1 ADDENDUM NO. 1 TO: PLANS AND SPECIFICATIONS FOR STATE OF MISSOURI KITCHEN RENOVATIONS BOONVILLE CORRECTIONAL CENTER BOONVILLE, MISSOURI PROJECT NO. C Bid Opening Date is: (Not Changed) 1:30pm, Thursday, April 13, 2017 Bidders are hereby informed that the Construction Plans and/or Specifications are modified as follows: SPECIFICATION CHANGES: 1. Section TABLE OF CONTENTS: ADD Section Plastic Paneling (4 pages) to Division 6 WOODS AND PLASTICS AND COMPOSITES and INSERT attached Section into project manual. 2. Section WALL AND DOOR PROTECTION: Paragraph 2.1-A and 2.1-A. 1. b: REVISE all stainless steel wall panels to 16 gauge. DRAWING CHANGES: 1. Sheet A-001 Wall Type Schedule and Details. Detail 1 WALL TYPES: Tag S1 - REVISE the SUPPORT description to: 16 GA STAINLESS STEEL PANELS UP TO 7 AFF. ABOVE 7, INSTALL NEW FRP PANELS UP TO CEILING. See section for requirements. 2. Sheet A-103 Main Level Phase Orientation Plan. REMOVE and REPLACE with attached revised sheet. Note interior elevation reference. Note added General Plan Note #9. 3. Sheet A-104 Main Level Phase Orientation Reflected Ceiling Plan. REMOVE and REPLACE with attached revised sheet. Note revisions to Reflected CLG Legend and Phase 1 & 2 ceiling revisions. 4. Sheet A-111 Main Level Plans Phase 1. REMOVE and REPLACE with attached revised sheet. Note revisions to General Plan Notes, Reflected CLG Legend and Reflected Ceiling Plan. 5. Sheet A-112 Main Level Plans Phase 2. REMOVE and REPLACE with attached revised sheet. Note revisions to Floor Plan, General Plan Notes, Reflected CLG Legend and Reflected Ceiling Plan. 6. Sheet A-113 Main Level Plans Phase 3. ADD General Plan Note #9: Refer to Mechanical plans for floor drain, floor sink and floor clean out locations. Page 1 of 3

2 7. Sheet A-114 Main Level Plans Phase 4. ADD General Plan Note #9: Refer to Mechanical plans for floor drain, floor sink and floor clean out locations. 8. Sheet A-115 Main Level Plans Phase 5. ADD General Plan Note #9: Refer to Mechanical plans for floor drain, floor sink and floor clean out locations. 9. Sheet A-116 Main Level Plans Phase 6 & 7. ADD General Plan Note #9: Refer to Mechanical plans for floor drain, floor sink and floor clean out locations. 10. Sheet A-117 Roof Demolition Plan & Roof Plan. REMOVE and REPLACE with attached revised sheet. Note revisions to the General Roof Demolition Notes 15 & 16. Note revisions to the Roof Plan and to Roof Plan General Notes 3 & Sheet A-202 Interior Elevations Phase 2. REMOVE and REPLACE with attached revised sheet. Note revisions to details 1 & Sheet A-203 Exterior Elevations & Wall Sections: a. Refer to Detail 3, REVISE EXST PLASTER CEILING to NEW 5/8 TYPE X GPDW, PT, LAMINATED ONTO EXST PLASTER CEILING. b. Refer to Detail 4, REVISE EXST PLASTER CEILING, PT to NEW 5/8 TYPE X GPDW, PT, LAMINATED ONTO EXST PLASTER CEILING. c. Refer to Detail 5, REVISE EXST CONC WALL to EXST CMU WALL. 13. Sheet A-301 Building Sections. REMOVE and REPLACE with attached revised sheet. Note revisions to details 1, 2 & Sheet A-501 Plan & Section Details: a. DETAIL E: REVISE SCHLUTER SCHIENE EDGE TRIM, STAINLESS STEEL to ALUMINUM EDGE TRIM PER SPEC TYP. b. ADD new Detail M attached. 15. Sheet A-801 Food Service Equipment Plan. REMOVE and REPLACE with attached revised sheet. Note revisions to Food Service Equipment Plan and Equipment Schedule. 16. Sheet A-803 Plumbing / Electrical Connection Plan. REMOVE and REPLACE with attached revised sheet. Note revisions to Plumbing / Electrical Connection Plan. 17. Sheet E-104 Main Level Lighting Plan. REMOVE and REPLACE with attached revised sheet. Note revisions to Main Level Lighting Plan, Lighting Fixture Schedule and Main Level Lighting Plan Notes. 18. Sheet E-105 Main Level Power & Auxiliary Systems Plan: a. Receptacles installed in the new partial height wall (between grid lines 2 & 3, and C.1 & C.9) shall be at +38 AFF, just below the bond beam of the new partial height wall. Coordinate with detail 4 sheet A-301. Page 2 of 3

