONRY PART 1 - GENERAL 1.01 SCOPE: A. The CONTRACTOR shall furnish all labor, materials and equipment necessary for the masonry construction as shown on the drawings or as

More information

A. Coordinate concrete unit masonry (also termed CMU and block ) work with work before and after, especially:

A. Coordinate concrete unit masonry (also termed CMU and block ) work with work before and after, especially: 04222 CONCRETE UNIT MASONRY (UNREINFORCED ONLY) SPECIFIER: Use this section only for UNREINFORCED concrete masonry. Its only reinforcement is in the horizontal joints. It covers ONLY plain blockwork (no

More information

PART A: JOB PROCDRE FOR PLASTERING

PART A: JOB PROCDRE FOR PLASTERING PART A: JOB PROCDRE FOR PLASTERING 1. SCOPE: The scope of this procedure shall apply to all cement plaster finishes to column, ceilings, walls and similar surfaces on backgrounds met with such as brick,

More information

SECTION BRICKWORK

SECTION BRICKWORK SECTION 04210 BRICKWORK THERE ARE NOTES AND CLAUSES IN THE SUSTAINABILITY GUIDE ON THIS TRADE. THIS TRADE SECTION DEPENDS ON COORDINATION BETWEEN THIS SPECIFICATION AND THE FINISHES SCHEDULE AS WELL AS

More information

Content Domain. NCCER Progress Blvd. Alachua, FL

Content Domain. NCCER Progress Blvd. Alachua, FL National Craft Assessment and Certification Program S P E C I F I C A T I O N S Masonry V1 June 2016 Focus Statement A journey level mason must be able to build, maintain and repair block and brick edifices,

More information

SECTION BRICKWORK PART I GENERAL

SECTION BRICKWORK PART I GENERAL SECTION 04210 BRICKWORK PART I GENERAL 101 Scope General: supply and build the brickwork shown on the drawings or needed to complete the brickwork, including but not limited to the following: Provide all

More information

Zenon Panel Assembly Guideline - Page 1

Zenon Panel Assembly Guideline   - Page 1 Zenon Panel Assembly Guideline www.zenonpanel.com - Page 1 This guide is the document that summarizes the key points to be considered in the assembly of Zenon Panel. It is very important to consider the

More information

Paragraph Description Page No General Materials Concrete Masonry Work Altitude Valve Vault Cover 25-4

Paragraph Description Page No General Materials Concrete Masonry Work Altitude Valve Vault Cover 25-4 City of Columbia Engineering Regulations PART 25: SPECIFICATIONS FOR ALTITUDE VALVE VAULT Table of Contents Paragraph Description Page No. 25.1 General 25-1 25.2 Materials 25-1 25.3 Concrete Masonry Work

More information

PARTICULAR SPECIFICATIONS MASONRY WORK BRICK WORK

PARTICULAR SPECIFICATIONS MASONRY WORK BRICK WORK PARTICULAR SPECIFICATIONS MASONRY WORK BRICK WORK (For Building & Area Development Work) 1.0 INDIAN STANDARDS: Work shall be carried out to Indian Standards and Code of practices. In absence International

More information

104 References Comply with applicable portions of current editions of the following Australian Standards:

104 References Comply with applicable portions of current editions of the following Australian Standards: SECTION 04210 BRICKWORK THERE ARE NOTES AND CLAUSES IN THE SUSTAINABILITY GUIDE ON THIS TRADE. THIS TRADE SECTION DEPENDS ON COORDINATION BETWEEN THIS SPECIFICATION AND THE FINISHES SCHEDULE AS WELL AS

More information

BRICKWORK 3.5 BRICKWORK 1 GENERAL

BRICKWORK 3.5 BRICKWORK 1 GENERAL BRICKWORK 1 GENERAL 1.1 INSPECTION Notice Give sufficient notice so that inspection may be made of the following: - Set out of brickwork to lintels, arches and other architectural features. - Damp-proof

More information

Division 04 - Masonry Section New Westminster Multi-Use Civic Facility & Office Building Project No Page 1

Division 04 - Masonry Section New Westminster Multi-Use Civic Facility & Office Building Project No Page 1 Project No. 210022 Page 1 1 GENERAL 1.1 REQUIREMENTS INCLUDED.1 Furnish all labour, material, services and equipment necessary for the supply, delivery and erection of concrete block masonry and reinforced

More information

SECTION UNIT MASONRY

SECTION UNIT MASONRY SECTION 04200 UNIT MASONRY PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, and equipment and perform functions required in the installation and maintenance of the work covered by this Section.

