Sand Relocation Project
|
|
- Elwin Smith
- 5 years ago
- Views:
Transcription
1 Sand Relocation Project (Contract E ) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE, Jacksonville District February 15, 2013 US Army Corps of Engineers JACKSONVILLE DISTRICT
2 Dade County Beach Erosion Control & Hurricane Protection Project ( Dade BEC&HP )
3 BUILDING STRONG
4 BUILDING STRONG
5 Before & After Fed Project Initial Fill = 15.1 Mcy / Renourishment = 3.3 Mcy
6 Erosion Continues
7 BUILDING STRONG
8 Hotspot!
9 Hotspot! Accretionary Zone
10 BUILDING STRONG
11 Most frequent area of renourishment (9)
12 Northern erosive area 32 nd St Breakwaters Southern erosive area
13 Miami Beach - Erosional Hotspots February 2009
14 South Beach Accretionary Zone
15 BUILDING STRONG
16 All Dade offshore BA s are exhausted. Future borrow options include : Cleaning out existing offshore BA s Upland sources Offshore BA s outside of Dade County Nondomestic sources Relocation of material from existing beaches
17 Basic Backpassing Strategy
18 Previous Backpassing Operations : Truck Haul Operations in 1996, 2002 Larger-scale pumping operations in 2007, 2012.
19 Backpassing Considerations Environmental Impacts (at borrow and fill areas) RSM / Downdrift Impacts Disruption (tourism, concessionaires, surrounding hotels and businesses) Public Safety Noise, vibration, pollution, aesthetics Opposition at the borrow site Low production rate vs erosion Truck-haul : Unconsolidated fill vs hydraulic placement
20 Pumping vs Trucking : Pro s & Cons Pumping is more efficient for moving large volumes Less traffic : environmental, safety, aesthetic concerns Slurry fill compacts better; better performance Less (?) equipment required Higher mob/demob costs Pump/Pipes can be maintenance intensive Pipeline can limit backpass distance
21 Challenging Construction Zone
22 Challenging Politics
23 Challenging Politics Original Design
24 Challenging Politics Final Design Original Design
25 (16 th St.)
26 Basic Layout of Contract E Backpassing Operation N. Fill R53-R54 S. Fill R60-R61 Borrow R64-R69
27 Contract E Sand Backpass Operation Total volume of 84,000 cy backpassed Length of fill areas = 2,100 feet Length of borrow area = 5,000 feet Pumping distances of 1.1 and 2.3 miles Fill area : 205-ft construction template Borrow area : 100-ft cut into seaward berm Methodology : Pipeline transport of slurry
28 Overall Project Layout
29 Overall Project Layout Borrow zone
30 Overall Project Layout Slurry Pump Borrow zone
31 Overall Project Layout Pipeline Pipeline Slurry Pump Borrow zone
32 Overall Project Layout Discharge / Earthmoving equipment Pipeline Pipeline Slurry Pump Borrow zone
33 Overall Project Layout Discharge / Earthmoving equipment Pipeline Pipeline Slurry Pump Borrow zone
34 Equipment / Setup
35 Overall Layout
36 Overall Layout
37 Overall Layout 100
38 Overall Layout
39 Overall Layout
40 Overall Layout
41 Overall Layout
42 Overall Layout
43 Excavation at the Borrow Site
44 Stockpiling Borrow Material
45 Safety Zone Around Loader
46 Pump and Hydraulic Loader
47 Loading the Hopper
48 Discharge Pipeline
49 Booster Pump
50 Slurry Discharge
51 Discharge / Fill Area
52 Discharge / Fill Area
53 Final Placement and Shaping
54 Finished Project
55 B/A -C
56 BUILDING STRONG
57 Lessons Learned Backpassing can be a viable method if : Downdrift effects are not important Distance between borrow and fill areas not too great Disruptions to beach use/operations not too great Requires special attention to : Public/political aspects : noise, disruption, safety, etc. Tradeoffs between trucking and pumping
58 Questions?