1 TENDERNO. 9/ TECHNICAL SPECIFICATION 7.A SCOPE: This specification covers the design, manufacture, testing, packing, supply, CFR delivery to Aqaba Docks in Jordan and guarantee (maintain) the following insulators and all the fittings types to be used in Double and Quadruple Circuits 132 kv OHTL s, Three phases, Single conductor per phase, OPGW Earthwires for the following lines:- Lot1: Quadruple circuits between the existing Rashadiyah Ma'an 132 kv OHTL and Fujaij Wind Project Substation of total route length approximately 8kms. Lot2: Double circuit between the existing Hasa Rashadiyah 132 kv OHTL and Tafila Wind Project Substation of total route length approximately 1km. Lot3: Quadruple circuits between the existing Bayader Fuheis 132 kv OHTL and Amman South - Salt 132 kv OHTL of total route length approximately 7kms. Lot4: Quadruple circuits between the existing Ma'an Sheidiya 132 kv OHTL and Ma'an Solar Project Substation of total route length approximately 1.5kms. 7.B PHYSICAL CHARACTERISTICS: Tenderers are requested to fill and submit all technical and price schedules for the following, suspension, heavy suspension and tension insulator sets of total minimum creepage path of 5510 as specified in addition to other items:- 1. Cap and pin insulator The insulators shall be designed with view to service in desert pollution for Aerodynamic & normal Tension Insulators and all pins shall be equipped with zinc sleeves. 51

2 2. Long Rod insulator The insulator shall be designed with view service desert pollution for both of the a/m types: - The surface of porcelain shells shall be free from unevenness and rough particles and the entire surface that will be exposed after assembly, shall be brown glazed to give a smooth finish of uniform color. The glaze shall be of the "Compression Type" and shall be unaffected by sudden changes of temperatures, immune to the effects of zone, acids or alkaline dust which may be encountered within the normal service conditions the glaze on porcelain insulators shall have translucent finish. The surface of the toughened glass shells, also, shall be free from unevenness and rough particles as well as interior bubbles. Socket caps shall be made of malleable cast or ductile cast iron and ball pins shall be made of high tensile steel and shall be hot dip galvanized after all necessary marking. Sockets and ball pins shall be hot dip galvanized in accordance with ASTM A 153 or equivalent. Retaining pins or locking devices for the insulators units shall be of phosphor bronze or stainless steel. The composition of which shall comply with B.S.S 369. The pins and locking devices shall be such that when set under any condition of handling or service nothing but extreme deformation shall allow separation of the insulator units or fittings or shall cause any risk of the retaining pins or locking devices shall be incapable of rotating when in position. All ball and socket joints on insulator sets shall be lightly coated with an approved grease. Technical Schedules shall be filled by the Tenderer for either porcelain or toughened glass Insulators and fittings and shall include all particulars of the offered insulators and conductor, fittings as applicable. 52

3 3. Composite Insulator: Composite Insulator shall consist either of individual sheds mounted on the core, with or without an intermediate sheath, or alternatively, of a housing directly moulded or cast in one or several pieces on to the core. 3.2 Core of a composite insulator : It shall be designed to ensure the mechanical characteristics. The core usually consist of either fibers (e.g. glass) which are positioned in a resin based matrix or a homogeneous insulating material (e.g. porcelain or resin). 3.3 Core diameter : The core diameter shall be:- - The geometric diameter of a core of circular section, and to be 18 mm for insulators of SML 120.above that shall be 22 mm. 3.4 Housing and sheds of a composite insulator: It shall provide the necessary creepage distance and protect the core from the weather. An intermediate sheath made of insulating material is a part of the housing. A shed shall be a projecting part of the housing intended to increase the creepage distance. The sheds can be with or without ribs. The housing material shall be high temperature vulcanized silicon rubber (HTV). 3.5 Metal fitting of a composite insulator : The metal fittings shall be intended to connect to a supporting structure, or to a conductor, or to an item of equipment, or to another insulator. 3.6 Connecting zone : Zone where the mechanical load shall be transmitted between the rod and the metal fitting. 3.7 Coupling : The coupling shall be ball and sockets according to IEC The following shall be considered during tests and if will be found not acceptable according to IEC (Version 2.0) the insulators will be rejected:- A) Tracking: Tracking shall be an irreversible degradation by formation of paths starting and developing on the surface of an insulating material. These paths are conductive even under dry conditions. 53