More information

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following: SECTION 03470 TILT-UP PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Work includes, but is not limited to, the following: 1. Precast wall panels. 2. Forms and casting beds. 3. Concrete. 4. Reinforcing

More information

CONCRETE FORMWORK CHECKLIST AT SITE

CONCRETE FORMWORK CHECKLIST AT SITE CONCRETE FORMWORK CHECKLIST AT SITE Concrete formwork is a temporary supporting structure for concrete when it is placed at the construction site to keep the concrete in position and shape till it gets

More information

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

PART 1-SAWN THIN VENEER GENERAL

PART 1-SAWN THIN VENEER GENERAL PART 1-SAWN THIN VENEER GENERAL WORK INCLUDED: All labor and material for the furnishing and installing of exterior or interior stone building veneer. RELATED WORK: Masonry Contractor shall include building

More information

Construction Masonry-Stone

Construction Masonry-Stone Job Ready Assessment Blueprint Construction Masonry-Stone Test Code: 3225 / Version: 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Hand and Power Tools Identify

More information

Pre-build: TOOLs & Materials

Pre-build: TOOLs & Materials Pre-build: TOOLs & Materials ITEM a. Builder s square b. Brick bolster c. Bricks d. Builder s bucket e. Mortar trowel f. Mason's string g. Square-nosed spade h. Spirit level i. Tape measure j. kg hammer

More information

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION This Technical Notes contains the guide specifications in CSI format for Part III

More information

CONCRETE BLOCK MASONRY

CONCRETE BLOCK MASONRY CONCRETE BLOCK MASONRY CONTENT Introduction Types Manufacturing process Properties Advantages Introduction These are the concrete blocks either hollow or solid. A hollow unit is that unit which has core

More information

Hardscaping Installation Manual

Hardscaping Installation Manual Hardscaping Installation Manual INDEX Installation of Pavers... 1 Installation of Meshed Flagstone... 2 Installation of Veneer Stone... 3 Sand Set Installation of Pavers 1. Preparing the ground Mark your

More information

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

SITE VISIT REPORT DATE: JOB: NO. OF VISIT: PAGE OF : PURPOSE OF VISIT: CONTRACTOR: Items to be checked Observations Actions SETTING OUT

SITE VISIT REPORT DATE: JOB: NO. OF VISIT: PAGE OF : PURPOSE OF VISIT: CONTRACTOR: Items to be checked Observations Actions SETTING OUT SETTING OUT Correct to boundaries Correct to building lines? Diagonals accurate? Levels correct? EXCAVATIONS Adjoining structures OK? Centres of foundations line with walls? Bottoms of trenches uniform,

More information

Compiled by: Civil Works Department, SSA Punjab.

Compiled by: Civil Works Department, SSA Punjab. 45 Compiled by: Civil Works Department, SSA Punjab. TIPS FOR CIVIL CONSTRUCTION WORKS 1. ISI marked 43 Grade cement of major manufacture must be used. 2. ISI mark Steel must be used. 3. Clean & Fine Sand

More information

Important: Before You Start

Important: Before You Start Advantage ICF System Advantage ICF System TM Field Guide Important: Before You Start Does Your Building Inspector Know You Are Building with the Advantage ICF System? You are required to check with your

More information

ThermaSteel Corporation ASSEMBLY MANUAL

ThermaSteel Corporation ASSEMBLY MANUAL ThermaSteel Corporation ASSEMBLY MANUAL TABLE OF CONTENTS 1- INTRODUCTION 1.1 THERMASTEEL TM WALL PANELS 1.2 Drawing and Element Numbers 2- ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation of Foundation

More information

Planning and installation instructions

Planning and installation instructions Planning and installation instructions Stofix Oy Ahlmaninkatu 2 E 40100 Jyväskylä Finland stofixgroup@stofix.com www.stofix.com 2 PLANNING AND INSTALLATION INSTRUCTIONS... 1 1 General... 3 2 Project Design...

