CERAMIC, STONE AND WATERPROOFING SYSTEMS AND WORK METHOD STATEMENTS
|
|
- Megan Cunningham
- 5 years ago
- Views:
Transcription
1 CERAMIC, STONE AND WATERPROOFING SYSTEMS AND WORK METHOD STATEMENTS
2 INDEX C0 C02 C03 C04 C05 C06 C07 C08 C09 W0 W02 W03 W04 W05 W06 SYSTEM FOR THE INSTALLATION OF TILES OVER UNEVEN CONCRETE SYSTEM FOR THE INSTALLATION OF TILES DIRECT TO A CONCRETE SUBSTRATE SYSTEM FOR THE INSTALLATION OF CERAMIC OR PORCELAIN TILES ON EXISTING TILES SYSTEM FOR THE INSTALLATION OF CERAMIC TILES ON METAL SURFACES FAST TRACK SYSTEM FOR THE INSTALLATION OF PORCELAIN TILES OVER A UNBONDED SCREED SYSTEM FOR THE INSTALLATION OF TILES OVER ACOUSTIC MATTING SYSTEM FOR THE INSTALLATION OF CERAMIC TILES & STONE MATERIAL ON BALCONIES SYSTEM FOR THE INSTALLATION OF TILES IN BATHROOMS AND DAMP ENVIRONMENTS SYSTEM FOR THE INSTALLATION OF CERAMIC OR STONE CLADDING SYSTEM FOR WATERPROOFING RETAINING WALLS WATERPROOFING SYSTEM FOR THE INSTALLATION OF GLASS MOSAICS IN SWIMMING POOLS SYSTEM FOR WATERPROOFING AND INSTALLING CERAMIC TILES IN NEW SWIMMING POOLS SYSTEM FOR WATERPROOFING PLANTER BOXES SYSTEM FOR WATERPROOFING AN EXPOSED NON-TRAFFICABLE ROOFTOP WATERPROOFING SYSTEM FOR THE INSTALLATION OF PEDESTAL TILING
3 SYSTEM FOR THE INSTALLATION OF TILES OVER UNEVEN CONCRETE C or concrete substrate primer Eco Prim T Plus 2 levelling compound UC Leveller 3 adhesive Ultralite S 4 grout Ultracolor Plus 5 sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 6 08/7 REV
4 Ceramic/Stone System Internal & External Installation of Tiles over Uneven Concrete C0 2/08/207 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System.2 CONCRETE SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 LEVELLLING MATERIAL Levelling material to be chosen from the following options: A. ADESILEX P4 ( AUS) Smoothing mortar. High performance, rapid-setting, full contact, cementitious adhesive for ceramic tile and stone material installations; smoothing compound for interiors and exteriors; mortar for brick and concrete block walls. à Apply using an appropriate trowel, as specified on the TDS. B. TOPCEM PRONTO ( AUS) Engineered screed. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds. Can receive tiling in 24 hours as opposed to roughly 3 weeks for a normal sand/cement screed according to AS NOTE: Prior to the application of the screed: à Ensure a slurry coat of PLANICRETE SP ( ) mixed with TOPCEM ( AUS) has been applied. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. à Screed to be in accordance with AS3958. (2007). à Mix water and TOPCEM PRONTO in strict accordance with the ratios described in the TDS. à Ensure a minimum thickness of 0 mm is applied. C. UC LEVELLER ( AUS) Levelling compound (Internal only). Fast hardening levelling smoothing compound for thicknesses from 3 mm to 70 mm: especially recommended for pumping. NOTE: Prior to the application of the levelling compound: à Apply primer ECO PRIM T PLUS ( ) with a brush or roller diluted in accordance with the TDS. à Spread the levelling compound in thicknesses from 3 to 70 mm per application, using a large metal trowel or float, tilting the trowel slightly to obtain the desired thickness. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 3
5 Ceramic/Stone System Internal & External Installation of Tiles over Uneven Concrete C0 2/08/207.4 ADHESIVE NOTE: Natural stone can be subjected to warping and staining, therefore Mapei recommends when using natural stone to refer to the manufactures guidelines. Adhesive selection for natural stone is also dependant on its moisture sensitiveness, which is represented by a class system. Please refer to EN467 and the Mapei technical notebook Laying Stone Materials for more information. Adhesive to be chosen from the following options: Normal-Set A. ULTRALITE S ( AUS) GOOD Solution. One-component, high-performance, flexible, lightweight, cementitious adhesive with no vertical slip and long open time and extremely high yield. Easy to apply by trowel with excellent wetting properties, very low emission of volatile organic compounds for ceramic tiles, stone (Class A) and thin porcelain tiles. NOTE: Option B required when applying externally with >5000 cm 2 (700x700 mm) tiles. B. KERABOND PLUS / ISOLASTIC ( , ) BEST Solution. Cement based powder with superior bond strength suitable for all types of tiles and natural stone (non-moisture sensitive, Class A), with a latex additive to improve the adhesive s characteristics and to elasticize the adhesive. Rapid-Set C. KERAQUICK S ( AUS) GOOD Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B*). NOTE: Option D required when applying externally with >5000 cm 2 (700x700 mm) tiles. D. KERAQUICK S + LATEX PLUS ( , ) BEST Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B*) with a latex additive to elasticize the adhesive. Resin-Based E. KERALASTIC T ( ). Two component, high performance polyurethane adhesive for ceramic tiles and stone material (Class A/B*/C**). à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 3
6 Ceramic/Stone System Internal & External Installation of Tiles over Uneven Concrete C0 2/08/207.5 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..6 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. Silicone to be chosen from the following options: A. MAPESIL AC ( GB) Ceramic/Porcelain. Solvent-free, acetic crosslinking mildew resistant silicone sealant. B. MAPESIL LM ( GB) Stone. Neutral mould resistant silicone sealant for stone and marble. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 3
7 SYSTEM FOR THE INSTALLATION OF TILES DIRECT TO A CONCRETE SUBSTRATE C concrete substrate adhesive Keraflex Maxi S 2 grout Ultracolor Plus 3 sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 4 08/7 REV 2
8 Ceramic/Stone System Internal & External Installation of Tiles Direct to a Concrete Substrate C02 2/08/207 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System.2 CONCRETE SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 WATERPROOFING MEMBRANE IF REQUIRED A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. NOTE: Prior to the application of the waterproofing membrane: à Junctions Option A: Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) wall/wall, wall/floor junctions and all other areas where movement is expected. à Junctions Option B: Apply a flexible fillet with MAPEFLEX PU45 FT ( GB) with the membrane reinforced with MAPETEX SEL ( GB) at all wall/wall, wall/floor junctions and other areas where movement is expected. Ensure fillet is dry and fully cured before applying membrane. à Ensure substrate has adequate falls in accordance with AS4654.2/AS3740, if required. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS3740 / AS and the TDS, and returned down into wastes. à Wall waterproofing membrane to be returned down across the floor substrate over the cured bond breaker/tape or flexible fillet. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 3
9 Ceramic/Stone System Internal & External Installation of Tiles Direct to a Concrete Substrate C02 2/08/207.4 ADHESIVE NOTE: Natural stone can be subjected to warping and staining, therefore Mapei recommends when using natural stone to refer to the manufactures guidelines. Adhesive selection for natural stone is also dependant on its moisture sensitiveness, which is represented by a class system. Please refer to EN467 and the Mapei technical notebook Laying Stone Materials for more information. Adhesive to be chosen from the following options: Normal-Set A. KERAFLEX MAXI S ( AUS) GOOD Solution. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive, Class A). NOTE: Option B required when applying externally with >5000 cm 2 (700x700 mm) tiles. B. KERABOND PLUS / ISOLASTIC ( , ) BEST Solution. Cement based powder with superior bond strength suitable for all types of tiles and natural stone (non-moisture sensitive, Class A), with a latex additive to improve the adhesive s characteristics and to elasticize the adhesive. Rapid-Set C. KERAQUICK S ( AUS) GOOD Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B*). NOTE: Option D required when applying externally with >5000 cm 2 (700x700 mm) tiles. D. KERAQUICK S + LATEX PLUS ( , ) BEST Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B*) with a latex additive to elasticize the adhesive. Resin-Based E. KERALASTIC T ( ). Two component, high performance polyurethane adhesive for ceramic tiles and stone material (Class A/B*/C**). à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 3
