ADDENDUM #2. FIBER OPTIC CABLE MAINTENANCE (Revised 1-18) IF BIDS WILL BE OPENED 1:00 PM February 23, 2018

Size: px
Start display at page:

Download "ADDENDUM #2. FIBER OPTIC CABLE MAINTENANCE (Revised 1-18) IF BIDS WILL BE OPENED 1:00 PM February 23, 2018"

Transcription

1 February 14, 2018 ADDENDUM #2 FIBER OPTIC CABLE MAINTENANCE (Revised 1-18) IF18158 BIDS WILL BE OPENED 1:00 PM February 23, 2018 ROOM 16, CITY HALL BUILDING 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA Please acknowledge receipt of this Addendum and include with your bid proposal. Jerry Bates Purchasing Director Company Authorized Signature Date Russell Frye Buyer BID CLARIFICATIONS Please see below for questions received from potential bidders and the City s response: 1. Question: Emergency Mobilization - This is normally bid as a percentage to the job, which always reflects real cost. Will the City consider changing the units on this item from each to a percentage? o Answer: Contractors will be compensated for Emergency Mobilization at a rate of 10% of the total job amount. 2. Question: Is all the traffic control is to be included or will a separate unit be provided to bid on? o Answer: (See Page 30) Under the traffic control paragraph the last sentence states: The cost of traffic control is not a separate item and shall be included in the bid price for other items. 3. Question: Are any and all down guys and anchors to be included in the unit price for the messenger? o Answer: (See Section 7 / Page 47) Guy assemblies have their own pay items Line No. 12 and Line No. 13. Anchors and all hardware to be included in guy assemblies.

2 4. Question: Who or what is the deciding factor when a anchor and guy wire is to be installed? If a cable installed by the winning contractor is found to have not been properly anchored and the warranty period has expired, how would this be handled after the 1-year warranty? o Answer: City of Winston Signal System staff will be the deciding factor for installation of guy assemblies. They will also have inspected the work before it could be paid or invoiced. If properly inspected by the City, the work has been paid for, and past the 1- year warranty there would be no liability of the contractor. 5. Question: NC DOT requires a SDR 11 duct to be used but I do not see this in the RFP. What rating is the city requiring? (This is discussed on page 48 but does not match the SDR 11 rating of SCH 80 that NC DOT requires under their roads). o Answer: (See attachment for HDPE from original Phase-A contract) would think we would want to meet the same ratings or requirements of the original signal system installation. The SDR 11 ratings is what was required for conduit in railroad right of ways or areas where it may be exposed to heavy weight. 6. Question: If a drill shot is attempted and rock is encountered how is this handled under these units? o Answer: (See page 45) Section States: No measurement will be made for conduit installation through rock or rock-like soil conditions, regardless of the installation method employed, as such extra work, materials, and equipment will be considered incidental to conduit installation. 7. Question: Are any drill logs or GEO information required by the contractor as was in the City IS project? o Answer: (See Section 5.3.a.4) Section States: Upon completion of the conduit system for communications, furnish the Project Coordinator with a plan of record drawing detailing both the horizontal and vertical (i.e., depth) locations of the conduit system. 8. Question: Is traffic control expected to be included in this unit or will that need to be a separate unit for different situations? o Answer: See the answer from Question-2 / Page-30. Should be considered the same. The cost of traffic control is not a separate item. 9. Question: Is the winning bidder to provide certified traffic control certifications with the bid? o Answer: Certifications is recommended but not required. All traffic control is to conform to the MUTCD guidelines. City is not liable for any incident that may occur from nonconforming traffic control devices. (See page 30 section for General Provisions / Traffic Control)

