1 5yr Condition Assessment 2006/07 to 2010/11 Construction Year Area ,813 Page 1 of 25

2 1. Architectural / Structural & Site Exec Summary Hillcrest Public School is a two storey structure of masonry construction with a basement boiler room. The original building was constructed in 1951 and is 2,524 square metres. Addition 1 was added in 1953 and is 750 square metres. Addition 2 was added in 1994 and is 146 square metres. Addition 3 was added in 2000 and is 390 square metres. The site is 2.8 hectares. Overall, the architectural components appear in good condition. Structural Summary The foundations consist of cast-in-place concrete grade beams and spread footings. The building has cast-in-place concrete slabs-on-grade with conventional steel reinforcement. The roof comprises of a wood and metal roof deck with a steel structure supported by exterior & interior concrete walls. The interior structural walls and columns are concrete block walls. Envelope Summary The exterior cladding consists primarily of brick and wood siding. The exterior windows are double glazed aluminum frame with fixed panels & operable slider units. The exterior doors are aluminum doors & frames and/or steel doors with hollow metal frames. The doors have a glazed opening and are typically prefinished and /or painted. The roof coverings has a Built-up Bituminous Roofing (Asphalt & Gravel) assembly and a Modified Bituminous Membrane Roofing (SBS) assembly. Interior Summary Vinyl Composite Floor Tile (VCT) is typically found in the classrooms, administration area, corridors, change-rooms and washrooms. Carpeting is located in library & in the administration area. Rubber flooring is in the gymnasium. Terrazzo is located throughout the washrooms and corridors. The utility rooms and custodial closets have a paint finish on the concrete slab. The majority of the interior walls are masonry block with a paint finish and gypsum board with a vinyl wall covering. The interior doors are either wood doors and/or painted steel doors in hollow metal frames. Most classroom doors have a glazed panel. The door hardware has a combination of levels and knobs. The ceilings typically, in several classrooms and corridors are finished with a suspended acoustical tile system. Several of the classrooms have the original sprayed stucco finish.the steel structure is painted and exposed in the original gymnasium & utility rooms. Painted gypsum board & plaster ceilings are located in the washrooms and change rooms. Site Summary The site of Hillcrest School includes an asphalt paved roadway & parking area accessible from the east end of the property. The site includes an asphalt playground and sodded playing field. Grass, shrubs and trees are located throughout the property. The walkways are poured in place concrete. Site drainage slopes away from the building with no problems indicated or observed. Overall the site was observed to be in good condition. Page 2 of 25

3 2. Mechanical Executive Summary Ventilation for the building is provided by 3 EngA rooftop air handling units and 4 M&I rooftop air handling units. The rooftop air handling units equip with hot water coils and DX coils with air condensers. Two gas-fired Raypak boilers provide hot water to heating coils, hot water radiators, heat pumps and other terminal units. Plumbing fixtures include floor mounted flush tank water closets, floor mounted flush valve water closets, stainless steel hand wash fountains, wall mounted vitreous china lavatories, stainless steel hand sinks, wall mounted vitreous china drinking fountains, wall mounted stainless steel drinking fountains, flush tank wall mounted urinals, janitor sink and mop sink. One gas-fired A.O. Smith domestic hot water tank was found to provide domestic hot water in the building. This building is not sprinkler protected. ABC type fire extinguishers locate in different locations to provide fire protection to the building. Honeywell control systems are monitoring and controlling the HVAC system. Both potable water and sanitary sewage is utilizing Municipal system. Gas service is available in this building. The gas meter is located on the east side of the building. Overall the mechanical systems within the building are in good condition. 3. Electrical Executive Summary The incoming service for Hillcrest P.S. is a 120/208V feed. The main electrical distribution equipment (located in room B18) consists of a 1200A, 120/208V Siemens main switchboard (1994) with a fusible switch distribution section that feeds the electrical equipment within the school. The branch circuit panelboards within the school are typically newer Siemens panels or aged Amalgamated Electric panels. The typical lighting fixtures within the classrooms are recessed 2 ft. x 4 ft. fluorescent fixtures or louvered fluorescent fixtures (1953 Addition). The fluorescent lighting fixtures have T8 lamps and electronic ballasts. Exterior lighting consists of HID wallpack fixtures and some incandescent fixtures. Battery powered emergency lighting units and remote heads provide the emergency lighting within the school. The exit signs in the original building have been retrofitted with LED lamps. The fire alarm system is an Edwards EST Quickstart, single stage, zoned system with associated alarm actuating devices. The P.A. system has been upgraded to the Board standard with rack mounted TOA amplifiers and audio components. The clocks, within the school, are battery-operated clocks. A GIT security system has been installed in the school. Motion detectors have been provided in selected areas. Overall the electrical systems within the building are in fair to good condition. Page 3 of 25