10 Ceramic/Stone System Internal & External Installation of Tiles Direct to a Concrete Substrate C02 2/08/207.5 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..6 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. Silicone to be chosen from the following options: A. MAPESIL AC ( GB) Ceramic/Porcelain. Solvent-free, acetic crosslinking mildew resistant silicone sealant. B. MAPESIL LM ( GB) Stone. Neutral mould resistant silicone sealant for stone and marble. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 3
11 SYSTEM FOR THE INSTALLATION OF CERAMIC OR PORCELAIN TILES ON EXISTING TILES C existing tiles primer Eco Prim Grip 2 adhesive Keraflex Maxi S 3 tiles 4 grout Ultracolor Plus sealant Mapesil AC 5 6 Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 08/7 REV
12 Ceramic System Internal/External Installation of Ceramic Tiles on Existing Tiles C03 8/08/207 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System.2 EXISITING CERAMIC TILE SUBSTRATE PREPERATION.3 PRIMER. Any existing loose/dummy tiles and loose/weak/cracked grout with large/deep joints should be removed and filled with ADESILEX P4 ( AUS). 2. Mechanically prepare the existing ceramic tile substrate using the diamond grind method to remove contaminants and to create a suitable surface profile. 3. All substrates must be structurally sound, dry, flat, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the exiting ceramic tile floor substrate that may inhibit bond shall be mechanically removed as per point 2. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS). A. ECO PRIM GRIP ( ).4 ADHESIVE. Multi-purpose, ready-to-use bonding promoter primer made from synthetic acrylic resin and silica inerts with a very low emission of volatile organic compounds (VOC) for render, smoothing and levelling compounds and adhesives for ceramic tiles. à Stir ready-to-use primer prior to application, no dilution is required. à Apply primer with either a roller or brush. Adhesive to be chosen from the following options: Normal-Set A. KERAFLEX MAXI S ( AUS) GOOD Solution. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive). NOTE: Option B required when applying externally with >5000 cm 2 (700x700 mm) tiles. B. KERABOND PLUS / ISOLASTIC ( , ) BEST Solution. Cement based powder with superior bond strength suitable for all types of tiles and natural stone (non-moisture sensitive), with a latex additive to improve the adhesive s characteristics and to elasticize the adhesive. Rapid-Set C. KERAQUICK S ( AUS) GOOD Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material. NOTE: Option D required when applying externally with >5000 cm 2 (700x700 mm) tiles. D. KERAQUICK S + LATEX PLUS ( , ) BEST Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material with a latex additive to elasticize the adhesive. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 2
13 Ceramic System Internal/External Installation of Ceramic Tiles on Existing Tiles C03 8/08/207.5 GROUT à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..6 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 2
14 SYSTEM FOR THE INSTALLATION OF CERAMIC TILES ON METAL SURFACES C metal sheet adhesive Keralastic T 2 ceramic tiles 3 grout Ultracolor Plus sealant Mapesil AC 4 5 Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 08/7 REV 2
15 Ceramic System Internal Installation of Ceramic Tiles on Metal Surfaces C04 24/08/207 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System.2 METAL SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any dust, rust, grease, oil, or paint present on the surface of the metal substrate that may inhibit bond, shall be removed. The substrate should be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 ADHESIVE Adhesive to be chosen from the following options: A. KERALASTIC T ( ). Two component, high performance polyurethane adhesive for ceramic tiles and stone material. B. KERAPOXY ADHESIVE ( ). Two-component, epoxy adhesive with no vertical slip for ceramic tiles and stone material. NOTE: If the substrate is particularly deformable, all coverings larger than 50 x 50 mm must be installed with wide joints. à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 2
16 Ceramic System Internal Installation of Ceramic Tiles on Metal Surfaces C04 24/08/207.4 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..5 SEALANT à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 2
17 FAST TRACK SYSTEM FOR THE INSTALLATION OF PORCELAIN TILES OVER A UNBONDED SCREED C existing substrate separating layer 2 unbonded screed Mapecem Pronto 3 adhesive Keraquick S 4 porcelain tiles 5 grout Ultracolor Plus 6 sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 7 08/7 REV
18 Ceramic System Internal Fast Track System Commercial Installation of Porcelain Tiles C05 8/08/207 PART SYSTEM. UNBONDED SCREED NOTE: A bonded screed applied over a bonding slurry may be used providing that the existing tile substrate is in great condition, with no drummy or cracked tiles and free of powder, loose parts, paint, wax, oil, grease, and any other contaminate which may restrict bonding. A. MAPECEM PRONTO ( AUS).2 ADHESIVE. Pre-blended, ready-to-use, quick-setting and drying (24 hours), controlled-shrinkage mortar for screeds. NOTE: Prior to the application of the screed: à Ensure an isolating layer made of polythene sheets or similar material is laid. à Screed to be in accordance with AS3958. (2007). à Mix MAPECEM PRONTO in strict accordance with the TDS paying particular attention to the surrounding environmental conditions. à Ensure a minimum thickness of 35 mm is applied. Adhesive to be chosen from the following options: A. KERAQUICK S ( AUS) GOOD Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material. B. KERAQUICK S + LATEX PLUS ( , ) BEST Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material with a latex additive to elasticize the adhesive. à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 2
19 Ceramic System Internal Fast Track System Commercial Installation of Porcelain Tiles C05 8/08/207.3 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. A. ULTRACOLOR PLUS ( GB).4 SILICONE. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 2
20 SYSTEM FOR THE INSTALLATION OF TILES OVER ACOUSTIC MATTING C concrete substrate matting adhesive Ultrabond Eco V4 SP or Ultrabond Eco S955 K refer to WMS for appropriate choice acoustic matting bond breaker/tape Mapeband waterproofing membrane Mapelastic AquaDefense tile adhesive Kerabond Plus and Isolastic 50 grout Ultracolor Plus sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information tiles 06/7 REV
21 Ceramic System Internal & External Installation of Tiles over Acoustic Matting C06 8/08/207 2 PART SYSTEM RUBBER & CORK AND BLACK RUBBER ACOUSTIC MATTING. REFERENCES. AS 3740 (200) Waterproofing of domestic wet areas 2. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 3. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System 4. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation.2 CONCRETE SUBSTRATE PREPARATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 MATTING ADHESIVE Matting adhesive to be chosen from the following table: Porous Substrate Non-Porous Substrate Internal Dry Area ULTRABOND ECO V4 SP ULTRABOND ECO S955 K Wet Area ULTRABOND ECO S955 K ULTRABOND ECO S955 K External All Areas ADESILEX G9 or ULTRABOND S965 K A. ULTRABOND ECO V4 SP ( ) ADESILEX G9 or ULTRABOND S965 K. Universal adhesive in water dispersion for resilient floor coverings, with very low emission of volatile organic compounds and with an extended open time. B. ULTRABOND ECO S955 K ( GB). One component, solvent free, sililated polymer based adhesive with a very low emission level of volatile organic compounds. C. ADESILEX G9 ( GB). Two-part epoxy-polyurethane adhesive for rubber, PVC and linoleum flooring. D. ULTRABOND S965 K ( ). One-component, sililate polymer-based adhesive with no solvents or isocyanates for all types of parquet, with extended open time and very low emission level of VOC s..4 ACOUSTIC MATTING A. PROPRIETARY ACOUSTIC MATTING à Apply acoustic matting into the wet adhesive in strict accordance with the relevant MAPEI TDS and acoustic matting manufacturers instructions. à With the system that is to be used, the acoustic underlay supplier should be fully accepting of the methods used and satisfied that the installation will perform under the expected environment conditions that the floor will experience. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 3
