1 PROGRESS REPORT OF DEVELOPMENT WORK UNIVERSITY TOWN 1-1

2 PROGRESS OF DEVELOPMENT WORK IN UNIVERSITY TOWN 1) MAIN AZIZ KHAN ROAD 2) BLOCK A 3) BLOCK B 4) BLOCK - C 5) BLOCK D 6) BLOCK E 7) BLOCK F 8) SEWERAGE SYSTEM 9) MAIN GATE 10) SITE OFFICE 11) S. WATER DRAIANGE 12) ELECTRIFICATION 13) SUI GAS LINE 14) OVER HEAD WATER TANK (100000) GALLONS 15) MODAL HOUSE 16) STREET LIGHT POLES 17) PARK TABLE OF CONTENTS 1-2

3 SITE ENGINEER ADMIN C.E.O 1) MAIN AZIZ KHAN ROAD Asphalt Premix Carpeting work of Main. Aziz khan Road 100% has completed Main. Aziz khan Road 1.28km 72ft width 100% has completed (including, i.e., cutting filling, Sub Base, Base Course, Street Light Pool has completed Land scaping and other flowering plant has completed Kerb stone work has completed Kerb Stone painting work has completed M. Bridge (Size 38 x72 x32 ) has completed Culvert Block B,C (Size 12 x72 x10 ) has completed Culvert Block D,E(Size 10 x72 x8 ) has completed Foot Path Drain has completed Road Marking has completed. 1-3

4 2) Block A EARTH WORK Cutting/Leveling of over Area has completed Internal Street No: 1. 40ft width has completed up to (D.S.T) Street No ft width 100% has completed up to ( D.S.T) Street No.3. 40ft width has completed up to (D.S.T) Street No ft width has completed up to (D.S.T) Street No ft width 100% has completed up to (Base Course) Street No 6. 35ft width has completed up to (Base Course) Street No. 7 35ft width has completed up to Sub Base,) Street No. 7A 35ft width has completed up to Sub Base,) Street No. 7B 35ft width has completed up to Sub Base,) Street No ft width has completed up to Base Course ) Street No ft width has completed up to (Base Course and D.S.T 50 %) Street No ft width has completed up to (Base Course and 50 % D.S.T) Street No ft width has completed up to (Base Course) Street No ft width has completed up to (Base Course ) Street No ft width has completed up to (Sub Base,) 1-4

5 Street No ft width has completed up to (Sub Base,) Street No ft width 100% has completed up to (Sub Base, 50 % Base Course) Street No ft. width 100 % has completed up to(base Course) Street No ft. width 100% has completed up to (Base Course) Street No ft. width 100 % has completed up to ( Base Course) Street No ft. width 100 % has completed up to (Base Course) Street No. Bank Road 35ft width has completed (Sub Base, 50% Base Course and 50 % DST) Street No ft. width has completed up to (Base Course) Street No ft. width has completed up to (Base Course) Street No ft. width has completed up to (Base Course) Street No. 23A 35ft. width has completed up to (Sub Grade ) Street No. 24A 35ft. width has completed up to (Sub Grade ) Street No. 19A 35ft. width has completed up to (Sub Grade ) Street No. 20A 35ft. width has completed up to (Sub Grade ) Drainage system Street No ft. Length 4 x12 x 5 ft. has completed Drainage system Street No.100 ft. Length 3 x 3 x 2 ft. has completed Sewerage system has completed R/Wall Size 1000 x /2 x 30 has completed Kerb Stone work Street No. 1,2,3,4,10,11,12,Bank Road has completed Kerb Stone painting Street no.1,2,3,4,10,11,12, Bank Road work has completed RCC Culvert Street No. 3,9,10,11,12,13,Size ( 8 X 28 ft.) 7Nos has completed Note: Possession Hand Over 1-5

6 EARTH WORK 3) Block B Cutting/Leveling of over Area has completed. Road earth work has completed Road Sub Base work has completed Road Base course work has completed Sewerage System has completed Road Site Kerb Stone work has completed Over Head Water Tank ( gallons has completed Tub Well work 500 ft. depth has completed DST work has completed Road Side Drain work has completed Note: Extension Area work has under progress Cutting/Leveling of over Area has completed Road earth work has completed RRM R/Wall 120 length work has completed. RRM Rain Water Drain 716 length has completed. 1-6

7 Note: Possession Hand Over EARTH WORK 3) Block C Cutting/Leveling of over Area work under progress Internal Street No: 1. 40ft width has completed up to (Sub Base) Lane No ft width has completed up to (Sub Base) Lane No. 02, 40ft width has completed up to (Sub Base) Lane No ft width has completed up to (Sub Base) Street No: 4, 35ft width has completed up to (Sub Base) Street No: 5, 35ft width has completed up to (Sub Base) Street No: 6, 35ft width has completed up to (Sub Base) Street No: 12, 35ft width has completed up to (Sub Base) Street No: 13, 35ft width has completed up to (Sub Base) remaining work under progress 1-7