4 01. Architectural & Structural 01.1 Foundations Footings & Foundations Element Instance: Footings & Foundations - Addition 1 Element Instance: Footings & Foundations - Addition 2 Element Instance: Footings & Foundations - Addition 3 Element Instance: Footings & Foundations - Original Building 01.2 Superstructures Structural Framing Element Instance: Structural Framing - Addition 1 Element Instance: Structural Framing - Addition 2 Element Instance: Structural Framing - Addition 3 Element Instance: Structural Framing - Original Building 01.3 Exterior Closures Exterior Walls Element Instance: Exterior Walls - Addition 1 Element Instance: Exterior Walls - Addition 2 Element Instance: Exterior Walls - Addition 3 Element Instance: Exterior Walls - Original Building Exterior Doors Element Instance: Exterior Doors - Addition 1 Page 4 of 25

5 Element Instance: Exterior Doors - Original Building Exterior Doors - Original Building Event #: 1 Replace 2007 $1 Low Board Inspection 2006 Replace Exterior Doors - Original Building Exterior Door Hardware Element Instance: * Exterior Door Hardware - Original Building Element Instance: Exterior Door Hardware - Addition Windows Element Instance: * Windows - Addition 1 Element Instance: * Windows - Original Building Element Instance: Windows - Addition Roofing Roofing Element Instance: Roofing - Section A Roofing - Section A1 Event #: 1 Replace 2008 $95,925 High Board Inspection 2006 Replace Roofing - Section A1 Element Instance: Roofing - Section A Roofing - Section A2 Event #: 1 Replace 2008 $108,450 High Board Inspection 2006 Replace Roofing - Section A2 Page 5 of 25

6 Element Instance: Roofing - Section A3 Element Instance: Roofing - Section B Roofing - Section B Event #: 1 Replace 2008 $39,610 High Board Inspection 2006 Replace Roofing - Section B Element Instance: Roofing - Section C Roofing - Section C Event #: 1 Replace 2008 $47,430 High Board Inspection 2006 Replace Roofing - Section C Element Instance: Roofing - Section D Roofing - Section D Event #: 1 Replace 2008 $21,879 High Board Inspection 2006 Replace Roofing - Section D Element Instance: Roofing - Section E Roofing - Section E Event #: 1 Replace 2008 $1,394 High Board Inspection 2006 Replace Roofing - Section E Element Instance: Roofing - Section F Roofing - Section F Event #: 1 Replace 2008 $1,190 High Board Inspection 2006 Page 6 of 25

7 Replace Roofing - Section F Element Instance: Roofing - Section G Roofing - Section G Event #: 1 Replace 2008 $1,530 High Board Inspection 2006 Replace Roofing - Section G Element Instance: Roofing - Section H Element Instance: Roofing - Section I Element Instance: Roofing - Section J Roofing - Section J Event #: 1 Replace 2008 $2,380 Medium Board Inspection 2006 Replace Roofing - Section J 01.5 Interior Construction Partitions Element Instance: Partitions - Addition 1 Element Instance: Partitions - Addition 2 Element Instance: Partitions - Addition 3 Element Instance: Partitions - Original Building Millwork Element Instance: * Millwork - Addition 1 * Millwork - Addition 1 Event #: 1 Page 7 of 25

8 Replace 2010 $25,000 Medium Replace [ Millwork - Addition 1] The millwork in the classrooms of addition 1 was observed to be in poor condition with deteriorated shelving below the chalkboards. The cupboards at the back of the classrooms are in good condition. Replacement of the millwork in poor condition is recommended. Classroom cupboards. Deteriorated classroom shelving. Element Instance: * Millwork - Addition 2 Element Instance: * Millwork - Original Building * Millwork - Original Building Event #: 1 Replace 2010 $120,000 Medium Replace [ Millwork - Original Building] The millwork in the classrooms of the original building was observed to be in poor condition with deteriorated shelving below the chalkboards. The cupboards at the back of the classrooms are in good condition. Replacement of the millwork in poor condition is recommended. Typical classroom cupboards. Page 8 of 25