22 Ceramic System Internal & External Installation of Tiles over Acoustic Matting C06 8/08/ WATERPROOFING MEMBRANE IF REQUIRED NOTE: Prior to the application of the waterproofing membrane: à Ensure a bond breaker/tape has been applied with MAPEBAND ( GB) or MAPEBAND SA ( ), or a flexible fillet with MAPEFLEX PU45 FT ( GB), at wall/wall, wall/floor junctions and all other areas where movement is expected. Ensure flexible fillet is fully cured. Waterproofing membrane to be chosen from the following options: A. MAPELASTIC AQUADEFENSE ( GB) INTERNAL. Ready-to-use, ultra-quick drying, flexible liquid membrane for internal and external waterproofing applications. à Waterproofing membrane must be applied to walls and floors in a minimum of two even coats or 0.4mm each to form a final flexible, continuous dry thickness of 0.8mm (DFT). B. MAPEGUM WPS ( ) INTERNAL. Fast drying flexible liquid membrane for waterproofing. à Waterproofing membrane to be applied using a trowel, roller, brush or spray to a minimum final thickness of mm, waiting until the first coat is dry before applying further coats crossways. C. MAPELASTIC SMART ( GB) EXTERNAL.6 TILE ADHESIVE. Two component, high flexibility cementitious mortar (with crack-bridging capacity >2mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) à Lay MAPENET 50 ( ) glass fibre mesh into the wet first coat of the waterproofing membrane, ensuring the MAPENET 50 is completely embedded, in strict accordance with the TDS. à Use MAPETEX SEL at the junctions if a flexible fillet was installed. NOTE: When direct tiling over black rubber acoustic matting, à GOOD SOLUTION: Use KERABOND PLUS / ISOLASTIC 50 OR prime the matting with undiluted ECO PRIM T PLUS ( ) before applying KERAFLEX MAXI S. à BEST SOLUTION: Apply an un-bonded screed, such as TOPCEM PRONTO or MAPECEM PRONTO. Particularly recommended for acoustic matting thicknesses above 4.5 mm or mattings with low densities. Tile adhesive to be chosen from the following options: A. KERAFLEX MAXI S ( AUS) GOOD SOLUTION. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive). B. KERABOND PLUS / ISOLASTIC 50 ( )/ ) BEST SOLUTION. Cement based powder with superior bond strength suitable for all types of tiles and natural stone with a latex additive to elasticize the adhesive. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 3
23 Ceramic System Internal & External Installation of Tiles over Acoustic Matting C06 8/08/ GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..8 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. However, MAPEI does have numerous references of past projects that have successfully applied this system in conjunction with proprietary acoustic matting. Testing has been completed in MAPEI s internal laboratory to confirm the compatibility of this system with similar proprietary acoustic mats. It must be noted that the proprietary acoustic matting is NOT a MAPEI product and as such MAPEI has no control over the formulation or the performance characteristics of this proprietary acoustic matting. For further information or recommendations for applications/installations, please contact MAPEI Technical Assistance Department. Please note, due to the varying methods of construction, we recommend that on-site testing by a certified acoustic engineer be conducted for suitability to the prevailing site conditions and acoustic objectives required. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 3
24 SYSTEM FOR THE INSTALLATION OF CERAMIC TILES & STONE MATERIAL ON BALCONIES C existing substrate waterproofing membrane Mapelastic Smart 2 bonding slurry Planicrete SP mixed with Mapecem 3 screed Mapecem Pronto 4 rubber tape Mapeband 5 waterproofing membrane Mapelastic Smart 6 adhesive Keraflex Maxi S 7 grout Ultracolor Plus 8 tiles 9 sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 0 08/7 REV
25 Ceramic System - External Installation of Ceramic/Stone Tiles on Balconies C07 8/08/207 PART SYSTEM. REFERENCES. ASAA Natural Stone Manual 2. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 3. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System 4. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation 5. MAPEI Technical Notebook Waterproofing Terraces and Balconies 6. MAPEI Technical Notebook Laying Stone Materials.2 SUBSTRATE PREPARATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the substrates that may inhibit bond shall be mechanically removed. The substrates should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI Technical Data Sheets (TDS)..3 WATERPROOFING MEMBRANE A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. NOTE: Prior to the application of the waterproofing membrane: à Junctions Option A: Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) wall/wall, wall/floor junctions and all other areas where movement is expected. à Junctions Option B: Apply a flexible fillet with MAPEFLEX PU45 FT ( GB) with the membrane reinforced with MAPETEX SEL ( GB) at all wall/wall, wall/floor junctions and other areas where movement is expected. Ensure fillet is dry and fully cured before applying membrane. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à It is highly recommended to lay MAPENET 50 ( ) alkali-resistant glass fibre mesh into the wet first coat of the waterproofing membrane, ensuring the MAPENET 50 is completely embedded, in strict accordance with the TDS. à If the substrate is CFC sheet, apply a reinforcement fabric along all joints with MAPETEX SEL ( GB), in strict accordance with the TDS. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS and the TDS, and returned down into wastes. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 4
26 Ceramic System - External Installation of Ceramic/Stone Tiles on Balconies C07 8/08/207.4 BONDED SCREED WHERE REQUIRED NOTE: Prior to the application of the screed: à Ensure a slurry coat of PLANICRETE SP ( ) mixed with either MAPECEM ( AUS) or TOPCEM ( AUS) has been applied depending on which product is chosen. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. Bonded screed to be chosen from the following options: A. TOPCEM PRONTO ( AUS) - GOOD Solution. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). B. MAPECEM PRONTO ( AUS) - BEST Solution. Pre-blended, ready-to-use, quick-setting and drying (24 hours), controlled-shrinkage mortar for screeds. à Screed to be in accordance with AS3958. (2007). à Mix in strict accordance with the TDS, paying particular attention to the surrounding environmental conditions. à Ensure a minimum thickness of 0 mm is applied..5 WATERPROOFING MEMBRANE IF SCREED IS USED A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity <2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. NOTE: Prior to the application of the waterproofing membrane: à Junctions Option A: Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) wall/wall, wall/floor junctions and all other areas where movement is expected. à Junctions Option B: Apply a flexible fillet with MAPEFLEX PU45 FT ( GB) with the membrane reinforced with MAPETEX SEL ( GB) at all wall/wall, wall/floor junctions and other areas where movement is expected. Ensure fillet is dry and fully cured before applying membrane. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à It is highly recommended to lay MAPENET 50 ( ) alkali-resistant glass fibre mesh into the wet first coat of the waterproofing membrane, ensuring the MAPENET 50 is completely embedded, in strict accordance with the TDS. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS and the TDS, and returned down into wastes. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 4
