1 MONTHLY PROGRESS REPORT IIM RAIPUR Development of Phase I Campus including building for IIM Raipur at Naya Raipur (PMC by Naya Raipur Development Authority) MONTHLY PROGRESS REPORT AS ON 31 st MAY -2017

2 MONTHLY PROGRESS REPORT CONTENTS 1.0 EXECUTIVE SUMMARY PROJECT BRIEF PROJECT SNAPSHOT STATUS OF PROGRESS OF WORK PICTORIAL STATUS OF WORK

3 SHEET 1 OF 45 A) EXECUTIVE SUMMARY a) Letter of Acceptance has been issued to M/s NCC for the development of Phase I Campus including building for IIM Raipur at Naya Raipur on 18 th Jan 2016 b) NCC has submitted the Performance Guarantee on 25 th Jan 2016 c) Date of commencement : 2 nd Feb 2016 d) Agreement signed on : 11 th Feb 2016 B) PROJECT BRIEF: a) Original total built up area - 76,842 Sqm (Phase I ) (Revised built up area under Phase-IA 61,706 Sqm) b) Total contract value for Phase -I Rs. 305 Crore (Revised scope of work under Phase -1A Rs Crore) c) Name of Contractor: M/s NCC Ltd d) Period of Completion: 24 months e) Stipulated date of completion: 1 st Feb, 2018 C) SCOPE OF WORK: a) Civil & Structural Works b) Ext & Internal Plumbing works c) Ext & Internal Electrical Works d) HVAC Works e) Ext & Internal Fire Fighting Works f) Internal Finishing & Façade Works g) Auxiliary Services like STP, ETP, Area development, Roads etc.

4 SHEET 2 OF 45 D) PROJECT SNAPSHOT Plot No Plot Area Permissi Max. ground Marginal set backs (Sqm.) ble FAR coverage Khasra as per approved master plan % Setback Front: 25 m Side : 9m BUILDINGS UNDER CONSTRUCTION OF PHASE IA S. No. Building / Block No of Floors Area in SQM 1 Admin& Faculty Block G Academic Block G MDC Building Columns up to GF only under Phase -1A 4 Library, Research & Incubation Centre B+G Sports Complex ( In Phase -1A) B Hostel (PGP) 5 Blocks G Dining Hall B+G Director House G Faculty Housing 4 Towers under construction (Columns of towers 5 & 6 up to GF only) G Staff Housing ( 1 Tower ) I BHK G Facilities (Shopping Complex, Facility Centre) G Substation and sewage treatment plant G Total Minor structures such as Gate 1,Gate-2 Covered Pathway etc Grand Total

5 SHEET 3 OF 45 STATUS OF WORKS AS ON 31 st MAY 2017: 1) Mobilization of Resource: About 800 labour available at Site. Tower Crane: Two number of Tower Crane functional Mobile Crane: Three number of Mobile Crane available at site Ready Mix Plant: Ready Mix Concrete Batching Plant Operational (60 Cum /Hr). Procurement of Reinforcement steel : about 600 ton available at site Form Work material : Shuttering material for current requirement is available at site. Site office, Store, Quality Control Lab, Cement godown, Labour camp etc. completed Temporary Power connection to State Electricity Board obtained for construction purpose. Three bore wells are functional at site for construction purpose. Additional requirement is sourced from outside also 2) Actual Progress at site : a) Earth Work in excavation and foundation work completed for all 18 Major buildings under Phase-1A. Terrace Level casting has been completed in 10 Buildings & the rest 8 Buildings are in different stages of construction. b) Block Work completed in 7 buildings, nearing completion in 5 buildings and rest 6 buildings are work in progress. c) Out of 18 Major Buildings under Phase-1A work in 6 buildings are on schedule and rest 12 are lagging behind as detailed below

