THE TREASURE TOWER PROGRESS REPORT

Size: px
Start display at page:

Download "THE TREASURE TOWER PROGRESS REPORT"

Transcription

1 THE TREASURE TOWER PROGRESS REPORT About the Project: Project Developer Title of Project Project Reference Design & Supervision Consultant Interior Design Consultant Main Contractor Bin Faqeeh Real Estate Investment Company S.P.C. The Treasure Tower BFTT/16/ /2017 Arab Architects Horizon Interiors United Arab Construction Co. (UACC) About Progress Report: Title of Document Progress Report of The Treasure Tower Reporting Period May 1, 2017 to May 31, 2017 Authors & project role United Arab Construction Co. (UACC) Date June 11, 2017

2 DESCRIPTION PERCENTAG E (%) OF COMPLETIO N REMARKS MOBILIZATION SUB STRUCTURE a. Earth work Excavation Rock Filling Desert Filling Backfilling to footing b. Concrete work Piling Pile setting out, trimming & soil removal Pile head waterproofing c. Blinding For pile cap bases 100mm For tie beams 100mm thick For underground water tank d. SRC 45N Concrete For pile cap For tie beams Columns, shear walls, lift, walls up to basement level Foundation for retaining wall For grade slab For underground water tank concrete Internal water proof for water tank (epoxy) External water proof for water tank SUPER STRUCTURE Block Works 200mm thick Al Abyad Insulated Work for external walls External block works 200mm Thickness 200mm, 150mm and 100mm Finishes Plaster to receive paint finish Internally Plastering as backing 12mm thick to receive ceramic wall tiles Plastering as backing 12mm thick to receive ceramic wall tiles kitchen Marbleized wall tiling (toilets & kitchens) glazed ceramic wall tiles of approved size, pattern (zero joint) Unglazed ceramic/ porcelain floor tiles bedded in cement sand 1:4 and pointed with waterproof grout as shown in detailed drawings and as per consultant approval, for bedrooms, living halls, corridors

3 Water Proofing For all toilets and bathrooms Roof water proofing to receive tiles Wall Finishes Painting in cement in plaster layers/concrete walls internally and externally 90% In Progress Ceiling Works Ordinary Gypsum 98% In Progress (moisture resistant) Gypsum 98% In Progress Other Works Preliminaries 95% In Progress Dewatering Waterproofing for Shear Wall Foundation, Shear Wall, Tie Beam, Ground Slab Bottom, Pile Cap Lintels Coping Beam Concrete Ramp Concrete AC Upstand (Mezzanine, 1st to 11th floor & roof Iso-board Vibration Pad for ACU upstand at Balcony, Roof Manhole Cover 90% In Progress Strengthening of Lift roof slab, Nib wall, External Plastering, Separator Beam inside lift Shaft Floor Screed Bedroom and Gym Ceiling Works on Balconies Painting, wall primer paint on lift shaft, Wall Skirting, Waterproofing Balconies, Fire sealant External Painting 95% In Progress Thick Block filled at Lift Lobby on all Levels Additional Water proofing for Landscape and Swimming Pool surrounding area Marble Protection

4 On-site photos: (Front Elevation) (Left Elevation) (Right Elevation) (Rear Elevation)

5 (Removal of Marble protection on 10th floor Lift Lobby) (10th Floor - Corridors) (Ground Floor Reception Area Light Fitting)

6 (Mezzanine Floor Spa Jacuzzi work in progress) (Ground Floor Fountain Area) (Epoxy Flooring Works, Building Protection System in Ground Floor Car Park Area) (Epoxy Flooring Works, Building System in Basement Floor Car Park Area)

7 (Swimming Pool Area Pergola work in progress) (Landscape Area Trellis work in progress) (1 st Floor Swimming Pool and Landscape Area work in progress)

8 (Cladding and Glazing Works in progress)