More information

INSULATED CONCRETE MASONRY UNITS Section 04220

INSULATED CONCRETE MASONRY UNITS Section 04220 INSULATED CONCRETE MASONRY UNITS Section 04220 PART 1 GENERAL 1.01 Summary A. Section Includes 1. Insulated masonry wall units (CMU's) 2. Decorative insulated masonry wall units 1.02 SUBMITTALS A. Samples:

More information

Drainage, Road Drainage and Collection Pit A - EXCAVATION:

Drainage, Road Drainage and Collection Pit A - EXCAVATION: 57 Drainage, Road Drainage and Collection Pit SCHEDULE OF QUANTITY Sl.N o. 1 Particulars Qty Unit Rate Amount A - EXCAVATION: Earth work in EXCAVATION IN FOUNDATION TRENCHES IN ALL KIND OF SOIL including

More information

City of Westerville Guide to Commercial Inspections

City of Westerville Guide to Commercial Inspections City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing

More information

1 Exam Prep Application and Finishing of Gypsum Board GA Tabs and Highlights

1 Exam Prep Application and Finishing of Gypsum Board GA Tabs and Highlights 1 Exam Prep Application and Finishing of Gypsum Board GA-216-2013 Tabs and s These 1 Exam Prep Tabs are based on the Gypsum Association GA-216-2013 Application and Finishing of Gypsum Panel Products. Each

More information

1 Exam Prep Application and Finishing of Gypsum Board GA Tabs and Highlights

1 Exam Prep Application and Finishing of Gypsum Board GA Tabs and Highlights 1 Exam Prep Application and Finishing of Gypsum Board GA-216-2016 Tabs and s These 1 Exam Prep Tabs are based on the Gypsum Association GA-216-2016 Application and Finishing of Gypsum Panel Products. Each

More information

Haener Block General Building Tips

Haener Block General Building Tips Haener Block General Building Tips Haener Block General Building Tips By Robert Shepersky (Masonry Contractor of 38 years) Intro for the Masonry Contractor: Using Haener Block will change the way you think

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

Masonry Instructional Framework

Masonry Instructional Framework Masonry Instructional Framework An instructional framework provides educators with a list of benchmark statements aligned to and national content area standards for a given course or program. The Missouri

More information

Unit Masonry

Unit Masonry 04 00 00 Unit Masonry This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes

More information

SECTION UNIT MASONRY SYSTEM

SECTION UNIT MASONRY SYSTEM SECTION 04320 UNIT MASONRY SYSTEM PART 1 GENERAL 1.01 SECTION INCLUDES A. Concrete masonry and face brick units. B. Reinforcement, anchorage, and accessories. 1.03 SUBMITTALS A. Submit product data under

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

SECTION BRICK MASONRY ASSEMBLIES

SECTION BRICK MASONRY ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Face brick. 2. Mortar and grout. 3. Ties and anchors. 4. Miscellaneous masonry accessories. 1.2 SUBMITTALS A. Product Data: For each type

More information

Installation Guide Wall Panels

Installation Guide Wall Panels Installation Guide Wall Panels Jointless or Dry-Stacked Installation (Read Prior to installation) The MStone system is a jointless / dry-stacked installation where panels and corners fit tightly together

More information

QUALIFICATIONS PACK OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY. 3. Power Generation (Hydro, Thermal & Nuclear)

QUALIFICATIONS PACK OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY. 3. Power Generation (Hydro, Thermal & Nuclear) QUALIFICATIONS PACK OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY What are Occupational Standards (OS)? OS describe what individuals need to do, know and understand in order to carry out a particular

More information

BUILDING STONE PRODUCTS, INC.