4 Tracking can occur on surfaces in contact with air and also on the interfaces between different insulating materials. B) Treeing : Treeing shall be an irreversible degradation consisting of the formation of microchannels within the material which can be conducting or non- conducting. These microchannels can progressively extend through the bulk of the material until electrical failure occurs. C) Erosion : Erosion shall be an irreversible and non-conducting degradation of the surface of the insulator that occurs by loss of material. This can be uniform, localized or tree-shaped. D) Chalking (flouring): Chalking shall be the appearance of some particles of the filler of the housing material forming a rough or powdery surface. E) Crazing : Crazing shall be made of surface micro-fractures of depths approximately 0.01mm to 0.1mm. F) Crack : Any surface fracture of depths greater than 0.1mm. G) Hydrolysis phenomena: Hydrolysis phenomena, due to water penetration in liquid form or as water vapor, can take place in the materials of the composite insulator which can lead to electrical and/ or mechanical degradation. H) Specified mechanical load (SML) : The SML shall be load indicated in requirement specification which is used for mechanical tests. I) Routine test load (RTL) : The RTL shall be the load applied to all assembled composite insulators during a routine mechanical test. 7.C STANDARDS The following or equivalent standards shall be considered in the design or testing of the offered insulators. These standards shall be applied in part or whole to the offered insulators. IEC 60 - High Voltage Test Techniques IEC Ball and socket coupling of string insulator units. 54

5 IEC Characteristics of string insulators of cap and pin. IEC Locking devices for ball and socket couplings of string insulator units. IEC Tests on insulators IEC Radio interference test on high Voltage insulators. IEC Thermal - mechanical performance test and mechanical performance test on string insulator unit. IEC Sampling rules and acceptance criteria when applying statistical control methods of mechanical and electromechanical tests. IEC (Edition 2.0) - Composite insulator for a.c overhead voltage greater than 1000 V. BS 309) 310) - Malleable Iron-Castings. 333) BS BS Hot dip galvanized coatings on iron and steel articles Forged Steel. BS Iron castings with spheroidal or modular graphite (ductile). BS Copper and copper Alloys (Table 8 for chemical composition and mechanical properties of phosphor bronze for pins or locking devices). 7. D TESTING Every facility is to be provided by the Contractor to enable the Employer s representatives to carry out the necessary inspection and testing of the purchased materials. The costs of all tests during manufacturing and preparation of test records shall be borne by the Contractor. 55

6 Insulator set tests will be witnessed by the Employer's staff (Two inspectors) and all costs associated with this shall be filled in by the Tenderers in the relevant item of detailed price schedules. Payment will be for the successful test only. These costs shall include visas, hotel accommodation in Five stars or equivalent hotel, transport, all meals and other expenses, airtickets of economic class for flights less than 5 hours without connection flight (station) out of that the airticket shall be busniss class and out of pocket expenses. Instruments shall be approved and shall, if required by the Employer's representative, be calibrated by the National physical Laboratory or such other body as may be approved at the expense of the contractor. The following test shall be carried out at the manufacturer's works. I. Type Test: One suspension, one heavy suspension and one tension string of each shall be subject to the following tests in accordance with the provisions of IEC publications 383,437, IEC1467 and (Edition 2.0) or such other standards as may be approved -: 1) Verification of the dimensions. 2 ) Radio interference tests. For these tests, single unit RIV test will be required on the complete insulator unit which are used to make up with fittings. The maximum value for acceptable noise should be not more than 25 db. 3) Dry Lightning Impulse withstand test : Dry withstand positive and negative polarity. 4) Wet switching Impulse withstand test : Wet withstand positive and negative polarity 5) Wet Power frequency withstand tests : Wet withstand tests shall be on complete insulator strings including string fittings and dampers and any other fittings attached to the conductors in service and shall be made with and without arc horns. To achieve this a set of fittings for each insulator string will be forwarded to the insulator manufacturer by NEPCO or his selected fittings manufacturer for assembly into complete strings. 6) Electro-mechanical failing load test (Porcelain only). 7) Mechanical failing load test (Composite & glass only). 56

