1 Resin Aggregate Reinforcement Equipment Resin Bound Gravel

2 Who are PermaPave? PermaPave are a resin bound gravel merchant who supply high-quality aggregates, resins and equipment to both trade and private customers. By sourcing the best materials available on the UK market, PermaPave are able to supply a huge range of different colours, coupled with both UV-stable and non-uv resins, directly to your door. For those who are just starting out in the resin bound trade or simply don t want to bear the cost of purchasing any specialised equipment, we also hire forced action mixers to help make your job as professional as it can be. When you place your order with PermaPave, you will receive ONE invoice from ONE company and when you need to price up your next project, you only need to make ONE call. Make the right call, call PermaPave today! What is Resin Bound Gravel? Resin bound gravel is a technique where an installer mixes a decorative aggregate with a polyurethane resin binder to create a highly-attractive and fully permeable, strong stone surface. This type of surfacing is growing in popularity due to its weight-bearing capabilities, durability and low-maintenance nature, as well as its affordability. Once laid, resin bound gravel does not migrate like loose gravel and does not require re-dressing with sand unlike block-paving. As the gravel is locked-in by the binder, the surface looks as good as the day it was laid for much longer. As the surface is porous and allows water to pass through it and, in turn, soak into the ground, it is fully SUDS compliant. This means that you are likely to have little or no issue with planning permission if looking to rejuvenate an existing block-paved, tarmac or concrete driveway. For more information, contact our helpful and friendly team. How is it supplied? How do I size my project? We understand that it can sometimes be difficult to get materials for a project priced up when there s not a great deal of information available regarding what you need to complete the job. At PermaPave, we have tried to take some of the mystique out of material ordering and we supply all of our resin bound gravels in fixed pack sizes. This way, you get exactly what you need without the worry or fuss. Our resins are supplied in a 6.5 or 7kg drum which consists of two buckets, part-a and part-b. These two parts should be mixed to activate the resin and causes the surface to become hard when it has fully cured. Our decorative gravels are supplied in two different bag sizes: 25kg and 12.5kg. The bag size will depend on the colour and size of gravel you have chosen and in order to provide the most stable and strong surface, gravel of two different sizes should be used. Our kits allow for this and the packs are supplied with two different sizes of gravel to give the best mix of strength and permeability. Our resin bound gravel packs are supplied based on a coverage of 3m 2 per pack based at a typical surface depth of 18mm. This can be reduced to 15mm for footpaths. In order to work out how many packs you need, simply measure the length and width and multiply them together, rounding the number up to the nearest 3. So for the example above, the 160m 2 driveway will require 54 packs as = and the number has been rounded up to the nearest whole number sales@permapave.co.uk 2

3 Resin Bound Gravel Surface Preparation Existing Surface Removal The first step towards creating a beautifully finished resin bound surface would be to remove any existing block-paving, concrete or tarmac surface. If removing block paving from the area, the blocks may be recycled later by using the bricks as edging around the installation should this be a desirable style of edging. If there is no existing surface in place, you may skip this process. Excavation Once the existing surface has been removed, the area should be carefully excavated to a depth which is appropriate for the type of installation carried out. Advice should be sought on the required depth for your particular installation, taking into account the firmness of the ground and the total weight of traffic using the surface. A recommended minimum depth would be to excavate to 220mm. Install Perimeter Edging Around the edges of the installation, an appropriate load bearing edging should be installed. We recommend products such as pre-cast concrete kerbstones, block-paving bricks or plastic lumber which do not rot over time and provide a solid edge around the installation. These should be installed according to the relevant manufacturers instructions however if guidance is needed, please contact our helpful team who will happy to advise on other suitable products. MoT Type 3 Once the perimeter edging has been installed properly and securely, then a base layer of MoT type 3 should be laid at the required depth. The minimum recommended depth of hardcore should be 150mm but this depends on a number of factors including sub-grade stability and intended use for the surface. This layer of MoT should be compacted using a roller or vibro-plate (whacker) to ensure the base is consolidated. If you need advice regarding the sub-base thickness, please contact us sales@permapave.co.uk

