MONTHLY PROGRESS REPORT AUGUST, 2018

Size: px
Start display at page:

Download "MONTHLY PROGRESS REPORT AUGUST, 2018"

Transcription

1 MONTHLY PROGRESS REPORT AUGUST, 2018 RAS OFFICERS INSTITUTE (CLUB HOUSE) (2, institutional Area, Near Dainik Bhaskar, Jaipur) Developers: M/S RAS Officers Institute 2, institutional Area, Near Dainik Bhaskar-Jaipur Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)

2 Project Highlights Total Built up Area: - 1, 20,000Sq.ft Total Floor of Project: -2 Basement + 6 Floors (Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash) Builders & Developers M/S RAS Officers Institute, Registered office at 2, institutional Area, Near Dainik Bhaskar- Jaipur (Raj.) Consultants & Management Team Architectural Consultant Project Management Consultants Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall, New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur Mr. Lokesh JoshiMob: Phone: , Mr. Kulvinder Singh Mob: Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur Mr. Sandeep Garg Mob: Mr. Sanjay Vajpayee Mob: Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR Ms. Ritu Khandelwal Mob:

3 Contractor Agencies Civil Contractor Electrical Work Contractor M/S H. R. Gwala M/S Vijay Electric service F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala. Mr. H.R. Gwala Mob: Mr. Shyam Vijay Mob: Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur Mr. Jeet Ram Mob: Mr. Shrikant Dandia Mob: Fire Fighting Contractor False Ceiling Contractor M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd. S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: Mr. Ravi Kumawat Mob: Heating, ventilation, and air conditioning (HVAC) Daikin Air conditioning India Pvt. Ltd (Higher Side) S , Second Floor, Geejgarh Tower, Hawa Sadak Jaipur, M/s K.P. Airtech (Lower Side) Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road, Jaipur , Rajasthan. Mr. K.K. Sharma Mob:

4 INDEX S. No. Content Page. No. (i) Executive Summary 5 (ii) Project View 5 (iii) Milestone Achieved: At Execution Level 6 (iv) Manpower & Material Status 6-8 (v) Proposed Schedule & Material Procurement Details 8-11 (vi) Drawing Status 12 (vii) Progress Photographs (viii) Cube Test Report 18 (ix) Pending Decisions & Requirements 19 Distribution to:- (i) RASO I Members (ii) Architect Design & Services (ADS)-Architectural Consultant (iii) Sthapatya- Interior Designer 4 P a g e

5 EXECUTIVE SUMMARY Terrace floor columns shuttering,bar binding & casting 40% completed. Upper basement ramp slab & driveway slab shuttering & bar binding completed. Upper Basement Ramp R/W steel binding, shuttering & casting completed. Fourth & fifth floor brick masonry work in progress. First Floor plastering work in progress. First & second floor low-voltage wall conducting work in progress. First & second floor electrical wall conducting work completed. Sprinkler line laying of third floor.(scope of fire fighting work). HVAC ducting work in progress. Fire Staircase third Floor LVL. BB, Shuttring & Casting in progress. PROJECT VIEW as on 31 st August 18 5 P a g e

6 MILESTONES ACHIEVED (i) At Execution Level:- (i) Terrace floor mumti slab shuttering completed. (ii) Casting of terrace floor columns concreting (casting) 40% completed. (iii) Brick masonry of second floor completed as per revisions. (iv) Plastering work started at first floor. (v) HVAC (Ducting) work Started. (vi) Electrical low-voltage wall conducting work started at first floor. (vii) Building Front Side Plantation completed. At Decision Level:- (i) Nil. MANPOWER DEPLOYED AT SITE STATUS Total Manpower Deployed at Site by different Agencies / Vendors Manpower Details Till 31 st August 18 S. No. Name of Contractor Work Skilled Unskilled Total 1.0 H.R. Gwala Civil Work SK Burman/ (H.R. Gwala) Shuttering Govind/(H.R. Gwala) Bar Binding Ashok/ (H.R. Gwala) Brick Work Bharosi/ (H.R. Gwala) Plaster Work Vijay Electrical Service Electrical Gayatri Plumbing Plumbing NS Solutions Waterproofing Man At Work Fire Fighting WhiteWash White Wash K.P. Airtech HVAC Total P a g e