BUILDING STONE PRODUCTS, INC. Specifications for Renaissance Masonry Units Developed by Arriscraft International Corporation To be used as a guide for Architectural Specifications Product A calcium silicate building unit produced for

More information

Unit 4 Brick Masonry. Part Ⅰ Illustrated Words and Concepts. Figure 4-1 Basic Vocabulary of Bricklaying

Unit 4 Brick Masonry. Part Ⅰ Illustrated Words and Concepts. Figure 4-1 Basic Vocabulary of Bricklaying Part ⅠIllustrated Words and Concepts Figure 4-1 Basic Vocabulary of Bricklaying Figure 4-2 The Procedure for Building Brick Walls Figure 4-3 A Reinforced Brick Load bearing Wall Part ⅡPassages Passage

More information

AN EXAMPLE OF ACOTEC WALL INSTALLATION

AN EXAMPLE OF ACOTEC WALL INSTALLATION AN EXAMPLE OF ACOTEC WALL INSTALLATION Elematic Oy Ab P.O. Box 33 37801 Toijala Finland www.elematic.com 1 1 During storage at factory and transportation, a maximum of two stacks can be placed on top of

More information

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION MORTAR AND MASONRY GROUT

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION MORTAR AND MASONRY GROUT SECTION 04110 MORTAR AND MASONRY GROUT PART 0 DESIGN STANDARDS 0.01 GENERAL DESIGN GUIDELINES A. In the absence of other information, the methods and recommendations of the National Concrete Masonry Association

More information

Building Construction 14. Dr Nabil El-Sawalhi Associate professor Engineering Projects Management

Building Construction 14. Dr Nabil El-Sawalhi Associate professor Engineering Projects Management Building Construction 14 Dr Nabil El-Sawalhi Associate professor Engineering Projects Management Plaster Plaster is a wet mixed material applied to internal walls as a finish to fill in any irregularities

More information

SECTION Specification for Building Limes Specification For Building Sands from Natural Sources Methods of Tests for Paints.

SECTION Specification for Building Limes Specification For Building Sands from Natural Sources Methods of Tests for Paints. SECTION 09200 PART 1 - GENERAL 1.01 DESCRIPTION A. Extent of Work: The extent of lath and plaster work is shown on the drawings and in schedules and includes interior and exterior plaster work, and fibreglass

More information

Conditions of the Contract and Division 1 General Requirements are a part of this section.

Conditions of the Contract and Division 1 General Requirements are a part of this section. NOTES TO SPECIFIER General notes about the specifications and the reasons for them are listed here in general statements. Use this as a guide when choosing the correct selection of statements that apply

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

INSTALLATION GUIDE COMPOSITE DECKING

INSTALLATION GUIDE COMPOSITE DECKING INSTALLATION GUIDE COMPOSITE DECKING sales@ecoscapeuk.co.uk CONTENTS STORAGE & HANDLING 03 SAFETY & USE 04 TOOLS 05 CALCULATING BOARDS 06 DECKING COMPONENTS + ACCESSORIES 07 PRE INSTALLATION NOTES 09 FALLS

More information

SECTION CONCRETE UNIT MASONRY. A. Section Includes: Concrete unit masonry construction as shown on Drawings and as specified.

SECTION CONCRETE UNIT MASONRY. A. Section Includes: Concrete unit masonry construction as shown on Drawings and as specified. SECTION 04220 CONCRETE UNIT MASONRY PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Concrete unit masonry construction as shown on Drawings and as specified. 1.02 SYSTEM DESCRIPTION A. Performance Requirements:

More information

Annex II- Lot 2. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State

Annex II- Lot 2. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State Annex II- Lot 2 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State Lot: 2 Site 2-1: Allakandie All Prices of items shall include Supplying,

More information

SECTION INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING

SECTION INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING SECTION 04210 INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING PART I GENERAL 1.1 SUMMARY A. Provide installation of new or replacement of masonry units and/or repointing of masonry units

More information

Annex III- Lot 3. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State

Annex III- Lot 3. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State Annex III- Lot 3 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State Lot: 3 Site 3-1: Sinja city All Prices of items shall include Supplying,

More information

F10. BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE:

F10. BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE: F10 BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE: Product Name: Pre War Common Size: 215x102x65mm Manufacturer and reference:

More information

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1 16 May 2014 Page 1 PART 1 GENERAL 1.1 DESCRIPTION This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

