Chapter 3 - Excavation

Size: px
Start display at page:

Download "Chapter 3 - Excavation"

Transcription

1 Chapter 3 - Excavation South Dakota Department of Transportation Structures Construction Manual

2 Excavation - Chapter 3 The What and Where of Excavation

3 What is Excavation The removal of Earth material

4 Where is Excavating Done For Structure Foundations (Bridges, Retaining Walls, Etc.) Box Culverts Cofferdams & Cribs

5 Types of Excavation Unclassified Excavation for building berms & channels performed with earth moving equipment Structure Excavation for structure foundations box culvert bottom slabs cutoff walls performed w/front-end loader, Track Excavator, backhoe, clam, etc.

6 Types of Excavation cont. Undercut for preparing grade for box culvert or pipe

7 Unclassified Excavation

8 Structure Excavation Excavator, Crane & Clam

9 Box Culvert Undercut

10 Excavation for Bridges How is the Quantity determined? Unclassified Excavation preliminary cross sections first they determine amount of excavation necessary

11 Excavation for Bridges Unclassified Excavation Cross section at break points help determine if berm is correctly built Pg 3-21 Fig 3.1

12 Excavation for Bridges Unclassified Excavation skewed structure more cross sections required Pg 3-21, Fig 3.2

13 Excavation for Bridges Unclassified Excavation (Channel) If channel work required cross sections at right angles to channel centerline Pg 3-22 Fig 3.3

14 Excavation for Bridges Structure Excavation Standard Specs state structure excavation will be paid for at plans shown quantities. However, Engineer can request measurements of excavation be taken.

15 Excavation for Bridges Structure Excavation Calculations Pg 3-22 Fig 3.4

16 Excavation for Bridges Structure Excavation Calculations some plans show dividing line between unclassified and structure excavation.

17 Excavation for Bridges Structure Excavation Calculations Pg 3-23, Fig 3.5

18 Excavation for Bridges Structure Excavation Calculationsusing top elevation fill has not begun Pg 3-23 Fig 3.6

19 Excavation for Bridges Structure Excavation Calculationsusing top elevation fill is complete Pg 3-24 Fig 3.7

20 Excavation for Bridges Structure Excavation Calculationsusing top elevation fill is complete Pg 3-24 Fig 3.8

21 Excavation for Box Culverts Split between unclassified & structure excavation is the flowline. Pay based on excavation from flowline to bedding grade

22 Excavation for Box Culverts Excavation Limits for Box Culvert Pg 3-25, Fig 3.9

23 Excavation for Box Culverts Cross Section Locations Pg 3-25 Fig 3.10

24 Foundation Bearings Spread Footings Box Culvert

25 Foundation Bearing Spread Footings large reinforced concrete pad that distributes load size depends on bearing strength of soil under footing check plans for framing method Cast to neat lines in undisturbed material Place concrete shortly after excavation

26 Spread Footing w/ Neat Lines

27 Foundation Bearing Box Culverts monitor excavation near bottom of box culvert excavation for suitable bearing material Substrata rock, gravel or moist sand is adequate base. no simple method to determine bearing adequacy of other materials. experience

28 Typical Undercut Limits

29 Foundation Bearing Box Culverts-Backfilling materials conform to Section 421 placed in horizontal lifts not to exceed 6 each compact to 95% of max. dry density take periodic tests to verify compaction per the SDDOT Materials Manual

30

31 Sump Pump and Rock Substrata

32 Undercut Backfill failure

33 Foundation Bearing Box Culverts-Extruded Insulation Board reduces effects of frost heave insure equipment used to place & spread top layer of backfill is only operated on full depth of backfill Pg 3-29, Fig 3.11

34 RCBC Insulation Board Fig 3.11 Pg 3-30

35 Insulation Board Installation

36 Cofferdam Cofferdam and Crib

37 Cofferdam and Crib Cofferdam Bracing ring placed inside built by driving sheet pile around excavation area Interior material removed from back side