7 MATERIAL STATUS A. Steel Received & Consumed Details in August 18 Diameter of Bar Received Till Date (MT) Received in August 18 (MT) Consumed in August 18 (MT) Total Consumed till Date (MT) Balance at Site as on (MT) 8mm mm mm mm mm mm mm Total (MT) B. Cement Consumed & Received Details in month of August 18 Location Received Till Date (Bags) Received in August 18 (Bags) Consumed Till Date (Bags) Consumed in August 18(Bags) Balance at Site as on (Bags) Remarks At Site At RMC Bags Amount adjusted in Vendor s Plant 372=5420 Bill Total (Bags) C. Aggregate Consumed & Received Details in month of August 18 (i) 10mm Aggregate Location Received Received Consumed Consumed in Balance at Site Remarks Till Date in August 18 Till Date August 18 as on At Site At RMC Excess 765 C.ft Amount adjusted in Vendor s Bill Plant Total (i) 20mm Aggregate Location Received Received in Consumed Consumed in Balance at Site Remarks Till Date August 18 Till Date August 18 as on At Site At RMC Excess 219 C.ft Amount adjusted in Vendor s Bill Plant Total P a g e

8 D. Sand Consumed & Received Details in month of August 18 Location Received Received Consumed Consumed in Balance at Site Remarks Till Date in August 18 Till Date August 18 as on At Site At RMC C.ft Amount adjusted in Vendor s Bill Plant Total E. Bricks Consumed & Received Details in month of August 18 Location Received Received in Consumed in Consumed Till Till Date August 18 August (Nos.) Date (Nos.) (Nos.) (Nos.) Balance at Site as on (Nos.) At Site Total (Nos.) F. AAC Block Consumed & Received Details in month of August 18 Location Received Till Date (Nos.) Received in August 18 (Nos.) Consumed Till Date (Nos.) Consumed in August (Nos.) Balance at Site as on (Nos.) At Site Total (Nos.) PROPOSED SCHEDULES FOR THE MONTH OF SEPTEMBER 18 Following activities are planned for the Month of September 18 (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) (xi) (xii) (xiii) Completion of Terrace Floor Parapet wall shuttering, bar binding & concreting (casting) work. Completion of Mumty & O.H. Tank Slab shuttering, bar binding & casting work. Fire Staircase up-to Fifth Floor Level bar binding, shuttering & Casting work. Fourth & Fifth Floor brick work. Driveway Slab with Ramp shuttering, bar binding & concreting (casting) work. Earth filling in surrounding areas of building. Lower Basement & Ground Floor Plumbing Drainage & Toilets Internal Works. U.G. Water tank Excavation & Raft shuttering, bar binding & concreting (casting) work. Second to fourth Floor Electrical Wall Conducting Works. First Floor to Third Floor Sprinkler line laying (Fire Fighting). Ground Floor HVAC Duct making & Installation. Boundary wall foundation & brick work. First & Second Floor Plastering Work. 8 P a g e

9 STEEL & CEMENT REQUIREMENT FOR THE MONTH OF SEPTEMBER 18 A. Steel Requirement Detail for the Month of September 18 S. No. Location of Use Dia. Of Bars # Required Quantity (MT) Available at Site (MT) Net Required Quantity (MT) 8mm mm O.H,U.G. water tanks, Fire staircase Boundary wall Beams & Columns. 12mm mm mm mm mm Total Qty Required (MT) MT 24.5 MT 7.50 MT A. Cement Requirement Detail for the Month of September 18 (i) Cement (PPC) At site S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags) 1 PCC & RCC Work (i) Drive way Slab & Ramp Casting (up to ground LVL.) 83 Cum (ii) Terrace Floor Columns & O.H Water Tanks & Mumti Slab 140 Cum (iii) U.G. water tank raft & Walls 50 Cum (iv) Brickwork of Fourth & Fifth Floor 150 cum Total Required Bags of Cement for the Month of September Total Available Bags of Cement at Site 900 Net Required Bags of Cement for the Month of September Say P a g e

10 B. Aggregate Requirement Detail for the Month of September 18 (i) 10mm Aggregate S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (i) Drive way Slab & Ramp Casting (up to ground LVL.) 83 Cum (ii) Terrace Floor Columns & O.H Water Tanks & Mumti Slab 140 Cum (iii) U.G. water tank raft & Walls 50 Cum Total Required Qty of 10mm Aggregates for the Month of September Total Available Qty of 10mm Aggregate at Site 1500 Net Required Qty of 10mm Aggregate for the Month of September Say 2000 (ii) 20mm Aggregate S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (i) Drive way Slab & Ramp Casting (up to ground LVL.) 83 Cum (ii) Terrace Floor Columns & O.H Water Tanks & Mumti Slab 140 Cum (iii) U.G. water tank raft & Walls 50 Cum Total Required Qty of 20mm Aggregates for the Month of September Total Available Qty of 20mm Aggregate at Site 1400 Net Required Qty of 20mm Aggregate for the Month of September Say 3500 C. Sand Requirement Detail for the Month of September 18 (i) Sand S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (i) Drive way Slab & Ramp Casting (up to ground LVL.) 83 Cum (ii) Terrace Floor Columns & O.H Water Tanks & Mumti Slab 140 Cum U.G. water tank raft & Walls 50 Cum (iii) Brickwork of Fourth & Fifth Floor 150 cum Total Required Qty of Sand for the Month of September Total Available Qty of Sand at Site 200 Net Required Qty of Sand for the Month of September Say P a g e