6 SHEET 4 OF 45 d) External fire fighting, Electrical, HVAC, Internal / External plumbing are nearing completion and Road work in progress. e) Tiling & Kota Flooring started in Faculty & Hostel Blocks 3(a) Progress as per Approved Construction Programme : Sl. No BLOCK No. PLANNED AS ON STATUS AS ON REMARKS Faculty Housing - 4 Faculty Housing - 3 Faculty Housing - 2 Faculty Housing - 1 Finishing Works Finishing Works Finishing Works Finishing Works Terrace Water proofing Internal Wall plastering to be completed Internal Sanitary & Plumbing work of 3rd Floor to be completed Internal Sanitary & plumbing works to be completed Waterproofing Treatment in all WC s & Toilets to be completed Fixing of Door Shutter at 1 st Floor to be started External Painting to be completed Toilet dadooing work to be completed in 2 nd Floor Internal plumbing & sanitation work to be completed Internal Wall Plaster to be completed Flooring work to be started in 1 st Floor Terrace water proofing work to be completed Completed Completed Completed Completed Completed Yet to be started Yet to be started In progress Completed Completed Yet to be started Completed Delay by 7 days Ahead of schedule Ahead of schedule Ahead of schedule Ahead of schedule Delay by 30 days Delay by 20 days Delay by 10 days Ahead of schedule Ahead of schedule Delay by 10 days Delay by 10 days

7 SHEET 5 OF 45 5 & 6 Faculty Housing 5 & 6 Deleted from Scope Ceiling plastering to be completed. Completed Ahead of schedule 7 Hostel - 1 Finishing works Electrical conduiting works to be completed in all floors Completed Ahead of schedule External plastering to be completed In progress-80% completed Delay by 20 days Internal plastering to be completed. Internal Plastering of 4th Floor in progress Delay by 10 days 8 Hostel - 2 Finishing works External Plaster to be completed Work in progress completed -60% Delay by 20 days Internal Plumbing & sanitation work to be completed up to 2 nd Floor Already completed Ahead of schedule Block work to be completed in all floors Completed-95% Delay by 15 days 9 Hostel - 3 Finishing works Toilet Dadoo work to be started Internal Sanitary & plumbing works to be completed upto 2 nd Floor Yet to be started Work in progress in 2 nd Floor Delay by 7 days On schedule Structural work Overhead Water tank slab to be completed Completed On schedule 10 H0stel - 4 Finishing work External Plastering work to be completed Electrical Conduiting work to be completed in all Floors Completed-90% Completed Delay by 10 days Ahead of schedule Internal Ceiling plaster to completed in all floors Completed Ahead of schedule 11 Hostel - 5 Finishing work Internal plumbing & sanitation work to be com pleted in 2 nd Floor Toilet Flooring work to be completed in Gr Floor 1 st Floor in Progress Delay by 15 days Not yet started Delay by 30 days

8 SHEET 6 OF 45 Toilet Dadoo work to be completed in 1 st Floor Not yet started Delay by 15 days Director s Residence Shopping Block Facility Block Finishing works RCC RCC Internal plastering work to be completed. External plastering work to be completed. Over head tank slab concreting to be completed. Internal Sanitary & plumbing works to be completed. Nearing completion External Plaster -95% completed. First floor slab concreting partly completed. Balance portion shuttering under progress. Yet to be started Delay by 7 days On schedule Delay by 40 days Delay by 30 days 15 Sports Block RCC RCC Ground level slab to be completed Internal RCC wall at Basement Level in progress Delay by 45 days 16 Dining Block RCC Over head tank slab concreting to be completed. Ground to First floor columns -50% completed Delay by 70 days Faculty &Admin Block MDC Block Library Block RCC Finishing work RCC Finishing works Over head tank Slab & Top roof beam concreting to be completed. Toilet Flooring work to be completed in 1 st Floor Internal wall Plastering to be completed up to 3 rd Floor Over head tank top slab concreting to be completed. Water proofing treatment to completed in WC s & toilets in Ground Floor slab Over head tank slab Completed, Roof beam completed Yet to be started Internal wall plastering up to 3rd completed - 90% Deleted from the Scope Second floor slab concreting -45% completed. Yet to be started Delay by 10 days Delay by 20 days Ahead of schedule by 20 days Delay by 120 days Delay by 40 days

9 SHEET 7 OF Academic Block RCC Finishing work Over head tank top Slab Concreting to be completed. Flooring work to be completed in 1 st Floor Second floor slab Concreting completed up to 60% & columns of 3 rd Floor completed-50% Yet to be Started Delay by 60 days Delay by 60 days 21 Staff Housing RCC Over head tank slab concreting to be completed Third floor column concreting completed- 70%. Delay by 75 days 22 STP RCC All Foundations to be completed Columns & wall concreting in progress Delay by 90 days 23 Plumbing work External Manhole chambers, pipe laying to be completed Water & Waste water pipe line laying work completed -85% On schedule 24 Electrical External Street Light poles to be erected Work in progress-80% completed Delay by 20 days 25 HVAC External Pipe laying to be started Piping works completed- 85% Delay by 20 days 26 Fire fighting External Pipe laying work to be completed Piping work completed - 90% On schedule 27 Road work External Bituminous & Concrete roads in progress DBM 1 st layer completed On schedule