9 Deteriorated shelving in a classroom. Staff millwork in fair condition. Element Instance: Millwork - Addition Interior Doors Element Instance: * Interior Doors - Addition 1 Element Instance: * Interior Doors - Original Building Element Instance: Interior Doors - Addition Interior Door Hardware Element Instance: * Interior Door Hardware - Original Building Interior Wall Finishes C01 Paint Wallcovering Element Instance: * C01 Paint Wallcovering - Addition 1 & 2 * C01 Paint Wallcovering - Addition 1 & 2 Event #: 1 Replace 2006 $20,000 Medium Replace [ C01 Paint Wallcovering - Addition 1& 2] Overall the paint finish is in fair condition. Repaint interior wall surfaces. Page 9 of 25

10 Pealing surface. Paint wall covering in the corridor with pealing surface. Pealing surface. Element Instance: * C01 Paint Wallcovering - Addition 3 Element Instance: * C01 Paint Wallcovering - Original Building C04 Ceramic Wall Tile Element Instance: * C04 Ceramic Wall Tile - Addition 1 Element Instance: * C04 Ceramic Wall Tile - Original Building - Washrooms C05 Acoustic Wall Treatment Element Instance: C05 Acoustic Wall Treatment - Addition Floor Finishes C03 Terrazzo Page 10 of 25

11 Element Instance: C03 Terrazzo - Addition 1 Element Instance: C03 Terrazzo - Original Building C04 Carpeting Element Instance: * C04 Carpeting - Original Building C05 Vinyl Floor Tile Element Instance: * C05 Vinyl Floor Tile - Original Building Element Instance: C05 Vinyl Floor Tile - Addition C08 Rubber Floor Element Instance: C08 Rubber Floor - Addition C12 Porcelain Floor Tile Element Instance: C12 Porcelain Floor Tile - Addition 2 Element Instance: C12 Porcelain Floor Tile - Original Building Ceiling Finishes C01 Gypsum Board Ceiling Element Instance: C01 Gypsum Board Ceiling - Addition 1 Element Instance: C01 Gypsum Board Ceiling - Original Building C02 Suspended Acoustic Panel Ceiling Page 11 of 25

12 Element Instance: C02 Suspended Acoustic Panel Ceiling - Addition 1 Element Instance: C02 Suspended Acoustic Panel Ceiling - Addition 2 Element Instance: C02 Suspended Acoustic Panel Ceiling - Original Building C03 Lath & Plaster Ceiling Element Instance: * C03 Lath & Plaster Ceiling - All * C03 Lath & Plaster Ceiling - All Event #: 1 Replace 2007 $200,000 Medium Replace [ C03 Lath & Plaster Ceiling - All] The lath and plaster ceiling which may contain asbestos in the some of the classrooms and washrooms was observed to be in poor condition with cracked & pealing surfaces in the washrooms and damaged surfaces in the classrooms. Replacement throughout is recommended. Typical classroom ceiling with repaired cracks. Typical classroom ceiling with repaired cracks. Severe pealing surface in a washroom C05 Painted Ceiling Structures Page 12 of 25

13 Element Instance: * C05 Painted Ceiling Structures - Addition Window Coverings Element Instance: * Window Coverings - Addition 1 Element Instance: * Window Coverings - Addition 2 Element Instance: * Window Coverings - Original Building Washroom Accessories Element Instance: * Washroom Accessories - Original Building Interior Stairs Element Instance: * Interior Stairs - Original Building * Interior Stairs - Original Building Event #: 1 Replace 2010 $25,000 Medium Board Inspection 2005 Replace [ Interior Stairs - Original Building] - South End Overall the interior stairs are in fair condition, however the steel frame is corroded Replacement of the stairs is recommended. Terrazzo Stairs - South End Terrazzo Stairs - South End - Corroded steel frame 01.6 Fittings & Equipment Fittings & Equipment Element Instance: *01.6 Fittings & Equipment - Chalkboards & Tackboards Page 13 of 25

14 *01.6 Fittings & Equipment - Chalkboards & Tackboards Event #: 1 Replace 2010 $75,000 Medium Replace [01.6 Fittings & Equipment - Chalkboards & Tackboards] The fittings and equipment in the classrooms and corridors of the original building were observed to be in fair condition with deteriorated surfaces chalkboards and tackboards. Replacement of these items is recommended. Worn chalkboard. Element Instance: *01.6 Fittings & Equipment - Other Than Chalkboards & Tackboards *01.6 Fittings & Equipment - Other Than Chalkboards & Tackboards Event #: 1 Replace 2010 $30,000 Medium Replace [01.6 Fittings & Equipment - Other Than Chalkboards & Tackboards] The fittings and equipment in the classrooms and corridors of addition 1 were observed to be in fair condition with deteriorated surfaces of the hangers..replacement of these items is recommended. Coat rack in fair condition. 03. Mechanical 03.1 HVAC (HW/S) Boilers Element Instance: (HW/S) Boilers - Original Building - Boiler 1 Element Instance: (HW/S) Boilers - Original Building - Boiler 2 Element Instance: (HW/S) Boilers - Original Building - Boiler 3 Page 14 of 25