3 10. Question: Will the winning contractor be required to hold a Corning NPI certification for the duration of the contract to maintain the manufactures warranty? This allows the current warranty form Corning to stay in place for 25 years. Will the cable for the IS be required to be a Corning to extend the warranty? o Answer: We are not sure. This seems too specific to using a specific manufacturer of cable. As the QPL list multiple vendors for fiber optic cable, not just Corning. Corning is not the sole manufacturer that can be used. All fiber optic cable used should meet the cable specifications that are stated in section 9.2. If using Corning, and the contractor is NPI certified, that would only be a bonus to the City. 11. Question: How is the material aspect being handled for the emergency part of the contract? Is the contractor expected to maintain and always have fiber cable and splice cases on hand so materials are not an issue for any emergency? I assume this should be covered in our units? What are the repercussions for the contractor who does not stock and cannot meet these needs? o Answer: The City of Winston-Salem will determine when fiber damage warrants an emergency situations. Contractors will be require to adhere to appropriate response time which would include furnishing materials. Spare material cost should be reflected within emergency mobilization cost for DOT and IS. Concerning repercussions, please see General Requirements sections C (contractor s responsibilities) and section E (failure to perform). 12. Question: Is tree trimming to be covered by the winning contractor under this contract? If so what unit should it be in or will a unit be established? Who is responsible for the debris and proper disposal of it? o Answer: (See section 1.2.d for Tree Trimming) Contractor must contact the City of Winston-Salem Urban Forester for review of tree trimming and to obtain permit (free) for actually performing the work to trim trees. o (See section D under the General Requirements) Contractor is responsible for disposal of all debris upon completion of work. o Tree trimming is incidental to the installation of cable. There will be no separate line item for tree trimming. 13. Question: Page 51 / Plan of Record Drawings - What exactly are the requirements? Please clarify whether we will update the current map or just turn in a new as built in the same format utilizing a Tremble GEO unit. And what unit is this to be priced in? o Answer: PDF Red line (using a PDF editing software) showing as-built conditions must be submitted electronically. See section F under the General Requirements for payment. Contractor must turn in all as-built drawings with invoices. Contact the project coordinator to obtain existing fiber plans for redlining.

4 14. Question: Page 57 / Over-sized Junction boxes provided by the city. Since these are being provided by the city can you please tell me the size so I can price in my unit accordingly? Where will we have to go to obtain these? Also what size is the special sized junction box? o Answer: Contact the project coordinator to get information on obtaining junction boxes. The oversized junction box is 30"(1) X 15"(w) X 24"(d). Special sized junction box is 36"(1) X 24"(w) X 24"(d). See Chart Below: 15. Question: Page 65 / GENERAL - The first sentence in this section talks about testing the data on the reel but I do not see where the work must be tested and the documentation the city requires upon completion of the project. What type of test results are required to be turn in on each job and what format? o Answer: With exception to the drop cable (Page-57), OTDR testing is provided or completed with the splice enclosures. Majority of cable installations for us will be done with a termination point / or splice enclosure to us an OTDR or to test from. For new cables and enclosures, OTDR reports is what is expected. If cable runs have change location or routes then updates to the as-builds would be expected as well. If doing anything with the 6 fiber drop cable or interconnect center for the drop cable, then only the OTDR traces for the fiber used from the neighboring traffic signal network locations would be expected. See section 10.3 (B) for other information or documentation to be provided with new enclosures and OTDR testing. 16. Question: Page 69 / MEASUREMENT AND PAYMENT - This unit is all inclusive and has pulling, termination and testing all in the Communications Cable and is based off the bid sheet on a specific footage. Would the City benefit from separate units based on Cable installation, Terminations and Testing so you only pay once for the exact work completed? o Answer: (NO) Work for installation of communication cable is inclusive to all things stated in that section. 17. Question: In the RFP there are no hourly rates or units just for fiber work or trouble shooting. If a cable is cut or the ring has an issue who will be able to determine the extent of the work needed? Does the city have this capability? o Answer: Space for an hourly rate quotation has been added to the proposal page, separate from the line item prices. Contractors are asked to enter their hourly rate for general services/troubleshooting there. A revised copy of the proposal pages is included with this addendum. Please substitute these revised pages when submitting your proposal.