7 8) Thermal-Mechanical performance test. 9) Test of housing -: Tracking and erosion test (composite only) 10) Test for the core material (composite only). 11) AC Power arc test (for glass and porcelain only). 12) Aging Test :- For composite insulators only, the report of this tests shall be submitted from an approved international independent laboratory,and the date of this tests shall be not before ten years,out of that this tests shall carried out without any extra costs and time extensions. All a/m tests or part of them should be carried out and witnessed by NEPCO s Representative depending on NEPCO decision. II. Additionally the following sample and routine tests shall be carried out on every shipment of suspension, heavy suspension and tension insulator sets /discs:- SAMPLE ROUTINE (IEC 383 Section 4) (IEC 383 Section 5 ) Verification of dimensions Visual examination Temperature cycle test Mechanical test. Electromechanical failing Load test (Porcelain only) Electrical test. Thermal shock test (glass only) Thermal shock test Puncture test Porosity test (porcelain only) Verification of the displacement Galvanizing test. Verification of the locking system Mechanical failing load test(glass only) III. for composite insulator all tests mentioned in IEC 1109 should be carried out on every shipment. In case that Testing by third Party is decided by the Employer in the place of manufacture, the Contractor will conduct on his own expense all the tests required by the Employer. 57

8 7.E MARKING Every insulator body shall have a durable and legible trade mark and year of manufacture as well as the rated combined M & E strength in Kilo Newton & Kilo Volt. 7.F PACKING The whole of the insulators shall be packed in non-returnable cases. The cases shall be convenient for ocean and overland transportation. Packing cases shall be strongly constructed and in no case timber less than 25mm in thickness is to be used. The contents of the packing cases shall be securely fastened in position with struts or cross battens. Aluminum, Plastic or PVC, name plate shall be fixed to each case and clearly marked with the following -: - Contract No. - Number and size of insulators. All packing will be inspected before shipment. 7.G SHIPPING MARK FORM : IS ATTACHED 7.H INSULATOR AND CONDUCTOR FITTINGS Routine and sample mechanical tests shall be carried out on fittings in accordance with the appropriate section of BS.3288 part 1 or such other standard as may be approved. 7.I TENSION CLAMPS AND JOINTS Two samples each of tension clamps and tension and nontension joints shall be submitted to mechanical and electrical type tests, galvanizing and mechanical routine tests in accordance with the appropriate section of BS.3288 part 1 or such other standard as may be approved. The Employer from time to time, shall make further similar tests as may be required to ensure, that the quality of the product is being maintained throughout the Contract. 7.J SCHEDULES The following schedules must be filled in by the Tenderer as applicable. 58

9 - Schedules No. (2A,2B,2C,2D, ) - Schedules No. (3A,3B,3C,3D,) - Schedules No. (4A,4B,4C,4D, ) - Schedules No. 5 - Schedules No. 6 - Schedules No. 7 - Schedules No. 8 - Schedules No. 9 - Schedules No K OBLIGATIONS OF THE SUCCESSFUL TENDERER: The successful Tenderer will coordinate with the Employer, after being awarded the contract, for the purposes of submitting the technical drawings for the insulator sets and their fittings and the conductor fittings to be approved by the Employer. No manufacturing, testing or shipping of materials is allowed before written approval of the Employer. Partial shipments can be approved. 59

10 TENDER NO. 9/2013 SCHEDULE NO.1 INSULATOR TYPES AND USES Item No. PARAMETER DESCRIOTION 1.0 String Configuration 1.1 Suspension insulator set Single 1.2 Heavy Suspension insulator set Single 1.3 Tension insulator set Single 1.4 Low duty upright insulator set Single 1.5 Low duty inverted insulator set Single 2.0 Insulator unit type 1- Cap& Pin 2- Long Rod 3- Composite Insulator 3.0 Dielectric Material Porcelain or Toughened Glass or composite 40 Coupling Type Ball and socket 5.0 Security Clip Required 6.0 Zinc Collars Required 7.0 Glass Color Brown for Porcelain & Green or transparent for Glass 7.1 Composite color To be filled by the contractor 8.0 Specific Creepage to IEC Type based on 38mm/kV 10.0 Total Creepage Path 5510mm 11.0 Zinc sleeves Required 12.0 Minimum overall length of single tension insulator string including the fittings. 2200mm 13.0 Maximum overall length of single tension insulator string including the fittings. 2700mm 14.0 Minimum overall length of single 2000mm suspension string including the 15.0 Maximum overall length of single suspension string including the fittings. 2200mm 60