15 Roof Top AHU - Heat&Cool Element Instance: Roof Top AHU - Heat&Cool - Addition 1 - East Element Instance: Roof Top AHU - Heat&Cool - Addition 1 - Gym Element Instance: Roof Top AHU - Heat&Cool - Addition 1 - West Element Instance: Roof Top AHU - Heat&Cool - Original RTU1 Element Instance: Roof Top AHU - Heat&Cool - Original RTU2 Element Instance: Roof Top AHU - Heat&Cool - Original RTU6 Element Instance: Roof Top AHU - Heat&Cool - Original RTU Packaged Terminal A/C AHU Element Instance: Packaged Terminal A/C AHU - Addition Heating & Cooling Piping Systems Element Instance: Heating & Cooling Piping Systems - Original Building Terminal Units Element Instance: Terminal Units - Addition 1 Element Instance: Terminal Units - Original Building Gas Piping System Element Instance: * Gas Piping System - Original Building 1951 * Gas Piping System - Original Building 1951 Event #: 1 Major Repair 2006 $4,500 High Major Repair Gas Piping System - Original 1951 Page 15 of 25

16 Gas piping in the original building will only require repainting to ensure its continued longevity. Gas piping paint is flaking and chipped. Gas piping in good condition. Gas piping branch take off needs to be painted to ensure continues longevity Duct Systems Element Instance: Duct Systems - Addition 1 Element Instance: Duct Systems - Addition 2 Element Instance: Duct Systems - Addition 3 Element Instance: Duct Systems - Original Building Stacks & Breaching Element Instance: Stacks & Breaching - Original Building 03.2 Control Systems Control Systems Element Instance: 03.2 Control Systems - Addition 1 Page 16 of 25

17 Element Instance: 03.2 Control Systems - Original Building 03.3 Plumbing Plumbing Fixtures Element Instance: Plumbing Fixtures - Addition Plumbing Fixtures - Addition 1953 Event #: 1 Replace 2007 $1 Low Board Inspection 2006 Replace Plumbing Fixtures - Addition 1953 Approximately 25 percent of the plumbing fixtures in addition 1953 are outdated and worn and should be replaced. Urinals are not cracked or corroded. Wash fountain has been replaced. Toilet is worn and outdated. Element Instance: Plumbing Fixtures - Addition 2 Element Instance: Plumbing Fixtures - Original Building Plumbing Fixtures - Original Building 1951 Event #: 1 Replace 2007 $1 Low Board Inspection 2006 Replace Plumbing Fixtures - Original Building 1951 Page 17 of 25

18 Approximately 25 percent of the plumbing fixtures in the original building are cracked or outdated, and should be replaced. Toilet is outdated. Toilet stand is cracked. Wash fountain has been updated Domestic Water Heaters Element Instance: Domestic Water Heaters - Original Building Plumbing Pumps Element Instance: Plumbing Pumps - Original Building Plumbing Piping Systems Element Instance: * Plumbing Piping Systems - Addition 1953 Element Instance: * Plumbing Piping Systems - Original Building 1951 * Plumbing Piping Systems - Original Building 1951 Event #: 1 Replace 2010 $215,000 Medium Replace Plumbing Piping Systems - Original Building 1951 Plumbing piping in the original building is not corroded or damaged, and no leaks were observed. The system does not need to be replaced in the next five years. Page 18 of 25

19 Sink plumbing has been protected by paint and is not corroded. Sanitary piping is in good condition. Mechanical joints are not corroded. Piping joints are not leaking. Element Instance: Plumbing Piping Systems - Addition Fire Protection Standpipe Systems Element Instance: Standpipe Systems - Addition 1 Element Instance: Standpipe Systems - Original Building Fire Extinguishers Element Instance: * Fire Extinguishers - Original Building 1951 * Fire Extinguishers - Original Building 1951 Event #: 1 Replace 2007 $13,000 High Replace Fire Extinguishers - Original Building 1951 Fire extinguishers in the original building1951 are worn and should be replaced. Fire extinguisher is outdated and worn. Page 19 of 25

