1 1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM 1016 Tree Preservation and Treatment 1. Description. This section specifies the requirements for protecting trees and related services including: trimming, fertilization, root prune trenching, vapor barrier installation, watering, chemical treatment and other tree preservation techniques as indicated on drawings and described herein. 2. Quality Assurance. All tree trimming, fertilizing, chemical treatment and work involving tree roots required to protect trees shall be performed by or under the supervision of a qualified Arborist or Urban Forester. 3. Job Conditions. a. Contractor shall not allow any vehicular traffic, construction equipment, parking of vehicles or stockpiling of excavated material or construction materials within tree protection fences. b. Trees to be preserved shall be watered to maintain their healthy growth and to ensure they do not become moisture stressed during the course of construction operations. 4. Definitions. a. Dripline. The dripline of a tree is defined as the outer tips or ends of the limbs and the soil below which contains tree roots. b. Root Zone Area. The root zone area of the tree is defined as the ground area extending out from the tree trunk to the end of the limb tips or dripline. This area is considered to be the most critical area of roots and should be protected. c. Zero Curb Cut. Zero curb cut - no soil disturbance back of curb. The process in which required work is conducted without cutting or otherwise disturbing soil located behind the existing curb

2 5. Materials. a. Tree Protection Fencing. Orange, plastic mesh fencing, 4 feet in height with 6 feet high t -bar posts installed as per drawings. Set posts 1.5 feet into ground. Stretch fencing material tight prior to securing. b. Plastic Vapor Barrier. 6 mil. polyethylene plastic sheeting (on rolls) min. 3 foot width. c. Fertilizer. Arbor-Green, mixed and applied per label instructions. the nitrogen per 1,000 sq. ft. will be as shown in the plans. 6. Construction Methods. a. General. Contractor and all sub-contractors shall attend a preconstruction meeting given by the Engineer and Project Forester to review tree preservation requirements and sequence of services for the construction process. b. Protection. 1. Protect tree root systems from damage due to noxious materials in solution caused by run-off or spillage during mixing and placement of construction materials, or drainage from stored materials. 2. Protect tree limbs, trunks and foliage from direct exposure to hot exhaust from equipment by providing adequate exhaust pipe deflectors. 3. Protect exposed roots and root zone areas from contamination from stabilization materials and concrete by placing a sheet of 6 mil poly over horizontal or vertical grade prior to pouring concrete curbs, inlets, driveways and ramps within root zone. 4. Designate limited areas as concrete washout areas. Locate concrete washout areas away from root zones. 5. Cover exposed roots within 24 hours to reduce damage caused by desiccation. Roots may be covered with soil, mulch, or wet burlap to help protect them from drying. 6. Site preparation work and/or construction work shall not begin in any area where tree preservation measures have not been completed and approved. c. Preparation. 1. Fencing operations will necessitate access areas for workers, materials and equipment. 2. Contractor shall not allow any vehicular traffic, parking of

3 vehicles or stockpiling of excavated material or construction material within the dripline of trees to be preserved. 3. Should access be necessary within root zone areas, place a 3/4" thick plywood driving surface over the existing grade to help distribute the weight of equipment and minimize soil compaction and rutting. This is not acceptable bridging for driving over exposed tree roots. Exposed roots should not be driven over. 4. Contractor shall notify Engineer if existing tree locations differ from locations represented on drawings. The dripline as observed in the field shall superceed that outlined on construction plans. d. Root Pruning and Vapor Barrier Installation. 1. Root pruning trenching and vapor barrier installation (if apllicable) locations are designated on the tree preservation plan. Exact locations shall be approved in the field by the Engineer or Project Forester. Trenching depth and vapor barrier shall extend 10 inches below proposed soil stabilization limits. After installation of vapor barrier, trench shall be backfilled with loose soil and compacted. e. Tree Protection Fences. 1. Each tree to be preserved shall be protected with a tree protection fence. The fencing shall be continuous between posts, shall be pulled taut prior to securing to posts, and shall be firmly attached to the posts with a minimum of 4 wire ties. 2. The fence shall be placed in a continuous alignment around a tree or group of trees designated to be preserved as shown on the preservation plan. Fences shall be placed to protect roots, trunks and foliage and generally shall be placed 5 feet outside the dripline of a tree or group of trees being protected, however the fence shall be located two feet from the back of curb. The location of a fence may be inside the above-stated limit in a situation where requirements of the work require operations inside the limit, as shown on the drawings or with the approval of the Project Forester prior to placing the fence. The Contractor shall not remove or relocate tree protection fencing and shall not operate within the limits shown without direct approval of the Project Forester. 3. Storage of equipment or materials will not be allowed inside a fence. Entryways into a protected area shall not be provided unless approved by the Project Forester. 4. Damage to tree fences occurring during the progress of the work shall be repaired immediately at no additional cost to owner. Workmen shall be clearly instructed to exercise caution in performance of work near trees being preserved