5 18. Question: Since the NC Statues requires a contractor for any job or bid over 30K to be a General Contractor with a Public Utilities License is this required to be in the bid to be awarded this job or contract? o Answer: The section of the NC Statutes (N.C.G.S Chapter 87, Article 1) to which you are referring applies to construction and repair projects and this project is being bid as a service. No general contractor or public utility license will be required. 19. Question: Line item 21 Is the drop cable (6-fiber) plenum rated? o Answer: (No) Plenum is for indoor use / ventilation areas. All 6 fiber drop cable will be installed outside. 20. Question: Line item 22 Interconnect Center In the description of this item, it states to furnish all components inclusive to the 1RU. However, it could include multiple cables or multiple splices. How do we price not knowing exactly the total number of cables/splices/splice trays involved in each interconnect center? o Answer: All Interconnect Centers are for the 6-fiber drop cables. It will be for a 6 fiber cable, 6-splices, 6-fiber pigtail for tray, 6-fiber face plate etc. These will be installed in traffic cabinets. 21. Question: Line items Hub Splice Center Same question as #20 above. o Answer: See answer to question #20. There is individual line items (23-25) for each size HUB Splice Center and corresponding cable size we have (EX: 24,36,48, 72 count fibers) 22. Question: Line items IS Hub Splice Center Same question as #20 above. o Answer: See answer to question #20. There is individual line items (47-50) for each size IS HUB Splice Center and corresponding cable size we have (EX: 24,48,96, 144 count fibers) 23. Question: Do you have any additional specifications or diagrams? o Answer: (YES) Winning bidder will be provided technical support for system infrastructure, including current as-built plans and or diagrams. 24. Question: Do all of the parts need to come from a single source manufacturer? a. Answer: (NO) But parts must be used from the QPL list. 25. Question: per Leviton, they do not make the RDP enclosures anymore. Is there an alternative? a. Answer: Parts must be used from the QPL list. Check it to see if a similar unit can be found.

6 Please send any additional questions pertaining to this bid to all three of the following individuals: o Russell Frye / russellf@cityofws.org o Jeffrey Fansler / jeffreygf@cityofws.org o Jason Toney / jasont@cityofws.org Additional Note: the original project manager, Larry Walker, has been replaced by current project manager, Jason Toney. Please disregard all references to Mr. Walker that may appear in your original bid documents. Please be sure to include a signed copy of this addendum with your bid!

7 PROPOSAL FORM FIBER OPTIC CABLE MAINTENANCE Submit bids to: U.S. Mail address: Hand-delivery or FedEx address: City/County Purchasing City/County Purchasing P.O. Box N. Main Street, 324 City Hall Winston-Salem, NC Winston-Salem, NC BIDDER NAME: The undersigned bidder affirms and declares that he/she has carefully examined the Specifications which are acknowledged to be a part of this proposal and agrees to provide all labor, materials, equipment, supervision, insurance, permits, as well as abide by all local, state and federal codes, rules, laws, regulations, ordinances and N.C.D.O.T. Standard Specifications for Roads and Structures applicable to Fiber Optic Cable Maintenance at various locations throughout the City as described herein per the attached Specifications for the following sum to wit: Contract Period. The initial contract term will be from Notice to Proceed through June 30, It may be renewed for three (3) additional years (until June 30, 2022) if the City and Contractor agree and funds are available for this purpose. No changes in the terms, conditions, etc. of this Contract will be made when an extension to the Contract is implemented A properly executed purchase order shall be evidence of an extension agreed to by the parties and that said purchase order shall become a self-executing amendment to the contract. Additional Quantities. The City reserves the right to add additional quantities up to a maximum 100% of the original contract. If Contractor agrees to said additional quantities, payment for such will be based on the Unit Prices submitted under the Itemized Section above. Any and all additions to this Contract will be subject to all of the terms and conditions of this Contract. No additions are allowed to this Contract after its expiration date. ITEM 1- Unit Cost prices for line items given below as a labor and materials contract: Estimated Item No. Description Quantity Unit TRAFFIC SIGNAL SYSTEM ITEMS Unit 1 MESSENGER CABLE (1/4") 500 LF 2 MESSENGER CABLE (3/8") 200 LF REATTACH EXISTING MESSENGER CABLE TO 3 NEW POLE 5 EA 4 TRACER WIRE 1000 LF 5 UNDERGROUND CONDUIT (1) (2") 200 LF 6 UNDERGROUND CONDUIT (2) (2") 200 LF 7 DIRECTIONAL DRILL (1) (2") 500 LF 8 DIRECTIONAL DRILL (2) (2") 500 LF Unit Price Extended Total IF18158 Fiber Optic Cable Maintenance Page 12 of 79 Revised

