1 SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: » Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1

2 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE» Continued Installing Attic Building G.» Continued Precast Building E.» Continued Foundations for Building E Sequence 2.» Completed 4th floor Topping Building F» Backfilled Building F.» Prep for Building G.» Installed HM Door Building G. Bldg. G Door Frames Bldg. E Precast Bldg. F Toping Slab SITE, HUB, & WEST ZONE» Continued Chilled Water Pipe West Zone» Continued Chipping Pile HUB.» Continued Footings and HUB.» Completed Storm Line West Spine» Completed Communication Ductbank HUB Utility Yard.» Began Forming Walls and HUB.» Completed Chilled Water Tie In from HUB to Cooling Tower. Erosion Newman Road Foundation HUB February 28, 2016 Page 2

3 NEXT WEEK S ACTIVITIES EAST ZONE» Continue Installing Attic Building G.» Begin Roof Building F.» Tie - In Sanitary Building G.» Begin Sequence 2 Building E.» Continue Framing Interior Building G 3rd Floor.» Continue Decking and Ice & Water Bldg. G. HUB Wall Formation SITE, HUB, & WEST ZONE» Begin Crane West Zone.» Continue Forming Walls and HUB.» Install Ductbank form MH4 E&C to MH6 E&C.» Continue Grade HUB.» Install Storm Line 9 South of Bldg. A.» Install Ductbank form Existing Manhole to MH 10. East Parking Lot Striping February 28, 2016 Page 3

4 MANPOWER TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Holder Construction Company General Contractor American Deep Foundation Auger cast piles Baker Roofing Sheathing and Shingles C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Gainesville Mechanical Plumbing Hutch-N-Son Early Site Work st Choice Glass Glass JBR Construction Early Site Work King Asphalt Asphalt Labor Finders Labor Force Metro Power Underground Electrical Osteen Chill Water pipe Precision Concrete R.E. Mclean Tank Tank Demo Reeves Grading Site Grading & Utilities RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Silt Fence Installation Site Erosion Control Southern Mechanical Inc. Electrical/Plumbing Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading TOTAL February 28, 2016 Page 4

5 WEATHER CURRENT WEEK Rain Days This Week = 2 Rain Days To Date = 43 SAFETY REVIEW LOG Man-hours worked Douthit Hills Monthly OSHA Statistics RCR/DART Mar-15Apr-15May-15Jun-15 Jul-15 Aug-15Sep-15Oct-15Nov-15Dec-15 Jan-16Feb-16 0 Mar-15 Apr-15 May- 15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Cumulative Man-Hours RCR DART R February 28, 2016 Page 5

6 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power American Deep Foundations Davis Crane Erectors Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Mechanical Baker Roofing Holder February 28, 2016 Page 6