3 b. DSS-1 in Manager Office 114, DSS-2 in Clerk Office 115, and DSS-3 in Inmate Breakroom 116 are to be in heavy lineweight as they are new equipment. Per Key Note 17 on this sheet. By the Order of: P. Bryan Chinn, PE Section Leader-Project Management Unit Division of Facilities Management, Design and Construction March 22, 2017 END ADDENDUM NO. 1 Page 3 of 3

4 SECTION PLASTIC PANELING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Plastic sheet paneling, Noted as FRP in the drawings. B. Related Requirements: 1. Section "Rough Carpentry" for wood furring for installing plastic paneling. 2. Section "Wall and Door Protection" for corner guards installed adjacent to plastic paneling. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product. Submit sufficient manufacturer's data to indicate compliance with these specifications, including: 1. Preparation instructions and recommendations. 2. Storage and handling requirements and recommendations. 3. Installation methods. B. Shop Drawings: Submit elevations of each wall showing location of paneling and trim members with respect to all discontinuities in the wall elevation. C. Selection Samples: Submit manufacturer s standard color pattern selection samples representing manufacturer's full range of available colors and patterns. D. Samples for Verification: Submit appropriate section of panel for each finish selected indicating the color, texture, and pattern required. 1. Submit complete with specified applied finish. 2. Exposed Molding and Trim: Provide samples of each type, finish, and color. E. Manufacturers Material Safety Data Sheets (MSDS) for adhesives, sealants and other pertinent materials prior to their delivery to the site. 1.4 REFERENCES A. American Society for Testing and Materials: Standard Specifications (ASTM): PLASTIC PANELING

5 1. ASTM D Izod Impact Strengths (ft #/in) 2. ASTM D Water Absorption (%) 3. ASTM D Tensile Strengths (psi) & Tensile Modulus (psi) 4. ASTM D Flexural Strengths (psi) & Flexural Modulus (psi) 5. ASTM D Barcol Hardness 6. ASTM D Standard Specification for Glass-Fiber Reinforced Polyester Wall and Ceiling Panels. 7. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials. 1.5 QUALITY ASSURANCE A. Conform to building code requirements for interior finish for smoke and flame spread requirements as tested in accordance with: 1. ASTM E 84 (Method of test for surface burning characteristics of building Materials) a. Wall Required Rating Class A. B. Sanitary Standards: System components and finishes to comply with: 1. United States Department of Agriculture (USDA) requirements for food preparation facilities, incidental contact. 2. Food and Drug Administration (FDA) 1999 Food Code Canadian Food Inspection Agency (CFIA) requirements. 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver materials factory packaged on strong pallets. B. Store panels and trim lying flat, under cover and protected from the elements. Allow panels to acclimate to room temperature (range of 60 to 75 F) for 48 hours prior to installation. 1.7 PROJECT CONDITIONS A. Environmental Limitations: Do not deliver or install plastic paneling until spaces are enclosed and weathertight and temporary HVAC system is operating and maintaining ambient temperature and humidity conditions at occupancy levels during the remainder of the construction period. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Acceptable Manufacturers: 1. Crane Composites, Inc.; W Eames St., Channahon,IL (800) FAX (815) sales@cranecomposites.com 2. Marlite; 1 Marlite Drive, Dover, OH FAX (330) info@marlite.com PLASTIC PANELING

