MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD
|
|
- Scarlett Brown
- 5 years ago
- Views:
Transcription
1 MARCH BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD
2 GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary School Mustang-Panther Stadium
3 GHS AGRICULTURAL SCIENCES BUILDING
4 AGRICULTURAL SCIENCES BUILDING - GHS Demolition of the existing building has begun
5 AGRICULTURAL SCIENCES BUILDING - GHS More photos of the demolition of the existing building
6 AGRICULTURAL SCIENCES BUILDING - GHS More photos of the demolition of the existing building
7 AGRICULTURAL SCIENCES BUILDING - GHS Site grading for curb and inlets is progressing
8 MULTI- PURPOSE ACTIVITY CENTERS
9 MULTIPURPOSE ACTIVITY CENTERS - CHHS Exterior metal panel and brick veneer installation is on-going
10 MULTIPURPOSE ACTIVITY CENTERS - CHHS Ductwork is approx. 90% complete on the 1 st floor. The exterior store front and glass are installed in Area 1
11 MULTIPURPOSE ACTIVITY CENTERS - CHHS The base coat of paint of the CMU has begun on the 1 st floor of Area 1
12 MULTIPURPOSE ACTIVITY CENTERS - CHHS CFMF installation approx. 95% complete for Area 1. Ceiling grid installation is on-going. The sprinkler piping is ready for the hydro test in Area 1
13 MULTIPURPOSE ACTIVITY CENTERS - CHHS Overhead MEP rough-in is on-going. CMU installation is approx. 95% complete on the 2 nd floor and Area 1
14 MULTIPURPOSE ACTIVITY CENTERS - CHHS Roof panel installation is ongoing, CMU installation on the West side on-going, exposed structural steel painting is 80% complete in Area 2.
15 MULTIPURPOSE ACTIVITY CENTERS - GHS Exterior wall panel, brick veneer, store fronts and glass installation is on-going in Area 1
16 MULTIPURPOSE ACTIVITY CENTERS - GHS Exterior damp proofing along the West side of building is on-going
17 MULTIPURPOSE ACTIVITY CENTERS - GHS Roof panel installation in Area 1 is approximately 90% complete
18 MULTIPURPOSE ACTIVITY CENTERS - GHS MEP rough-in is on-going in Area 1
19 MULTIPURPOSE ACTIVITY CENTERS - GHS Preparation of CMU for paint on 1 st floor of Area 1 is underway
20 MULTIPURPOSE ACTIVITY CENTERS - GHS CMU installation is on-going on 2 nd floor of Area 1
21 MULTIPURPOSE ACTIVITY CENTERS - GHS Painting of main frame in Area 2 is approximately 65% complete
22 TIMBERLINE ELEMENTARY SCHOOL
23 ADDITION TIMBERLINE ELEMENTARY SCHOOL Addition Awaiting casework and doors to be shipped and installed
24 ADDITIONS AND RENOVATIONS - TES Polished concrete floors are to be re-worked before final curing and sealing them completely
25 GRAPEVINE MIDDLE SCHOOL
26 ADDITION GRAPEVINE MIDDLE SCHOOL Small addition - damp proofing and exterior brick veneer installation is on-going
27 ADDITIONS AND RENOVATIONS - GMS South elevation of big addition brick veneer and pre-cast stone installation are underway
28 ADDITIONS AND RENOVATIONS - GMS Big addition 1 st floor CFMF is complete, sheetrock and overhead MEP and sprinkler system installation is on-going
29 ADDITIONS AND RENOVATIONS - GMS Big addition 2 nd floor CFMF is complete, sheetrock and overhead MEP and sprinkler system installation is on-going. Scheduled to get Northside of addition dried-in next week.
30 ADDITIONS AND RENOVATIONS - GMS Big addition 3 rd floor CFMF is complete, sheetrock and overhead MEP and sprinkler system installation is on-going
31 ADDITIONS AND RENOVATIONS - GMS North elevation of existing building. New storefront is installed, glass to be delivered and installed next week
32 CANNON ELEMENTARY SCHOOL
33 CANNON ELEMENTARY SCHOOL Sections 3, 4 & 5 - Structural steel erection is on-going
34 CANNON ELEMENTARY SCHOOL Sections 3, 4 & 5 - Structural steel erection is on-going
35 CANNON ELEMENTARY SCHOOL Sections 3, 4 & 5 - Structural steel erection is on-going
36 CANNON ELEMENTARY SCHOOL Steel erection for sections 6 & 7 is complete. Sections 10 & 11 steel erection is on-going
37 CANNON ELEMENTARY SCHOOL MEP overhead rough-in and installation is on-going in sections 6 & 7
38 MUSTANG PANTHER STADIUM
39 MUSTANG PANTHER STADIUM Concession Building B - Grade beams and retaining walls have been poured, forms are being wrecked and back-filling and compaction is underway
40 MUSTANG PANTHER STADIUM Press Box Building A & Home Bleachers Piers and pier caps have been poured, grade beams are being formed and below grade utilities are being installed
41 MUSTANG PANTHER STADIUM Press Box Building A & Home Bleachers Piers and pier caps have been poured, grade beams are being formed and below grade utilities are being installed
42 MUSTANG PANTHER STADIUM Press Box Building A & Home Bleachers Piers and pier caps have been poured, grade beams are being formed and below grade utilities are being installed
43 MUSTANG PANTHER STADIUM Concession Building C Retaining walls and below grade utilities are complete and the slab is poured and curing, exterior backfill along grade beams is on-going
44 MUSTANG PANTHER STADIUM Concession Building C Retaining walls and below grade utilities are complete and the slab is poured and curing, exterior backfill along grade beams is on-going
45 MUSTANG PANTHER STADIUM Concession Building C Retaining walls and below grade utilities are complete and the slab is poured and curing, exterior backfill along grade beams is on-going
46 MUSTANG PANTHER STADIUM Storm drainage installation is on-going
47 MUSTANG PANTHER STADIUM Utility and rough grading is underway at Fire Lane on visitor s side
48 QUESTIONS?