4 Resin Bound Gravel Surface Preparation Lay Geotextile Membrane Once the MoT layer has been laid and compacted, then an appropriate permeable geotextile membrane should be spread across the top. This membrane should be of a weight of no less than 110 grams per m2. Any joins should have a 100mm overlap and should be fixed into place with either plastic fixing pegs or galvanised steel U-Pins. This will ensure the optimal suppression of weeds as well as keeping the build-up layers separated and will negate sand wash-out. Sand Bedding Layer After the geotextile membrane layer has been laid and secured, a bedding layer of sharp sand should be laid at approximately 10mm in depth, the upper surface of which should be completely level and checked with a spirit measure. This is not a fixed depth as this layer is intended to smooth out any undulation present in the hardcore layer, the depth may vary slightly. This bedding layer can be lightly compacted using a whacker plate. Lay Reinforcement Layer After the sand has been spread and compacted lightly, the area should be covered using a suitable ground reinforcement layer. This can be of a tarmac, concrete or X-Grid ground reinforcement grid type. We recommend the use of X-Grid as there is no time wasted between laying the reinforcement layer and floating the resin as there is no curing needed unlike concrete or tarmac. Contact us for more details. Tarmac should be laid at >50mm depth and concrete at >80mm depth. X-Grid Limestone Fill If using X-Grid as your reinforcement layer, the grid should be filled with limestone chippings with a diameter of no larger than 20mm. Care should be taken to ensure that as much excess dust is removed from the limestone as possible. Gravel requirement can be calculated by: Once evenly distributed across the whole X-Grid layer, the limestone and grid should be lightly compacted using a light vibration plate (whacker) to ensure it is sufficiently bedded into the sharp sand and that the limestone fill is as level as possible sales@permapave.co.uk

5 Resin Mixing Checking Materials As there are several components required for a resin bound gravel installation, prior to commencing work on mixing the aggregate materials such as the decorative aggregates, the resin buckets and sand should all be split into complete mixes to save time and negate mistakes when adding the components to a mixer. Components should be separated and mixed to this formula: 3qty 25kg Large Grade Gravel (e.g. 2-5mm) 1qty 12.5kg Small Grade Gravel (e.g. 1-3mm) 1qty 2-part bucket resin (Part A & Part B) 1qty 6.25kg Chelford 52 Sand By working in this way, you will have no surprises towards the end of your job as you ve counted all the bags already and ensured they re mixed to the correct formula. All bags of aggregate should be stored in a dry location as any moisture within the aggregate will affect the overall finish of the resin and may cause instability. Mixing the Aggregate Once the two-part resin has been mixed, ensure that all four bags of decorative gravel have been added to the forced action mixer and allowed to dry-mix for seconds to remove any excess dust. With the mixer in operation, slowly add the complete bucket of mixed resin to the forced action mixer pan. Tip: If using a forced action mixer with a safety grille over the pan, try using a funnel to add the resin into the mixer to reduce the resin build up on the mixer. Once the complete bucket of resin has been added to the mixer, wait for 30 seconds and gradually add the full bag of sand to the mix. Take care not to add too much, too quickly as this can become clumpy and form worm-casts on the surface of the installation. By adding the sand to the mix, the surface will have a non-slip finish which will not squeak underfoot, as well as making the mix incredibly strong. The components should be combined in the mixer for around two minutes in total and normally has a consistency of porridge. Tip: To ensure the optimal finish and to avoid any surface texture differences, all batches should be mixed for the same amount of time. Mixing the Resin When you are satisfied that all of the materials are present and sectioned into individual mixes, it s time to start mixing the resin components. After opening the tubs containing both parts of the resin, mix the resins by pouring the part A component into the part B bucket and mix for around 30 seconds using a motorised paddle mixer until the mix turns to a creamy consistency. While the resin is mixing, we recommend adding the aggregate to the forced action mixer and allowing it to be mixed dry for seconds to remove any dust which may have gathered on the aggregate. Be careful not to over-mix the resin and to mix each batch for the same period of time, using the same method to give the most consistent finish after the screed has cured. Laying the Mix Once all the components have been mixed for the allotted time, empty the mixer pan into a series of buckets or, ideally, a wheelbarrow and tip onto the general area, working from the furthest edge backwards towards your exit. These piles can be roughly raked to distribute the mix before being trowelled down. Wipe a trowel with a suitable cleaning agent (often white spirit is used) which will stop the resin from sticking to the trowel. Using the tool, press down on the resin mixture, compacting it to the sub-base and spreading it to an even 18mm depth. Tip: The use of batons may help with the even distribution and to provide a consistent depth across the surface. Each complete pack should cover approximately 3m 2 at 18mm deep. For different depths and spreading rates, please see the table in the technical information section. The closest edge should be left fluffed up and uncompacted until the next mix is ready, to help with the seamless overlap of the two mixes. If left too long between mixes it is possible that there will be darker lines as one mix has partially cured before the next has been laid next to it. Dependent on weather conditions, the resin mix starts to cure almost immediately and you will have around minutes per mix to screed the resin to the required level. This may come down to 10 minutes during warm weather sales@permapave.co.uk 5

