Update on FCPS Construction/Renovation Projects. November 2015

Size: px
Start display at page:

Download "Update on FCPS Construction/Renovation Projects. November 2015"

Transcription

1 Update on FCPS Construction/Renovation Projects

2 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (7): $50,804 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 66.0% Revised Completion Date per GC: No Change

3 Squires Elementary -- Renovation Rendering of Final Façade

4 Squires Elementary -- Renovation Work Completed to Date: Area B grade beams and footings are complete (Phase 2A). Area B CMU load-bearing walls are complete (Phase 2A). Area B window installation is complete in the classroom wing being renovated (Phase 2). Area B mechanical, electrical and plumbing rough-ins have begun (Phase 2). Area B terrazzo installation has begun (Phase 2). Current Work Effort (November): Area B VCT to complete in the classroom wing being renovated (Phase 2). Area B exterior spray insulation to start (Phase 2A). Area B laying of brick to begin (Phase 2A). Area B roof joist and decking to continue (Phase 2A). Area B roofing to begin (Phase 2A).

5 Squires Elementary -- Renovation Classroom Addition Ground Face Masonry Steel Supports Bar Joists

6 Squires Elementary -- Renovation Wood Window Blocking Terrazzo Flooring VCT in Classroom Renovated Restroom

7 New Elementary at Passage Mound Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (5): $131,750 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 38.24% Revised Completion Date per GC: No Change

8 New Elementary at Passage Mound Rendering of Final Façade

9 New Elementary at Passage Mound Work Completed to Date: Install insulation on Gym roof. Install bar joists & decking- Area D. Install modified roof on Administration Area. Continue with above-ceiling MEP insulation. Complete Area A Classroom brick Current Work Effort (November): Install metal studs in Administration Area. Install ceiling grid- Area A Classrooms. Install metal roof panels- Area A and Area B. Install insulation on Roof Area C. Install gravel front parking lot

10 New Elementary at Passage Mound Site Towards Area B Entrance Roof Area D Media Center Steel

11 New Elementary at Passage Mound Corridor Framing Admin. Area Framing Layout Lobby Entrance Street View

12 New Elementary at Georgetown Road Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (5): $54,482 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 41.0% Revised Completion Date per GC: No Change

13 New Elementary at Georgetown Road Rendering of Final Façade

14 New Elementary at Georgetown Road Work Completed to Date: Fine grading behind installed curb & gutter continues. Installation of DGA base for parking lots and drive lanes started. Interior sanitary and vent piping and domestic water rough-in on-going. CMU in Areas A & C are around 95% complete, 85% in Area D, 80% in Area B. Below grade brick masonry is approximately 50%. Current Work Effort (November): Site contractor to continue grading parking lot and begin binder installation. Concrete floor slab installation will continue at the stage and mezzanines. Structural steel will continue, mezzanine decking / structural steel / concrete will complete. Foam cavity insulation to begin in Area A, B & C. CMU installation will continue. Above grade brick veneer will start. Installation of above deck roof insulation and dry-in will continue.

15 New Elementary at Georgetown Road Exterior of Gym Gym Roof Deck Media Ctr. Towards Lobby Media Center

16 New Elementary at Georgetown Road Phase B Wing Phase C Wing Admin. Suite Phase C Wing

17 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (2): $637 Scheduled Contract Completion Date: July 2017 % of Contract Completed: 18.94% Revised Completion Date per GC: No Change

18 New High at Winchester Road Rendering of Final Façade

19 New High at Winchester Road Work Completed to Date: Fill at athletic fields and storm drains at parking lot have continued. Geothermal has 242 wells drilled and 11 circuits tied-in. Foundations are 99% complete in all areas of the academic building. ICF near roof bearing in Area C. Second floor ICF has begun in Area B. Area A ICF stem walls continue. Precast concrete planks have been set in Area E3 with 2 concrete cap. Area E3 roof bearing CMU walls have continued. Area C roof bearing CMU is near complete. Area B second floor CMU bearing walls are complete. Foundation CMU has continued. Steel joist and deck has continued in Areas E3 & E4. Hollow metal frames are being set as needed. Above-ceiling electric and plumbing have continued in Area C. Underslab roughins have continued in Areas D, E1, & E2.

20 New High at Winchester Road Current Work Effort (November): Storm drains will continue at the parking lot. Fill at athletic fields will continue. Geothermal drilling and tie-ins will continue. Foundations will be completed at the academic building. Foundations will begin at the fieldhouse. ICF second floor bearing will be complete in Area B. Floor slabs will begin in Area D and continue in Area E2. Area E3 gym roof bearing CMU will be completed. Area C roof bearing CMU will be completed. Area E3 second floor CMU will be near complete. Steel joists and deck will begin in Area E3 (including gym). Area C roof joists will begin. Second floor joists will begin in Area B. Electric and plumbing rough-ins will continue above ceilings. Under-slab rough-ins will be near complete in all areas.

21 New High at Winchester Road View from SW Corner View from Entry Down Corridor ICF Walls CMU Walls & Door Frames

22 New High at Winchester Road Footings & Stem Walls Precast Concrete Planks -- Gym Walk-in Freezer Slab Acoustic Metal Decking Aux. Gym