1 2018 CONSTRUCTION SUMMIT CDA DESIGN AND CONSTRUCTION Alex Leon Deputy Commissioner February 7, 2018

2 TERMINAL AREA PLAN

3 O HARE CAPITAL PROGRAMS OVERVIEW O Hare is taking steps to reconfigure and modernize for long-term growth Working in partnership with United, American and other domestic and international airlines on facility needs Projects are funded with multiple sources 2

4 POTENTIAL CONFIGURATION FOR NEW CONCOURSES Terminal Area Development - TAP Over 400 acres available for gate expansion Taxiways comply with FAA guidance to eliminate irregular geometry 3

5 EXPANSION OF TERMINAL 5 TO SUPPORT INCREASED DEMAND Terminal expansion includes 9 new wide-body gates Provides for a second A380 capable gate at O Hare Addresses near-term demand and capacity of International Terminal gates and facilities Provides additional capacity for domestic flights Includes expanded security screening and Federal Inspection Services (FIS) facilities 4

6 CM AT RISK FOR T5 EXTENSION AND ADDITIONAL O HARE 21 PROJECTS (ANTICIPATED TO BE AT LEAST TWO CONTRACTS) CM at Risk contracts to deliver the Terminal 5 M Extension projects as well as additional O Hare 21 Projects O Hare 21 Projects will include airside facility projects, landside facility projects, terminal projects and security packages Anticipated Term: TBD Advertisement Date: 2 nd Quarter 2017 Anticipated Award Date: 2 nd Quarter

7 ORD TERMINAL 5 M EXTENSION SITE/CIVIL The civil component of the building extension will include four (4) new hardstand positions, including all site, apron, lighting, security, fueling & taxiway design. Also included are modifications to the pavement area near Gates M1 to M6 for two additional contact gates for future operations. ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2018 ESTIMATED CONTRACT VALUE: $90- $100 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: DBE 30% 6

8 TARGET MARKET CONTRACTS Contracts designated for competition limited to MBEs or WBEs The Target Market Program reserves a percentage of the City s non-construction contracts and limits participation to M/WBEs Contracts are not eligible for the program unless there are at least three qualified MBEs or WBEs interested in participating in that type of contract The prime contractor on a Target Market Contract must perform at least 50 percent of the dollar value 7

9 TARGET MARKET CONSTRUCTION MANAGEMENT SERVICES Multiple target market Construction Manager contracts will be awarded to oversee various segments of O Hare 21 Terminal Area Plan, the Capital Improvement program and the TAP enabling projects Projects will include airside projects, landside projects, terminal projects, site preparation and security packages Anticipated Term: 5 Years Anticipated Advertisement Date: 1st Quarter 2018 Anticipated Award Date: 3rd Quarter

10 TARGET MARKET DESIGNS/TASK ORDERS Multiple target market design/task order for O Hare 21 and CIP projects. Projects will include airside work, landside projects, terminal projects, site preparation and security packages Anticipated Term: 5 Years Advertisement Date: 2 nd Quarter 2017 Award Date: 4 th Quarter

11 TARGET MARKET, FEDERAL, NON-FEDERAL DESIGNS/TASK ORDERS Multiple target market design/task order for O Hare 21 and CIP projects. Projects will include airside work, landside projects, terminal projects, site preparation and security packages Anticipated Term: 5 Years Advertisement Date: 2 nd Quarter 2017 Award Date: 2 nd Quarter

12 LEAD DESIGNER TUNNEL FOR AIRSIDE PEOPLE MOVER (APM) Tunnel system from the east end of Terminal 2, through the Satellite Concourses, to a point beyond the relocated Taxiways A & B for the purpose of conveying passengers (sterile and non-sterile), baggage, utilities and bag carts/gse The tunnel provides sufficient width to enable the future installation of an APM Designer will be tasked to bring up to 15% Design Anticipated Duration: To task completion Advertisement Date: 2 nd Quarter 2018 Award Date: 4 th Quarter

13 LEAD DESIGNERS O HARE GLOBAL TERMINAL (OGT) AND SATELLITE GT will CONCOURSES provide Gate Space for a Multiple Aircraft Ramp System (MARS) configuration to allow flexible use of Gate Space between regional jets, narrow body and wide body aircraft (as deemed appropriate) to serve international and domestic operations, as well as a Customs & Border Protection (CBP) arrival hall Satellite concourses will provide Gate Space for a Multiple Aircraft Ramp System (MARS) configuration to serve international, precleared international and domestic operations Up to two designers can be selected Anticipated Duration: To task completion Advertisement Date: 2 nd Quarter 2018 Award Date: 4 th Quarter