10 SHEET 8 OF 45 (b) STATUS OF PROCUREMENT OF LONG LEAD ITEMS: Sl No Item of Work Status of approval Vendor Name Date on Expected of technical data which date of sheet PO delivery placed by NCC A. Electrical Works DG Set Yes M/s Jakson Limited Already Delivered 800KVA Substation Compact Yes M/s ABB India Ltd KVA Copper wound Cast Resin Dry Type Transformer Yes M/s ABB India Ltd KVA Copper wound Cast Resin Dry Type Transformer Yes M/s ABB India Ltd KV HT Panel(11 panel board) Yes M/s Crompton Greaves Power & Industrial Solutions Limited KV HT Panel(3 Panel Board Yes M/s Crompton Greaves Power & Industrial Solutions Limited KV Synchronizing Yes M/s Crompton panel Greaves Power & Industrial Solutions Limited 6.3MVA 33/11 KV Yes M/s Crompton

11 SHEET 9 OF 45 Copper Wound oil Type Transformer Greaves Power & Industrial Solutions Limited Passenger Lifts Yes M/s Thyssenkrup Elevator (India) Pvt. Ltd Ring main Unit Yes M/s Schnider Electric Infrastructure Limited B. Fire Fighting Works Fire Pumps Yes Kirloskar C. HVAC Chillers Yes Daiken AHU s& FCU Yes Zeco (Faculty & Admin) AHU s& FCU(Academic Block) Under process Zeco AHU s& FCU Under process Zeco (Library Block AHU s& FCU Under process Zeco (Dining Block) Cooling Tower Yes Paharpur D. Plumbing Works Sewage Treatment yes M/s Aztek Private Plant Ltd Solar Heating System Yes M/s Aditya Solar Energy Pvt. Ltd

12 SHEET 10 OF 45 Water Treatment Plant No M/s Aztek Pvt. Limited E Civil Works Fire rated Doors Under process M/s Shakti Hormann Pvt Ltd (c ) During meeting held on along with Director IIM Raipur, CE(E), NRDA, M/S NCC Limited has agreed for completion of project by 31 st March ) Financial Progress : a. Financial progress in respect of ongoing construction work Rs Crore up to (Net value of work done Rs Crore + secured advance on material at site Rs Crore) Outstanding Mobilisation and plant & machinery advance-rs Crore. b. Percentage Progress : I. With respect to revised tender cost (Rs Crore): / = 36.30% (Financial progress of ongoing work Rs Crore, Revised tender cost = Rs Crore) II. With respect to project cost (Rs. 333 Crore) : / 333 = 31.33% (Approved DPR cost Rs.333 Crore, up to date expenditure Rs Crore) III. With respect to overall project i /c phase -I &II : / = % (Proposed DPR cost Rs Crore, up to date expenditure Rs Crore & advance = Crore)

13 SHEET 11 OF 45 (c ) Project Expenditure Vs Budget (All amount in Crores) Sl No Description Payment already made Bill Raised but payment pending Expenditure Booked so far Balance Amount Total Budget Remarks Agency Item of work Towards Work Done Towards secured advance Towards mobilization advance NCC Ltd Towards tools and plant advance Interest on a/c of mobilisation and T&P advance Bill raised up to Towards Escalation Ongoing work EPF & ESI reimbursement Service tax reimbursement TOTAL TCE Bill payment ( i /c service tax) ARCOP Bill payment ( i /c service tax) Bill raised up to Feb 2017 Bill raised up to April NRDA Actual cost reimbursement ( i /c service tax) Bill raised up to December IIT Delhi Proof Checking Left out work Furniture & furnishing, IT Equipment, Horticulture etc Completed Work Compound wall Grand Total * For other financial details related to M/s NCC Ltd as on please refer last page.

