1 RESUME SENIOR CONSTUCTION MANAGER PERSONAL DETAILS NAME: NATIONALITY: OTHER INFORMATION: Thomas John Johnston Australian Holding Current Australian Passport Non-Smoker. KEY ABILITIES Project Manager; Study Manager; Construction Manager and Civil Engineer with over 35 years professional project management experience. Highly developed concept and strategy development skills in the mining and civil earthworks. Demonstrated ability to Manage and supervise teams through all project phases comprising technical staff, design office staff and all levels of construction personnel. Demonstrated ability to integrate and undertake systems of visible felt leadership in all aspects of construction safety through concept, development and project execution. Demonstrated ability to incorporate relevant Safety requirements into detailed design for operation and constructability. Demonstrated ability to appreciate and focus on Client big picture objectives in relation to projects and develop relevant fit for purpose, safe and environmentally compliant options within the constraints of budget. High level of strategic, analytical and planning skills with ability to think outside the immediate bounds of a problem to develop technical or managerial solutions. Strong management and leadership skills with proven ability to make decisions to achieve critical objectives. High level of communication skills with an ability to interact with all levels of corporate, management and operations personnel. RESUME ~ John Johnston ~ Page 1 of 10 Current as of 22/10/14

2 KEY EXPERIENCE CATAGORIES Experience in Major Project development and management through concept, Design and Construction. Safety & Environmental management, implementation and integration into project development and construction. Economic and Costing development for project viability, with strong emphasis on civil, earthworks and infrastructure for the mining and O&G industrial sectors. Project and Construction Management, Engineering Management, Critical Path Planning, Budget and Estimate preparation & control, demonstrable experience through all project development phases. Tender and Contract preparation, execution and closeout for all areas of execution, engineering, logistics, procurement and construction/commissioning. Engineering and Management experience in Civil, Mining and Gas fields Concept development and Construction Management of Marine in fracture - main wharves, construction wharves, general infrastructure, access and haul roads, laydown and warehousing facilities and camps. RECENT SUMMARY OF WORK HISTORY FOR T. J (John) JOHNSTON Role Dates of Service Project Senior Construction Manager and Senior Construction Engineer July 2010 to Current APLNG Upstream Gathering Area Manager Earthworks (Integrated Owners and CEMP December 2008 to July 2010 Koniambo Nickel Mine (KNS) Team) Area Manager Earthworks and Marine (Integrated Owners and October 2008 to December 2008 Koniambo Nikel Society (KNS) CEMP Team) Site Manager (Owners Team) April 2008 to October 2008 Koniambo Nikel Society (KNS) Superintendent Civil Works (Owner s Team) October 2007 to April 2008 Koniambo Nikel Society (KNS) Senior Civil Engineer June 2007 to September 2007 Hatch Project Delivery Group Senior Project Engineer April 2007 to May 2007 Gold Coast Desalination Alliance Plant Construction Manger with ECM Contractor (Parsons Brinckerhoff) July 2005 to March 2007 Moura Coal Mine Expansion Area Manager and Senior Project November 2004 to July Hail Creek Coal Mine RESUME ~ John Johnston ~ Page 2 of 10 Current as of 22/10/14

3 Engineer with EPCM Contractor (SKM) Senior Project Engineer Senior Project Engineer (Goro Nickel) Senior Civil Engineer (Inco) Senior Civil Engineer (Bechtel Technip Hatch) 2005 Expansion Project May 2004 to November Highlands Kainantu 2004 Limited Gold Mining Project PNG October 2003 to May Goro Nickel Project 2004 February 2003 to Goro Nickel Project October 2003 April 2002 to February Goro Nickel Project 2003 WORK EXPERIENCE HISTORY July 2010 to Current APLNG CSG Project Sigma Engineering Brisbane & West QLD Sites Position: Senior Construction Manager and Senior Construction Engineer Working in house in Brisbane with Origin Energy on the Central Queensland APLNG Coal Seam Gas Project. This part of the project, Phase 1, includes the upstream gas gathering system with over km of HDPE water and gas pipes, plus over km high voltage and low voltage electrical and communication network, associated with over 1100 well sites. As Senior Construction Manager conducted constructability reviews, unit rate analysis, design reviews on a regular basis and construction supervision of Tier 1 contractor. Visible felt leadership in Construction safety on site Safety reviews of designs Tender reviews were undertaken of submissions from tier 1 and tier 2 Contractors including having the tenderers complete some early works as part of their review process. Planning and associated contractual documentation (Basis of Design, Technical Specification, Scope of Work) for two 350 person construction villages. RESUME ~ John Johnston ~ Page 3 of 10 Current as of 22/10/14