14 O Hare Modernization Program

15 O HARE - AIRFIELD The Modernization of O Hare has completed approximately $5.8B of improvements, including: Two New Airport Traffic Control Towers Extension of Runway 10L/28R New Runway 9L/27R New Runway 10C/28C New Runway 10R/28L Multiple Taxiway Improvements (K&L, LL, others) Ongoing Runway 9C/27C Ongoing Consolidated Rental Car/Parking Multimodal facility Ongoing ATS Modernization and Extension 14

16 RUNWAY 9C/27C CONSTRUCTION PACKAGES LEGEND Runway 9C-27C East Package Runway 9C-27C Package 1 Runway 9C-27C Package 2 Runway 9C-27C Package 3 Airline Employee Parking Lot 15

17 RWY 9C/27C PACKAGE 2 Construction of airfield pavements, PCC and AC, airfield lighting and signage, demolitions of existing structures and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA). ADVERTISEMENT DATE: 1/19/2018 ESTIMATED CONTRACT VALUE: $120 - $160 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: DBE 30% 16

18 AIRLINE EMPLOYEE PARKING LOT PKG #2 Roadway intersection improvements on Bessie Coleman Drive to access new Employee Parking Lot, the expansion of the entrance to the new lot with supporting five lane check point, and the construction of a new Guard Post. ANTICIPATED ADVERTISEMENT DATE: 1st QUARTER 2018 ESTIMATED CONTRACT VALUE: $6-$8 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: M/WBE 26/6% 17

19 RWY 9C/27C PACKAGE 3 Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA). ANTICIPATED ADVERTISEMENT DATE: 3 RD QUARTER 2018 ESTIMATED CONTRACT VALUE: $40 - $60 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: DBE 30% 18

20 CDF CONTROL TOWER Construction of a building to serve as a operations control tower for airlines management of their winter deicing operations at the Centralized Deicing Facility. ANTICIPATED ADVERTISEMENT DATE: 1st QUARTER 2018 ESTIMATED CONTRACT VALUE: $4-6 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: M/WBE 26/6% 19

21 CENTRAL BASIN RECONFIGURATION Modifications to the Central and South Basins to accommodate the future terminal developments. Work may include earthwork, large diameter deep tunnel construction, modifications to mechanical equipment, including an existing pump station. Project may be delivered as design-build. ANTICIPATED ADVERTISEMENT DATE: 4 th QUARTER 2018 ESTIMATED CONTRACT VALUE: $100-$120 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: M/WBE 26/6% 20

22 RELOCATION OF TAXIWAYS A&B Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, pavement removal, PCCP crushing, and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA). ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2019 ESTIMATED CONTRACT VALUE: $80 - $100 MILLION LOCATION: AIRSIDE ELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS LABORERS SURVEYORS CEMENT MASONS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 21

23 ATS LOT E STATION DEMOLITION Demolition of the structure and platform of this station, modification of wayside systems, power systems and track work as required and site restoration. Construction will require coordination with and limited interruption of services of the Airport s Transit System Project site is in the current Public Parking Lot E. ANTICIPATED ADVERTISEMENT DATE: 4 TH QUARTER 2019 LOCATION: LANDSIDE ELECTRICIANS OPERATORS LABORERS IRON WORKERS ESTIMATED CONTRACT VALUE: $10 - $20 MILLION DBE/MBE/SBE/WBE GOALS: DBE 30% 22

24 O Hare International Airport Capital Improvement Program

25 BESSIE COLEMAN WATERMAIN REPLACEMENT Replacement of approximately 5,000 lf of water main along Bessie Coleman, a connection to the existing 12 service line adjacent to the E Lot ATS Station, and abandoning the existing water main running underneath I-190. Other work items will include: lateral runs to fire hydrants, isolation valves, valve boxes, fire hydrants, cathodic protection and other pertinent items integral to the installation of a new water distribution and/or capping and connections to the existing water main. ADVERTISEMENT DATE: 2/1/2018 LOCATION: LANDSIDE OPERATORS CARPENTERS LABORERS ELECTRICIANS ESTIMATED CONTRACT VALUE: $2 - $3 MILLION TEAMSTERS PLUMBERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 24

26 NORTH AIRFIELD SANITARY SEWER REPLACEMENT Construction of a sanitary sewer system that will serve the North Airfield buildings. Existing flow that travels NW to the MWRD Kirie Plant will be intercepted and sent to an existing forcemain sewer on airport property near Building 850. That existing pipe outfalls near Mannheim Road where it enters the MWRD Stickney system. A new lift station will be included as well as approximately 6400LF of gravity pipe and forcemain. ANTICIPATED ADVERTISEMENT DATE: 1 ST QUARTER 2018 LOCATION: LANDSIDE ELECTRICIANS PLUMBERS OPERATORS CARPENTERS ESTIMATED CONTRACT VALUE: $2.5 - $3.5 MILLION LABORERS SURVEYORS LANDSCAPERS WELDERS PIPE FITTERS TEAMSTERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 25