27 Ceramic System - External Installation of Ceramic/Stone Tiles on Balconies C07 8/08/207.6 ADHESIVE NOTE: With natural stone, it can be subjected to warping and staining. Therefore Mapei recommends to refer to the stone manufactures instructions. Adhesive selection is also dependant on moisture sensitiveness of the stone, which is represented by a class system. Please refer to EN467 and the Mapei technical notebook Laying Stone Materials for more information. Adhesive to be chosen from the following options: Normal-Set A. KERAFLEX MAXI S ( AUS) GOOD Solution. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive, Class A stones). NOTE: Option B required when applying >5000 cm 2 (700 x 700 mm) tiles. B. KERABOND PLUS / ISOLASTIC ( , ) BEST Solution. Cement based powder with superior bond strength suitable for all types of tiles and natural stone (non-moisture sensitive, Class A stones), with a latex additive to improve the adhesive s characteristics and to elasticize the adhesive. Rapid-Set C. KERAQUICK S ( AUS) GOOD Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B* stones). NOTE: Option D required when applying >5000 cm 2 (700 x 700 mm) tiles. D. KERAQUICK S + LATEX PLUS ( , ) BEST Solution. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B* stones) with a latex additive to elasticize the adhesive. à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 4
28 Ceramic System - External Installation of Ceramic/Stone Tiles on Balconies C07 8/08/207.7 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..8 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB) - Ceramic/Porcelain. Solvent-free, acetic crosslinking mildew resistant silicone sealant. B. MAPESIL LM ( GB) - Stone. Neutral mould resistant silicone sealant for stone and marble. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 4 of 4
29 SYSTEM FOR THE INSTALLATION OF TILES IN BATHROOMS AND DAMP ENVIRONMENTS C concrete substrate rubber tape Mapeband primary waterproofing membrane Mapelastic AquaDefense bonding slurry Planicrete SP mixed with Mapecem screed Mapecem Pronto secondary waterproofing membrane Mapelastic AquaDefense adhesive Keraflex Maxi S 7 grout Ultracolor Plus 8 sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 9 08/7 REV
30 Ceramic/Stone System Internal Installation of Tiles in Bathrooms and Damp Environments C08 6/09/207 2 PART SYSTEM. REFERENCES. AS 3740 (200) Waterproofing of domestic wet areas 2. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 3. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System.2 CONCRETE SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 WATERPROOFING MEMBRANE NOTE: Prior to the application of the waterproofing membrane: à Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) or a flexible fillet with MAPEFLEX PU45 FT ( GB) at all wall/wall, wall/floor junctions and all other areas where movement is expected. Ensure flexible fillet is dry and fully cured if used before applying membrane. à Ensure substrate has adequate falls in accordance with AS3740. If not, apply a screed which incorporates falls. Waterproofing membrane to be chosen from the following options: A. MAPELASTIC AQUADEFENSE ( GB). Ready-to-use, ultra-quick drying, flexible liquid membrane for internal and external waterproofing applications (DFT of minimum 0.8 mm). B. MAPEGUM WPS ( ). Fast drying flexible liquid membrane for waterproofing (DFT of minimum mm) à Waterproofing membrane must be applied to walls and floors in a minimum of two even coats to form a final flexible, continuous dry film thickness in accordance with which membrane was used. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS3740 and the TDS, and returned down into wastes. à Wall waterproofing membrane to be returned down across the floor substrate over the cured bond breaker/tape or flexible fillet. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 4
31 Ceramic/Stone System Internal Installation of Tiles in Bathrooms and Damp Environments C08 6/09/ SCREED IF REQUIRED Screed to be chosen from the following options: A. TOPCEM PRONTO ( AUS) - GOOD Solution. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). B. MAPECEM PRONTO ( AUS) - BEST Solution. Pre-blended, ready-to-use, quick-setting and drying (24 hours), controlled-shrinkage mortar for screeds. à Screed to be in accordance with AS3958. (2007). à Mix and apply in strict accordance with the TDS based on bonded or unbonded application, paying particular attention to the surrounding environmental conditions. Incorporate falls in accordance with AS3740. à Ensure the appropriate minimum thickness is applied..5 WATERPROOFING MEMBRANE IF SCREED WAS USED NOTE: Prior to the application of the waterproofing membrane: à Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) or a flexible fillet with MAPEFLEX PU45 FT ( GB) at all wall/wall, wall/floor junctions and all other areas where movement is expected. Ensure flexible fillet is dry and fully cured if used before applying membrane. Waterproofing membrane to be chosen from the following options: A. MAPELASTIC AQUADEFENSE ( GB). Ready-to-use, ultra-quick drying, flexible liquid membrane for internal and external waterproofing applications (DFT of minimum 0.8 mm). B. MAPEGUM WPS ( ). Fast drying flexible liquid membrane for waterproofing (DFT of minimum mm) à Waterproofing membrane must be applied to walls and floors in a minimum of two even coats to form a final flexible, continuous dry film thickness in accordance with which membrane was used. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS3740 and the TDS, and returned down into wastes. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 4
32 Ceramic/Stone System Internal Installation of Tiles in Bathrooms and Damp Environments C08 6/09/ ADHESIVE NOTE: Natural stone can be subjected to warping and staining, therefore Mapei recommends when using natural stone to refer to the manufactures guidelines. Adhesive selection for natural stone is also dependant on its moisture sensitiveness, which is represented by a class system. Please refer to EN467 and the Mapei technical notebook Laying Stone Materials for more information. Adhesive to be chosen from the following options: A. KERAFLEX MAXI S ( AUS) Normal Set. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive, Class A). B. KERAQUICK S ( AUS) Rapid Set. High performance, deformable, fast setting cementitious adhesive with no vertical slip, for ceramic tiles and stone material (Class A/B*). à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 4
33 Ceramic/Stone System Internal Installation of Tiles in Bathrooms and Damp Environments C08 6/09/ GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..8 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. Silicone to be chosen from the following options: A. MAPESIL AC ( GB) Ceramic/Porcelain. Solvent-free, acetic crosslinking mildew resistant silicone sealant. B. MAPESIL LM ( GB) Stone. Neutral mould resistant silicone sealant for stone and marble. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 4 of 4
34 SYSTEM FOR THE INSTALLATION OF CERAMIC OR STONE CLADDING C concrete substrate repair and smoothing render (if required) Planitop Smooth & Repair R4 cementitious waterproofing membrane Mapelastic Smart CLASS A STONE Kerabond Plus and Isolastic 50 adhesive CLASS B STONE Granirapid CLASS C STONE Keralastic T ceramic/stone grout Ultracolor Plus or Kerapoxy silicone Mapesil AC or Mapesil LM Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 06/7 REV 0
35 Ceramic/Stone System - External & Internal Installation of Ceramic/Stone Cladding C09 8/08/207 PART SYSTEM. REFERENCES. AS 3740 (200) Waterproofing of domestic wet areas 2. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation 3. AS (2007) Ceramic Tiles; Part : Guide to the Installation of Ceramic Tiles 4. AS (992) Ceramic Tiles; Part 2: Guide to the Selection of a Ceramic Tiling System 5. ASAA Natural Stone Manual 6. MAPEI Technical Notebook Laying Stone Materials.2 SUBSTRATE PREPARATION. All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the substrates that may inhibit bond shall be mechanically removed. The substrates should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI data sheets. 2. It is advisable to use mechanical fixings, such as metal angles or pin fixings, where the tile/stone is to be applied at a wall height exceeding 3 m above the ground, where the stone/tile has a mass greater than 32 kg/m 2, and has a tile size greater than 600 x 600 mm..3 SMOOTHING COMPOUND WHERE REQUIRED A. PLANITOP SMOOTH & REPAIR R4 ( ). Structural R4 class, rapid setting, shrinkage compensated, thixotropic, fibre reinforced, cementitious mortar, applied in a single layer from 3 to 40 mm thick, for repairing and smoothing concrete. à Saturate the substrate with water, then wait until any excess water has evaporated. à Apply mortar with a smooth trowel in a single layer from 3 to 40 mm in thickness..4 WATERPROOFING MEMBRANE IF REQUIRED A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à For CFC sheet substrates, apply the waterproofing membrane with a reinforcement fabric along all joints with MAPETEX SEL ( GB), in strict accordance with the TDS. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 3
