SHOT I Workshop. BalloonSat Construction, Integration, & Test

Size: px
Start display at page:

Download "SHOT I Workshop. BalloonSat Construction, Integration, & Test"

Transcription

1 SHOT I Workshop BalloonSat Construction, Integration, & Test 1

2 2

3 - Your team will have 45 minutes today and 140 minutes tomorrow to do the following: - Layout and construct BalloonSat structure - Insulate structure - Integrate and test systems - Install switches - Secure and organize wiring - Install flight string attachment tube 3

4 - BalloonSats are commonly made of foam core - Foam core is a simple, low cost composite panel - You will use hot glue and Xacto knives to create your box - There is a OK way of building with foam core - Cut individual pieces and glue them together - This way works but is not the best and requires more belts and suspenders 4

5 BalloonSat Construction: - There is a BETTER way of building with foam core - Requires algebra and geometry - See paper in back of your course book -

6 BalloonSat Construction: - When cutting foam core, remember you are cutting through three layers - Best to cut each layer individually - Go slow, use metal edge ruler - Be mindful

7 BalloonSat Construction: - Step 1: Layout box design on foam core sheet

8 - For sake of time, each team will be given a pre-traced foam board (black with labels) 8

9 BalloonSat Construction: - Step 2: Cut it out

10 - Draw center lines between inner and outer lines - All edge cuts are at 45 degree angles to the centerline - Cut inside edges first and only through top paper and foam not bottom paper (hinge) - Cut outside edges last but all the way through - Go Slow Video here

11 - Cut holes for solar cell, switches, and temp probe - Cut hole through center for balloon attachment tube - Tube hole should not be on open side

12

13 BalloonSat Construction: - Step 3: Practice integration and make modifications

14 - Hold box together and figure out how much insulation you want to use. Will affect how your components sit in box

15 Hands-on: Construction and Integration - Balloon attachment tube hole should run through center of box on nonopening side - Make hole diameter as close to tube diameter as possible - Secure with paper clip - Make sure paper clip does not interfere with inner diameter

16 BalloonSat Construction: - Step 4: Glue it together and strengthen corners - Your template was designed using the Better Method

17 - When you think you have everything where you want it, glue you box together - After gluing, it would be a good idea to cover you BalloonSat seams with aluminum tape, especially around seams. - Please don t go overboard, weight is still an issue

18 BalloonSat Construction: Resources in the Room: - Construction examples in the room - Two HOBO launching stations - Two Soldering stations - Four voltmeter stations - One weigh-in station - ½ and ¼ foam insulation - Velcro - Tape - Helpers - Peace and love

19 BalloonSat Construction: Things to remember: - Camera aperture and sensors 19

20 BalloonSat Construction: Things to remember: - Switches 20

21 - Install switches to box and glue switches in place from back side before making electrical connections - Keep switches on both sides and label ON/OFF positions - Make sure to re-connect to heater and 12 V 21

22 BalloonSat Construction: Things to remember: - Flight tube integration - Temperature probe (metal outside) - Launch day access - Testing 22

23 - Install Solar Cell, must disconnect from HOBO 23

24 24

25 - Integrate camera system - Verify camera settings - Integrate Flight String attachment tube and test clearance with sample string - Integrate HOBO system - Launch Pressure HOBO - Install temp probe (channel 4), metal tip must extend beyond wall of structure 25

26 - Install voltage cable (channel 3) - Install Heater - Test switches (will use one picture) - Tape in off position - Label outside box - Bring to Chris for inspection and weigh in - Have team picture taken 26