Brick Works (cont.) Building in bricks: Factors affecting the stability of brick building: Properties of bricks:

Brick Works (cont.) Building in bricks: Factors affecting the stability of brick building: Properties of bricks: Brick Works (cont.) Building in bricks: Building in brick by using mortar of cement and sand or gypsum paste. When a mortar cement and sand used, bricks must be soaked with water before use to achieve:

More information

04221 CONCRETE UNIT MASONRY

04221 CONCRETE UNIT MASONRY 04221 CONCRETE UNIT MASONRY ****************************************** SPECIFIER: This section replaces 04230. It is MDCPS s more comprehensive block masonry section. It covers reinforced blockwork with

More information

Uses. architectural works. 1) Building foundations, walls, piers, pillars, and. 2) Lintels, Beams, beams Arches, domes etc.,

Uses. architectural works. 1) Building foundations, walls, piers, pillars, and. 2) Lintels, Beams, beams Arches, domes etc., STONE MASONRY etc. Stone Masonry The construction of stones bonded together with mortar is termed as stone masonry where the stones are available in a abundance in nature, on cutting and dressing to the

More information

F10. BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE:

F10. BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE: F10 BRICK/BLOCK WALLING To be read with Preliminaries/General conditions. TYPES(S) OF WALLING 110 CLAY FACING BRICKWORK SHALL BE: Product Name: Olde English Grey Size: 215x102x65mm Manufacturer and reference:

More information

STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING

STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING Sl. No. Description of the Works Unit Quantity Rate Amount 1 DISMANTLING WORKS Surface cleaning of roof by

More information

Impression Graphic panels

Impression Graphic panels Impression Graphic panels Installation Guidelines 6003.I Rev. 02 8/15 Please Read Disclaimers: PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNING INSTALLATION!! These guidelines are provided in good faith to

More information

SECTION UNIT MASONRY ASSEMBLIES

SECTION UNIT MASONRY ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Concrete masonry units. 2. Decorative masonry units. 3. Mortar and grout. 4. Steel reinforcing bars. 5. Masonry joint reinforcement. 6. Ties and anchors.

More information

PPC Cement TUTORIAL. how to screed a floor

PPC Cement TUTORIAL. how to screed a floor PPC Cement TUTORIAL how to screed a floor Pre-build: TOOLs & Materials ITEM Quantity Check. Builders bucket. Wheelbarrow 3. Shovel 4. Builder s line 5. 50mm steel pegs 6. Rigid timber forms 7. Flexible

More information

BRANZ Appraisal Certificate # 461 (2010) Internal wet areas.

BRANZ Appraisal Certificate # 461 (2010) Internal wet areas. SPECIFICATION FOR PROTECTO WRAP AFM-WM FOR INTERNAL WET AREAS BRANZ Appraisal Certificate # 461 (2010) Internal wet areas AFM/WM INTERNAL 0104 Page 1 AFM-WM INTERNAL SPECIFICATION PRODUCT DESCRIPTION Anti

More information

MASONRY. Level One. Competencies / Objectives MODULE INTRODUCTION TO MASONRY MODULE MASONRY TOOLS AND EQUIPMENT

MASONRY. Level One. Competencies / Objectives MODULE INTRODUCTION TO MASONRY MODULE MASONRY TOOLS AND EQUIPMENT National Center for Construction Education & Research P. O. Box 141104, Gainesville, FL 32614-1104 Tel: (352) 334-0920 Fax: (352) 334-0931 E-mail: info@nccer.org MASONRY Competencies / Objectives Level

More information

MANUFACTURER'S SPECIFICATIONS Section ST. ASTIER LIME PLASTER (NHL) PLASTER ON CONCRETE

MANUFACTURER'S SPECIFICATIONS Section ST. ASTIER LIME PLASTER (NHL) PLASTER ON CONCRETE MANUFACTURER'S SPECIFICATIONS Section 09225 ST. ASTIER LIME PLASTER (NHL) PLASTER ON CONCRETE ST. ASTIER NATURAL HYDRAULIC LIME PLASTER PART 1 GENERAL 1.1 Summary A. This Section includes St. Astier Natural