6 3. Parkland Plastics, Inc; P.O. Box 339, 104 Yoder Drive, Middlebury, IN (800) FAX (574) Or equal product from other approved manufacturers, if and as specifically approved by Architect by Addendum during bidding period. B. Source Limitations: Obtain plastic paneling and trim accessories from single manufacturer. 2.2 PLASTIC SHEET PANELING A. Glass-Fiber-Reinforced Plastic Paneling: Gelcoat-finished, glass-fiber-reinforced plastic panels complying with ASTM D Panels shall be USDA accepted for incidental food contact. Surface-Burning Characteristics: As follows when tested by a qualified testing agency according to ASTM E 84. Identify products with appropriate markings of applicable testing agency. a. Flame-Spread Index: b. Smoke-Developed Index: 450 or less. 2. Nominal Thickness: Not less than 0.09 inch (2.3 mm). 3. Surface Finish: Smooth. 4. Color: White. Color selection to be verified with Architect. 2.3 ACCESSORIES A. Trim Accessories: Manufacturer's standard Heavy weight extruded aluminum 6063-T5 alloy extrusions prefinished at the factory designed to retain and cover edges of panels. Provide division bars, inside corners, outside corners, and caps as needed to conceal edges. 1. Color: Factory Oven-Baked Finish to match spec d panel. B. Exposed Fasteners: exposed fasteners are not allowed. C. Concealed Mounting Splines: Continuous, H-shaped aluminum extrusions designed to fit into grooves routed in edges of factory-laminated panels and to be fastened to substrate. D. Adhesive: Construction adhesives complying with ASTM C 557. E. Sealant: Mildew-resistant, single-component, neutral-curing or acid-curing silicone sealant recommended by plastic paneling manufacturer and complying with requirements in Section "Joint Sealants." PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work. B. Proceed with installation only after unsatisfactory conditions have been corrected. PLASTIC PANELING

7 3.2 PREPARATION A. Remove wallpaper, vinyl wall covering, loose or soluble paint, and other materials that might interfere with adhesive bond. B. Prepare substrate by sanding high spots and filling low spots as needed to provide flat, even surface for panel installation. C. Clean substrates of substances that could impair adhesive bond, including oil, grease, dirt, and dust. D. Condition panels by unpacking and placing in installation space before installation according to manufacturer's written recommendations. E. Lay out paneling before installing. Locate panel joints to provide equal panels at ends of walls not less than half the width of full panels so that trimmed panels at corners are not less than 12 inches (300 mm) wide. 1. Mark plumb lines on substrate at panel joint locations for accurate installation. 2. Locate panel joints to allow clearance at panel edges according to manufacturer's written instructions. 3.3 INSTALLATION A. Install plastic paneling according to manufacturer's written instructions. B. Install panels in a full spread of adhesive. C. Install panels with fasteners. Layout fastener locations and mark on face of panels so that fasteners are accurately aligned. 1. Drill oversized fastener holes in panels and center fasteners in holes. 2. Apply sealant to fastener holes before installing fasteners. D. Install factory-laminated panels using concealed mounting splines in panel joints. E. Install trim accessories with adhesive. Do not fasten through panels. F. Fill grooves in trim accessories with sealant before installing panels, and bed inside corner trim in a bead of sealant. G. Maintain uniform space between panels and wall fixtures. Fill space with sealant. H. Maintain uniform space between adjacent panels and between panels and floors, ceilings, and fixtures. Fill space with sealant. I. Remove excess sealant and smears as paneling is installed. Clean with solvent recommended by sealant manufacturer and then wipe with clean dry cloths until no residue remains. END OF SECTION PLASTIC PANELING

8 NEW FRP PANEL, TYP EXST PLASTER, SUBSTRATE VARIES ALUM EDGE TRIM PER SPEC, TYP HORIZONTAL FRP, TYP M A 001 Kitchen Renovations Boonville, Missouri TCEP No.: Architecture + Landscape Architecture + Engineering + Interiors 1251 NW Briarcliff Parkway, Suite 400 Kansas City, MO Fax Lincoln, NE Fairway, KS Addendum 001 Supplemental Drawing: SDA001 Revision of Sheet: A-501 Date: 03/22/17