36 Ceramic/Stone System - External & Internal Installation of Ceramic/Stone Cladding C09 8/08/207.5 ADHESIVE NOTE: Natural stone can be subjected to warping and staining, therefore Mapei recommends to refer to the stone manufactures instructions. Adhesive selection is also dependant on moisture sensitiveness of the stone, which is represented by a class system. Please refer to EN467 and the Mapei technical notebook Laying Stone Materials. Adhesive to be chosen from the following options: Normal-Set A. KERAFLEX MAXI S ( AUS) GOOD Solution. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive, Class A stones). B. KERABOND PLUS / ISOLASTIC 50 ( )/ ) BEST Solution. Cement based powder with superior bond strength suitable for all types of tiles and natural stone (Class A stones) with a latex additive to elasticize the adhesive. Fast-Set C. GRANIRAPID ( ). Two component high performance fast setting and hydrating cementitious adhesive for ceramic tiles and stone materials (Class A/B* stones). Resin-Based D. KERALASTIC T ( ). Two component, high performance polyurethane adhesive for ceramic tiles and stone material (Class A/B*/C** stones). à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 3
37 Ceramic/Stone System - External & Internal Installation of Ceramic/Stone Cladding C09 8/08/207.6 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..7 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. A. MAPESIL AC ( GB) - Ceramic/Porcelain. Solvent-free, acetic crosslinking mildew resistant silicone sealant. B. MAPESIL LM ( GB) - Stone. Neutral mould resistant silicone sealant for stone and marble. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 3
38 SYSTEM FOR WATERPROOFING RETAINING WALLS W block wall waterproofing bandage Mapeband TPE smoothing mortar Planitop Fast 330 cementitious mortar Mapegrout T waterproof coating Plastimul Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 5 corflute 6 backfill 7 09/7 REV
39 Waterproofing System External Waterproofing Retaining Walls W0 7/08/207 PART SYSTEM. BLOCK WALL SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..2 SMOOTHING MORTAR WHERE REQUIRED WHERE TO USE: To repair, to fill mortar joints, and to smooth over any rough areas to create a sufficiently even substrate. Smoothing mortar to be chosen from the following options: A. PLANITOP FAST 330 ( ) GOOD Solution. Quick setting, fibre reinforced cementitious mortar for internal and external floors and walls, applied at a thickness from 3 to 30 mm to smooth out irregularities. B. PLANITOP SMOOTH & REPAIR R4 ( ) BEST Solution. Structural R4 class, rapid setting, shrinkage compensated, thixotropic, fibre reinforced, cementitious mortar, applied in a single layer from 3 to 40 mm thick, for repairing and smoothing concrete. à Saturate the substrate with water, then wait until any excess water has evaporated. à Apply the mortar with a smooth trowel in a single layer in accordance with the relevant thickness limits of the chosen product..3 CEMENTITIOUS MORTAR COVE FILLET, WHERE REQUIRED A. MAPEGROUT T40 ( ). Medium strength (40MPa), shrinkage compensated, fibre reinforced, thixotropic mortar for repairing concrete. à Wet the substrate with water and wait for excess water to evaporate prior to the application of the repair mortar. à Apply the mortar at a radius of 30 to 40 mm with a float or trowel at all wall/wall, wall/floor junctions, and any other point of expected movement. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 2
40 Waterproofing System External Waterproofing Retaining Walls W0 7/08/207.4 WATERPROOFING MEMBRANE NOTE: Prior to the application of the waterproofing membrane: à Ensure structural joints are sealed and applied with MAPEBAND TPE ( ) in strict accordance with the TDS, à All sharp edges are to be rounded off. A. PLASTIMUL ( GB) GOOD Solution. All-purpose bituminous waterproofing emulsion. à Substrate must first be primed with a diluted mix (45-50% clean water) of the waterproofing membrane, as per the TDS. à Waterproofing membrane must be applied in two further coats of.5 mm each (wet thickness) to form a final dry thickness of 3 mm (DFT). NOTE: PLASTIMUL can be further used as an adhesive on top of the already cured waterproofing membrane to adhere subsequent protective layers such as Corflute and Geofabric materials. B. MAPELASTIC SMART ( GB) BEST Solution. Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm..5 PROTECTIVE LAYER A. Corflute or similar material Protective layer must be installed to protect the integrity of the waterproofing membrane prior to backfilling. A drainage system should be installed at the base of the wall to direct and channel water. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 2
41 WATERPROOFING SYSTEM FOR THE INSTALLATION OF GLASS MOSAICS IN SWIMMING POOLS W concrete structure reinforced bonding slurry Planicrete SP mixed with Topcem 2 screed Topcem Pronto cementitious render Planitop Smooth & Repair R4 monolithic sealing of the coving to the substrate Eporip and Mapegrout T40 cementitious waterproofer Mapelastic Smart polypropylene fabric Mapetex Sel adhesive Kerabond Plus and Isolastic glass mosaics grout Kerapoxy Design sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 08/7 REV
42 Waterproofing System Internal & External Installation of Glass Mosaics in Swimming Pools W02 4/08/207 4 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to Selection of Ceramic Tiling System 3. MAPEI Technical Notebook Waterproofing baths and swimming pools.2 CONCRETE SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 SCREED FLOOR NOTE: Prior to the application of the screed: à Ensure all pipe penetrations, light fittings, water circulation and filtration units are appropriately detailed. Contact Mapei Technical Assistance for more information if required. à Ensure a slurry coat of PLANICRETE SP ( ) mixed with either MAPECEM ( AUS) or TOPCEM ( AUS) has been applied depending on which product is chosen. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. Screed to be chosen from the following options: A. TOPCEM PRONTO ( AUS) - GOOD Solution. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). B. MAPECEM PRONTO ( AUS) - BEST Solution. Pre-blended, ready-to-use, quick-setting and drying (24 hours), controlled-shrinkage mortar for screeds. à Screed to be in accordance with AS3958. (2007). à Mix in strict accordance with the TDS, paying particular attention to the surrounding environmental conditions. à Ensure a minimum thickness of 0 mm is applied. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 4