4 f. Pruning. 1. Where canopy of tree extends over the street, prune for clearance of normal vehicle traffic only. Prune to clear street feet. Extent of pruning shall be based upon requirements to clear limbs to a maximum height of feet over the street. Additional clearance pruning for construction activity access will not be allowed. All pruning shall be approved by the Project Forester before beginning. 2. Contractor shall notify property owner prior to trimming or pruning any trees on private property. 3. Trees shall be pruned in a manner that will not destroy or alter the natural shape and character of the tree. Apply appropriate, non-toxic wound paint to all fresh wounds on oak trees after pruning. 4. All cuts should be made sufficiently close to the parent limb or trunk without cutting into the branch collar or leaving a protruding stub, so that closure can readily start under normal conditions. Clean cuts should be made at all times. g. Fertilizer 1. Deep root fertilize designated trees. Fertilization application dates shall be determined by the Project Forester. 2. Fertilize entire root zone area within the dripline of the tree and continue 10 feet beyond the dripline. 3. Fertilizer shall be Arbor-Green, , or approved substitute. 4. Mixture shall be injected into the top 10 inches of soil under pressure of psi. 5. Application of nitrogen per 1,000 square feet will be as shown in the plans. Inject to a depth of 10 inches and a spacing of 3 feet between injection points. 6. Fertilizer shall be mixed in a tank with mechanical agitation capability. h. Watering. 1. Trees which have received root damage should be watered regularly to eliminate additional stress caused by lack of moisture. Water during periods without adequate rainfall. For example, should 1.5" of rain not be received within a week period, the trees should be thoroughly watered. March through September, water once every two weeks. October through February, water every three weeks. Water thoroughly to saturate the entire root zone area

5 2. Foliage, limbs and trunks shall be rinsed with fresh water to remove dust accumulated during the demolition and construction process as necessary. Frequency shall be determined by the forester. i. Chemical Treatment. Treat tree trunks with evidence of borer activity with the appropriate approved insecticide mixed and applied per the manufacturer's product application recommendations. Trees shall be sprayed within 24 hours after observance of borer activity. j. Excavation Around Trees. 1. Excavate within the dripline of trees only where indicated. where trenching for construction of utilities is required within the dripline, tunnel under the root zone using the tunnel boring method at a minimum depth of over 4 feet. Bore pits and peep holes shall be located outside of root zone areas. 2. Where excavating is required within root zones at shallow depths of up to 4 feet, hand excavate and tunnel under or around roots to minimize damage. Provide trench excavation protection at excavations to minimize trench width, use only vertical trench walls. Where necessary, cut roots over 1 inch in diameter with sharp pruning instruments to leave a smooth, clean-cut surface. 3. Do not allow exposed roots to dry out before permanent backfill is placed. Provide temporary earth cover, or wrap with burlap. Water and maintain exposed roots in moist condition and temporarily support and protect from damage until permanently covered with soil. k. Grading and Filling Around Trees. 1. Maintain existing grade within the dripline of trees, unless otherwise indicated. 2. Where existing grade around trees is above new finish grade, under supervision of Project Forester, carefully hand excavate within the dripline to make transition to new finish grade. 3. Where existing grade is below new finish grade, place clean bank sand in a single layer to make the transition to new grade. Do not compact. Hand grade to required elevation. l. Demolition of Existing Concrete. 1. Caution should be used during removal of the existing street and curb to minimize damage to root systems. The following procedures shall be used when removing the existing concrete: a. Zero curb cut - damage behind the curb within root zones of trees designated for zero curb cut shall be prohibited. If the curb cannot be removed without disturbing soil or damaging roots back of the curb when using equipment for demolition purposes, the curb shall