4 Dec 08 July 2010 Koniambo Nikel Mine (KNS) KNS New Caledonia Position: Area Manager Earthworks (Integrated Owners and CEMP Team) From start of December 2008 all Earthworks, approximately 7.7 million m3, to be carried out as a self perform activity by the integrated team using local sub contractors. Responsible for construction of all earthworks with a team which included approximately 300 machines and approximately 70 supervisory and support stall; Oct 08 - Dec 08 Koniambo Nikel Mine (KNS) - KNS New Caledonia Position: Area Manager Earthworks (Integrated Owners and CEMP Team) Scope of work included Approximately 8 million m3 dredging, Construction of Man Wharf and Construction Wharf, and approximately 7.7 million m3 earthworks April 08 Oct 08 Koniambo Nikel Mine (KNS) - KNS New Caledonia Position: Site Manager (Owners Team) Owners Team Responsible for Owner s Construction Team on site and oversight of all of the EPCM Contractor s team Oct 07 April 08 Koniambo Nikel Project (KNS) KNS New Caledonia Position: Superintendent Civil Works (Owners Team) Owner s team responsible for oversight of EPCM Contractors team relating to Earthworks and Marine (scope of work referred to above) RESUME ~ John Johnston ~ Page 4 of 10 Current as of 22/10/14

5 June 07 - Sept 07 Hatch Project Delivery Group Brisbane Position: Senior Civil Engineer Developing Port concepts on Nautilus project (3 locations in PNG). Reviewing port concepts Bahodopi and Halmahera projects (2 locations in Indonesia) Special emphasis on catering for project modularization in all sites. Senior Civil Engineer, Koniambo Nickel Project, New Caledonia. Working onsite with client to develop early works program that maximizes input from local community in terms of plant and equipment and personnel hire April 07 May 07 Gold Coast Desalination Alliance Plant Gold Coast, Australia Position: Senior Project Engineer Reported to Civil Construction Manager. Prepared a range of subcontracts for various construction activities. Advised on constructability and risk assessment issues. July 05 March 07 Moura Coal Mine Expansion Moura, Central Queensland Position: Construction Manager with ECM Contractor Approximately A$ 1 billion, initially Area Manager and then, from September 2005, Construction Manager with ECM contractor Parsons Brinckerhoff. Reported to Project Manager in an Integrated Anglo Team. Responsible for a team of 10 persons involved in the supervision of Building and Civil Contractors with a budgeted scope of works of approximately A$ 160 million. Scope includes 288 room expansions to existing single person quarters, new 500 room construction camp (including mess and other ancillary requirements) $36 million Mine Industrial Area offices and workshops, constructing Highway intersection works, new haul roads; dump stations, general earthworks and 36 km of water pipe lines and H V power lines. RESUME ~ John Johnston ~ Page 5 of 10 Current as of 22/10/14

6 Nov 04 July 05 Hail Creek Coal Mine Expansion Project West of Mackay - Central Queensland Position: Area Manager with EPCM Contractor Rio Tinto s Hail Creek Coal Mine expansion project, approximately $ 360 million. Area Manager (Civil and Infrastructure) and Senior Project Engineer (Design) with EPCM contractor Sinclair Knight Merz. Reporting to Construction Manager. Responsible for supervision of Contractor constructing A$ 3 million coal co disposal area and return water dam. Also responsible for supervision of contractors involved in all other civil works and camp building program. Design of new haul roads. May 04 Nov 04 Highlands Kainantu Limited Gold Mining Project - PNG PNG Engaged as: Senior Project Engineer Position: Senior Project Engineer Reporting to Construction Manager. Responsible for supervision of Contractor constructing A$ 4 million tailings dam, responsible for supervision of contractors involved in camp building program. In addition direct control of a team of 20 building personnel including supervisors and tradesmen. Oct 03- May 04 Goro Nickel Project Brisbane Project Office with Extension to Site Position: Senior Project Engineer Senior Civil Engineer Design and Construction working on site with Goro Nickel SA at their Nickel mine and process plant in New Caledonia. Responsible to Construction Manager for preparation of technical reports, design associated with US$ 2 million interim works program and other work as requested. Also responsible for supervisors of day labour and contract activities. Represented Construction Manager during periods of his absence. Feb 03 - Oct 03 Goro Nickel Project RESUME ~ John Johnston ~ Page 6 of 10 Current as of 22/10/14

7 Brisbane Office Position: Senior Civil Engineer (Inco) $US 1.8 billion total project value. Significant roles and areas of involvement included: Deputy Study Manager Civil Engineering, Quantity Review Team (February to March) Carried out in association with the Study Manager, a review of quantities in the previous project estimate and established new benchmark quantities; Prepared planning and scheduling activities for Quantity reviews and monitored team progress against agreed schedule. Deputy Study Manager Civil Engineering, Design Review Team (March to June), Port and Infrastructure Carried out, in association with the Study Manager, a review of the previous design for the Port and associated infrastructure; My team was responsible for creating an alternative design for the Port and associated infrastructure. Combined savings, including Bulk Liquid and Solids handling facilities, amounted to approximately $US30 million. Supervised marine and geotechnical sub consultants. As Deputy Study Manager, Port, Infrastructure and Services (June to October) participated in the development of an Early Works program in the following areas: Civil engineering design input into Services, Sewerage Design, Fire Water and Potable Water distribution, Bulk Fuel Storage in conjunction with Lead Piping and Mechanical engineer. Civil engineering input into Quarry development, reactivation of Concrete Batch plant, the construction wharf and associated laydown area. Planning and schedule development of all associated activities necessary to complete this component of the Early Works program. Assisted Project Manager, in the preparation of BOOT expression of interest and scope of work, document for the Port Bulk Liquids and Bulk Solids Infrastructure. Assisted Project Manager in the preparation and assessment of tenders for the transportation of the Acid Plant pre-assembled modules to site in New Caledonia. This included assessment of required Civil Engineering works and the preparation of cost estimates to carry out the work. Field trip to New Caledonia with prospective bidders to assess extent of work required. April 02 - Feb 03 Goro Nickel Project RESUME ~ John Johnston ~ Page 7 of 10 Current as of 22/10/14

