Storage & loading on site SOFREGAZ
|
|
- Arnold Pearson
- 5 years ago
- Views:
Transcription
1 Large Cryogenic above ground LNG Tank Full Containment (9% inner wall + Pre-stressed concrete outer wall) Typical Construction Sequence March 4 th 2011
2 Storage & loading on site
3 Storage & loading on site
4 Storage & loading on site
5 Soil Improvement STEP 1a Soil Improvement (CMC)
6 Soil Improvement STEP 1b Controlled Modulus Columns (CMC) Bottom Slab Ground Level Working Platform Level (CMC) Transition Layer Controlled Modulus Columns
7 LNG Storage Tanks erection Concrete slab STEP 1 - Bottom Slab Corner Anchor to be installed before bottom slab concreting. Concrete Wall Corner Anchor (Carbon Steel) Bottom Slab Stud Bolt Detail of A Re-bar A Bottom Slab Ground Level
8 Concrete slab
9 Slab reinforcement & prestressing cables casing
10 LNG Storage Tanks - erection STEP 2 Concrete wall Re-bar Reinforcement Anchor Plate to be installed. Concrete Forms Reinforcement Re-bar Bottom Slab Re-bar B Detail of B Concrete Form Concrete Form Bottom Slab Ground Level
11 LNG Storage Tanks erection STEP 3 Concrete wall Re-bar Panel Reinforcement Concrete Forms C Re-bar Platform Re-bar Concrete Form Concrete Form Platform Detail of C Platform Bottom Slab Ground Level
12 LNG Storage Tanks erection STEP 4 Concrete wall Re-bar Panel Reinforcement Concrete Forms D Re-bar Panel Platform Concrete Form Hanger Platform Platform Hanger Platform Detail of D Hanger Platform Bottom Slab Ground Level
13 Jumping formwork
14 LNG Storage Tanks erection STEP 6 Assembly of roof center, outer supports & outside rain protection From Crane Outer Support Stairway Center Support Outer Support Ground Level
15 Roof structure details
16 Central temporary support
17 Roof section lifting (25t)
18 Roof section adjustment
19 General view
20 Roof plates welding
21 Rainy weather impact Taking care of rainy weather conditions on site, bottom liner will be erected & welding as soon as the metallic roof is water tight
22 LNG Storage Tanks erection STEP 7 Assembly of roof sections and liner plates From Crane From Crane Roof Rafter Top Ring Outer Support Stairway Center Support Outer Support Annular Plate Bottom Liner Plate Ground Level
23 Bottom liner plates welding
24 LNG Storage Tanks erection STEP 8 Assembly of Suspended deck Roof Suspended Rod Temporary Support Outer Support Suspended Deck Outer Support Ground Level
25 Suspended deck
26 Suspended deck welding
27 LNG Storage Tanks erection STEP 9 Insulation work on Annular space Concrete Wall Outer Support Secondary Annular Corner Anchor Inner Annular Plate Concrete Ring Beam Foam glass Perlite Concrete Detail of E Roof Suspended Rod Outer Support Suspended Deck Outer Support E Ground Level
28 LNG Storage Tanks erection STEP 10 Ring Plate(Compression Ring Plate) Ring Plate F Ring Plate Re-bar Support Detail of F Roof Suspended Deck Ground Level
29 Metallic compression ring
30 Metallic compression ring
31 LNG Storage Tanks erection STEP 11 Roof Air Raising Roof Suspended Deck Ground Level
32 Roof at lowest position
33 Venting equipment
34 Air rising
35 Connection with compression ring
36 Roof climbing
37 Final position
38 LNG Storage Tanks erection Roof Concrete STEP 13 Side Liner Plate (Vapor Barrier) Hoist 3 Installation 2 Side Liner Plate Opening Fabrication 1 Ground Level
39 Wall liner erection & welding
40 Corner protection insulation
41 Corner protection plates
42 LNG Storage Tanks erection Roof Concrete STEP 12 Roof Concreting & Pressurizing Compressor Opening Ground Level
43 Pressurization & concreting
44 Pressurization & concreting
45 LNG Storage Tanks erection STEP 14 Inner shell plates erection Roof Concrete Inner Shell Plate Opening Inner Shell Plate Inner Shell Plate Turning Table Inner Shell Plate Ground Level
46 LNG Storage Tanks erection STEP 15 Secondary barrier Roof Concrete Concrete Wall Inner Shell Plate Secondary Barrier PIR Inner Shell Plate Inner Shell Plate G Opening Detail of G Ground Level
47 Inner tank shell erection
48 Automatic welding machine
49 Welding machine Operator
50 Shell top stiffener
51 LNG Storage Tanks erection STEP 16 Bottom Insulation and Plate Roof Concrete Secondary Bottom Plate(9%Ni) Perlite Concrete Inner Bottom Plate(9&Ni) Foam Glass Inner Shell Plate Bottom Liner Plate(C.S.) Bottom Slab Detail of H Inner Shell Plate Opening H Ground Level
52 Foam Glass layers installation
53 LNG Storage Tanks erection STEP 17 Pump Column Roof Concrete Inner Shell Plate Opening Pump Column Ground Level
54 Bottom inlet stand pipe
55 Inlet top nozzle with splash plate
56 Pump column prefabrication
57 Pump column erection
58 Stilling well and bottom connection
59 Cool down ring
60 Purge piping
61 NDE
62 DIMENSIONAL
63 VACUUM BOX
64 LIQUID PENETRANT TEST
65 X-RAY INSPECTIONS
66 ALLOY MATERIAL IDENTIFICATION
67 PRESSURE TEST
68 AUTOMATIC US TEST
69 LNG Storage Tanks erection STEP 18 Hydrostatic, vacuum and Pneumatic Test PRV Inner Shell Plate Pump Column Inner Stairway Hydrostatic Test Level Ground Level
70 SEA WATER TEST
71 Pumping station
72 PRESSURE & VACUUM TEST
73 LNG Storage Tanks erection Platform Walkway STEP 19 TOP PLATFORM PRV Nozzle Suspended Deck Inner Shell Plate Staircase Pump Inner Stairway Column Ground Level
74 Metallic top platform
75
76 MAIN TOP PLATFORM
77
78
79
80
81
82 Instrumentation
83 INSTRUMENTATION
84 VACUUM VALVES
85
86 LNG Storage Tanks erection STEP 20 Wall Insulation Glass Wool Glass Wool Gondola Inner Shell Side Liner Inner Shell Outer Shell Ground Level
87 RESILIENT BLANKET
88 RESILIENT BLANKET
89 LNG Storage Tanks erection STEP 21 Dome Space Insulation & Perlite Powder Filling Walkway PRV Nozzle Perlite Filling Nozzle Glass Wool Suspended Deck Inner Shell Plate Staircase Pump Column Inner Stairway Perlite Powder Perlite Powder Ground Level
90 PERLITE FURNASE
91 PERLITE VIBRATION & RESERVE
92 SUSPENDED DECK INSULATION
93 LNG Storage Tanks erection Oxygen Platform Nitrogen Inlet Line STEP 22 Box-up and Nitrogen Purging Walkway PRV Nozzle Perlite Filling Nozzle Glass Wool or Perlite powder Suspended Deck Inner Shell Plate Staircase Pump Inner Stairway Column Nitrogen Perlite Powder Ground Level
94 DRYING EQUIPMENT
95 N2 REGASIFICATION UNIT
96 O2 ANALYSER & DEW POINT