27 RUNWAY 9R-27L RWSL INSTALLATION Install approximately 10,000 linear feet of electrical ductbank, handholes, and airfield lighting cable to complete the installation of the FAA Runway Status Lights (RWSL) system for Runway 9R- 27L. A FAA-RWSL shelter to be located adjacent to the existing Runway 27L ALSF shelter will also be installed. A new Com Ed service feed as well as fiber optic cable connectivity to the air traffic control tower will be required to make the RWSL shelter fully functional. ANTICIPATED ADVERTISEMENT DATE: 1 ST QUARTER 2018 LOCATION: AIRSIDE OPERATORS ELECTRICIANS TEAMSTERS LABORERS ESTIMATED CONTRACT VALUE: $2.5 - $3 MILLION DBE/MBE/SBE/WBE GOALS: DBE 30% 26

28 MIAMI BEACH LIFT STATION IMPROVEMENT Demolish existing Lift Station and specified equipment, erosion control and paving, site utility installation, including jacked sanitary sewer, excavation and construction of the new Lift Station Facility in the SW corner of LOT B, electrical and communications duct bank installation, SMS installation and tie-in, and C1 Electrical Vault Switchboard replacement and lighting upgrades. ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2018 LOCATION: LANDSIDE OPERATORS CARPENTERS LABORERS ELECTRICIANS ESTIMATED CONTRACT VALUE: $5 - $6 MILLION TEAMSTERS PLUMBERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 27

29 BAGGAGE SERVICE ROAD RETAINING WALL REPAIR Repair the Baggage Service Road Retaining Wall from approximately Guard Post 7 to Guard Post 10 (excluding Terminal 2). Scope will include the drilling of piles to support the wall footing; concrete and crack repair; cap replacement; new underdrain system; select stem replacement; cleaning and repainting and replacement of conduit and circuitry to roadway and apron lighting. ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2018 LOCATION: AIRSIDE OPERATORS PAINTERS ELECTRICIANS FINISHERS ESTIMATED CONTRACT VALUE: $1 - $2 MILLION TEAMSTERS LABORERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 28

30 RING AND UTILITY TUNNEL CONCRETE REPAIRS Phased approach to address the areas in need of structural concrete repair in two utility tunnel locations. Scope varies from spall repair, cathodic protection of reinforcement to entire beam replacement. This project will address the 2 nd Phase in the program. ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2018 ESTIMATED CONTRACT VALUE (PH 2): $8 - $10 MILLION LOCATION: AIRSIDE ELECTRICIANS PLUMBERS OPERATORS TEAMSTERS LABORERS IRONWORKERS CONCRETE MASONS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 29

31 PEDESTRIAN TUNNEL REPAIRS Remediation of water infiltration throughout the pedestrian tunnels below the concourses and roadways. Scope also includes interior remodeling and updating of pedestrian tunnels. New finishes will allow for a back-up drainage system as a second line of defense to any possible water migration through the tunnel structure. New energy efficient lighting and mechanical distribution is included. Project area extends into the area of the tunnels under the Hilton for finishes continuity. ANTICIPATED ADVERTISEMENT DATE: 2 ND QUARTER 2018 ESTIMATED CONTRACT VALUE : $25 - $30 MILLION LOCATION: AIRSIDE ELECTRICIANS PLUMBERS OPERATORS TEAMSTERS LABORERS IRONWORKERS CONCRETE MASONS ELECTRICIANS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% CARPENTERS PAINTERS 30

32 I-190 LIFT STATION REPLACEMENT This project consists of improvements to the existing Taxiway Lift Station. Work includes removal and replacement of existing ventilation, pumps, valve, motors, motor starters, wet well control panel, associated piping, and electrical infrastructure. The project also includes Supervisory Monitoring System (SMS) integration, upgrades to the facility's lighting control, replacement of an existing "ship's ladder", and installation of a wet well concrete liner and partial depth concrete repair. ANTICIPATED ADVERTISEMENT DATE: 3 RD QUARTER 2018 LOCATION: AIRSIDE ELECTRICIANS PLUMBERS CARPENTERS PIPE FITTERS ESTIMATED CONTRACT VALUE: $3-4 MILLION LABORERS TEAMSTERS OPERATORS FINISHERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 31

33 REPLACEMENT OF ROTUNDA AIR HANDLING UNITS Replacement of 11 Rotunda Air Handling Units. Recondition of the existing ductwork. The new, efficient, code complying units will serve the environments that require different temperature controls, air movement, cooling capacities, heating capacities, with separate multi-zone controls to reconnect to existing ducting. ANTICIPATED ADVERTISEMENT DATE: 3 RD QUARTER 2018 ESTIMATED CONTRACT VALUE: $15 - $20 MILLION SHEET METAL WORKERS LOCATION: AIRSIDE ELECTRICIANS PLUMBERS LABORERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 32

