1 Los Angeles Area Council Boy Scouts of America 2012 FLSR FIX N FUN PROJECTS MAY 25-27, 2012 CAMP PEPPERDINE MAINTENANCE CREW OF (2 DAYS) Sweep interior of all buildings. Sweep roofs and rake around all buildings for fire clearance. General clean up, pressure wash/campsite, raking as time permits. Provided: Roll off, brooms and rakes, wheel barrels, ladders, pressure washer and garden hose. BIG HORN/CIRCLE X RIFLE RANGE PLATFORM RECONSTRUCTION CREW OF 6 TO 8 ADULTS (2-3 DAYS ) SKILLS - YES Remove floor planking, install concrete piers, cement around piers, install new 6 x 4 supports and re-plank floors. Major project or call us for more information. Provided: Skill saw, cement, cement mixer, shovels, wood, generator, hammers, nails and jacks. TRAIL TO SHOTGUN RANGE- BIG HORN/CIRCLE X CREW OF (2 DAYS+) TROOP PROJECT FOR FOLLOW UP AT SUMMER CAMP Construct Path and install steps from Pepperdine Road to Range Call us for plan and details. Provided: 24 railroad ties, saws, shovels and reinforcing rod to secure step. 1

2 ROAD GATEWAY REPAIR HOOK CREEK ROAD ENTRANCE CREW OF 2-3 (1/2 DAY) SKILLS SOME NORTHROP BUILDING MAINTENANCE CREW OF 6 TO 8 (1/2 DAY) NORTHROP RESTROOM BUILDING INTERIOR PAINTING (2 DAYS) CREW OF 4 TO 6 Re-mortar Damage gateway post. Provided: Mortar pan, trowels, mixing hoe, shovel and 8 sacks of mortar mix. Fire Clearance and raking around all building, sweep and pressure wash interiors of restrooms and sweep roofs. Provided: Rake and shovels, brooms, ladder, garden hose and pressure washer. Pressure wash, scrape, sand and paint. Provided: Step ladders, pans, rollers, drop cloths, brushes, gloves and white enamel paint. POLLOCK ELECTRICAL SWINIS AND MODOC CAMPSITE CREW OF 2 OF 3 (1 DAY) SKILLS REQUIRED Re-pull #10 wire to Siwinis restroom. Remove excess old electrical conduit; repair and check plugs in Modoc Campsite. Call / us for details. Provided: Wire POLLOCK TRAINING CENTER EROSION CLEAN UP & CONTROL CREW OF 6 TO 8 (1/2 DAY) Remove dirt and silt from area behind kitchen training center, transformer, etc. Place straw on bank. 2

3 Provided: Shovels, wheel barrels and straw. Needed: Work gloves. POLLOCK ADMINISTRATION TO TRAINING CENTER WALKWAY WALK REPAIR CREW OF 2 TO 3 (1/2 DAY) Repair concrete walkway. Provided: Cement, sand, shovel and trowel. BIG HORN/CIRCLE X STAFF CABINS INTERIOR PAINTING CREW OF 3 TO 5 OLDER SCOUTS AND ADULTS (2 DAYS) ACTIVITY LEVEL-MODERATE BIG HORN/CIRCLE X WOOD GUARD RAILS HANDICRAFT/BRIDGES AND CAMPFIRE BENCHES, ETC. CREW OF 3-6 (2 DAYS) Paint interior wall of staff cabins Navajo white. Provided: Paint, drop cloths, pans, rollers, paint brushes, step ladders and gloves. Apply preservative to wood guard rails, bridges and campfire benches after prepping surfaces. Also apply oil to benches at Scoular Chapel and other benches throughout camp. Provided: Brooms, wood guard, bushes, drop cloths and gloves. BIG HORN/CIRCLE X DIRT REMOVAL AROUND SWIMMING POOL FENCE CREW OF 8 10 (1 DAY) Remove silt and dirt from fence and adjacent areas. Provided: Shovels and wheel barrels. 3

4 BIG HORN/CIRCLE X DINING HALL GUARD RAILS, FENCING AND FACIA BOARD CREW OF 3-5 ADULTS/STAFF (1 DAY) /HIGH BIG HORN/CIRCLE X DINING HALL MAINTENANCE CREW OF 4-6 STAFF (1/2 DAY) COPE TRAINING ASSISTANCE /HIGH BIG HORN/CIRCLE X TRAIL FROM POOL HOUSE TO HORSE CORRAL CREW OF (1 Days) Operate high lift equipment. Apply preservative to expose structural beams, quad side and fascia board driveway side. Must have no fear of heights. Provided: Ladders, safety harness, brushes, dark brown stain, sand paper; and high lift equipment. Operate high lift equipment, change light bulbs in ceiling, clean and vacuum rafters and interior roof. Must have no fear of heights. Provided: Lift equipment, blower/dusters, vacuum, safety harness, ladder/broom and scaffolding Relocate Trail from canyon bottom and improve existing trail. Provided: Shovels, trail tools, etc. Needed: Work gloves, hats, and water bottles. PROJECT RESERVED BY TED HARTLEY POLLOCK COMMISSARY SHED CREW OF 2 (1 DAY) ACTIVITY LEVEL MODERATE Paint exterior of compressor shed with green paint and metal door with dark brown Rust-oleum (same color as Commissary). Provided: Paint brushes, rollers, gloves, covers, pans and step ladder. 4