6 be broken using a hand-held jackhammer and removed by hand. b. Root removal - roots extending into the street in areas to be paved shall be cut and removed by hand prior to disturbance or removal with equipment. Roots shall be pruned flush with the proposed back of curb. Roots one inch in diameter and larger shall be cut in a manner to provide a smooth, clean cut surface. Cuts shall be made with the appropriate pruning shears or pruning saws. Roots shall not be chopped or broken. 7. Sequence of Tree Protection Procedures and Services. 1. Fertilize all designated trees. Fertilizing should be accomplished first, however, it will be determined by the time of year the project begins. Fertilizing shall be accomplished between the months of November and May. 2. Root prune and install vapor barrier (if applicable) prior to site work. 3. Place tree protection fence around designated trees. Place fencing prior to any construction activity. 4. Trim trees to clear limbs feet above surface of proposed street. 5. During removal of curb and street, hand cut roots flush with back of curb after curb and street debris has been removed and prior to any excavating or grading. 6. Cover any exposed roots with recommended materials to prevent desiccation and soil contamination by the lime slurry. 7. Root prune for utility construction purposes prior to excavating. 8. Remove tree protection fences upon completion of project. 8. Existing Stressed & Declining Trees. Trees which appear stressed or declining in health are as shown in the plans. Prior to beginning the construction phase, all trees should be reviewed and stressed or declining trees should be documented. 9. Protecting Exposed Roots. Protect exposed roots and root tips from drying out. Cover exposed roots and root tips with soil, mulch, or wet burlap within 24 hours of exposure. 10. Site Monitoring. a. It is recommended that the Project Forester as shown in the plans is hired to enforce and monitor the tree preservation program during demolition and construction to ensure tree protection procedures and techniques are practiced as specified

7 and to address concerns and conditions which occur in-the-field. b. The program must be monitored a minimum of two times weekly to ensure proper tree preservation techniques and procedures are practiced. Monitoring will be required more frequently at the beginning of the project until techniques and procedures are understood by all parties involved. c. Tree protection procedures and practices as outlined in these specifications should be reviewed at the preconstruction meeting. The Project Urban Forester should be responsible for presenting this information during the preconstruction meeting. addition, the Project Urban Forester should address the subcontractors, laborers and equipment operators in a brief meeting in order to ensure that all parties understand the requirements and the importance of the tree preservation program. In 11. Accidental Spill of Toxic Materials. Concrete, lime or other chemicals accidentally spilled within root zone protection areas should be completely removed. Contaminated soil should be completely removed at the time of the spill and removed by hand making certain that tree roots are not disturbed. fresh soil should be added as necessary to bring the soil level to that of natural grade. 12. Damage to Existing Trees. The Contractor should be assessed for damages to trees designated to be protected that result from the Contractor s negligence or failure to comply with the requirements of this specification. Damages should be assessed in accordance with the criteria established in the guide for plant appraisal, 8th edition, by the International Society of Arboriculture. Damages at the rate applicable therein should be deducted from any monies due the Contractor as liquidated damages. 13. Care of Trees After Construction is Complete. a. Proper maintenance should include fertilizing the trees once yearly and maintaining adequate moisture conditions to ensure the trees do not experience moisture stress. b. After construction is complete the trees designated for fertilizing and watering should be maintained for a minimum of two (2) years as per the fertilizing and watering specifications designated in the construction documents. Trees designated to be fertilized should be fertilized one time per year for a period of two (2) years after construction is complete. 14. Measurement. This Item will be measured as each tree treated as herein specified. 15. Payment. The work performed and materials furnished in accordance with this Item and measured as provided under measurement will be paid for at the unit price bid for tree preservation and treatment. This

8 price shall be full compensation for trimming, chemical treatment, vapor barrier (if applicable) for furnishing all required materials, including backfill, excavation, tools, labor, equipment, inspection and testing as required, and incidentals required to complete this work. Tree protection fencing shall be paid for under Item Watering shall be paid for under Item

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES PART I GENERAL 1.02 The objective of this section is to reduce the negative impacts of construction on trees. Tree protection

More information

Tree Protection Policy

Tree Protection Policy Appendix F Tree Protection Policy The following is according to the City of Hamilton s special provision SP-97. General Tree Protection shall be in accordance with OPSS 801 as amended by this special provision.