34 RECIRCULATION BRIDGE RECONSTRUCTION The project includes the replacement of the three-span entrance roadway recirculation bridge and associated ramp and approaches for the structure. ANTICIPATED ADVERTISEMENT DATE: 4 TH QUARTER 2018 ESTIMATED CONTRACT VALUE: $3 - $4 MILLION OPERATORS CEMENT MASONS LOCATION: AIRSIDE ELECTRICIANS FINISHERS TEAMSTERS LABORERS IRON WORKERS CARPENTERS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 33

35 TERMINAL AREA FIRE MAIN REPLACEMENT Relocation of the terminal area fire main loop including approximately 7000 lf of 12 fire main, 1500 lf of 8 hydrant fire main and 32 fire hydrants. New alignment will minimize impacts to traffic by locating portions of the loop within the commercial vehicle lanes. Medians and center lanes will be reconstructed within the terminal area to meet ADA and will include new sidewalks and utility replacements. Approximately 2,500 lf of ComEd ductbank will be included to replace an existing ductbank that is at risk of failure. ANTICIPATED ADVERTISEMENT DATE: 1 ST QUARTER 2019 LOCATION: AIRSIDE LABORERES PIPEFITTERS OPERATORS PLUMBERS ESTIMATED CONTRACT VALUE: $20 - $25 MILLION TEAMSTERS FINISHERS IRON WORKERS CARPENTERS ELECTRICIANS DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6% 34

36 Midway International Airport Capital Improvement Program

37 MDW AIRFIELD LIGHTING INFRASTRUCTURE IMPROVEMENTS Installation of a new duct bank system that will provide a more efficient way to maintain airfield electrical system. This will include new duct bank runs to provide more direct routing of circuits, the installation of new manholes and hand holes that minimize the need to access Runway and Taxiway safety areas during maintenance, replacement of aging cabling, and additional capacity to handle future improvements. This project also includes new fiber optic duct bank in the SW corner of the airfield. ANTICIPATED ADVERTISEMENT DATE: 1 ST QUARTER 2018 LOCATION: AIRSIDE ELECTRICIANS OPERATORS TEAMSTERS LABORERS ESTIMATED CONTRACT VALUE: $8 - $10 MILLION DBE/MBE/SBE/WBE GOALS: DBE 30% 36

38 MDW AIRPORT MAINTENANCE COMPLEX IMPROVEMENTS Replacing the HVAC for the garage with an energy efficient system, replacing the overhead doors and associated hardware, an upgrade to the emergency generator and switchgear, and the replacement of the boilers with more energy efficient boilers. Expanding and replacing the potassium acetate pumps and tanks to allow for a total of 90,000 gallons of onsite storage. The project also includes replacing the roof membrane, an upgrade of the windows, replacing the HVAC system in the office area, replacement of the emergency egress doors and hardware, and improvements for ADA accessibility. ANTICIPATED ADVERTISEMENT DATE: 1 ST QUARTER 2018 ESTIMATED CONTRACT VALUE: $11 - $12.5 MILLION DBE/MBE/SBE/WBE GOALS: DBE 30% LOCATION: LANDSIDE ELECTRICIANS OPERATORS LABORERS SURVEYORS CARPENTERS PLUMBERS IRON WORKERS PAINTERS CEMENT MASONS 37

39 Residential Sound Insulation Program (RSIP)

40 ON-CALL A/E SERVICES FOR THE RSIP On-call architectural and engineering ( A/E ) design and consulting services for the RSIP for O Hare and Midway. Federally-funded. DBE participation of 30% required. Services may include, but are not limited to: making at least two site visits per home, computer-aided design and drafting, developing window and door schedules, preparing specifications, and reviewing submittals and code requirements. Anticipated Term: 5 Years Advertisement Date: 1 st Quarter 2018 Award Date: 2 nd Quarter

41 O HARE PHASE 17 HISTORICAL HOMES Sound-insulate 133 historical dwelling units in single-family homes and multifamily buildings in the Chicago Norwood Park Historical District near Harlem Avenue and Higgins Avenue. Work to include installation of approximately 2,600 acoustical window treatments, 2,600 storm windows, 260 acoustical prime door treatments, 260 storm doors, 20 central air conditioning systems, upgrades to electrical service and other miscellaneous work. ANTICIPATED ADVERTISEMENT DATE: 2 nd QUARTER 2018 ESTIMATED CONTRACT VALUE: $10 - $15 MILLION DBE/MBE/SBE/WBE GOALS: DBE 22% LOCATION: LANDSIDE PAINTERS TAPERS LABORERS INSULATORS ELECTRICIANS CARPENTERS SHEET METAL WORKERS PIPE FITTERS ASBESTOS WORKERS 40