43 Waterproofing System Internal & External Installation of Glass Mosaics in Swimming Pools W02 4/08/ SMOOTHING MORTAR WALL NOTE: Prior to the application of the smoothing mortar, ensure all pipe penetrations, light fittings, water circulation and filtration units are appropriately detailed. Smoothing mortar to be chosen from the following options: A. PLANITOP FAST 330 ( ) - GOOD SOLUTION. Quick setting, fibre reinforced cementitious mortar for internal and external floors and walls, applied at a thickness from 3 to 30 mm to smooth out irregularities. à Apply a feather edge layer to the substrate and then immediately apply a layer at the thickness required. B. PLANITOP SMOOTH & REPAIR R4 ( ) - BEST SOLUTION. Structural R4-class, rapid setting, shrinkage compensated, thixotropic, fibre reinforced, cementitious mortar, applied in a single layer from 3 to 40 mm thick for repairing and smoothing concrete. à Ensure substrate is prepared in accordance with the TDS to have a roughened surface that has been saturated and left for excess water to evaporate..5 COVE FILLET WHERE REQUIRED A. MAPEGROUT T40 / EPORIP ( / ). Medium strength (40 MPa), shrinkage compensated, fibre reinforced, thixotropic mortar for repairing concrete, with a two component, solvent free epoxy adhesive for construction joints and for monolithic sealing of cracks in screeds. à à Apply EPORIP to slightly damp substrate using a flat trowel or brush, ensuring subsequent products are applied within the open times listed on the TDS. Apply MAPEGROUT T40 over the EPORIP using a flat trowel..6 WATERPROOFING MEMBRANE Waterproofing membrane to be chosen from the following options: A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing swimming pools. à à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. It is highly recommended to apply a reinforcement fabric such as MAPETEX SEL ( GB), in strict accordance with the TDS. B. MAPELASTIC FOUNDATION ( GB) For negative hydrostatic pressure. Two component, flexible cementitious membrane for waterproofing concrete surfaces subject to both positive and negative water pressure. à Before applying the waterproofing membrane, apply a coat of PRIMER 3296 ( ) with a brush or roller, diluted : with water. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 4
44 Waterproofing System Internal & External Installation of Glass Mosaics in Swimming Pools W02 4/08/ OSMOTIC CEMENTITIOUS MORTAR SCUM GUTTERS, WHERE REQUIRED A. IDROSILEX PRONTO ( ) [Also known as PLANISEAL 88 ( )].8 ADHESIVE. Osmotic cementitious mortar suitable for contact with drinking water, for waterproofing masonry and concrete structures. à Apply mortar with a brush or trowel in a minimum of 3 coats. à Ensure previous coat is sufficiently dry before subsequent applications. à Observe the area to determine if a fourth coat is required. à The final thickness should be a minimum of approximately 2-3 mm. NOTE: IDROSILEX PRONTO is a rigid waterproofing mortar, if flexibility in the waterproofing layer is required, please seek further assistance from the Mapei Technical Assistance Department. NOTE: KERAPOXY OR KERAPOXY DESIGN is recommend as an adhesive for finger grips where applicable. Adhesive to be chosen from the following options: A. KERAFLEX MAXI S ( AUS) - GOOD SOLUTION. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive). B. KERABOND PLUS / ISOLASTIC ( )/ ) - BETTER SOLUTION. Cement based powder with superior bond strength suitable for all types of tiles and natural stones with a latex additive to elasticize the adhesive. C. KERAPOXY (4--206) OR KERAPOXY DESIGN ( ) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm. Can also be used as an adhesive, OR Two component, decorative, acid resistant epoxy grout, ideal for glass mosaics. May also be used as an adhesive. à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 4
45 Waterproofing System Internal & External Installation of Glass Mosaics in Swimming Pools W02 4/08/ GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. NOTE: KERAPOXY OR KERAPOXY DESIGN is especially recommended in spill over, wet edges, and exposed wall areas. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) OR KERAPOXY DESIGN ( ) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm OR Two component, decorative, acid resistant epoxy grout, ideal for glass mosaics..0 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. When adding chemicals to the spa and/or pool, ensure they are diluted with water, and are NOT poured directly onto any sections of the covering (e.g. tiles, grout, joints etc.), as this can damage the integrity of the product. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 4 of 4
46 SYSTEM FOR WATERPROOFING AND INSTALLING CERAMIC TILES IN NEW SWIMMING POOLS W concrete structure reinforced bonding slurry Planicrete SP mixed with Topcem screed Topcem Pronto cementitious render Planitop Smooth & Repair R4 rubber tape Mapeband cementitious waterproofer Mapelastic Smart fibre glass mesh Mapenet 50 adhesive Keraflex Maxi S ceramic tiles grout Ultracolor Plus sealant Mapesil AC Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 05/7 REV
47 Waterproofing System Internal & External Installation of Ceramics in Swimming Pools W03 4/08/207 PART SYSTEM. REFERENCES. AS (2007) Ceramic Tiles; Part : Guide to Installation of Ceramic Tiles 2. AS (992) Ceramic Tiles; Part 2: Guide to Selection of Ceramic Tiling System 3. MAPEI Technical Notebook Waterproofing baths and swimming pools.2 CONCRETE SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 SCREED FLOOR NOTE: Prior to the application of the screed: à Ensure all pipe penetrations, light fittings, water circulation and filtration units are appropriately detailed. Contact Mapei Technical Assistance for more information if required. à Ensure a slurry coat of PLANICRETE SP ( ) mixed with either MAPECEM ( AUS) or TOPCEM ( AUS) has been applied depending on which product is chosen. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. Screed to be chosen from the following options: A. TOPCEM PRONTO ( AUS) - GOOD Solution. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). B. MAPECEM PRONTO ( AUS) - BEST Solution. Pre-blended, ready-to-use, quick-setting and drying (24 hours), controlled-shrinkage mortar for screeds. à Screed to be in accordance with AS3958. (2007). à Mix in strict accordance with the TDS, paying particular attention to the surrounding environmental conditions. à Ensure a minimum thickness of 0 mm is applied..4 SMOOTHING MORTAR WALL NOTE: Prior to the application of the smoothing mortar, ensure all pipe penetrations, light fittings, water circulation and filtration units are appropriately detailed. Smoothing mortar to be chosen from the following options: A. PLANITOP FAST 330 ( ) - GOOD SOLUTION. Quick setting, fibre reinforced cementitious mortar for internal and external floors and walls, applied at a thickness from 3 to 30 mm to smooth out irregularities. à Apply a feather edge layer to the substrate and then immediately apply a layer at the thickness required. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 4
48 Waterproofing System Internal & External Installation of Ceramics in Swimming Pools W03 4/08/207 B. PLANITOP SMOOTH & REPAIR R4 ( ) - BEST SOLUTION. Structural R4-class, rapid setting, shrinkage compensated, thixotropic, fibre reinforced, cementitious mortar, applied in a single layer from 3 to 40 mm thick for repairing and smoothing concrete. à Ensure substrate is prepared in accordance with the TDS to have a roughened surface that has been saturated and left for excess water to evaporate..5 WATERPROOFING MEMBRANE NOTE: Prior to the application of the waterproofing membrane: à Ensure constructions joints are sealed and applied with MAPEBAND TPE ( ) in strict accordance with the TDS, à Junctions Option A: Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) at wall/wall, wall/floor junctions and all other areas where movement is expected. à Junctions Option B: Apply a flexible fillet with MAPEFLEX PU45 FT ( GB) with the membrane reinforced with MAPETEX SEL ( GB) at all wall/wall, wall/floor junctions and other areas where movement is expected A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. B. MAPELASTIC FOUNDATION ( GB) For negative hydrostatic pressure. Two component, flexible cementitious membrane for waterproofing concrete surfaces subject to both positive and negative water pressure. NOTE: Before applying the MAPELASTIC FOUNDATION, apply a coat of PRIMER 3296 ( ) with a brush or roller, diluted : with water. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à It is recommended to lay MAPENET 50 ( ) alkali-resistant glass fibre mesh or a reinforcement fabric with MAPETEX SEL ( GB), into the wet first coat of the waterproofing membrane, ensuring it is completely embedded, in strict accordance with the TDS. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS3740 / AS and the TDS, and returned down into wastes. à Wall waterproofing membrane to be returned down across the floor substrate over the cured bond breaker/tape or flexible fillet. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 4
