1 1 / 15 Saraswathi Saraswathi is situated in a posh yet serene locality in Besant Nagar, a stone s throw away from Elliots Beach. The property covers 3 grounds and houses 8 apartments in a spacious 3 BHK configuration, a perfect fit for those who prefer smaller communities. The proximity to the beach makes for invigorating morning walks and healthy activities. Floor Plans

2 2 / 15 KEY PLAN

3 3 / 15 Availability Block 1 Floor Flat / Section Area (Sq. Ft.) Availability No of Bedrooms Floor 1 FLAT 1A 1489 SOLD OUT Triple FLAT 1B 1489 SOLD OUT Triple Floor 2 FLAT 2A 1489 SOLD OUT Triple FLAT 2B 1489 SOLD OUT Triple Floor 3 FLAT 3A 1489 SOLD OUT Triple FLAT 3B 1489 AVAILABLE Triple Floor 4 FLAT 4A 1489 SOLD OUT Triple FLAT 4B 1489 SOLD OUT Triple Construction Specifications CONSTRUCTION SPECIFICATIONS 1.0 The flat is to be constructed to this specification subject to minor changes in dimension, locations found desirable or necessary to ensure sound engineering practice at the sole discretion of the Builder. 2.0 TYPE OF CONSTRUCTION 2.1 RCC framed structure with non load bearing POROTHERM / BRICK masonry walls.

4 4 / Ceiling height will be 10 feet 6 inches approximately, except in the toilet where it will be 9 feet 6 inches. 2.3 Generally internal partition walls will be 4 inches and outer walls will be 6 inches. 3.0 WALL FINISH 3.1 Walls will generally be plastered and painted inside and outside. 3.2 In the toilets, walls will be covered with ceramic tiles upto 7 feet height. 3.3 In the wash area, tiles will be provided upto the height of 2 feet. 3.4 Ceramic tiles will be plain series. 4. FLOORING Flooring will be vitrified tiles 3' x 3' for living and dining and 2 x 2 tiles for other areas. Bathroom tiles will be of Kajaria or equivalent reputed make of builders choice. 5. DOORS Main door frame will be of good quality wood with skin molded doors finished with varnish. Other doors will be with good quality wood frames and flush doors finished with paint. All door fittings will be of antique brass. Main door will be provided with secure lock, one aldrop, safety chain and peep hole. Doors to the bedrooms will be provided with secure locks. 6. WINDOWS AND VENTILATORS Pre fabricated windows of Fenesta make will be provided. Ventilators will be of good quality wooden frames with glass louvers. Split A/c provision will be provided in all bed rooms. 7.0 KITCHEN 7.1 G 20 Black Granite slab will be provided for the kitchen cooking platform. 7.2 A Single bowl stainless steel sink with drain board will be provided. 8.0 PLUMBING AND SANITARY FITTINGS 8.1 Concealed plumbing lines from the overhead tank for each floor. 8.2 All closets and wash basins will be of white colour. 8.3 Provision in plumbing for connecting one geyser in each toilet. 8.4 Hot and cold mixers for shower and tap in each toilet. 8.5 Toilet closets will be floor / wall mounted EWC / IWC as desired by the Contracting Party. 8.6 Bathroom fittings - Jaguar continentals / equivalent.

5 5 / Health faucets will be provided in each toilet. 9.0 WATER SUPPLY 9.1 One common bore well and metro water sump will be provided. 9.2 Two pumps one for bore and one for sump will be provided ,000 ltr., capacity sump will be provided. 9.4 Overhead tank of 8000 ltr. capacity will be provided ELECTRICAL 10.1 Concealed copper wiring with Finolex cables and MK or equivalent switches will be provided Separate meter will be provided for lighting in common areas, the lift and the pumps / motors Three phase power supply with automatic phase change over switches will be provided in each flat Amp power plug sockets will be provided for water heater in the toilet, for air conditioners in the bedrooms, two in the kitchen and one in the service balcony for washing machine In all the flats, 5 Nos., 5 AMP sockets will be provided in the kitchen Two 5 amp plug sockets will be provided in each room in the living room in addition a multiple socket with 3 outlets will be provided for connections to TV, stereo and VCR One calling bell point will be provided Except for the light points in the staircase, all other light and fan points will be controlled from single point Generator with sufficient capacity for lift, pumps and lights in common areas and all light and fan points inside the flats will be provided OTHERS 11.1 One common name board and letter boxes for each flat will be provided at the entrance to the building Concealed PVC pipes for TV antenna will be provided in the living room and bed rooms A common board will be provided near the entrance to the building for incoming telephone line, with provision for concealed wiring from this board to one in the living room and each one in the bed rooms and study rooms The common area within the compound shall be paved and suitably landscaped One lift of reputed make will be provided.

6 6 / Rainwater harvesting will be carried out in the proposed building. Project Status Project Status as on 13th May 2016 Elevation

7 7 / 15 All flats Bed room, toilet door shutter fixing work is in progress. Balcony S.S handrail fixing work is in progress. All floors toilet wall & floor tiles work is completed.

8 8 / 15 Balcony M.S hand rail fixing work is completed. Upto 3rd floor primer coat painting work is completed. External drainage pipe line laying work is in progress.

9 9 / 15 Upto 3rd floor primer coat painting work is completed. Up to 3rd floor kitchen counter slab granite & tiles laying work is completed. Terrace floor weathering course work is in completed.

10 10 / 15 All floor tile flooring work is 90% completed. Balcony flooring work is completed. 4 th floor 1 coat wall putty work is completed. Upto 3 rd floor primer coat painting work is completed. All balcony hand rail fixing work is in progress. All flats Bed room, toilet door shutter fixing work is in progress. External first coat primer painting work is completed Staircase flooring work is completed. External drainage pipe line laying work is in progress. Terrace floor weathering course work is in completed. Terrace parapet plumbing bracket fixing work is completed. Compound wall gate fixing work is in progress. Project Status as on 7th May 2016 Front side view External first coat primer painting work is completed

11 11 / 15 Front side compound wall plastering work is completed. All balcony handrail fixing work is in progress

12 12 / 15 External drainage pipe line laying work is in progress Upto 3rd floor primer coat painting work is completed

13 13 / 15 All floor tile flooring work is 90% completed. (expect balcony) All floor tile flooring work is 90% completed. (expect balcony)

14 14 / 15 4th floor 1 coat wall putty work is completed Terrace floor weathering course work is in progress. Terrace floor weathering course work is in progress.

15 Powered by TCPDF ( 15 Terrace parapet plumbing bracket fixing work is completed All floor tile flooring work is 90% completed. (expect balcony) 4 th floor 1 coat wall putty work is completed. Upto 3 rd floor primer coat painting work is completed. All balcony handrail fixing work is in progress. External first coat primer painting work is completed Staircase flooring work is completed. External drainage pipe line laying work is in progress. Terrace floor weathering course work is in progress. Terrace parapet plumbing bracket fixing work is completed / 15