8 PROPOSAL FORM / PAGE 2 Estimated Item No. Description Quantity Unit INSTALL CITY SUPPLIED JUNCTION BOX 9 (OVERSIZED, HEAVY DUTY) 2 EA 10 INSTALL CITY SUPPLIED JUNCTION BOX (SPECIAL SIZE, HEAVY DUTY) 2 EA 11 GUY ASSEMBLY (STANDARD) 2 EA 12 GUY ASSEMBLY (SIDEWALK) 2 EA 13 1" RISER WITH HEAT SHRINK TUBING 2 EA 14 2" RISER WITH HEAT SHRINK TUBING 5 EA 15 HEAT SHRINK TUBING RETROFIT KIT 15 EA 16 COMMUNCATIONS CABLE (24-FIBER) 500 LF 17 COMMUNCATIONS CABLE (36-FIBER) 200 LF 18 COMMUNCATIONS CABLE (48-FIBER) 500 LF 19 COMMUNCATIONS CABLE (72-FIBER) 200 LF 20 DROP CABLE (6-FIBER) 1500 LF 21 INSTALL INTERCONNECT CENTER 5 EA 22 HUB SPLICE CENTER (24-FIBER) 1 EA 23 HUB SPLICE CENTER (36-FIBER) 1 EA 24 HUB SPLICE CENTER (48-FIBER) 1 EA 25 HUB SPLICE CENTER (72-FIBER) 1 EA 26 INSTALL SPLICE ENCLOSURE 5 EA 27 MODIFY EXISTING SPLICE 15 EA Unit Price Extended Total 28 REMOVE EXISTING COMMUNICATIONS CABLE 500 LF 29 AERIAL CABLE PROTECTOR 500 LF 30 INSTALL SIDEWALK REPAIR 100 SY INFORMATION SYSTEMS ITEMS 31 IS TRACER WIRE 1000 LF 32 IS UNDERGROUND CONDUIT (1) (2") 200 LF 33 IS UNDERGROUND CONDUIT (2) (2") 200 LF 34 IS DIRECTIONAL DRILL (1) (2") 500 LF 35 IS DIRECTIONAL DRILL (2) (2") 500 LF 36 INSTALL CITY SUPPLIED IS JUNCTION BOX (OVERSIZED, HEAVY DUTY) 2 EA 37 INSTALL CITY SUPPLIED IS JUNCTION BOX (SPECIAL SIZED, HEAVY DUTY) 2 EA 38 IS 2" RISER WITH HEAT SHRINK TUBING 4 EA 39 IS HEAT SHRINK TUBING RETROFIT KIT 10 EA 40 IS COMMUNICATIONS CABLE (24-FIBER) 500 LF 41 IS COMMUNICATIONS CABLE (48-FIBER) 500 LF IF18158 Fiber Optic Cable Maintenance Page 13 of 79 Revised

9 Estimated Item No. Description Quantity Unit 42 IS COMMUNICATIONS CABLE (96-FIBER) 250 LF 43 IS COMMUNICATIONS CABLE (144-FIBER) 250 LF Unit Price Extended Total 44 INSTALL IS SPLICE ENCLOSURE 5 EA 45 MODIFY EXISTING IS SPLICE 10 EA 46 IS HUB SPLICE CENTER (24-FIBER) 1 EA 47 IS HUB SPLICE CENTER (48-FIBER) 1 EA 48 IS HUB SPLICE CENTER (96-FIBER) 1 EA 49 IS HUB SPLICE CENTER (144-FIBER) 1 EA 50 REMOVE EXISTING IS COMMUNICATIONS CABLE 500 EA EXTENDED UNIT PRICE SUM TOTAL: $ Hourly Rate for Troubleshooting/General Contract Work: _$ Per Hour Note: Emergency Mobilization will be compensated at the rate of 10% of the total job amount. Note: Should math errors occur in the calculation of extended totals, UNIT PRICES SHALL PREVAIL. Contractor may not begin work and a Purchase Order WILL NOT be issued until the individuals doing business with or for the City has satisfied specification provisions for Insurance and the Contract has been executed. All bidders MUST submit with their bid the enclosed Non-Collusion Affidavit of Prime Bidder. IF18158 Fiber Optic Cable Maintenance Page 14 of 79 Revised