49 Waterproofing System Internal & External Installation of Ceramics in Swimming Pools W03 4/08/207.6 OSMOTIC CEMENTITIOUS MORTAR SCUM GUTTERS, IF REQUIRED A. IDROSILEX PRONTO ( ) [Also known as PLANISEAL 88 ( )].7 ADHESIVE. Osmotic cementitious mortar suitable for contact with drinking water, for waterproofing masonry and concrete structures. à Apply mortar with a brush or trowel in a minimum of 3 coats. à Ensure previous coat is sufficiently dry before subsequent applications. à Observe the area to determine if a fourth coat is required. à The final thickness should be a minimum of approximately 2-3 mm. NOTE: IDROSILEX PRONTO is a rigid waterproofing mortar, if flexibility in the waterproofing layer is required, please seek further assistance from the Mapei Technical Assistance Department. NOTE: KERAPOXY ( GB) is recommend as an adhesive for finger grips where applicable. Adhesive to be chosen from the following options: A. KERAFLEX MAXI S ( AUS) - GOOD SOLUTION. High performance, deformable cementitious adhesive with an extended open time and no vertical slip, for ceramic tiles. Especially suitable for the installation of large porcelain tiles and natural stone (non-moisture sensitive). B. KERABOND PLUS / ISOLASTIC ( )/ ) - BETTER SOLUTION. Cement based powder with superior bond strength suitable for all types of tiles and natural stones with a latex additive to elasticize the adhesive. C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm. Can also be used as an adhesive. à To ensure good adhesion, apply a thin coat of the adhesive with the straight edge of the trowel. Immediately follow this with a layer of adhesive at the correct thickness using a suitable notched trowel. à Adhesive should also be applied to the back of the tile/stone (back-buttering). à Ensure the adhesive stays fresh and does not form a skin, especially in hot environments, prior to the application of the tile/stone. à Place the tile/stone firmly into position with a slight twisting motion, merging the adhesives together wet-on-wet, to ensure good contact coverage is achieved. à It is recommended that once the first tile/stone is laid, it should then be removed to assess the coverage. If it is acceptable, then continue, if it is not acceptable, reassess the trowel used and the application technique. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 4
50 Waterproofing System Internal & External Installation of Ceramics in Swimming Pools W03 4/08/207.8 GROUT NOTE: Prior to the application of the grout, ensure the joints are clean, free of dust and empty down to at least 2/3 of the thickness of the tiles. It is then suggested to carry out a m 2 sample area for approval by the architect. NOTE: KERAPOXY ( GB) is especially recommended in spill over, wet edges, and exposed wall areas. Grout to be chosen from the following options: A. KERACOLOR RANGE - GOOD SOLUTION. High performance, polymer-modified, cement-base grouts. B. ULTRACOLOR PLUS ( GB) - BETTER SOLUTION. High-performance, anti-efflorescence, quick-setting and drying polymer-modified mortar with water-repellent technology C. KERAPOXY (4--206) - BEST SOLUTION. Two component, acid resistant epoxy grout for joints of at least 3 mm..9 SILICONE à Fill the joints completely with the grout using the appropriate trowel or rubber float, ensuring the joints are completely compacted with no unevenness. à Remove excess grout while still fresh from the surface of the tile/stone by moving the float diagonally across the joints. A. MAPESIL AC ( GB). Solvent-free, acetic crosslinking mildew resistant silicone sealant. NOTE: Prior to the application of the silicone, it is recommended that the silicone is applied in a test area to be approved by the client and to ensure it doesn t stain the stone/tile. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. When adding chemicals to the spa and/or pool, ensure they are diluted with water, and are NOT poured directly onto any sections of the covering (e.g. tiles, grout, joints etc.), as this can damage the integrity of the product. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 4 of 4
51 SYSTEM FOR WATERPROOFING PLANTER BOXES W concrete smoothing mortar Planitop Fast 330 cementitious coving Mapegrout Fast Set waterproofing membrane Mapelastic Smart membrane protection Geotextile drainage cell or similar Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information 09/7 REV 0
52 Waterproofing System External System Waterproofing Planter Boxes W04 7/08/207 0 PART SYSTEM. REFERENCES. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation.2 CONCRETE OR BLOCKWORK SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the concrete substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 SMOOTHING MORTAR WHERE REQUIRED WHERE TO USE: To repair, to fill mortar joints, and to smooth over any rough areas to create a sufficiently even substrate. Smoothing mortar to be chosen from the following options: A. PLANITOP FAST 330 ( ) GOOD Solution. Quick setting, fibre reinforced cementitious mortar for internal and external floors and walls, applied at a thickness from 3 to 30 mm to smooth out irregularities. B. PLANITOP SMOOTH & REPAIR R4 ( ) BEST Solution. Structural R4 class, rapid setting, shrinkage compensated, thixotropic, fibre reinforced, cementitious mortar, applied in a single layer from 3 to 40 mm thick, for repairing and smoothing concrete. à Saturate the substrate with water, then wait until any excess water has evaporated. à Apply the mortar with a smooth trowel in a single layer in accordance with the relevant thickness limits of the chosen product. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 3
53 Waterproofing System External System Waterproofing Planter Boxes W04 7/08/ JUNCTION DETAIL Junction detail to be chosen from the following options: Cementitious Cove If no screed to be used A. MAPEGROUT T40 ( ) Normal Set. Medium strength (40 MPa), shrinkage compensated, fibre reinforced, thixotropic mortar for repairing concrete. B. MAPEGROUT FAST-SET ( ) Rapid Set. Fast setting and drying, shrinkage compensated, fibre reinforced mortar for concrete repair. à à Wet the substrate with water and wait for excess water to evaporate prior to the application of the repair mortar. Apply the mortar at a radius of 30 to 40 mm with a float or trowel at all wall/wall, wall/floor junctions, and any other point of expected movement. Flexible Fillet If screed to be used C. MAPEFLEX PU45 FT ( GB). One component, rapid hardening, paintable, thixotropic polyurethane sealant and adhesive with a high modulus of elasticity. NOTE: Flexible sealant to be used at all junctions (wall-to-wall, wall-to-floor) and other locations that may be subjected to movement with a gap no larger than 0 mm..5 WATERPROOFING MEMBRANE A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à Ensure substrate has adequate falls in accordance with Clause of AS4654.2, if not, apply a screed after the primary membrane to create falls. à If a flexible fillet was used with MAPEFLEX PU45 FT, ensure MAPETEX SEL is applied at all wall/wall, wall/floor junctions, and any other point of expected movement in accordance with the TDS. à Floor waterproofing membrane to be returned up wall substrates over the cove or flexible fillet in accordance with AS and the TDS, and returned down into wastes. à Wall waterproofing membrane to be returned down across the floor substrate over the cured cove or flexible fillet. Wall membrane shall extend vertically to a minimum height of 00 mm above the soil or fill level. à If no screed is to be used, ensure waterproofing membrane is covered and adequately protected from point loads, abrasion, root damage, and any other potential cause of damage. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 3
