1 VDOT Major Projects Update April 20, 2017

2 Agenda Introduction Peninsula Projects Southside Projects Harbor Crossing Questions/Comments 2

3 Summary Construction Execution Timeline I-64 Peninsula Seg. I PE Start 2014 I-64 Peninsula Seg. I Construction NTP I-64 Peninsula Seg. II PE Start I-64 Peninsula Seg. II Construction NTP I-64 Peninsula Seg. III PE Start Phase 1 64/264 Interchange Construction NTP Activity Completed 3

4 Summary Construction Execution Timeline Phase 2 64/264 Interchange Construction NTP I-64 Southside High Rise Br. Construction NTP I-64 Pen. Seg. I Construction Complete I-64 Pen. Seg. III Construction NTP I-64 Pen. Seg. II Construction Complete Phase 1 64/264 Interchange Construction Complete 2020 I-64 Southside High Rise Br Construction Complete Phase 2 64/264 Interchange Construction Complete I-64 Pen. Seg. III Construction Complete Activity Scheduled

5 I-64 Peninsula Projects Exit 234 Rt. 199 Newman Rd SEGMENT III Exit 238 Williamsburg Rt. 143 / Camp Peary York River Exit 242 Rt. 199 Humelsine Parkway Exit 243 US 60/Rt. 143 Busch Gardens Exit 247 Rt. 143 SEGMENT II Exit 247 Rt. 238/Yorktown Rd Exit 250 Fort EusKs Blvd SEGMENT I Exit 255 Jefferson Ave James River

6 I-64 Peninsula Capacity Improvements Segment I General Scope: Construction Contractor: Contract Completion 01 Dec 17 Current Status: 6 $122M Project Schedule: Shirley Contracting Company, LLC Construction Budget: 5.4 Miles of Interstate Widening New General Purpose Lane and Left Shoulder Constructed in the Median Widening Six Existing Bridges Managed Shoulder to Ft Eustis Blvd. Bridge Widenings Substantially Complete Traffic Shifts to New Lanes to be Complete by End of April Constructing Soundwalls Projected to Complete on Schedule

7 I-64 Peninsula Capacity Improvements Segment II General Scope: Construction Contractor: Contract Completion 24 May 19 Current Status: 7 $189M Project Schedule: Allan Myers Construction Budget: 6.7 Miles of Interstate Widening New General Purpose Lane and Left Shoulder Constructed in the Median Reconstruction of Existing Lanes Widening Nine Existing Bridges Finalizing Design Documents Barrier Placement and Lane Shifts Clearing and Grubbing Operations Starting Bridge Widening Work

8 I-64 Peninsula Capacity Improvements Segment III General Scope: Construction Contractor: Request for Proposals to be Issued June 17 Current Status: 8 $311M Project Schedule: To Be Determined Project Budget: 8.2 Miles of Interstate Widening New General Purpose Lane and Left Shoulder Constructed in the Median Widening of Four Existing Bridges Replacing Two Overpass Bridges Replacing Queens Creek Bridges Contractor Preparing RFQ Responses Technical Requirements Being Refined and Developed Public Coordination

9 Hampton Roads Southside Projects Hampton Roads Bridge Tunnel 64 Express Lanes 64/Northampton Blvd Bowers Hill 64/264 Interchange 58/460/13 Connector 64 Southside and High Rise Bridge 9

10 I-64 Southside and High Rise Bridge Replacement Phase 1 General Scope: 8.75 Miles of Interstate Widening New Managed Lane and Left Shoulder Constructed in the Median Widening of Six Existing Bridges Replacing Great Bridge Blvd. Bridge Construct New High Rise Bridge Phase 1 Construction Contractor: To Be Determined Three Contractor Teams are Shortlisted Project Budget: $600M Project Schedule: Project Award Projected for Fall 2017 Current Status: Technical Proposals Due June 2017 Contractors Working Through Alternate Technical Concept Processes 10

11 11 I-64/I-264 Interchange Improvements Phase 1 General Scope: 2.2 miles of Interstate Improvements Widen WB I-64 between Twin Bridges and I-264 Interchange New two-lane flyover ramp from WB I-64 to existing EB I-264 CD Road New two-lane EB I-264 CD Road New exit ramp from WB I-64 to new EB I-264 CD Road Construction Contractor: Tutor Perini Corp. Project Budget: $158M Project Schedule: Scheduled Completion Oct 19 Current Status: Clearing and Grubbing Working on Structure Foundations Relocating Tidal Stream

12 I-64/I-264 Interchange Improvements (I-264 to Witchduck Road) Phase 2 General Scope: Extends C-D Road from Newtown to Witchduck Reconfigure Newtown Road Interchange Reconfigure Witchduck Road Interchange Construct Greenwich Road Flyover Construction Contractor: To Be Determined Project Budget: $192M Project Schedule: Project is Scheduled for Advertisement in June 17 Current Status: Contract Package Being Prepared for Advertisement Final Right of Way Processes Being Addressed 12

13 I-64/I-264 Interchange Improvements Phase 3 General Scope: Construction Contractor: NEPA Document Approval 24 Months Current Status: 13 $10M in Funding Project Schedule: To Be Determined Project Budget: NEPA Document Development IMR Development and Approval Preliminary Engineering Pre-Scoping Activities Underway Developing Resourcing for the Project

14 Route 58/460/13 Connector General Scope: NEPA Document Development IMR Development and Approval Preliminary Engineering Construction Contractor: To Be Determined Project Budget: $5M in Funding Project Schedule: NEPA Document Approval 36 Months Current Status: Pre-Scoping Activities Underway Developing Resourcing for the Project 14

15 Bowers Hill Interchange General Scope: Identify Short/Long Term Operational Improvements Construction Contractor: To Be Determined Project Budget: $4M in Funding Project Schedule: Operational Analysis 24 Months Current Status: Pre-Scoping Activities Underway Developing Resourcing for the Project 15

16 Hampton Roads Bridge Tunnel General Scope: Expand the Hampton Roads Bridge Tunnel Provide 6 Lane Capacity to I-64 from I-664 to I-564 Construction Contractor: To Be Determined Project Estimate: $3.3B (2016$) Project Schedule: Contract Award Projected in 2019 Current Status: SEIS Being Completed $25M in Funding to Begin Preliminary Work Corridor Survey in Progress Initial Geotechnical Work in Progress Industry Outreach and Feedback 16

17 I-64 Express Lanes- Segment I General Scope: 8.4 Miles of Two-Lane Reversible HOV Conversion to Express Lanes Tolling Contractor: TransCore, LP Project Budget: $19M (State Funding) Project Schedule: Operational December 2017 Current Status: Overhead Gantry and Sign Installation Late April August 2017 System Testing Begins Fall

18 I-64/Northampton Blvd. Interchange Improvements General Scope: Modifications to Ramp from 64WB to Northampton Blvd. Modifications to Ramp from 64EB to Northampton Blvd. Extend the Acceleration Lane from Northampton Blvd. to 64WB Construction Contractor: To Be Determined Project Budget: $8M Project Schedule: Currently Advertised Completion Date Scheduled 30 May 2018 Current Status: Construction Bids to be Received April 26 th 18

19 Questions - Comments