5 POLLOCK AND BIG HORN/CIRCLE X CAMPSITE PLATFORM LEVELING CREW OF (2 DAYS) Level platforms on concrete blocks and wooden cut logs in Tombstone and Abilene campsites. Provided: Shovels. Needed: Work gloves. POLLOCK CAMPFIRE REPAIR CREW OF 3-6 (1 DAY) SKILLS YES Repair stage backdrop and benches. Clean up campfire area. Provided: Saws, hammers, nails, screws and drills. Needed: Generator desirable MAINTENANCE BUILDING COUNCIL PROPERY MANAGEMENT SYSTEM DATA ENTRY CREW OF 2 (2-3 DAYS) ACTIVITY LEVEL-LOW SKILLS COMPUTERS Inventory items in Maintenance Building and enter into system. Provided: Laptop POLLOCK AND BIG HORN/CIRCLE X BULLETIN BOARDS CREW OF 3-4 (1-2 DAYS) (BUILT AT MAINTENANCE) SKILLS CARPENTRY SKILLS Construct and install additional bulletin boards (14). Provided: Skills saw, power drills, hand tools and power post digger. POLLOCK AND BIG HORN/CIRCLE X PLYWOOD DISTRIBUTION CREW OF 8-12 CAMPSTAFF (1 DAY) Move plywood from storage to campsite start at Big Horn Circle X. Provided: Stake bed truck. 5

6 MAINTENANCE YARD TABLE REPAIRS AND PAINTING CREW OF 6-10 (1-2 DAYS) ACTIVITY LEVEL MODERATE BIG HORN CIRCLE X AND NORTHROP ROOFING REPAIRS CREW OF 4-6 (1 DAY) ADULTS CIRCLE X LOWER YUMA CAMPSITE BRIDGE RAILING CREW BIG HORN CREW OF 3-5 (1 DAY) ACTIVITY LEVEL-MEDIUM SKILLS YES CARPENTRY Repair and paint tables after repairs. Transport tables to and from maintenance yard. Provided: Bolts and nuts, skills saw, drills, drop cloths, gloves and paint sprayer. Repair and re-roof as needed Big Horn Rifle Range, Big Horn Friendship Shed, Northrop Cabin Provided: Asphalt singles, roofing paper, nails, hammers, caulking. Install 2 x 6 / 4 x 4 post railings on bridge section. Precut and pre-assemble at maintenance yard. Provided: Skill saw, power drill, wrench, screws and nuts. MAINTENANCE AREA COT REPAIR CREW OF 6-8 (1 DAY) ACTIVITY LEVEL-LOW Repair and salvage cots. Provided: Cot covers, wrenches, cot bolts and nuts. POLLOCK TRAINING CENTER WINDOW WASHING CREW OF (1-2 DAYS) ACTIVITY LEVELE-NONE Washing windows Training center administration building also Big Horn Circle X Vinzant Center. Provided: Window washing supplies. 6

7 BIG HORN/CIRCLE X RIFLE RANGE PROGRAM AREA REPAIRS CREW OF 3-4 (1-2 DAYS) SKILLS-SOME HEALTH LODGE HOT WATER HEATER HOUSING SEALING OR REMOVING CREW OF 2-3 (1DAY) ACTIVITY LEVEL MODERATE SKILLS CARPENTRY POLLOCK STAFF HOUSING- ASSEMBLY OF PRE-FABRICATED HOUSING CREW OF (2-3 DAYS) ACTIVITY LEVEL MODERATE TO STRENUOUS SKILLS CONSTRUCTION POLLOCK MAINTENANCE ADMINISTRATION BLDG CREW OF 3 TO 5 ( ½ DAY ) Repair fencing and seating logs. Oil floor boards and vertical posts. Provided: Fencing materials, post digger, brooms, wood guard, bushes, drop cloths and gloves. Seal or raze abandoned hot water heater connected to Health Lodge. Provided: Hammers, screws, crow bar, caulking and lumber. Level area and assemble prefabricated housing near Pollock Pool House. Provided: Hammers, screws, screwdrivers, shovels, caulking and lumber. Remove leaves and winter debris from rear of Admin Building. Remove silt and dirt and clean drains north westerly of fireplace. Provided: Wheel barrel, shovels and rakes Needed: Work gloves. 7