More information

SECTION TREE & PLANTING PROTECTION

SECTION TREE & PLANTING PROTECTION SECTION 32 0193 PART 1 - GENERAL 4.1 SUMMARY A. The work includes labor, equipment, and materials necessary for existing tree & plant protection, tree trimming and protection of the Critical Root Zone

More information

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball.

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball. Adopted 12/5/00; revised 3/5/02 Marietta Tree Commission Rules and Regulations I. Tree Planting A. Planting Specifications These specifications are Adapted from recommendations of the OSU Extension Service.

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t Standard Specification SECTION 01 56 39 TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 WORK INCLUDED A. Perform all Work necessary and required to protect and maintain all trees, shrubs, groundcover and

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

TOWN OF ATHERTON. Tree Preservation Guidelines. Standards and Specifications

TOWN OF ATHERTON. Tree Preservation Guidelines. Standards and Specifications TOWN OF ATHERTON Tree Preservation Guidelines Standards and Specifications February 2004 TOWN OF ATHERTON TREE PRESERVATION GUIDELINES STANDARDS AND SPECIFICATIONS SECTION 1.00 DEFINITIONS For the purpose

More information

Tree Protection & Preservation

Tree Protection & Preservation IV. Tree Protection & Preservation A. Participation at the Construction Planning Stage 1. All Contracted Design Services shall receive a copy Tree Care Plan Sections appropriate to the given project as

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving. SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.

More information

SECTION 503 TEMPORARY PAVEMENT RESTORATION

SECTION 503 TEMPORARY PAVEMENT RESTORATION SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with

More information

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL

More information

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION Urban trees need to be protected from damage to maximize their health, safety, benefits and functionality. Mature, young and newly transplanted trees need

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING Section Number Title 301 GENERAL 302 MATERIALS SPECIFICATIONS 303 CLEARING

More information

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements. SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD

TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD 2-1 CHAPTER 1. TREE BOARD. TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD SECTION 2-101. Purpose. 2-102. Definitions. 2-103. Creation of a tree board. 2-104. Operation. 2-105. Duties and responsibilities.

More information

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows: Section 02775 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Reinforced concrete sidewalks. B. Wheelchair ramps. C. Reinforced slope paving. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB #4320 2014 RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN The following changes, additions, and/or deletions shall be made to the Bid Documents

More information

Village of Glen Ellyn TREE PRESERVATION GUIDELINES

Village of Glen Ellyn TREE PRESERVATION GUIDELINES Village of Glen Ellyn TREE PRESERVATION GUIDELINES TREE PRESERVATION PLAN APPLICATION REQUIREMENTS It is important that you become familiar with the requirements in Village Code Title 8, Chapter 4, and

More information

SECTION PORTLAND CEMENT CONCRETE

SECTION PORTLAND CEMENT CONCRETE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this

More information

UNIVERSITY OF CENTRAL FLORIDA SECTION TEMPORARY TREE AND PLANT PROTECTION

UNIVERSITY OF CENTRAL FLORIDA SECTION TEMPORARY TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 RELATED SECTIONS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Divisions 01 Specification Sections, apply to this Section.

More information

Main Campus Urban Forest and Landscape Management Policy

Main Campus Urban Forest and Landscape Management Policy Main Campus Urban Forest and Landscape Management Policy Policy Statement: Clemson University is committed to providing a safe, attractive, educational and sustainable campus urban forest that faculty,

More information

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS Section Page 10-1 DUST CONTROL...10.1 10-2 AIR POLLUTION CONTROL...10.1 10-3 BURNING...10.1 10-4 EROSION, SEDIMENT, AND WATER POLLUTION

More information

ISA Certified Arborist PN-6545A PO Box ISA Tree Risk Assessment Qualified Lake Forest Park, WA WA. Business #

ISA Certified Arborist PN-6545A PO Box ISA Tree Risk Assessment Qualified Lake Forest Park, WA WA. Business # Michael A. Woodbury Consulting Arborist 206-659-4288 pnrc@comcast.net ISA Certified Arborist PN-6545A PO Box 55162 ISA Tree Risk Assessment Qualified Lake Forest Park, WA 98155 WA. Business #602218294

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 02222 - EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES PART 1 - GENERAL 1.01 SECTION INCLUDES A. Excavating trenches for the installation of utilities and stormwater detention facilities. B.