8 Brisbane Office Position: Senior Civil Engineer (Bechtel Technip Hatch) Responsible for creating and updating the earthworks mass balance for the project. Area Civil Engineer for the civil engineering design associated with the Port area, Bulk Liquids and Bulk Solids. Directed designers. Designed major drainage system around Port Yard. Supervised geotechnical sub consultants assessment of sedimentation pond requirements. Assisted the Permitting group with production of relevant drawings and commentary for inclusion into Permit applications. Also acted as one of two liaison engineers between the Engineering group and the Permitting group. Prior to April 2002 Projects: Various Engagements - Queensland Queensland Senior Engineering Consultant - working in-house on concept designs for major projects in Roads and Traffic Planning Section, Ipswich City Council during calendar years 2001 and 2000 Mining Consultant - Idemitsu South Queensland Coal and Contractors. Advised contractors on construction of coal storage pads, supervision of contractors, advised on repairs to coal storage pads, designed coal haulage roads around washing plant, designed concrete hard stand areas washing plant, advised on Civil Engineering maintenance program Consultant - During 1998 (approx. 12 months) Senior Engineering Consultant working in-house in charge of Ipswich City Council Infrastructure Delivery Section, comprising two Technical Officers and one Administrative Assistant. Responsible for delivery of Council s Capital & Rehabilitation Works Budget, circa $16 million. Also responsible for final design review and my signature was required on all design plans Consultant - From December 1998 January 1999, Senior Engineering Consultant working in-house as Acting Deputy Works Manager (Design, Survey, Infrastructure Delivery, Assets Management Sections approx. 60 staff). Also responsible for final design review and my signature was required on all design plans. Consultant - As Study Manager prepared planning report Waterworks Road - $14 million incorporating a pilot study to give buses priority through Brisbane s coordinated traffic signal system RESUME ~ John Johnston ~ Page 8 of 10 Current as of 22/10/14

9 Senior Engineering Consultant working in-house, during 1995 and 1996, with Brisbane City Council, preparing conceptual designs and detailed design briefs for annual major works program of $6 million Consultant - as Study Manager on many projects undertaken by Johnston Consulting, have had specific input into the following areas Initiation, feasibility, design, estimates and job specification, construction supervision, contract administration, acceptance and certification, quality assurance Consultant - Prepared and presented evidence for 12 cases involving various court jurisdictions Consultant / Lecturer Queensland University of Technology (parttime) 1989 to 1992 Senior Traffic Engineer Brisbane City Council 1987 to 1989 Senior Traffic Engineer Ipswich City Council 1978 to 1987 Engineering Surveyor Ipswich City Council 1972 to 1978 Engineering Surveyor Townsville City Council 1972 Engineering Surveyor Johnstone Shire Council 1963 to 1972 ACADEMIC QUALIFICATIONS QUEENSLAND INSTITUTE OF TECHNOLOGY (1987) Graduate Diploma in Environmental and Municipal Engineering QUEENSLAND INSTITUTE OF TECHNOLOGY (1985) Bachelor of Engineering -Civil QUEENSLAND INSTITUTE OF TECHNOLOGY (1977) Certificate in Civil Engineering. DEPARTMENT OF EDUCATION QUEENSLAND (1970) Certificate Engineering Surveyor PROFESSIONAL QUALIFICATIONS REGISTERED PROFESSIONAL ENGINEER QUEENSLAND - NUMBER 2352 TRADE BASED TRAINING & CERTIFICATION QUEENSLAND UNIVERSITY OF TECHNOLOGY (November 2000) Road Safety Audit Course INDUSTRIAL & MANAGEMENT TRAINING RESUME ~ John Johnston ~ Page 9 of 10 Current as of 22/10/14

10 Generic Induction to Coal Mining Surface, 30254QLD - Course 1 - December 2004 Site Safety and Health Representative, 39065QLD - Course (QMS1, QMS2, QMS3) - 29 Nov 2004 Facilitate the Risk Management Process, MNC.G2.A in partial completion of MNC Certificate IV in Coal Operational Management 3 - December 2004 Apollo Root Cause Analysis - October 2006 Practical Erosion and Sedimentation Control COMPUTER SKILLS INTERESTS Fishing, Windows 98, 3.11 & MsDos operating systems. Microsoft Office Suite including MS Project REFEREES On request, position specific ADDRESS: 1137/56 Scarborough Street Southport Qld TELEPHONE / FAX: Mobile (+61) jo74296@bigpond.net.au RESUME ~ John Johnston ~ Page 10 of 10 Current as of 22/10/14