20 Fire extinguisher is in poor condition. 04. Electrical 04.2 Secondary Electrical Secondary Switchgear Element Instance: * Secondary Switchgear - All * Secondary Switchgear - All Event #: 1 Major Repair 2007 $15,000 Medium Routine Data Entry Major Repair Secondary Switchgear - All Panels in the original building and the 1953 addition have exceeded their theoretical life. The panels are in poor condition and replacement parts are no longer available. Replacement is recommended. Aged Amalgamated Electric panel. Aged electrical distribution panel Cabling, Raceways & Bus Ducts Element Instance: * Cabling, Raceways & Bus Ducts - Original Building 1951 and Addition 1953 * Cabling, Raceways & Bus Ducts - Original Building 1951 and Addition 1953 Event #: 1 Study 2006 $10,000 High Study Cabling, Raceways & Bus Ducts - Original Building 1951 and Addition 1953 Page 20 of 25

21 A study should be performed to determine the condition of the existing cabling and to make recommendations as to the extent of cabling replacement and associated costs. * Cabling, Raceways & Bus Ducts - Original Building 1951 and Addition 1953 Event #: 2 Replace 2007 $350,000 High Replace Cabling, Raceways & Bus Ducts - Original Building 1951 and Addition 1953 Cabling in the original building and the 1953 addition has exceeded its theoretical life. A study should be performed to determine the condition of the existing cabling and to make recommendations as to the extent of cabling replacement and associated costs. Replace cabling as recommended by study. Wiring devices in the older sections of the school have exceeded their theoretical life expectancy. Replacement of the aged wiring devices is recommended. Aged lighting switches. Element Instance: Cabling, Raceways & Bus Ducts - Addition Lighting Fixtures Interior Lighting Element Instance: Interior Lighting - Addition 1 Element Instance: Interior Lighting - Addition 2 Element Instance: Interior Lighting - Addition 3 Element Instance: Interior Lighting - Original Building Exterior Lighting Element Instance: * Exterior Lighting - Original Building 1951 and Addition 1994 * Exterior Lighting - Original Building 1951 and Addition 1994 Event #: 1 Replace 2009 $10,000 Medium Board Inspection 2005 Replace Exterior Lighting - Original Building 1951 and Addition 1994 Page 21 of 25

22 The exterior wall mounted light fixtures on the original building and the 1994 addition are showing signs of age. Discoloured lenses were identified. The light fixtures are approaching the end of their theoretical life. Replacement is recommended. Aged exterior lighting fixture. Element Instance: Exterior Lighting - Addition 1953 Element Instance: Exterior Lighting - Addition Exit Lighting Element Instance: Exit Lighting - Original Building Emergency Lighting Element Instance: Emergency Lighting - Addition 1 Element Instance: Emergency Lighting - Original Building 04.5 Electrical Systems Fire Alarm System Element Instance: Fire Alarm System - Devices Fire Alarm System - Devices Event #: 1 Replace 2007 $1 Medium Board Inspection 2006 Replace Fire Alarm System - Devices Fire alarm devices in the original 1951 building and 1953 addition have exceeded their theoretical life expectancy. Replacement is recommended. Aged fire alarm pullstation. Page 22 of 25

23 Element Instance: Fire Alarm System - Original Building panel Fire Alarm System - Original Building panel Event #: 1 Replace 2007 $1 Medium Board Inspection 2006 Replace Fire Alarm System - Original Building panel Communication Systems Element Instance: * Communication Systems - Original Building 1951 Element Instance: * Communication Systems - Original Building 1951 and Addition 1953 Element Instance: Communication Systems - Addition 1 - int. tel/pa Element Instance: Communication Systems - Original Building - cont.unit/handsets Security System Element Instance: Security System - Original Building 04.6 Special Systems Clock Systems Element Instance: * Clock Systems - All 04.7 Information Technology Systems Information Technology Systems Element Instance: *04.7 Information Technology Systems - All 06. Functional 06.2 Single Gymnasium Element Instance: 06.2 Single Gymnasium - Addition Single Gymnasium - Addition 3 Event #: 1 Functional Events 2006 $0 Low Page 23 of 25