38 C T y p i c a l o f f e r d a m

39

40

41

42 Cofferdam Cofferdam and Crib

43 Cofferdam and Crib Crib built complete with bracing set over area to be excavated sinks as area is excavated

44 Steel Crib

45 Cribs Trench Box

46 Cofferdam and Crib Problems to watch for water buildup in excavation area remove with pumps or well points insure sheet piling is deep enough to prevent blow-in failures foundation seal area large enough to allow work on foundation. Allow 2-3 Safety concerns should be coordinated with Project Engineer, Temporary Work Spec

47 Cofferdam Failure

48

49 Backfilling Most structural concrete units can not be backfilled until the concrete reaches full design strength, Sec Q of Standard Spec Backfill material usually is the same material that was originally removed. Place in layers - 3 to 6 in depth Compaction with pan type vibrating equipment to same density as surrounding material Backfill brought up evenly on both sides structural member

50

51 Backfilling Box Culverts and Large Pipe Standard Backfill Method with like Materials. Backfill brought up evenly in < 6 lifts and compacted by mechanical compactors Usually same material as excavated material but may be a backfill material as specified in plans Imperfect Trench Flowable Fill Special Provisions may apply

52

53 Imperfect Trench

54 Backfilling Flowable Fill Portland Cement Fine Aggregate FlyAsh Water

55 Bridge End Backfill Bridge Berm Constructed per Plans and Cross Sections Review Special Provision, Plans and Specifications Construct Bridge Backfill per plans.

56 Bridge End Backfill Construct Embankment to plan configuration Embankment optimium moisture: < 25% Complete the necessary embankment densities (97% of maximum dry) Backfill limits: 100 ft back of abutment bound by toe of bridge berm 3 equally spaced densities for embankments less than 7 ft 4 equally spaced densities for embankments greater than 7 ft

57 Bridge End Backfill

58 Bridge End Backfill Select Granular Backfill - plan sheet on 3-32 Excavate to plans lines, scarify top 6 inches and recompact the area to 97% of max. dry density Install underdrain system Layout drainage fabric in which granular material is wrapped in Place embankment and granular material in 8 lifts and compact each layer Wrap fabric around granular material Place Poly sheeting over the granular material

59 Bridge End Backfill Sequence of Operation Install Underdrain System Adjacent to Abutment Backwall Place polyethylene sheeting Install vertical drain Place porous backfill and 4 in drainage 1/8 inch per foot

60 Bridge End Backfill Sequence of Operation Placement of Granular Bridge End Backfill Material must meet plan or special provision specifications. Testing requirements per the MSTR of the SDDOT Materials Manual Two Densities at even interval throughout the height of the abutment.

61 Bridge Backfill Detail

62 Bridge End Backfill Excavation Limits

63 Backfill Daylight on Shoulder

64 Bridge Backfill Profile

65 Bridge End Backfill Underdrain Detail

66 Bridge End Backfill Phased Construction Phase Construction shall be mechanically stabilized in accordance with the plans Verify all Geotextile Fabric is taut & free of wrinkles. Repair all torn and punctured Geotextile Fabric per Special Provisions. Overlapped 3 ft. Seams shall be overlapped a minimum of 2 ft Seams shall sewn using High Strength Polyester, Polypropylene or Kevlar thread. Nylon thread shall not be used. Geotextile Fabric shall be enclosed in a heavy duty opaque wrapping to protect from direct sunlight during storage.

67 Mechanically Stabilized backfill

68 Bridge End Backfill Sequence of Operation cont. Approach Slab Underdrain: Complete embankment constructed prior to excavating for approach slab underdrain Trench shall be 8 to 12 inches wide with vertical sides Trench bottom transversely 1/8 th inch/ft for proper drainage Place 4 inch perforated drainage tubing and backfill trench with porous backfill. Compact porous backfill to the satisfaction of the Engineer.

69 Approach Underdrain

70 Bridge End Backfill Tools

71 Bridge End Backfill

72 More Information? Review Plans Special Provisions Review Spec Book Check chapter 3 of the Structures Construction Manual Ask your supervisor Questions? Call Office of Bridge Design

73 Not all goes well.

74

75

76

77

78