SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Size: px
Start display at page:

Download "SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )"

Transcription

1 SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) BUDGET - $ 72,000, PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE

2 As part of the Bond 2016 Program, Samuel Clemens High School Additions and Renovations will consist of expansion of square footage and renovation of existing spaces to meet current educational/industry standards. Some main points regarding scope of work included in this project: New Event Center (connected to Beard Gym) to house new auditorium, new auxiliary gym, new choir and dance areas, new locker rooms and support spaces. New Career & Technology (CTE) Building (near Baseball Field) to house welding, woodshop, floral design, small animal, and other learning spaces, including new classrooms. The existing Auxiliary Gym will be renovated to include additional CTE classrooms and labs, including a new culinary kitchen, health occupations spaces and other learning areas. The existing auditorium will be removed and the courtyard space will be enlarged. New Front Addition (facing Elbel Rd.) which will include new classrooms and new administration and support spaces. Renovation of JROTC spaces and existing spaces. Additional renovated spaces throughout the building, such as art rooms, teacher work spaces, nurse s clinic. Additional parking space, to include new parking along Elbel and near stadium. ESTIMATED PROJECT COMPLETION SPRING 2020.

3 SCHEDULE ACTION/EVENT PROJECTED DATE FINAL DESIGN APPROVED (BOT) January 2017 BIDS OUT FOR CONTRACTORS February 22, 2017 BIDS RECIEVED March 30, 2017 EVALUATION OF BIDS March 30 April 5, 2017 CONTRACTOR RECOMMENDATION TO BOT April 18, 2017 NOTICE TO PROCEED May 24, 2017 PROJECT COMPLETION February 2020 ONGOING ACTIVITIES CTE Building Exterior Site work Practice Gym Roofing Electrical rough-ins Exterior masonry Event Center (Locker Rm Facilities) Forming up Mezzanine slab Greenhouse Structural framing MEP rough-ins Classroom / Admin Add MEP rough-ins Exterior sheathing & waterproofing Roofing installation Event Center (Auditorium) Formwork for suspended slab

4

5 Career, Technology, and Engineering Building Site Work Expected Completion Feb New Career, Technology, and Engineering building has ongoing punch-list finish out and perimeter site work. Located near baseball field on what used to be old tennis courts. This building will house welding, woodshop, small animal and other Career & Technology classes

6 Classroom and Administration Addition Expected Completion August 2018 New Classroom and Administration addition. Metal stud framing, interior masonry, prep for exterior masonry, sheathing/waterproofing, roofing, ongoing MEP work. This building will be an addition to the front of the main high school front entry. This building will include nineteen instructional classrooms and support additional administration offices

7 Classroom and Administration Addition Expected Completion August 2018 New Classroom and Administration addition. Metal stud framing, interior masonry, prep for exterior masonry, sheathing/waterproofing, roofing, ongoing MEP work. This building will be an addition to the front of the main high school front entry. This building will include nineteen instructional classrooms and support additional administration offices

8 Auxiliary Gym Addition Expected Completion August 2018 New Auxiliary Gym addition has metal stud framing, exterior sheathing, MEP work, & roofing This building will be an addition to Beard Gym and the future Event Center Gym will support as the new practice gym and seat approximately 300 people

9 Event Center Expected Completion August-November 2018 New Event Center continues with support framing/concrete columns for mezzanine slab and formwork for auditorium slab. The New Event Center area will consist of: new auditorium, new dance/cheer studio, new choir room and new locker room facilities

10 Buffalo Drive Parking Lot Expected Completion February 2018 New Buffalo Drive Paring Lot is underway with curbs in place and asphalt paving to follow New Parking Lot on the NE side of the property along Buffalo Drive will bring added parking spaces for the Clemens students

11 Greenhouse Expected Completion March 2018 New Greenhouse is underway with structural framing & MEP rough-ins. New Greenhouse is located north of the baseball field

12 Two Week Look Ahead CTE Building 1. Exterior site work continues south side of Bldg. J Classroom /Admin Addition 1. MEP installation continues 2. Metal stud framing/sheathing/waterproofing 3. Roofing installation Auxiliary Gym 1. Metal stud framing/sheathing/waterproofing 2. MEP work continues 3. Roofing installation 4. Exterior masonry Event Center 1. P Bldg. supports/concrete columns for mezzanine slab 2. Q Bldg. formwork for auditorium slab 3. Steel erection to start up

13 Samuel Clemens High School Schedule Overview *Schedule is subject to change throughout the construction lifecycle Phase Description Start Date Finish Date 1A Summer 1 (MDF, D-Wing Admin, S-Wing Admin, Utilities, Beard Gym HVAC Units) 6/5/2017 8/25/2017 1B North East Parking Lot 6/5/2017 Mid-January New CTE Building 6/5/ /29/2017 3A Classroom and Admin Addition (Front of Building) 6/5/2017 7/31/2018 3B Renovate Existing Admin 6/4/ /28/2018 4A New Auxiliary Gym 6/5/2017 7/31/2018 4B Event Center (Locker Rooms, Choir, Dance, Bridge to B-Wing) 6/5/2017 7/31/2018 4C New Auditorium 6/5/ /1/2018 5A Summer 2 (Renovate ROTC, Campus Lighting Replacement, Terrazzo Floor) 6/4/2018 8/17/2018 5B ROTC Renovation (Start Early) 1/1/2018 8/15/2018 5C Alt #3. Construct New Stair on West Side of Building 6/4/ /28/2018 6A Demo Existing Auditorium and Auxiliary Gym 6/4/2018 8/2/2018 6B Culinary Arts, HOSA, Forensics, Courtyard, Science Renovation, Bridge Addition 8/3/2018 8/16/2019 7A A-Wing Renovation 6/3/2019 8/16/2019 7B B-Wing Renovation 6/3/2019 8/16/2019 7C Remove Portables and Complete Parking Lot Near Schertz Pkwy 6/10/ /31/2019