24 Functional Events - [06.2 Single Gymnasium - Addition 3] The single gymnasium is approximately 376 squared metres and does meet the space requirement for 615 students. The single gymnasium is approximately 5.8 metres high and does meet the specified height requirement. Single Gymnasium The single gymnasium is approximately 376 squared metres and does meet the space requirement for 615 students. The single gymnasium is approximately 5.8 metres high and does meet the specified height requirement. Single Gymnasium 06.3 Library Resource Centre Element Instance: 06.3 Library Resource Centre - Original Building 06.3 Library Resource Centre - Original Building Event #: 1 Functional Events 2006 $0 Medium Functional Events [06.3 Library Resource Centre - Original Building] The Library in the original building is located in room 112 on the north-east side of the school building. The Library is approximately 258 square metres and does not meet the specified space requirements for 615 students. Library Resource Centre The Library in the original building is located in room 112 on the north-east side of the school building. Page 24 of 25

25 The Library is approximately 258 square metres and does not meet the specified space requirements for 615 students. Library Resource Centre Page 25 of 25

26 5yr Condition Assessment 2006/07 to 2010/11 Hillcrest PS (Barrie), Campus ID Site Construction Year Area ,719 Hillcrest PS (Barrie), Campus ID Site Page 1 of 7

27 Hillcrest PS (Barrie), Campus ID Site Page 2 of 7

28 00. Property 00.1 Site Underground Utilities Element Instance: * Underground Utilities - Site * Underground Utilities - Site Event #: 1 Study 2006 $10,000 Urgent Study Underground Utilities - Site A study is recommended to determine the condition of the underground utilities and identify the correct time for this major expenditure to be undertaken. * Underground Utilities - Site Event #: 2 Replace 2007 $1,000,000 Urgent Replace Underground Utilities - Site Aboveground Utilities Element Instance: Aboveground Utilities - Site - Portables Signage Element Instance: * Signage - Site Undeveloped Lands Element Instance: * Undeveloped Lands - Site Site Related Stairs, Plazas & Decks Element Instance: * Site Related Stairs, Plazas & Decks - Site * Site Related Stairs, Plazas & Decks - Site Event #: 1 Replace 2006 $30,000 Medium Board Inspection 2005 Replace [ Site Related Stairs, Plazas & Decks - Site] - Entrances The concrete stairs at the main & side entrance appear to have been repaired several times and are in poor condition. Replace exterior stairs. Hillcrest PS (Barrie), Campus ID Site Page 3 of 7

29 Deteriorated concrete stairs at main entrance. Detail - Deteriorated concrete stairs at main entrance. Entrance E Retaining Walls Element Instance: Retaining Walls - Site Soft Landscaping Element Instance: * Soft Landscaping - Site Site Improvements Element Instance: Site Improvements - Site Stormwater Management Systems Element Instance: * Stormwater Management Systems - Site * Stormwater Management Systems - Site Event #: 1 Replace 2007 $33,000 High Replace Stormwater Management Systems - Site The site falls naturally away to the south-west and there are plenty of catch basins throughout the site to catch water build up. There is also a swell on the north side of the site. It was reported that there a lot of areas on the site that still flood during the spring. Additions of extra swells around the site is recommended. Hillcrest PS (Barrie), Campus ID Site Page 4 of 7

30 Swell in high side of the site. Storm water catch basin on south-west side. Storm water catch basin on south side. Catch basin on the north-west side Paved Surface Systems Paved Parking Lots Element Instance: Paved Parking Lots - Site Paved Roadway Element Instance: Paved Roadway - Site Paved Playgrounds Element Instance: * Paved Playgrounds - Site * Paved Playgrounds - Site Event #: 1 Replace 2007 $75,000 Low Board Inspection 2005 Hillcrest PS (Barrie), Campus ID Site Page 5 of 7

31 Replace [ Paved Playgrounds - Site] Cracks were observed throughout the asphalt paved playground. Grass has intruded between the cracks. Replace asphalt paved playground. Asphalt paved playground. Asphalt paved playground. Asphalt paved playground Paved Walkways Element Instance: * Paved Walkways - Site * Paved Walkways - Site Event #: 1 Replace 2007 $40,000 Medium Replace [ Paved Walkways - Site] The paved walkways on the south-west side and on the west side of the original building were observed to be in poor condition with deteriorated surfaces. The other walkways around the site have been replaced in Replacement of the original walkways is recommended. Deteriorated asphalt walkway on the west side of the original building. Hillcrest PS (Barrie), Campus ID Site Page 6 of 7

32 Deteriorated asphalt walkway on the west side of the original building. Poor condition of asphalt paved walkways 00.3 Unpaved Surface Systems Unpaved Playgrounds Element Instance: * Unpaved Playgrounds - Site Hillcrest PS (Barrie), Campus ID Site Page 7 of 7