Emerging construction technologies

Size: px
Start display at page:

Download "Emerging construction technologies"

Transcription

1 Emerging construction technologies C A PRASAD DIRECTOR METEY ENGINEERING CONSULTANTS, HYD/VJA

2 Different types of construction technologies for high rise structures for speedy delivery Shear wall / Monolithic construction using aluminum shuttering Insulated wall panel construction using shotcreteing of concrete Light gauge steel or cold formed steel construction Precast/Prefabricated construction using concrete/steel Composite construction 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 2

3 SHEAR WALL / MONOLITHIC CONSTRUCTION USING ALUMINUM SHUTTERING Methodology: The elements like walls, beams and slabs made of RCC are cast together at one go by using aluminum form work. Panels of 2 (0.6m) wide X 10 (3m), floor height are connected together with connectors. Merits: Construction speeds can be achieved faster due to light weight of forms and less labor required for carrying the form work. Quality of finish achieved is very good to receive painting directly without plaster. Formwork components are durable and can be used for 100 repetitions. 5 to 7 days cycle is easily achieved in most of the constructions and construction for overall project is dramatically reduced. 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 3

4 Demerits: Initial investment on formwork is higher at the rate of Rs.10,000/sqm About 50 repetitions are easy to achieve and there after maintenance is required to be done for correctness of shape such that another 50 repetitions could be completed No. of sets of formwork to be decided based on time of construction and the repetitions to be achieved. 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 4

5

6 Insulated wall panel construction using shotcreteing of concrete. Methodology: System is conceived with insulated wall and roof panels of corrugated extruded polystyrene(eps), which consists of zinc coated square mesh on either sides of it connected by a shear connectors The panels are coated with concrete through shotcreting machines Merits: Light weight, seismic resistant, sound and thermal resistant EPS will reduce the Air conditioning loads too and there will be a difference of 4 deg C in these buildings 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 6

7 Demerits: Shotcreting means insitu work and needs to be closely monitored and inspected 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 7

8 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 8

9 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 9

10 Light gauge steel or cold formed steel construction. Methodology: Light weight cold formed steel sections for speedy low rise building construction. Gauge thickness from mm. These could be used in industrial townships, residential and commercial buildings, hospitals and schools etc., External and internal walls are to be covered with plaster boards duly putting the rock wool in between them, which will give the thermal insulation. 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 10

11 Merits: Light weight, Seismic resistance, Thermal and acoustic insulation. With rock wool insulation inside, Air conditioning loads will be lesser Demerits: Spacing of studs and joists will have an effect on internal and external planning of structure Plaster boards are required to be fire resistant and should be durable against the external environment, thereby, its cost is prohibitive compared to conventional systems 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 11

12 Composite construction. Methodology: Structural Steel columns and beams with Deck slab + Concrete or Insitu concrete with shuttering is a method of construction Steel columns could be encased to get additional strength in addition to steel. Merits: Very faster construction Concrete encasement makes the steel fire resistant and protects from corrosion/ durability 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 12

13 Demerits: Cost is higher by about 20 to 30% compared to RCC type of construction Fire resistant paint to be applied to structural steel elements is very prohibitive 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 13

14 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 14

15 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 15

16 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 16

17 1/20/2018 METEY ENGINEERING AND CONSULTANCY PVT LTD 17

18 PRECAST DEVELOPMENT SO FAR IN INDIA IMPLEMENTATION CHALLENGES PLANNING FOR PRECAST Awareness of precast Future of precast

19 Development of Precast in India so far Number of precast manufacturing units have been set up and are being set up in India. The demand for precast systems is rising day by day The developers and Govt. Institutions have felt the necessity of completion of projects faster and thus pass on benefits to the customers early as well as for themselves

20 Spirol from UK have set up a facility in south India to supply the steel plates required for beds duly tying up with a local firm Bianchi from Italy have set up the facility near to Mumbai and are supplying the tilting moulds required for making walls, as well as for forms for columns, beams and have already supplied to number of precast manufacturers in India.