More information

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution. ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special

More information

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

Standing Permit for Repair by Utility Providers

Standing Permit for Repair by Utility Providers City of Stevens Point Department of Parks, Recreation, and Forestry 2442 Sims Ave., Stevens Point, WI 54481, Phone (715) 346-1532 Fax (715) 346-1582 Standing Permit for Repair by Utility Providers Any

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SPECIAL SPECIFICATION 4653 Polypropylene Pipe 2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

SECTION GENERAL EXCAVATION

SECTION GENERAL EXCAVATION 02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,

More information

SECTION 14 EMBANKMENT

SECTION 14 EMBANKMENT SECTION 14 EMBANKMENT 14.1 DESCRIPTION A. General: This work consists of constructing roadway embankments, including preparation of the areas upon which embankments are to be placed; the construction of

More information

Reinforced Soil Slopes (RSS)

Reinforced Soil Slopes (RSS) Supplemental Technical Specification for Reinforced Soil Slopes (RSS) SCDOT Designation: SC-M-206-1 (4/16) 1.0 DESCRIPTION 1.1 Construct a reinforced soil slope in accordance with these specifications,

More information

Concrete Waste Management WM-8

Concrete Waste Management WM-8 Standard Symbol BMP Objectives Soil Stabilization Sediment Control Tracking Control Wind Erosion Control Non-Storm Water Management Materials and Waste Management Definition and Purpose Appropriate Applications

More information

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL This section covers the restoration of roadways and sidewalks, in whole or in part, with bituminous concrete paving. WITHIN 4 DAYS OF BACKFILLING IN AREAS

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS 1 PART ONE - GENERAL 1.1 COORDINATION SECTION 02466 DRILLED CONCRETE PIERS AND SHAFTS A. The General, Supplementary, and Special Conditions of these specifications shall all be considered as a part of

More information

IM 0291(108)0 UNION COUNTY INDEX OF SHEETS. Index of Sheets. Estimate of Quantities. Table of Fence Quantities. Details for Right-of-Way Fence

IM 0291(108)0 UNION COUNTY INDEX OF SHEETS. Index of Sheets. Estimate of Quantities. Table of Fence Quantities. Details for Right-of-Way Fence INDEX OF SHEETS Sheet 1 Sheet 2 Sheet 3 Sheet 4 Sheets 5 & 6 Sheet 7 Sheets 8-15 Layout Map Index of Sheets Estimate of Quantities Table of Fence Quantities Plan Notes Traffic Control Details for Right-of-Way

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 04821 TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Installation Guidelines

Installation Guidelines 815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Guidelines Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles (optional),

More information

TREE PROTECTION/PRESERVATION POLICY

TREE PROTECTION/PRESERVATION POLICY TREE PROTECTION/PRESERVATION POLICY THE CORPORATION OF THE TOWN OF AURORA PARKS AND RECREATION SERVICES 100 John West Way, Aurora, Ontario, L4G-6J1 T.905-727-3123 F.905-727-3903 www.aurora.ca JUNE 2015

More information

St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA Phone: (985) Fax: (985)

St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA Phone: (985) Fax: (985) St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA 70434 Phone: (985) 898-2520 Fax: (985) 898-5227 Pat Brister Parish President February 5, 2016 Please find the following

More information

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES SECTION 2831 ITEM F-162 CHAIN-LINK FENCES PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications and the details

More information

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts. Supplemental Technical Specification for SILT FENCE SYSTEMS SCDOT Designation: SC-M-815-2 (03/08) 1.0 Silt Fence Systems This Supplemental Specification replaces Sections 815.2.5 and 815.4.6, Silt Fences,

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts. Supplemental Technical Specification for SILT FENCE SYSTEMS SCDOT Designation: SC-M-815-2 (7/18) 1.0 Silt Fence Systems This Supplemental Specification replaces Sections 815.2.5 and 815.4.6, Silt Fences,

More information

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section

More information

TREE CONSERVATION REPORT

TREE CONSERVATION REPORT 1 INTRODUCTION Pursuant to Section 4.7.2 of the City of Ottawa s Official Plan, this Tree Conservation Report has been prepared in support of a Site Plan Control Application for the proposed residential