10 ... C-5224A- Winston-Salem Signal System - Phas.JL ~ DESCRIPTION 6. UNDERGROUND CONDUIT Furnish and install conduit for underground installation with tracer wire, miscellaneous fittings, all necessary hardware, marker tape, backfill, graded stone, paving materials, and seeding and mulching MATERIALS (A) General Except for HDPE conduit, furnish material, equipment, and hardware under this section that is pre-approved on the ITS and Signals QPL. (B) Refer to the following articles of the Standard Specifications: Backfill Graded Stone and Conduit Bodies, Boxes and Fittings Use conduit bodies, boxes, and fittings that meet UL Standard 514A or 514B for electrical and communications installations. (C) Conduit Types (1) Rigid Metallic Conduit Provide rigid hot dipped galvanized steel conduit that meets UL Standard 6 with rigid full weight sherardized or galvanized threaded fittings. (2) PVC Conduit Provide non-metallic conduit and duct including associated couplings, approved for below ground use with or without concrete encasement in accordance with UL Standard 651A. Provide Schedule 40 conduit unless otherwise specified. (3) Solid Wall HDPE Conduit Use HDPE conduit that conforms to UL Standard 651B. Provide conduit meeting the requirements of the table below with minimum wall thickness ratios corresponding to EPEC-40 (Schedule 40), EPEC-80 (Schedule 80) or EPEC-B (SDR 13.5) as listed in UL Standard 651B, Table 5.1, 5.2 and 5.3. Provide HDPE conduit with an outer diameter to minimum wall thickness ratio that complies with ASTM D 3035, Standard Dimension Ratio (SDR) 11 or better (thicker wall) for use in railroad rights-of-way. Provide HDPE conduit with an outer diameter to minimum wall thickness ratio that complies with ASTM D 3035, Standard Dimension Ratio (SDR) 13.5 for all other applications. Based on NCDOT ITSS Project Special Provisions, Version Print Date: 2/7/2013

11 C-5224A- Winston-Salem Signal System - Phase,A_ 99 Conduit Trade Size HDPE CONDUIT SIZE Furnish 1" EPEC /4" EPEC " EPEC-B (SDR 13.5) 2" EPEC-B (SDR 13.5) 2-112" EPEC-B (SDR 13.5) 3" EPEC-B (SDR 13.5) 4" EPEC-B (SDR 13.5) 5" EPEC-80 6" EPEC-80 Ensure the PE resin compounds used in manufacturing the conduit meet or exceed the cell classification PE C (black with 2% minimum carbon black) or PE E (colored conduit with UV inhibitors) in ASTM D3350 and the table below. RESIN PROPERTIES Property Density Melt Index (condition 190/2.16 is acceptable) Flexural Modulus Tensile Strength Elongation Slow Crack Growth Resistance Hydrostatic Design Basis UV Resistance (Outdoor Conduit Only) Requirement Test Method ASTMD g/ctru ASTMD792 ASTMD4883 < 0.4 grams/10 minutes ASTMD ,000 psi, min. ASTMD790 Tensile Strength 3,000 psi, min. Elongation 400%, min. An ESCR as per condition B, 10% IGEP AL requirement off50>24 hrs is allowable "0" for Non-Pressure Rated Pipe Stabilize with at least 2% by weight carbon black or colored with UV Inhibitor ASTMD638 ASTMD638 ASTMD1693 ASTMD2837 ASTMD4218 Based on NCDOT ITSS Project Special Provisions, Version Print Date: 2/7/2013

