Humboldt Bay Power Plant Decommissioning Progress Update

Size: px
Start display at page:

Download "Humboldt Bay Power Plant Decommissioning Progress Update"

Transcription

1 Humboldt Bay Power Plant Decommissioning Progress Update EPRI 2016 Conference Presented by Kerry Rod, P. E. Decommissioning Manager June 20, 2016 Pacific Gas and Electric Company

2 Presentation Objectives 2 Learn how PG&E has adapted to the challenges involved in decommissioning a nuclear power plant and hear about some of the innovative solutions we've applied Assess the major achievements that have been made during the decommissioning program at Humboldt Bay this past year including: License Termination Plan approved by the U.S. Nuclear Regulatory Commission May 2016 PG&E Sibley Award received at HBPP for Safety May 2016 PG&E Final Site Restoration permit approved by the California Coastal Commission April 2016

3 PG&E Site Overview 3 Close to the community Very small foot print Many projects at same time Adjacent to Humboldt Bay Remote Northern CA

4 HBPP: A Unique Decommissioning 4 The reactor vessel is located inside the drywell below grade within the Refueling Building

5 And Close Proximity to the Bay 5

6 First and Foremost Safety at HBPP 6 Continue making safety the #1 priority Twice completed more than 1,000 Safe Work Days Recipient of PG&E s Sibley award for 2008, 2009, 2010, 2014 and 2015

7 Understanding Our Safety Culture 7 PRINCIPALS Everyone is responsible Making the work place a safe place Preemptive in lieu of reactive Stop work authority EXPERIENCE Continuity across successful projects Bring right resources at right time Planning the work is essential Supervision and Oversight DEMONSTRATE Management briefing prior to badging Senior leadership walk downs Posters of our family throughout site Walk the talk ASSESSMENT Benchmarking Management Observation Program Adverse Trending Continually Evaluate Risk

8 One Permanent Building Remaining 8 Tremendous progress being made in the field and its all about the team

9 Project Planning Process 9

10 Discharge Canal Remediation 10

11 Turbine Building Substructure Removal

12 East Yard Pre-Trench Concrete Removal 12 Timely execution to allow continual CSM wall installation at the east end of the Refueling Building

13 Liquid Radwaste Building Demolition 13 Performed high risk high contamination demo early in lieu of at end of project RP monitoring established baseline to allow open air demo of RFB and caisson LRW demo demonstrated that the theoretical open air demo procedure was very conservative Limits were raised based on the effectiveness of water sprays Based on the empirical data, eliminated over 21 locations in the RFB that were designated to be shaved or scabbled before open air demo

14 The Last Active Operating Systems 14 Stack Monitoring and Building Ventilation

15 Refuel Building Prep and Demolition 15 Commence RFB Demo West and North Scaffolding Demo Stack Base RFB 75T Bridge Crane West and North ready for Asbestos Contaminated Material (ACM) Removal

16 Completed CSM Wall Installation 255 Panels 16 DEEPEST APPLICATION OF CSM DRILLING EVER PERFORMED IN THE WORLD USING KELLY BAR EQUIPPED MACHINERY

17 Cutter Soil Mix Operations 17 Starting the First Panel

18 Key Caisson Removal Mitigation Tasks 18 Execute Strong Contract Management Transition to Civil Works Project Implement Stringent Oversight Optimize Health and Safety Performance Job Specific Activity Hazards Analysis Obtain Relevant Subject Matter Expertise Optimize Excavation Stability Design Verification Top Lander/Spotter Logistics Coordination Plan

19 Truck and Rail Shipping Campaigns 19 To evaluate alternate means and methods to further reduce the risk of a traffic accident or incident associated with the preparation, loading, and transportation of solid waste from HBPP SWEETS Solid Waste Efficiency and Expediency Test Shipments

20 HBPP Insights and Key Strategies Always work toward earn value Be flexible - things change opportunities arise Having the right resources and bandwidth Understand work control and oversight Do not underestimate site infrastructure needs Well vet your decommissioning cost estimates Establish a good regulatory and community relationships Mock-ups do work and are a prudent investment Deliver on promise, communications and alliance 20

21 Person-Rem for Various U.S. Plants 21 PG&E anticipates that the total decommissioning exposure will be less than 80 Person-Rem, setting a very high standard for future decommissioning total exposures Haddem Neck Main Yankee Big Rock Point 400 Trojan San Onofre I Rancho Seco HBPP REACTOR SHELL SEGMENT

22 SAFETY FIRST THANK YOU