11 D. Bricks Requirement Detail for the Month of September 18 S.No Description of Work Unit Qty Reqd. (i) Fourth &Fifth Floor Brickwork. Nos (ii) Boundary Wall Brickwork.(front Side) Nos Total Required Qty. of Bricks for the Month of September Total Available Qty of Bricks at Site Net Required Qty of Bricks for the Month of September Say E. AAC Block (9 )Requirement Detail for the Month of September 18 S.No Description of Work Unit Qty Reqd. (i) Third & Fourth Floor Brick work. Nos Total Required Qty. of Bricks for the Month of September Total Available Qty of Bricks at Site - Net Required Qty of Bricks for the Month of September Say 3500 A. Weekly Material Procurement Schedule month of September 18 S. NO. WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF SEPTEMBER 18 MATERIAL DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK TOTAL QUANTITY Remarks (if any) 1 Steel MT 2 Cement(PPC) Bags 3 10mm Aggregate C.Ft 4 20mm Aggregate C.Ft 5 Sand C.Ft 6 Bricks Nos. 6 AAC Block Nos. 11 P a g e

12 12 P a g e DRAWING STATUS Status of Drawings in the Month of August 18 Following is the status of drawings in month of August from Architect Design & Services (ADS) by PMC Engineer and issued to concerning Contractors at site. S.No Date of Rev. Drawing Title Drawing No. Received No. Remark Guard Room Working Plan D/Exterior/RASCLUB/GFP - Received H.T.Room & Guard Room Working Plan D/Exterior/RASCLUB/GFP - Received Fifth Floor Working Plan 176/RASC/FFW/14 - Received 4 - Terrace Floor Working Plan - - Not Received Ramp slab at driveway lvl.detail - - Received Lower Basement Fire Fighting Layout 176/RASC/LBP/SD - Received Upper Basement Fire Fighting Layout 176/RASC/UBP/07 Received Ground Floor Fire Fighting Layout 176/RASC/GBP/09 Received First Floor Fire Fighting Layout 176/RASC/FBP/10 Received Second Floor Fire Fighting Layout - Received Third Floor Fire Fighting Layout 176/RASC/FBW/10 Received Fourth Floor Fire Fighting Layout 176/RASC/FBW/10 Received Fifth Floor Fire Fighting Layout 176/RASC/FBW/14 Received Lower Floor Electrical Plan - Received Upper Floor Electrical Plan - Received Ground Floor Electrical Plan - Received First Floor Electrical Plan - Received Lower basement spl Beam Detail - Received Ramp Slab at Driveway lvl Detail - Received Lower Basement to Fifth Floor Working Received - Plans Lower Basement to Fifth Floor L.V. Details - Received CCTV Diagram - Received DATA Diagram - Received 24 Electrical Distribution & load breakup Received with DB Schedule. 25 Mumti & water bottom slab Shuttering Received /RASC/TFP/WTS/15B Plan List of Drawings Required in September 18 Following Drawings are required at site in the Month of September 18 S. No. Drawing Title Date of Requirement on OR Before 1 Revised U.G. Water Tank Shuttering & Reinforcement Details Terrace Floor Column & Covering Details with Sections STP & Rain water harvesting Pit Details With Sections West & South Side Boundary Wall Plans With Sections Final Building Elevation Details With Sections Outer Development Details With Sections Electrical working plan (Third to Fifth Floor) rd to Terrace Floor Fire Staircase Reinforcement Details Revised Door-Window Schedule Revised MEP Plan (HVAC, Fire Fighting System) False Ceiling Plans (Lower to Fifth Floor) with Section & Sectional 11 Details

13 PROGRESS PHOTOGRAPHS Site View 31 th August 18 Site visit by Structural consultant & Architect 13 P a g e

14 Progress Review Meeting at DLB Office 14 P a g e

15 Project Review Meeting at Site Project Review meeting at Site on every Thursday with all vendors and consultants P a g e

16 Plastering Work in Progress at First Floor AAC Block Masonry Work In Progress at Fourth & Fifth Floor 16 P a g e

17 Fire Fighting Work In Progress at Second & Third Floor Front Side Plantation at Site 17 P a g e

18 Cube Testing Report Month of August P a g e

19 MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE Some other decisions pending at site are as follows:- (i) (ii) (iii) (iv) Plumbing Material Vendors to be finalized for procurement. Elevator (Lift) Vendor to be finalized. Swimming pool Vendor to be finalized. Flooring & Wall Tiles Make & Pattern to be finalized. Signature Signature Mr. Vipin Pachlangia Mr. Kulvinder Singh (Project Head) (PMC Head) Mobile: Mobile: P a g e