54 Waterproofing System External System Waterproofing Planter Boxes W04 7/08/ SCREED IF REQUIRED A. TOPCEM PRONTO ( AUS). Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). NOTE: Prior to the application of the screed: à Ensure a slurry coat of PLANICRETE SP ( ) mixed with TOPCEM ( AUS) has been applied. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. à Screed to be in accordance with AS3958. (2007). à Mix water and TOPCEM PRONTO in strict accordance with the ratios described in the TDS. à Ensure a minimum thickness of 0 mm is applied. à Ensure screed has adequate falls in accordance with Clause of AS WATERPROOFING MEMBRANE IF SCREED WAS USED A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. NOTE: Prior to the application of the waterproofing membrane: à Ensure a flexible fillet has been applied with MAPEFLEX PU45 FT ( GB), at wall/wall, wall/floor junctions and all other areas where movement is expected, à Ensure flexible fillet is adequately cured. à Waterproofing membrane must be applied in at least two coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à Apply a reinforcement fabric with MAPETEX SEL ( GB), at all wall/wall, wall/floor junctions and all other areas where movement is expected, à Floor waterproofing membrane to be returned up wall substrates over the flexible fillet in accordance with AS and the TDS, and returned down into wastes. à Ensure waterproofing membrane is covered and adequately protected from point loads, abrasion, root damage, and any other potential cause of damage. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 3 of 3
55 SYSTEM FOR WATERPROOFING AN EXPOSED NON-TRAFFICABLE ROOFTOP W concrete concrete patching compound Mapecem Quickpatch or 2 engineered screed Topcem Pronto rubber tape Mapeband waterproofing membrane Aquaflex Roof Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information /7 REV
56 Waterproofing System External System Exposed Non-Trafficable Roof Waterproofing W05 7/08/207 0 PART SYSTEM. REFERENCES. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation.2 SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS). Concrete or screed surface should have a minimum equivalent of a wood float or light broom finish to aid in adhesion..3 LEVELLING MATERIAL WHERE REQUIRED NOTE: Ensure substrate has adequate falls in accordance with Clause of AS If not, the below two options should be utilized to create falls. Levelling material to be chosen from the following options: A. MAPECEM QUICKPATCH (PR494, 200) Recommended <0 mm. High performance, high flow concrete patch. à Immediately after mixing, pour mix onto the surface and work it in to obtain an excellent mechanical bond, in thicknesses from to 75 mm. B. TOPCEM PRONTO ( AUS) >0 mm. Ready-to-use normal setting, controlled-shrinkage mortar for quick-drying screeds (4 days). NOTE: Prior to the application of the screed: à If the entire area of the roof is to receive a screed, Mapei recommends adding a primary waterproofing membrane prior to screeding with MAPELASTIC SMART ( GB). à Ensure a slurry coat of PLANICRETE SP ( ) mixed with TOPCEM ( AUS) has been applied. Refer to the TDS for mixing details, à Ensure screed is applied over the slurry coat whilst the slurry coat is still wet. à Screed to be in accordance with AS3958. (2007). à Mix water and TOPCEM PRONTO in strict accordance with the ratios described in the TDS. à Ensure a minimum thickness of 0 mm is applied. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of 2
57 Waterproofing System External System Exposed Non-Trafficable Roof Waterproofing W05 7/08/ WATERPROOFING MEMBRANE A. AQUAFLEX ROOF ( AUS). Ready-to-use flexible liquid membrane with fibres for continuous waterproofing layers on exposed surfaces. NOTE: Prior to the application of the waterproofing membrane: à Apply a bond breaker/tape with MAPEBAND ( GB) or MAPEBAND SA ( ) or a flexible fillet with MAPEFLEX PU45 FT ( GB) at all wall/wall, wall/floor junctions and all other areas where movement is expected. Ensure flexible fillet is dry and fully cured if used before applying membrane. à Ensure structural joints are sealed and applied with MAPEBAND TPE ( ) in strict accordance with the TDS, à Prime the surface with a coat of AQUAFLEX ROOF diluted with 0% water. à Apply two dry coats of AQUAFLEX ROOF approximately 0.4 to 0.5 mm thick each with a suitable long-haired roller, brush or airless spray. à It is recommended (required when micro cracks are present) to lay MAPETEX SEL ( GB) or MAPETEX 50 ( GB) reinforcement mesh into the wet first coat of the waterproofing membrane, ensuring it is completely embedded, in strict accordance with the TDS. à Wait until the first coat is completely dry and that it becomes slightly dark in colour (Approx. 8-2 hours) before applying the second coat in a criss-cross direction to the first. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape in accordance with AS and the TDS, and returned down into wastes. à Ensure termination of membrane is in accordance with AS MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. This system is intended for light foot traffic only. Point loads larger than light foot traffic must always be evaluated by the site owner as they have the potential to damage the system. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page 2 of 2
58 WATERPROOFING SYSTEM FOR THE INSTALLATION OF PEDESTAL TILING W concrete rubber tape Mapeband waterproofing membrane Mapelastic Smart fibre glass mesh Mapenet 50 waterproofing membrane Mapelastic Smart Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information Please refer to the corresponding Work Method Statement for complete list of suitable products and installation information pedestals tiles 09/7 REV
59 Waterproofing System External System Pedestal Tiling W06 7/08/207 0 PART SYSTEM. REFERENCES. AS (202) Waterproofing membranes for external above-ground use Part 2: Design and installation.2 SUBSTRATE PREPERATION All substrates must be structurally sound, dry, solid and stable. Any laitance, dust, grease, oil, paint or curing compounds present on the surface of the substrate that may inhibit bond, shall be mechanically removed. The substrate should then be cleaned and prepared in accordance with the relevant standards and as per the MAPEI technical data sheets (TDS)..3 WATERPROOFING MEMBRANE A. MAPELASTIC SMART ( GB). Two component, high flexibility cementitious mortar (with crack-bridging capacity >2 mm) applied by trowel or roller for waterproofing balconies, terraces, bathrooms and swimming pools. NOTE: Prior to the application of the waterproofing membrane: à Junctions Option A: Apply a bond breaker/tape with MAPEBAND ( ) or MAPEBAND SA ( ) at wall/wall, wall/floor junctions and all other areas where movement is expected. à Junctions Option B: Apply a flexible fillet with MAPEFLEX PU45 FT ( GB) with the membrane reinforced with MAPETEX SEL ( GB) at all wall/wall, wall/floor junctions and other areas where movement is expected à Ensure substrate has adequate falls in accordance with Clause of AS à Waterproofing membrane must be applied in at least three coats by trowel or with a roller within 60 minutes of it being mixed, to give a final thickness (DFT) of at least 2 mm. à Lay MAPENET 50 ( ) glass fibre mesh into the wet first coat of the waterproofing membrane, ensuring the MAPENET 50 is completely embedded, in strict accordance with the TDS. à Floor waterproofing membrane to be returned up wall substrates over the bond breaker/tape or flexible fillet in accordance with AS and the TDS, and returned down into wastes. à Ensure waterproofing membrane is adequately protected from point loads and abrasion from the pedestal system and any other potential cause of damage. MAPEI provides technical data sheets (TDS) for all products which should be read in conjunction with this Work Method Statement. The TDS can be obtained from or by clicking directly on the listed products within the PDF. This Work Method Statement (WMS) provides general recommendations only and is not intended to be interpreted as a generic specification for the application/installation of the listed products. Mapei provides technical data sheets (TDS) for all products which should be read in conjunction with this WMS. The TDS can be obtained from Each project differs in exposure/condition, therefore specific recommendations may vary from the information contained above. For recommendations for specific applications/installations please contact MAPEI Australia Pty. Ltd. MAPEI Australia Pty. Ltd. 80 Viking Drive Wacol, Queensland 4076 Phone: Page of
60 The MAPEI App is now available for quick and easy access via your smartphone or tablet. FREE DOWNLOAD Access product information, technical note books, brochures, product calculators and project references, all easily navigated at your fingertips. Download the FREE MAPEI app from your devices: Android mobile Android tablet iphone ipad Just look for MAPEI.