11 TENDERNO. 9/2013 SCHEDULE NO.2A PARTICULARS OF AERODYNAMIC CAP&PIN PORCELAIN INSULATORS WITH 5510mm MINIMUM NOMINAL CREEPAGE PATH PER STRING ITEM DESCRIPTION NO. 1. Manufacturer & Unit Number. 2. Number of discs per set. 3. Total length of Creepage path per set. 4. Total length of protected Creepage path per set. 5. Minimum 50HZ flashover unit (kv) 6. Minimum 50HZ wet flashover unit (kv) 7. Minimum 50HZ puncture voltage of unit (kv) 8. Minimum dry impulse 50% flashover voltage of insulator set. (kv) 9. Spacing of units in set. SUSPENSION HEAVY SUSPENSION TENSION 61

12 TENDERNO. 9/2013 SCHEDULE NO.2A (CONTINUED) ITEM DESCRIPTION SUSPENSION HEAVY TENSION NO. SUSPENSION 10. Total length of insulator set including all fittings. 11. Outside diameter of the unit 12. Required Minimum failing load per complete set (KN) 13. Actual minimum failing load per complete set (KN) 14. Maximum recommended working load (KN) 15. Required insulator pin diameter (KN) 16. Mass of unit (kg) 17. Unit Creepage Distance 62

13 TENDER NO. 9/2013 SCHEDULE NO.2. B PARTICULARS OF AERODYNAMIC CAP&PIN TOUGHENED GLASS INSULATORS WITH 5510mm MINIMUM NOMINAL CREEPAGE PATH PER STRING ITEM NO. DESCRIPTION SUSPENSION HEAVY SUSPENSION 1. Manufacturer & Unit Number. 2. Number of discs per set. 3. Total length of Creepage path per set. 4. Total length of protected Creepage path per set. 5. Minimum 50HZ flashover unit (kv) 6. Minimum 50HZ wet flashover unit (kv) 7. Minimum 50HZ puncture voltage of unit (kv) 8. Minimum dry impulse 50% flashover voltage of insulator set. (kv) 9. Spacing of units in set. TENSION 63

14 TENDER NO. 9/2013 SCHEDULE NO.2 B (CONTINUED) ITEM DESCRIPTION SUSPENSION HEAVY TENSION NO. SUSPENSION 10. Total length of insulator set including all fittings. 11. Outside diameter of the unit 12. Required Minimum failing load per complete set (KN) Actual minimum failing load per complete set (KN) 14. Maximum recommended working load (KN) 15. Required insulator pin diameter (KN) 16. Mass of unit (kg) 17. Unit Creepage Distance 64

15 TENDER NO. 9/2013 SCHEDULE NO.2. C PARTICULARS OF LONG ROD PORCELAIN INSULATORS WITH 5510mm MINIMUM NOMINAL CREEPAGE PATH PER STRING ITEM NO. DESCRIPTION SUSPENSION HEAVY SUSPENSION 1. Insulator type 2. Manufacturer & Unit Number. 3.1 Number of long rod units per set. 3.2 Number of sheds per longrod unit 4. Total length of Creepage path per set. 5. Total length of protected Creepage path per set. 6. Minimum 50HZ flashover unit (kv) 7. Minimum 50HZ wet flashover unit (kv) 8. Minimum 50HZ puncture voltage of unit (kv) 9. Minimum dry impulse 50% flashover voltage of insulator set. (kv) 10. Spacing of units in set. TENSION 65

16 TENDERNO. 9/2013 SCHEDULE NO.2. C (CONTINUED) ITEM DESCRIPTION SUSPENSION HEAVY TENSION NO. SUSPENSION 11. Total length of insulator set including all fittings. 12. Outside diameter of the unit 13. Required Minimum failing load per complete set (KN) Actual minimum failing load per complete set (KN) 15. Maximum recommended working load (KN) 16. Required insulator pin diameter (KN) 17. Mass of unit (kg) 18. Unit Creepage Distance 66

17 TENDER NO. 9/2013 SCHEDULE NO.2 D PARTICULARS OF COMPOSITE INSULATORS WITH 5510mm MINIMUM NOMINAL CREEPAGE PATH PER STRING ITEM NO. DESCRIPTION SUSPENSION HEAVY SUSPENSION 1. Manufacturer & Unit Number. 2. Type of core 3. Type of housing and sheds 4. Number of sheds per set. 5. Outside diameter of the sheds (D1/D2) 6. Diameter of the core 7. Total length of Creepage path per set. 8. Total length of protected Creepage path per set. 9. Minimum 50HZ flashover unit (kv) 10. Minimum 50HZ wet flashover unit (kv) 11. Minimum 50HZ puncture voltage of unit (kv) 12. Minimum dry impulse 50% flashover voltage of insulator set. (kv) 13. Spacing of units in set. TENSION 67

