Update on FCPS Construction/Renovation Projects. December 2015

Size: px
Start display at page:

Download "Update on FCPS Construction/Renovation Projects. December 2015"

Transcription

1 Update on FCPS Construction/Renovation Projects

2 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (8): $52,818 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 70.0% Revised Completion Date per GC: No Change

3 Squires Elementary -- Renovation Rendering of Final Façade

4 Squires Elementary -- Renovation Work Completed to Date: Area B plumbing rough-in and fixtures are complete (Phase 2). Area B ceramic tile is complete (Phase 2). Area B casework is complete (Phase 2). Area B interior masonry partition walls are complete (Phase 2A). Area B roof joists and decking are complete (Phase 2A). Current Work Effort (December): Area B terrazzo to complete (Phase 2). Area B doors and hardware to complete (Phase 2). Area B exterior spray insulation to complete (Phase 2A). Area B brick to continue (Phase 2A). Area D selective demolition to begin (Phase 3).

5 Squires Elementary -- Renovation Completed Restroom VCT Flooring Completed Casework Terrazzo Base

6 Squires Elementary -- Renovation Supply Ducts Exterior Doors Prepping CMU Walls Exterior Spray Insulation

7 New Elementary at Passage Mound Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (6): $143,211 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 50.93% Revised Completion Date per GC: No Change

8 New Elementary at Passage Mound Rendering of Final Façade

9 New Elementary at Passage Mound Work Completed to Date: Install metal studs & drywall in Administration Area. Start Media Center metal Studs. Install ceiling grid - Area A Classrooms. Start metal roof panels - Area A. Start windows - Area A. Current Work Effort (December): Continue with above-ceiling MEP installation. Continue with window installation Area A and Area B. Complete brick on the Media Center. Permanent power on to the building. Start ceiling grid in Area B - Classrooms.

10 New Elementary at Passage Mound Site Towards Area B Entrance Typical Classroom Media Center - Exterior

11 New Elementary at Passage Mound Media Center -- Interior Kitchen Last Corridor Cap Street View

12 New Elementary at Georgetown Road Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (6): $48,441 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 49.0% Revised Completion Date per GC: No Change

13 New Elementary at Georgetown Road Rendering of Final Façade

14 New Elementary at Georgetown Road Work Completed to Date: Fine grading behind installed curb & gutter continues. Installation of DGA base for parking lots and drive lanes on-going. Begin exterior window installation starting in Area C. CMU in Areas A & D are around 95% complete. Brick veneer is on-going. Mechanical, Plumbing & Electrical are on-going Tectum Roof deck installation complete. Area A & D roof insulation on-going. Current Work Effort (December): Site contractor to continue grading parking lot and begin binder installation. Exterior window installation on-going. Structural steel framing and roof decking will complete. Foam cavity insulation to begin in Area D & complete in Area A. CMU and brick veneer installation will continue. Installation of above deck roof insulation and dry-in will continue.

15 New Elementary at Georgetown Road Entrance Front Gym Roof Base Sheet Mezzanine Sprinkler Piping

16 New Elementary at Georgetown Road Mezzanine Raceway Roof Deck Installation South End South Wall Gym

17 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (2): ($16,111) Scheduled Contract Completion Date: July 2017 % of Contract Completed: 21.13% Revised Completion Date per GC: No Change

18 New High at Winchester Road Rendering of Final Façade

19 New High at Winchester Road Work Completed to Date: Fill at the Athletic Fields has continued. Storm drain installation has continued in parking lot. Geothermal wells have continued. Field house foundations have begun. Foundations are 99% complete for academic building. ICF walls are to roof bearing height in Area C. ICF walls are to second floor bearing height in Area B. Floor slabs have begun in Area D. Masonry is up to roof bearing height in the Main Gym. Masonry is up to roof bearing height in Area C. Masonry is up to second floor bearing height in Area B and Area E3. Area E2 masonry has begun. Stem wall CMU has been completed in Areas E1 and D and has begun in Area A. Steel joist and metal deck work has begun on the second floor of Area B and at the roof of Area C. Mechanical rough-ins have continued above ceiling in Area C on the first floor. Underground plumbing in Areas A, D, and E1 has continued and is near completion. Underslab electrical rough-ins have been completed in Area E1 and have begun in Area D. Electric primaries have been roughed-in at the mechanical room.

20 New High at Winchester Road Current Work Effort (December): Fill at athletic fields will be completed. Storm drains will continue at the parking lot. Geothermal drilling and tie-ins will continue. Foundations will be completed at the field house. Foundations will begin at the grandstand bleachers and restrooms at the bleachers. Floor slabs will be completed in Area D. Floor slabs will be placed on the second floor in Areas E3, E4, and B. Floor slabs will begin in Area A. Masonry will begin in Area B on the second floor and on the first floor in Area E1 and D. Foundation CMU will be completed in Area A. Second floor masonry will begin in Areas E3 and E4. All CMU masonry will be completed in Area C. Roof Joist and metal deck will continue in Area C. Second floor joist/deck will be completed in Area E3 and E4 and will begin in the Main Gym. Above ceiling MEP work on the first floor of Area C will continue and will begin in Area E4. Underground plumbing will be complete in all areas of the academic building. Underslab electrical will continue in Areas A, D, & E1. Underground plumbing will begin in the Field House. Secondary electrical rough-ins will begin in the Field House.

21 New High at Winchester Road Area A Progress Area D Progress Area E1 Progress Area E4 and C

22 New High at Winchester Road Area C Ductwork Stored Ductwork Gym CMU Gym Upper Bleachers