8 EARTH WORK 4) Block D Cutting/Leveling of over Area has completed Road earth work has completed Road Sub Base work has completed Road Base course work has completed Sewerage System has completed Road Site Kerb Stone work has completed Road Side Drain work has completed Over Head Water gallons has completed Tube well has completed 6 Kanal park has completed DST work has completed Note: Possession Hand Over 1-8

9 EARTH WORK 5) Block E Cutting/Leveling of over Area up to 90% work has completed Lane No: 1,2.40ft width has completed up to (Sub Base) Lane No: 2.40ft width has completed up to (Sub Base) Street No: 3. 40ft width has completed up to(sub Base) Street no:4, 35ft width has complete up to Sub Base) Street no:5, 35ft width has complete up to Sub Base) Street no:6, 35ft width has complete up to Sub Base) Street no:8, 35ft width has complete up to Sub Base) Street no:10, 35ft width has complete up to Sub Base) Street no:11, 40ft width has complete up to Sub Base) Street no:12, 35ft width has complete up to Sub Base) Street no:13, 35ft width has complete up to Sub Base) Street no:14, 35ft width has complete up to Sub Base) Street no:15, 35ft width has complete up to Sub Base) Street no:16, 35ft width has complete up to Sub Base) Street no:17, 35 width has complete up to Sub Base) Street no:18, 35 width has complete up to Sub Base) Street no:19, 35 width has complete up to Sub Base) Street no:20, 35 width has complete up to Sub Base) 1-9

10 Street no:21, 35 width has complete up to Sub Base) Street no:22, 35 width has complete up to Sub Base) Street no:23, 35 width has complete up to Sub Base) Stone work Drainage system 2400ft length and 4 x 4 x4.5 ft. Has completed Remaining work under progress 1-10

11 EARTH WORK 6) Block F Cutting/Leveling of over Area under progress Sir Syed Road 72 ft. width has completed (including i.e., cutting filling, sub Base, base course and kerb stone) Lane no: 1, 40 ft. Width has completed (including i.e., cutting filling, sub Base) Lane no: 2.40 ft. Width has completed (including i.e., cutting filling, sub Base) Street no:7 ( 0.37 km 40 ft. Width has completed(including i.e., cutting filling, sub Base) Street no:11 earth work Under progress Street no:12 earth work under progress Street no:13 earth work under progress Street no:14 earth work under progress Street no:15 earth work under progress 1-11

12 7) SEWERAGE SYSTEM SEWERAGE SYSTEM BLOCK A = COPMPLETED SEWERAGE SYSTEM BLOCK D = COPMPLETED SEWERAGE SYSTEM BLOCK B = COMPLETED 8) WATER SUPPLY SYSTEM WATER SUPPLY SYSTEM BLOCK A = COPMPLETED WATER SUPPLY SYSTEM BLOCK B, D = under progress. 9) M.GATE 1-12

13 M. Entrance gate has completed Site office building has completed 10) STOME WATER DRAINSGE SYSTEM Stone work Drainage system 1250ft length and 30 x 36 ft. has completed Stone work Drainage system 1200ft length and 4 x 9 x4.5 ft. Has completed Drainage system Street No ft. Length 4 x12 x 5 ft. has completed Drainage system Street No.100 ft. Length 3 x 3 x 2 ft. has completed 1-13

14 11) ELECTRIFICATION WORK Fixing/Installation HT overhead Line 11kv from (Block A to Block F) completed. Fixing/Installation Internal HT overhead Line has completed. Construction of Plinth for Distribution Transformer 13 No s has completed. Fixing/Installation of 200 KV Transformer Pad Mounted 12 No s has completed Fixing/Installation of 100 KV Transformer Pad Mounted 12 No s has completed Excavation of LT Line (CABLE) underground internal streets has completed. Lying/Installation of LT Line (CABLE) underground Block A 100 % has completed Construction/Fixing of RCC Base for Lt Distribution box 198 no s has completed Installation/Fixing of Distribution Box 198 no s has completed Construction of road crossing for LT Underground 210 Mtr has completed Construction of Gate crossing for LT underground 640 Mtr has completed 12) GAS LINE WORK Fixing/Installation 4 dia pipe of SUI GAS LINE Aziz khan road has completed. Fixing/Installation 2 dia pipe street no. 3,4,16 bank road (BLOCK A) has completed. Fixing/Installation 2 dia pipe street no. 2,lane no.2,34, (BLOCK B) has completed. Fixing/Installation 2 dia pipe street no. 2,6lane no.1,2 (BLOCK D) has completed. Fixing/Installation 4 dia pipe sir syed road has completed. 1-14

15 13) OVER HEAD WATER TANK Overhead water tank gallons (Block B) has completed Overhead water tank gallons (Block D) has completed. 14) MODAL HOUSE (35 X 65) 10 Marla Modal House Block D has completed. (35 X 65) 10 Marla Modal House Block A has completed. (25 X 50) 5 Marla Modal House Block A has completed. 15) STREET LIGHT Fixing of Street Light work internal Street Block A has completed. 16) PARK 6 Kanal park Block D has completed. 4 Kanal park Block A has completed. 17) COMMERCIAL PLAZA Commercial Plaza 80 x 60 structure work complete up to 4 th floor 1-15

16 Brik work of basement, Ground 1 st floor,2 nd floor has complete 1-16