6 Further Information Curing Times The time it takes for a surface to cure is dependant on a number of factors including screed depth, type of resin (UV or non-uv), air temperature, ground temperature and relative humidity. This means that calculating an exact curing time is incredibly difficult. The resin starts to skin and cure as soon as both parts are mixed together and a method should be used to ensure that mixes are barrowed to the site when they are needed and that the wetedge does not start to dry before the next mix is ready to screed. Generally, the surface is tack-dry within four hours of laying and may be ready for foot traffic. If the surface is to be driven on, it is recommended that 24 hours should elapse before driving a vehicle on the surface. If possible, all installations should be afforded the full 24 hour curing time before use. UV Stable vs. Non-UV There are two main types of polyurethane resin which are used for resin bound surfacing. The two are known by a variety of different names such as: standard, UVR, aliphatic, aromatic, UV stable, nonstable and other manufacturer specific names. The differences between the two are as follows: Non-UV Stable (aka aromatic, standard resin) is the least expensive resin which has a slightly more yellow tone and gives a honeylike tint to the aggregate with which it is mixed and will slightly yellow over time with the effects of UV rays from daylight. UV-Stable (aka aliphatic, UVR) is a premium resin which is clear and resistant to the effects of UV rays from daylight. This should be used in situations where the natural colour of the aggregate is to be retained or to negate the honey tones produced by gravel mixed using a standard aromatic resin. Technical Information Spreading Rates Depending on the intended purpose for the surface, the top resin bound layer depth can be adjusted, meaning each pack can cover a different surface area depending on the thickness. For a guideline on the required thickness, please see the table below: Application Thickness (mm) Coverage (m 2 ) Pedestrians Domestic Vehicles 18 3 Commercial Vehicles Laying Conditions The weather during an installation can have a huge impact on the success of a resin bound gravel installation. Resin bound gravel should only be laid in dry conditions and optimally between o C. Below this temperature the resin may not cure and above this temperature the resin will cure too quickly to maintain a wet edge. Be aware that applies to both ground and air temperature. Sub-grade Strength/Ground Condition In order to work out the required depth of MoT type 3 to install as a sub-base, you must first calculate the CBR value of the existing soil present at the proposed site. Use the below table to indicate the stiffness of the ground before using the table on the following page to determine the sub-base thickness required. Consistency Indicator Strength Very Soft Soft Medium Firm Stiff Tactile (feel) Visual (observation) Mechanical (test) CBR CU Hand sample squeezes through fingers Easily moulded by finger pressure Moulded by moderate finger pressure Moulded by strong finger pressure Cannot be moulded but indented by thumb Man standing will sink >75mm Man walking sinks 50-70mm SPT % kn/m 2 <2 <1 < Around 1 Around 25 Man walking sinks 25mm Utility truck ruts 10-25mm

7 Technical Information Sub-base Depth The MoT type 3 hardcore sub-base depth will vary from project to project dependent on the volume and weight of the traffic using the surface as well as the ground stiffness. See the table below to work out the required sub-base depth, for determining the CBR value of the existing sub-grade soil please refer to the table Sub-grade Strength/Ground Condition : Application Load CBR % MoT Type 3 (mm) Fire trucks, coaches & occasional HGV access Light vehicle access & overspill car parking >6 =4<6 =2<4 =1<2 >6 =4<6 =2<4 =1< X-Grid Fill If using X-Grid as a sub-base layer in place of a tarmac or concrete base, the grid should be filled with a suitable and appropriate medium to provide maximum stability and durability of the installation. We recommend filling the X-Grid with angular gravel with a stone diameter of up to 20mm. Limestone chippings are a cost effective and suitable choice for the fill, however it can be substituted for another material which meets this criteria. Once the grid has been filled, we highly recommend the use of a vibrating plate compactor (whacker) to consolidate the gravel and help the X-Grid to bed into the sand layer below. If you are in any doubt regarding your choice of gridfill material, please seek advice from our helpful and knowledgeable team. Preparing Existing Base If installing resin bound gravel onto an existing concrete or tarmac base then there is a little work to be done to ensure that the base is sound and suitable for use. Firstly, the surface should be carefully inspected for cracks, crumbling, algae, weeds and other debris. If cracks are present then these should be cut into a V shape to prevent the crack from reflecting upwards into the resin surface. Porous or open grade concrete surfaces should be coated with a primer product in accordance with the manufacturer s instructions to enable a cohesive bond with the resin and to prevent degradation. Picture shows a crack in concrete which has been chase-cut into a V shape sales@permapave.co.uk 7