More information

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines. SECTION 15.0 PIPE TRENCHES 15.01 Clearing and Grubbing The developer/contractor shall be responsible for the clearing and grubbing of the entire right-of-way. See Sections 13.01 and 14.01. Clearing and

More information

ROLLED EROSION CONTROL PRODUCTS (RECP)

ROLLED EROSION CONTROL PRODUCTS (RECP) Supplemental Technical Specification for ROLLED EROSION CONTROL PRODUCTS (RECP) SCDOT Designation: SC-M-815-9 (07/17) 1.0 Rolled Erosion Control Products (RECP) This Supplemental Specification replaces

More information

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES PART 1 - GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

ITEM 706 PIPE SLOPE DRAIN

ITEM 706 PIPE SLOPE DRAIN AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN 706.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway.

(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway. Last Revision by CO Special Provisions: 09/14/18 Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2018-143 ((2360) PLANT MIXED ASPHALT PAVEMENT (MSCR)) when using this writeup.

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

Gas meter clearances and service installation requirements

Gas meter clearances and service installation requirements FEBRUARY 2018 Gas meter clearances and service installation requirements CALL PSE S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION. Builder/owner/developer

More information

SECTION EMBANKMENT

SECTION EMBANKMENT 02260-1 of 8 SECTION 02260 EMBANKMENT 02260.01 GENERAL A. Description 1. Embankment shall be formed of suitable material obtained from General, Structure, Borrow, Trench, and other excavations included

More information

Muhlenberg College Tree Plan

Muhlenberg College Tree Plan Muhlenberg College Tree Plan 2014 1) Purpose: The purpose of the Muhlenberg College Tree Care Plan is to identify the policies, procedures, and practices that are to be used in establishing, protecting,

More information

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications. SECTION 31 22 00- GRADING 1.0 GENERAL.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.. 2 Excavate to exact line and grade as

More information

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS Section Page 10-1 DUST CONTROL... 10.1 10-2 AIR POLLUTION CONTROL... 10.1 10-3 BURNING... 10.1 10-4 EROSION, SEDIMENT, AND WATER POLLUTION

More information

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction

More information

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

DOCUMENT ADDENDA AND MODIFICATIONS

DOCUMENT ADDENDA AND MODIFICATIONS DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications

More information

SECTION ASPHALT PAVING AND SURFACING

SECTION ASPHALT PAVING AND SURFACING SECTION 02500 ASPHALT PAVING AND SURFACING PART 1 - GENERAL 1.01 WORK INCLUDED A. Traffic control as required to divert vehicular and pedestrian traffic around construction. B. Spreading and compacting

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

TREE CONSERVATION REPORT

TREE CONSERVATION REPORT 1 INTRODUCTION Pursuant to Section 4.7.2 of the City of Ottawa s Official Plan, this Tree Conservation Report has been prepared in support of a Site Plan Control Application for the proposed 180 Huntmar

More information

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements... SECTION 02530 CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Inspection And Tests... 1 1.04 Quality Assurance...

More information

SECTION EROSION CONTROL DEVICES

SECTION EROSION CONTROL DEVICES SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment

More information

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PUBLIC WORKS DEPARTMENT GENERAL NOTES PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard

More information

PAY QUANTITY NOTES INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS EARTHWORK WHERE NO QUANTITY IS SHOWN ON P & P SHEETS.

PAY QUANTITY NOTES INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS EARTHWORK WHERE NO QUANTITY IS SHOWN ON P & P SHEETS. PAY QUANTITY NOTES (F-1) (F-2) (F-3) (F-4) (F-5) (F-6) (F-7) (F-8) (F-9) (F-10) (F-11) (F-12) (F-13) (F-14) (F-15) (F-16) (F-17) (F-18) (F-19) INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

TREE RETENTION AND PROTECTION SPECIFICATIONS

TREE RETENTION AND PROTECTION SPECIFICATIONS DENVER PARKS AND RECREATION OFFICE OF THE CITY FORESTER UPDATED JULY 2015 SECTION 01 56 39 SPECIFICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Contract Drawings and general provisions of the Contract,

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information