18 TENDERNO. 9/2013 SCHEDULE NO.2 D (CONTINUED) ITEM DESCRIPTION SUSPENSION HEAVY TENSION NO. SUSPENSION 14. Total length of insulator set including all fittings. 15. Outside diameter of the unit 16. Required Minimum failing load per complete set (KN) 17. Actual minimum failing load per complete set (KN) 18. Maximum recommended working load (KN) 19. Required insulator pin diameter (KN) 20. Mass of unit (kg) 21. Unit Creepage Distance 68

19 TENDERNO. 9/2013 SCHEDULE NO.3 A MANUFACTURERS AND PLACE OF MANUFACTURE TESTING, INSPECTION, SHIPMENT AND STANDARDS CAP AND PIN PORCELAIN INSULATORS ITEM No. DESCRIPTION Manufacturer and place of Manufacturer 1. Aerodynamic Porcelain cap & pin, suspension, heavy suspension and tension insulators 2. Fittings for YEW conductor. Place of testing and inspection Port of shipment Standard 69

20 TENDERNO. 9/2013 SCHEDULE NO. 3. B MANUFACTURERS AND PLACE OF MANUFACTURE TESTING, INSPECTION, SHIPMENT AND STANDARDS CAP AND PIN TOUGHENED GLASS INSULATORS ITEM No. DESCRIPTION 1. Aerodynamic Glass cap & pin, suspension,heavy suspension and tension insulators 2. Fittings for YEW conductor Manufacturer and place of Manufacturer Place of testing and inspection Port of shipment Standard 70

21 TENDERNO. 9/2013 SCHEDULE NO.3 C MANUFACTURERS AND PLACE OF MANUFACTURE TESTING. INSPECTION. SHIPMENT AND STANDARDS PROCELAIN LONG ROD INSULATORS ITEM No. DESCRIPTION 1. Aerodynamic Porcelain long rod, suspension, heavy suspension and tension insulators 2. Fittings for YEW conductor. Manufacturer and place of Manufacturer Place of testing and inspection Port of shipment Standard 71

22 TENDERNO. 9/2013 SCHEDULE NO.3 D MANUFACTURERS AND PLACE OF MANUFACTURE TESTING. INSPECTION. SHIPMENT AND STANDARDS FOR COMPOSITE INSULATORS ITEM No. DESCRIPTION 1. Composite, suspension, heavy suspension and tension insulators. 2. Fittings for YEW conductor. Manufacturer and place of Manufacturer Place of testing and inspection Port of shipment Standard 72

23 TENDERNO. 9/2013 SCHEDULE NO.4. A DATES FOR MANUFACTURE, TESTING AND DELIVERY CAP AND PIN PORCELAIN INSULATORS This schedule must be completed by the Tenderer and the entered periods shall be binding to the contractor DESCRIPTION 1 Aerodynamic Porcelain cap & pin, suspension, heavy suspension and tension insulators 2 Fittings for YEW conductor. Commencement Completion exworks Testing Delivery CFR Aqaba Docks 73

24 TENDERNO. 9/2013 SCHEDULE NO.4. B DATES FOR MANUFACTURE, TESTING AND DELIVERY CAP AND PIN TOUGHENED GLASS INSULATORS This schedule must be completed by the Tenderer and the entered periods shall be binding to the contractor DESCRIPTION 1 Aerodynamic Glass cap & pin, suspension,heavy suspension and tension insulators 2 Fittings for YEW conductor. Commencement Completion exworks Testing Delivery CFR Aqaba Docks 74

25 TENDERNO. 9/2013 SCHEDULE NO.4 C DATES FOR MANUFACTURE, TESTING AND DELIVERY PORCELAIN LONG ROD INSULATORS This schedule must be completed by the Tenderer and the entered periods shall be binding to the contractor DESCRIPTION 1 Aerodynamic Porcelain long rod, suspension, heavy suspension and tension insulators 2 Fittings for YEW conductor. Commencement Completion exworks Testing Delivery CFR Aqaba Docks 75

26 TENDERNO. 9/2013 SCHEDULE NO.4 D DATES FOR MANUFACTURE, TESTING AND DELIVERY Composite INSULATORS This schedule must be completed by the Tenderer and the entered periods shall be binding to the contractor DESCRIPTION 1 Composite, suspension, heavy suspension and tension insulators 2 Fittings for YEW conductor. Commencement Completion exworks Testing Delivery CFR Aqaba Docks 76