14 SHEET 12 OF 45 d). Payment status of Contractor M/s NCC Ltd. RA Bill Value of Bill in Date of Date of Date of Payment Delay in payment No Rs Crores ( Net value of work done) submission by NCC to PMC submission by PMC TO IIM Payment by IIM in days (Beyond 21 working days) In process RA bill no 1 & 4 are related to mobilisation advance. As per clause 7 of agreement payment shall be made within 21 working days after submission of bill by the contractor i.e. M/s NCC Ltd. e) Time Over run: The planned financial progress up to 31 st May 2017 Actual financial progress up to 31 st May 2017 : Cr. : Cr. Date for planned financial progress to the tune of Crore : Project time over run ( =183 days ) : 183 days.

15 f) Financial progress Vis a Vis planned progress (in Rs. Crores) is as under SHEET 13 OF 45

16 SHEET 14 OF 45

17 SHEET 15 OF 45 MAJOR MILESTONES OF THE CONTRACT (As per Clause 5 of Agreement): S No Description of Milestones Date of Milestone Actual Progress Remarks 1 Mobilization & Completion of Site Office 2 Completion of Foundation for all the works including buildings completed Photographs attached (Page 13-15) Completed Completed 3 Completion of earthwork for roads & parking area Work in progress Photographs attached 4 Completion of RCC for all buildings, roads, drainage, trenches, culverts, water bodies, area development, STP etc Works in progress Photographs attached 5 Completion of All external services Nearing completion Photographs attached 6 Completion of internal services Work in progress 7 Completion of all internal Finishing & Facade Works Works to be taken up after RCC work 8 Final inspection and completion of all works in all respects, ready for the handing over including minor, touch-up and cleaning Works to be taken up after completion of internal finishing works Milestone date rescheduled for mile stone no- 2,3 & 4

18 SHEET 16 OF BOTTLENECKS AND HINDRANCES There is delay in receipt of Architectural, Structural Drawings, Services Drawings Shop drawings from the technical consultant M/S ARCOP. A bituminous road and WBM Road is passing through the construction area of the site which needs to be shifted by Local Authority. 6. URGENT ACTION REQUIRED Process of calling of tender of left out items such as for Furniture & furnishing, Audio visual signage etc is yet to be started.

19 SHEET 17 OF 45 MOBILIZATION RMC Plant Commissioned Tower Crane erected near Library building

20 SHEET 18 OF 45 3 No. of Mobile Tower Crane available at Site Reinforcement Steel about 600 ton available at site

21 Material Testing Lab SHEET 19 OF 45

22 SHEET 20 OF 45 WORK IN PROGRESS Faculty Housing (FH1) AS ON

23 SHEET 21 OF 45 Faculty Housing (FH2) AS ON

24 SHEET 22 OF 45 Faculty Housing (FH3) AS ON

25 SHEET 23 OF 45 Faculty Housing (FH4) AS ON

26 SHEET 24 OF 45 Director s Residence AS ON

27 SHEET 25 OF 45 Faculty and Administrative Block AS ON

28 SHEET 26 OF 45 Library block AS AS ON ON

29 SHEET 27 OF 45 Academic Block AS ON

30 SHEET 28 OF 45 Dining Block AS ON

31 SHEET 29 OF 45 Facility Block AS ON

32 SHEET 30 OF 45 Shopping Block AS ON

33 SHEET 31 OF 45 Sports Complex AS ON

34 SHEET 32 OF 45 Student Hostel Block (H1) AS ON

35 SHEET 33 OF 45 Student Hostel Block (H2) AS ON

36 SHEET 34 OF 45 Student Hostel Block (H3) AS ON

37 SHEET 35 OF 45 Student Hostel Block (H4) AS ON

38 SHEET 36 OF 45 Student Hostel Block (H5) AS ON

39 SHEET 37 OF 45 Staff Housing AS ON

40 SHEET 38 OF 45 Electrical Substation I AS ON

41 SHEET 39 OF 45 Electrical Substation III AS ON

42 SHEET 40 OF 45 Electrical Substation IV AS ON

43 SHEET 41 OF 45 Entry gate I AS ON

44 SHEET 42 OF 45 Utility Services (External) Utility Services (Internal)

45 SHEET 43 OF 45 Roads & External Development AS ON

46 SHEET 44 OF 45 PARKING AREA AS ON

47 SHEET 45 OF 45 SEWAGE TREATMENT PLANT AS ON