More information

Perkins Statewide Articulation Agreement. Documentation item: Secondary Competency Task List Coversheet

Perkins Statewide Articulation Agreement. Documentation item: Secondary Competency Task List Coversheet Perkins Statewide Articulation Agreement Documentation item: Secondary Task List Coversheet The Secondary School agrees to: A. Implement the approved PDE Program(s) of Study. B. Provide assessment of student

More information

OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. RobinsonBrick.com

OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. RobinsonBrick.com OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide RobinsonBrick.com OLD BRICK ORIGINALS THIN BRICK VENEER Page 2 INTRODUCTION Check local building codes for proper installation guidelines

More information

REINFORCED CONCRETE MASONRY SECTION

REINFORCED CONCRETE MASONRY SECTION SECTION 04 22 02 - REINFORCED CONCRETE MASONRY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification

More information

0331 Brick and block construction

0331 Brick and block construction 0331 BRICK AND BLOCK CONSTRUCTION 1 GENERAL 1.1 STANDARDS Materials and construction: To AS 4773.1 and AS 4773.2. 2 PRODUCTS 2.1 DURABILITY Exposure environment: [complete/delete] Exposure locations: To

More information

Building Construction Occupations

Building Construction Occupations Job Ready Assessment Blueprint Building Construction Occupations Test Code: 2011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge

More information

Annex I- Lot 1. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State

Annex I- Lot 1. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State Annex I- Lot 1 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State Lot: 1 Site 1-1: Sinnar city All Prices of items shall include Supplying,

More information

Guide to using the Ultimate Building Block

Guide to using the Ultimate Building Block Energy efficient Solid Concrete Core High Thermal & Acoustic Insulation All weather Construction Create Curved Walls BRANZ Appraised -#362 4hr FFR- Fire Rated Mechanical Fixing for Linings-Interior & Exterior

More information

DIVISION 22 PLUMBING SECTION INTERIOR SANITARY WASTE AND VENT PIPING SYSTEM

DIVISION 22 PLUMBING SECTION INTERIOR SANITARY WASTE AND VENT PIPING SYSTEM DIVISION 22 PLUMBING PART 1 GENERAL 1.01 DESCRIPTION A. Provide a complete system of soil, waste, and vent piping to fixtures and equipment, including traps, floor drains and cleanouts, extending to a

More information

US Pool Lift Model #114 (Independence) Installation Guide

US Pool Lift Model #114 (Independence) Installation Guide US Pool Lift Model #114 (Independence) Installation Guide This manual has been provided to assist with lift installation. For further assistance please contact your authorized US Pool Lift dealer. Toll

More information

INSTALLATION CHECKLIST 2 ND EDITION. Fox Blocks Abbott Drive Omaha, NE

INSTALLATION CHECKLIST 2 ND EDITION. Fox Blocks Abbott Drive Omaha, NE Fox Blocks INSTALLATION CHECKLIST ND EDITION Fox Blocks Installation Checklist: ND Edition 6110 Abbott Drive Omaha, NE 6110-69-6 WWW.FOXBLOCKS.COM INSTALLATION CHECKLISTS The Checklists on the following

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AG s APPARELS LIMITED. Plot No. A/1&2 Block-B, BSCIC I/A Fouzderhat, Sagarika Road, Dhaka-1207, Bangladesh Factory List: 1. AG s Apparels Limited. Inspected by: Sherub

More information

What can I do with a bag of cement (Start simple and upgrade for toilets and wells)

What can I do with a bag of cement (Start simple and upgrade for toilets and wells) What can I do with a bag of cement (Start simple and upgrade for toilets and wells) Peter Morgan 2016 Introduction Start simple and upgrade over time sounds to me like a good idea. It s a method which

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06110 WOOD FRAMING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But Not Supplied

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

Table of Contents. 1 Introduction. 2 Description. 3 Tools and materials. 4 Footings or slabs. 5 Coursing placement. 6 Reinforcing steel

Table of Contents. 1 Introduction. 2 Description. 3 Tools and materials. 4 Footings or slabs. 5 Coursing placement. 6 Reinforcing steel Table of Contents 1 Introduction 2 Description 3 Tools and materials 4 Footings or slabs 5 Coursing placement 6 Reinforcing steel 7 Alignment scaffold installation 8 Concrete placement 9 Exterior and interior