27 TENDER NO. 9/2013 SCHEDULE NO.5 PARTICULARS OF ``YEW``( A.A.A.C) CONDUCTOR FITTINGS Tenderers are required to complete this schedule in full : No DESCRIPTION SUSPENSION HEAVY SUSPENSION 1. Manufacturer 2. Reference Number (Drg. No.) 3. Overall length 4. Weight (KG) 5. Required minimum failing load without tension deadend (KN) 6. Actual minimum failing load without tension deadend (KN) 7. Required minimum failing load of deadend (KN) 8. Actual minimum failing load of deadend (KN) 9. Material of clamps 10. Average hardness value in vichers number of : One) Midspan Joint. (a) before compression (b) after compression Two) deadend Joint. (a) before compression (b) after compression 11. Stockbridge dampers TENSION 77

28 TENDER NO. 9/2013 PRICE SCHEDULE SCHEDULE NO.6 For * * INSULATORS. Prices are valid for the whole contract period and for CFR supply on Aqaba Docks. item Description no. 1. Single suspension insulator set C/W arc horn for total Creepage path 5510mm per set 2. Single heavy suspension insulator set C/W arc horn for total Creepage path 5510mm fittings per set 3. Tension insulator without fittings of total Creepage path 5510mm each 4. Fittings for Tension insulator of total Creepage path 5510mm as attached C/W arc horn (Without Insulator) per set 5. Single upright low duty insulator set C/W arc horn for total Creepage path 5510mm (included turn buckle) per set 6. Single inverted low duty insulator set C/W arc horn of total Creepage path 5510mm (include turn buckle) QTY Rate Unit rate Total *Foreign currency per set Total carried forward *state foreign currency ** state material and type of insulator. 78

29 TENDER NO. 9/2013 SCHEDULE NO.6 For * *INSULATORS. (Continued) item no. Description Total brought forward 7. Midspan joints for 400 mm2 Yew conductor 8. Repair Sleeves for 400 mm2 Yew conductor each each 9. Dead end joints including fittings for jumper lugs for Yew 400 mm2 conductor 1. Stockbridge vibration dampers for Yew 400 mm2 conductor each each 11. Performed Armour rods for YEW Conductor Each 12. witnessing of tests by the employer's inspector per clause 7d of specification per inspector Total QTY Rate Rate Rate 2 unit rate total *foreign currency *state foreign currency ** state material and type of insulator 79

30 TENDER NO. 9/2013 SCHEDULE NO. 7 TENDER PRICE SUMMARY ** INSULATOR SCH No. 6 Description Complete Insulator sets including insulator and conductor fittings and witnessing of tests. TOTAL Unit Rates CFR Total for CFR Aqaba Docks Aqaba Docks * Foreign Currency * State foreign currency ** State insulator material and type. Total Tender Price.( SAY ) 80

31 TENDER NO. 9/2013 SCHEDULE NO. 8 ALTERNATIVE STANDARDS AND DEVIATIONS OR EXCEPTIONS TO THE TENDER DOCUMETNS Tenderers shall enter below all deviations from the Tender documents in sequential order. In the absence of any listed deviation it is deemed that the Tender document requirements are fully complied with. Clause No. in the Tender Document Deviation The Tenderer hereby confirms that, except for the deviations listed in this schedule; this proposal is fully in compliance with the Tender Documents. Tenderer's signature and Stamp: 81

32 TENDER NO. 9/2013 SCHEDULE NO. 9 ELIGIBILITY AND QUALIFICATION FOR 132KV INSULATOR & FITTINGS Item Project Name / Country Date of installation Insulator Type Quantity End User& contact details IMPORTANT NOTE. 1. Same schedule must be filled for fittings. 2. NEPCO will contact with end users, so clear address should be indicated other wise the offer will be rejected. 82

33 TENDER NO. 9/2013 SCHEDULE NO. 10 EVIDENCES TO BE ATTACHED WITH OFFER Type tests certificate No. and place of issuance Design tests certificate No. and place of issuance Aging test certificate No. and place of issuance Documentary evidence for source of materials and annual quantity. End users certificates No. Important Not:- 1- Detail address and clear contact person on each certificate should be indicated, other wise the offer will be rejected. 2- Evidence of good performance outside manufacturer country shall clearly indicate that no tracking, no cracking, no treeing on external surface, no puncture, and no erosion. 83