21 S.N o I Client Equipment supplied from Unit Hyderabad 1 Janapriya Developers, Elematic, FINLAND Battery Mould 2 PRECA Prensoland, Spain 3 Skill promoter Nordimpianti, Italy II COIMBATORE TEEMAGE PRECAST ECHO, from NETHERLANDS, & WECKENMANN, Germany 5 bed HCSplant Battery Mould III CALICUT Weckenmann, Germany Battery Mould IV Chennai VME PRECAST Elematic, Finland HCS & Tilting Table wall unit

22

23 Precast construction is fast catching up and is establishing itself as the construction technology for the future The different precast projects so far came up in India and are built by the different precast companies are a testimony of the same which are indicated below:

24 Brigade Orchards

25 Brigade Orchards

26 Precast Multi-Level Car Park, Terminal 1B, Domestic Airport Mumbai Multi-level Car Park (MLCP) was a unique project that has been successfully completed by L&T despite the challenges of being situated at busy junction of Domestic Airport and Western Express highway surrounded with many live line underground services.

27 Precast Multi-Level Car Park, Terminal 1B, Domestic Airport Mumbai Built up area 30,497sqm 8 Levels car parking Comprising 2B + G+ 4

28 Bharat Forge Research and Development Centre (BFRD) Total Area: 1.1 lakh sq.ft Total No. of Floors: G+L1+L2+L3+Terrace Delivered in 7.5 months

29 Schmersal India Built up area 8880 sq m

30 PRODUCTION FACILITY FOR SCHMERSAL India Pvt. Ltd, PUNE

31 TRANSPORTATION OF COLUMNS

32 ERECTION OF COLUMNS /STAIRS

33 COLUMNS AND BEAMS

34 BOUNDARY WALLS

35 Infosys Multi Level Car Parking Total Area = 4.5 Lakh Sq.Ft Total No of Floors Basement+10 Floors

36 Infosys multi level car park pune

37 FACADE INFOSYS MLCP

38 INFOSYS MLCP

39 INFOSYS MLCP

40 INFOSYS MLCP

41 INFOSYS MLCP

42 INFOSYS MLCP

43 INFOSYS MLCP

44 INFOSYS MLCP

45 WTC-WORLD TRADE CENTRE, PUNE Built up area :16.5 Lakh Sq.Ft Total No of Floors: Basement+Podium+10 Floor

46 BDA Project Bangalore Development Authority (BDA) B+S+18 floor housing project Doddabanahalli Bangalore B+S+18 FLOOR HOUSING PROJECT, DODDABANAHALLI, BANGALORE M/s. B.G.Shirke Construction Technology Pvt Limited, Pune built the structure using Prefab technology

47 Office Building in Hyderabad: Stilts- 2no s + G +4 ; 1,65,000 sft Delivered in 4.5 months

48 G+4 1,20,000 sft : Built in 4 months Precast elements used are, viz., Precast Prestressed Hollow core slabs, Prestressed beams, Precast Retaining walls, Precast Stairs, Precast Lift walls, Precast Architectural elements, Precast ducts Hospital Building:

49 Industrial Building in Hyderabad Cadbury s project- 2,20,000 sft Composite Construction: Steel columns and Beams + Precast Hollow core slabs Delivered in 5 months

50 Few of the projects carried out by VME Group, Chennai

51 D.R.D.O, CABS HANGER & OFFICES BUILDINGS, BANGALORE.

52 NOVOTEL IBIS COMBO HOTEL, CHENNAI.

53 KHIVRAJ MOTORS CAR SHOWROOM, CHENNAI

54 CHENNAI SILKS SHOWROOM, TIRUNELVELI

55 OFFICE BUILDING GUINDY, CHENNAI

56 LAKESIDE, CHENNAI

57 Few of the projects carried out by TEEMAGE, Coimbatore

58 M/s TSM Canteen Block Built-up Area : 13,500 Sq.Ft Scope : Beams, Columns, Hollow core slabs, Wall panels, Solid Slabs and Staircase Time: 38 days

59 M/s. Rotary School, Tirupur, Tamilnadu Duration : 28 Days Built-up Area : 19,000 Sq.Ft Scope : Beams, Columns, Hollow core slabs, Wall panels, Solid Slabs and Staircase

60 M/s. SCM Silks (P) Ltd : Tirupur, Tamil Nadu Duration : 30 Days Built-up Area : 52,300 Sq.Ft Scope : Beams, columns, Hollow core slabs, Wall panels and staircase

61 M/s.Christian Medical College Vellore, Tamil Nadu Duration : 27 Days Built-up Area : 49,500 Sq.Ft Scope : Beams, Columns, Hollow core slabs, Wall panels and Staircase

62 Supertech, from Noida, Shobha Developers are meeting their in House requirements, while, KEF Infra, and other companies have also done different structures across India.

63

64 THANK YOU