12 C-5224A- Winston-Salem Signal System - Phase" 100 Furnish conduits in the colors for the applications shown in the table below. For conduits manufactured with stripes, ensure the stripes are uniformly located around the conduit with 120 degrees of separation. Do not use "Solid Yellow" or "Black with Yell ow Stripes" conduit. CONDUIT COLORS Conduit Contents Preferred Solid Color Alternate Signal Cable Black None Loop Lead-in Cable White Black with White Stripes Communications Cable (Copper, Fiber Optic, Coaxial)_ Orange Black with Orange Stripes Electrical Power Cable Red Black with Red Stripes Ensure the HDPE conduit is resistant to benzene, calcium 1 chloride, ethyl alcohol, fuel oil, gasoline, lubricating oil, potassium chloride, sodium chloride, sodium nitrate and transformer oil and is protected against degradation due to oxidation and general corroston. Furnish factory lubricated, low friction, conduit with a coefficient of friction of0.10 or less in accordance with Telcordia GR-356. Ensure the supplied conduit is identified and certified as meeting, UL Standard 651B. Ensure the conduit is marked at least with the following information on 10 ft or less intervals: 1) Material: HDPE 2) Trade Size: i.e., 2" 3) Conduit Type: SDR 13.5 or EPEC-B 4) Manufacturer's name or trademark 5) Manufacturer's identity code to identify manufacturing date, facility, etc. 6) UL symbol or UL listing number Furnish coilable conduit that is supplied on reels in continuous lengths for transportation and storage outside. Ensure that the process of installing the coilable conduit on the reel does not alter the properties or performance of the conduit for its intended purpose. (D) Conduit Plugs, Pull Line, and Tracer Wire Furnish conduit plugs that provide a watertight barrier when installed in conduit. Furnish conduit plugs sized in accordance with conduit. Ensure conduit plug provides a means to secure a pull line to the end of the plug. Provide removable and reusable duct plugs. Conduit plugs are not required to be listed electrical devices. For all spared conduits, furnish 3/4", pre-lubricated, woven polyester tape, pull line with minimum rated tensile strength of 2,500 lb. Pull lines are not required to be listed electrical devices. Based on NCDOT ITSS Project Special Provisions, Version Print Date: 2/7/2013

13 ... C-5224A- Winston-Salem Signal System - Phas!..~ 11.2 (C) Junction Box Sizes Provide junction boxes and covers of the following sizes as called for in the Plans: Junction Box Size Standard Size Oversized Special-Sized Minimum Inside Dimensions 16"(1) x lo"(w) x 10"(d) 30"(1) X 15"(w) X 24"(d) 36"(1) X 24"(w) X 24"(d) 7.3. CONSTRUCTION METHODS (A) General Install junction boxes flush with finished grade. Backfill beneath and around the junction box using #67 washed stone as shown in NCDOT Roadway Standard Drawing No Do not install sealant compound between junction boxes and covers. Upon completion of junction box installation and backfilling of all excavations, restore the disturbed ground to its original condition as determined and approved by the Engineer. For paved areas, replace removed or damaged pavement with in kind materials, matching the elevation, color, texture/finish and general appearance of the surrounding pavement. Refer to Section 1 of these Project Special Provisions for additional requirements concerning sidewalks and curbs in historic districts. For unpaved areas, backfill excavations with removed material, tamp the backfilled material and rake smooth the top 1 Yz inches. Finish unpaved areas flush with surrounding natural ground and to match the original contour of the ground. Seed with same type of grass as surrounding area and mulch the newly seeded area. If unpaved area was not grassed, replace the original ground cover in kind as directed by the Engineer. Complete restoration of all ground disturbed during junction box installation within five consecutive calendar days following initial removal and excavation. If the Contractor fails to repair and restore the disturbed ground in accordance with these Project Special Provisions within the time frame specified, the Department reserves the right to make the necessary repairs, and all expenses incurred by the Department in making the repairs and restoring the ground will be deducted from payment due the Contractor, plus $500 liquidated damages per occasion, per day, or any portion thereof, until corrected. Install standard size junction boxes as shown in the Plans and where underground splicing of electrical cables is necessary. Install standard size junction boxes within 3 feet of pole or pole foundation where transitioning from below ground to a riser assembly. Install standard size junction boxes within 5 ft of each end of each lateral run of conduit for electrical cables. When lateral runs for electrical cables are greater than 150 feet, install additional junction boxes to ensure distances between junction boxes does not exceed 150 feet. Install oversized junction boxes as shown in the Plans in underground fiber-optic communications cable runs where the conduit run transitions from directionally drilled conduit to trenched conduit and where transitioning from below ground to a riser assembly. Install Based on NCDOT ITSS Project Special Provisions, Version Print Date: 2/7/2013