More information

FEDDERLITE PANEL SYSTEM Prefabricated, Lightweight, Outsulation Exterior Wall Panels with Integrated Reinforcing Channels

FEDDERLITE PANEL SYSTEM Prefabricated, Lightweight, Outsulation Exterior Wall Panels with Integrated Reinforcing Channels FEDDERLITE PANEL SYSTEM Prefabricated, Lightweight, Outsulation Exterior Wall Panels with Integrated Reinforcing Channels Fedderlite Panel System Fabrication and Installation Instructions FABRICATION Materials

More information

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS SECTION 270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Communications equipment coordination and installation. 2. Sleeves for pathways and cables. 3. Raceway

More information

Confined masonry. An illustrated guide for masons. This manual explains this technique. Confined masonry. RC frames. Columns first, walls after

Confined masonry. An illustrated guide for masons. This manual explains this technique. Confined masonry. RC frames. Columns first, walls after S D C Confined masonry An illustrated guide for masons This manual explains this technique RC frames Columns first, walls after Confined masonry Walls first, columns after 1. Site selection and form of

More information

Table of Contents. General Installation Guidelines Pages 2-3. Delivery & Staging of Materials Pages 4-5

Table of Contents. General Installation Guidelines Pages 2-3. Delivery & Staging of Materials Pages 4-5 Table of Contents General Installation Guidelines Pages 2-3 Delivery & Staging of Materials Pages 4-5 Installing Aercon Block Pages 6-9 Installing Aercon Vertical Wall Panels Pages 10-15 Installing Aercon

More information

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE:

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE: SECTION 07651 FLEXIBLE COPPER SHEET FLASHINGS Advanced Building Products, Inc. manufacturer many types of flexible copper sheet flashings. Due to their ductility, high tensile strength, and resistance

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

ORDINANCE NO BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BOULDER, COLORADO: CHAPTER 98 - Baled Straw Structures SECTION PURPOSE

ORDINANCE NO BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BOULDER, COLORADO: CHAPTER 98 - Baled Straw Structures SECTION PURPOSE ORDINANCE NO. 5891 AN ORDINANCE AMENDING CHAPTER 10-5, B.R.C. 1981, CONCERNING ALTERNATIVE BUILDING MATERIALS, INCLUDING ADOBE AND STRAW BALE CONSTRUCTION AND RECYCLED LUMBER. BE IT ORDAINED BY THE CITY

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

Unit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M.

Unit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M. Bill of Quantities Nature of work : Construction of Health Center with 8 rooms (Clinics, Pharmacy, Labs, Fence & Latrines) Location: Shakreen- El Fasher Town- North Darfur State No. Description Qty Unit

More information

SECTION UNIT MASONRY

SECTION UNIT MASONRY PART 1 GENERAL 1.01 SECTION INCLUDES A. Concrete Masonry Units. B. Mortar and Grout. C. Accessories. 1.02 RELATED REQUIREMENTS 1.03 REFERENCE STANDARDS SECTION 042000 UNIT MASONRY A. Unless otherwise noted

More information

SECTION GLASS UNIT MASONRY ASSEMBLIES

SECTION GLASS UNIT MASONRY ASSEMBLIES PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor, equipment and incidentals required to install glass unit masonry as shown on the contract drawings and

More information

Spec Master 5/7/ For each product requiring color and texture selection, provide full size samples.

Spec Master 5/7/ For each product requiring color and texture selection, provide full size samples. SECTION 04812 (042012) MECHANICALLY ATTACHED BRICK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Short Term Programs for Civil Engineering Students (Diploma/Degree) Specialization: Lab Testing

Short Term Programs for Civil Engineering Students (Diploma/Degree) Specialization: Lab Testing Specialization: Lab Testing 1. CE/INT/LAB/01/17 How to test the Aggregate 2. CE/INT/LAB/02/17 How to test the Cement. 3. CE/INT/LAB/03/17 Why do we use fly ash in construction 4. CE/INT/LAB/04/17 How to

More information